TIMBERLINE AND KECHTER
RIGHT TURN LANES
BID NUMBER: 7650
PRE-BID MEETING
May 29, 2014
10am @ 215 North Mason – Room 1B
City of Fort Collins – Engineering Department
Capital Projects Group
2
INTRODUCTIONS
Engineering – Capital Projects
Mark Laken – Project Engineer 222-3546
Craig Farver – Construction Inspector 222-0854
Tim Kemp – Design & Bid Assistance 416-2719
Purchasing
John Stephen – Senior Buyer 221-6777
3
ATTENDANCE
Please be sure to register
Bid Opening
June 13, 2014 @ 3:00pm (Our Clock)
Location - 215 North Mason Street
Submit Bids to Purchasing Department
4
IMPORTANT CONTRACT DATES
Pre-Construction Meeting
Mandatory Meeting prior to Commencing Construction
Date and Time to be determined after Contract Award
Construction Start Date
Approximately July 2, 2014
Sixty (60) Calendar Day Contract
Poudre School District starts Monday, August 18
5
IMPORTANT CONTRACT DATES
Substantial Completion
Forty-five (45) Calendar Days
Further Defined in General Conditions Slides
Final Acceptance
Fifteen (15) Calendar Days from Substantial Completion
Further Defined in General Conditions Slides
6
CONTRACT DOCUMENTS BID #7650
Plan Sheets
Prepared by: AECOM (Sheets 1 to 30)
Specification Book
Prepared by: AECOM and City of Fort Collins
Subgrade Investigation and Pavement Recommendation
Prepared by: CTL Thompson
7
PROJECT LIMITS
8
SUMMARY OF WORK
Removals – Clearing and Grubbing, Asphalt, Concrete
Embankment Material and Topsoil Placement
Install Aggregate Base, Curb, Gutter and Asphalt
Install Concrete Sidewalk and Curb Ramps
Pavement Rehab – Mill and Inlay
Install Native Seeding (NB Turn Lane Only)
Provide Traffic Control
Approved Traffic Control Plans thru Syl Mireles
9
SUMMARY OF WORK
Construction Staking
Provided by the City of Fort Collins
48 Hours (Minimum) Required for Notification
Testing
Paid for by the City of Fort Collins thru CTL Thompson
Contractor will schedule Testing as required
Striping
Provided by the City of Fort Collins
10
HIGHLIGHTS OF GENERAL CONDITIONS
Superintendents
The General Contractor SHALL employ a full time
superintendent whose sole responsibility is to monitor and
coordinate all facets of the work
Liquidated Damages – Substantial Completion
If the Contractor goes past the 45 calendar days for
substantial completion, damages in the amount of Eight
Hundred Dollars ($800.00) for each calendar day will be
assessed
11
HIGHLIGHTS OF GENERAL CONDITIONS
Substantial Completion - Defined
Completion and Acceptance of: Removals, Embankment,
Topsoil Placement, Slope Grading, Asphalt (Bottom Mat),
Curb and Gutter, Curb Ramps, Ditch Paving and Inlet
Liquidated Damages – Final Acceptance
If the Contractor goes past the 15 calendar days for final
acceptance, damages in the amount of Eight Hundred
Dollars ($800.00) for each calendar day will be assessed
12
HIGHLIGHTS OF GENERAL CONDITIONS
Final Acceptance - Defined
Completion and Acceptance of: New Fence, Fine Grading,
Native Seeding, Mulching and Tackifier, Removal of Tree
Protection, Removal of Erosion Control Items (except those
as directed by the City to remain in place), Asphalt (Top
Mat), Sidewalk and Completed Punch List Items
Project Coordination Meetings
Weekly On-Site Meetings (including ticket collection)
Contractor to update Schedule weekly. The Contractor
may be required to submit additional Schedules
dependent upon progress of the project.
13
HIGHLIGHTS OF GENERAL CONDITIONS
Construction Hours
Standard Working Hours are from 7:00am to 6:00pm
Monday through Friday
Weekend Work and / or Extended Hours Work may be
granted. Requests for either must be made in Writing a
minimum of 48 hours in advance. Requests are subject
to approval by the City of Fort Collins.
Special Conditions for Arterial / Arterial Intersections
o Not Permitted between 7 to 8:30am or 3:30 to 6pm
unless approved by City Traffic Operations Dept.
o Weekend or Extended Hours may be granted
14
HIGHLIGHTS OF GENERAL CONDITIONS
Haul Routes
Arterial and Collector Streets ONLY. Contractor will not
be allowed to use Residential Streets to access the site.
Site Clean Up
The construction work shall be kept and accomplished in
a neat, clean and orderly fashion
Street sweeping may be required in order to minimize
vehicle tracking and to meet EPA storm water quality
requirements
Dust control will be required as necessary
15
TRAFFIC CONTROL
Contractor Responsibilities:
Maintain vehicle, bicycle, and pedestrian traffic at all
times. ALL detours for ALL modes of transportation shall
be approved by the City prior to construction.
Maintain access to all local businesses
Review all upcoming lane closure needs and /or changes
in traffic control set up at Weekly Progress Meetings
Traffic Control Plans need to be submitted to the City
seven (7) days prior to setup
16
EROSION CONTROL - SWMP
Contractor Responsibilities:
Erosion Control in accordance with Sheets 21 - 24
The Contractor is responsible for maintaining and
repairing all erosion control devices throughout the
project
Contractor will designate a SWMP Administrator prior to
the start of construction. The SWMP Administrator will
conduct weekly inspections and submit a signed, log of
activity weekly to the City.
Payment will be made under the “208” line items
17
MATERIAL SUBMITTALS
Reviewed by the City
Process Time – 5 days per submittal
Shop Drawings – 2 copies (1 City, 1 back to Contractor)
WEATHER DAYS
See “Summary of Work” Section
Monthly Anticipated Calendar Days Lost to
Adverse Weather Conditions
18
HIGHLIGHTS FROM
SPECIFICATIONS
19
201 Clearing and Grubbing
SB Right Turn Lane
20
201 Clearing and Grubbing
NB Right Turn Lane
21
202 Removal of Inlet
SB Right Turn Lane
22
202 Removal of Pipe / End Section
NB Right Turn Lane
23
202 Removal of Guard Post
NB Right Turn Lane
24
202 Removal of Fence
NB Right Turn Lane
25
202 Removal of Sidewalk
SB Right Turn Lane
26
202 Removal of Curb and Gutter
SB Right Turn Lane
27
202 Removal of Concrete Curb Ramp
SB Right Turn Lane
28
202 Removal of Asphalt Mat (Full Depth)
SB Right Turn Lane
29
202 Removal of Asphalt Mat
(Planing) (2” Depth)
Intersection
30
202 Removal of Caissons
(Top Three Feet)
Existing Traffic Signals
31
EARTHWORK
203 Embankment Material (CIP) CY
203 Muck Excavation CY
203 Borrow (Muck Ex. Backfill) TON
203 Blading HOUR
203 Potholing HOUR
32
TOPSOIL
207 Topsoil (Stockpile and Redistribute) CY
33
EROSION CONTROL
208 Erosion Log (12 Inch) LF
208 Aggregate Bag LF
208 Concrete Washout Structure EACH
208 Storm Drain Inlet Protection LF
208 Vehicle Tracking Pad EACH
34
EROSION CONTROL
208 Removal and Disposal of
Sediment (Labor) HOUR
208 Removal and Disposal of
Sediment (Equipment) HOUR
208 Sweeping (Sediment Removal) HOUR
208 Erosion Control Supervisor HOUR
35
GROUND COVER AND TREE PROTECTION
212 Seeding (Native) ACRE
212 Tree Retention and Protection LS
213 Mulching (Weed Free Hay) ACRE
213 Mulch Tackifier LB
Note: These Pay Items are for the NB Turn Lane. The
Contractor will be responsible for “fine grading” disturbed
areas along the SB Turn Lane (restoration by others).
36
BASE & ASPHALT
304 Aggregate Base Course (Class 6) TON
403 Hot Mix Asphalt (Grading S) (100)
(PG 64-28) TON
403 Hot Mix Asphalt (Grading SG) (100)
(PG 58-28) TON
403 Hot Mix Asphalt (Hand Patching) TON
Narrow Widening Areas less than Paver Width
37
PAVEMENT SECTION
Both Turn Lanes – Full Depth Section
2” HMA (S) over 6” HMA (SG) over 6” ABC
Placed atop “Approved” Recompacted Subgrade
38
GEOTEXTILE & DITCH PAVING
420 Geotextile (Reinforcement) SY
As directed by the Engineer for stabilization
507 Bituminous Slope and Ditch
Paving (Asphalt) TON
Run down area at Southeast corner of intersection
The mixture used shall conform to the requirements
for the asphalt pavement used on the project
615 Embankment Protector (Type 5) EACH
Used in conjunction with Pay Item 507 (above)
39
INLET
604 Inlet Type R (L 5) (5 Foot) EACH
FENCES
607 Fence Plastic LF
Along Grading Limits for NB Turn Lane
607 Fence (“T” Post) (Smooth Wire) LF
Along NB Turn Lane
40
SIDEWALKS, CURB & GUTTER
608 Concrete Sidewalk (6 Inch) SY
608 Concrete Curb Ramp SY
Detectable Warning (domes) are incidental
608 Sidewalk Drain EACH
609 Curb and Gutter, Type 2 (Section II-B) LF
41
620 Sanitary Facility EACH
CONSTRUCTION SURVEYING
NO Pay Item – Provided by City of Fort Collins
FIELD FACILITIES
MOBILIZATION
626 Mobilization LS
42
TRAFFIC CONTROL
630 Flagging HOUR
630 Traffic Control Management DAY
630 Traffic Control Inspection DAY
Please review Section 630.15 of CDOT Specifications
630 Construction Zone Traffic Control LS
630 Portable Message Sign Panel DAY
43
TURN LANES / UTILITIES
Northbound Right Turn Lane
FCLWD Manhole Adjustment - Contractor
PVREA Moving Overhead Lines and Poles East
City Traffic has moved Traffic Signal Pole
City Traffic will place permanent vault after embankment
Southbound Right Turn Lane
Four Trees already transplanted
Century Link will rebuild vault – traffic rated
City Traffic has moved Traffic Signal Pole
City Traffic is rotating traffic vault
Contractor will mark, cap and cut irrigation lines
44
Thanks for Attending!
Questions and Clarifications can be Directed to:
John Stephen – Senior Buyer
Office (970) 221-6777
Email jstephen@fcgov.com
AND
Tim Kemp – Capital Projects Engineer
Office (970) 416-2719
Email tkemp@fcgov.com