EXHIBIT "A"
WORK ORDER FORM
PURSUANT TO AN AGREEMENT BETWEEN
THE CITY OF FORT COLLINS
AND
Adolfson & Peterson Construction
DATED: 7/25113
Work Order Number. OP-425796
Project Title: Block 32 Master Plan
Commencement Dale: July 25, 2013
Completion Date: June 30, 2014
Maximum Fee: (lime and reimbursable direct costs): $12,600
Protect Description:
Develop a conceptual master plan for Block 32 and potential surrounding parcels with the express purpose
of defining a site location for the Customer Service Building that responds and respects the long term
development of the Civic Center.
Scope of Services:
The Construction ManugedGoneral Contractor (CWGC) will collaborate with all consultants and the design
team to work as an Integrated design team and help maintain the focus and commitment to the Integrated
energy/Mgh performance goals of the project. The CM/GC will assist the project team with cost estimating,
construction methods and approach evaluations, construction sequencing and scheduling and other
conslruclability considerations during planning and design. The CMIGC will be compensated for their
participation based on approved labor and equipment rates with a cost not to exceed as listed In the Fee
proposal. General condition charges will be allowed as per Exhibit C of the RFP along with the approved
rates. Each invoice which shall have detailed Itemization of each Item submitted be within the not to exceed
amount as listed for each Item In the Fee proposal.
Professional agrees to perform the
services Identified above and on the
attached forms In accordance with the
terms and conditions contained herein
and In the Professional Services
Agreement between the parties. In the
event of a conflict between or ambiguity
In the terms of the Professional
Services Agreement and this work
order (including the attached forms) the
Professional Services Agreement shall
control. The attached forms consisting
of Nineteen (19) pages are hereby
accepted and incorporated herein, by
this reference, and Notice to Proceed is
hereby given.
City of Fort Collins
Facilities 0ject Mana a tip ell
By:
Date:
By:
Director of Purchasing and Risk Management
(If over $60,000.00)
Date:
AP Mountain Stales, LLC dha Adulfsun
Contractor: & Peterson Construction
Signature:}
Name: Eric P. Kimindshuc, Sr. PM
Date: 0/6/2014
EXHIBIT "A"
WORK ORDER FORM
PURSUANT TO AN AGREEMENT BETWEEN
THE CITY OF FORT COLLINS
AND
Adolfson & Peterson Construction
DATED: 7/25/13
Work Order Number: OP-452626
Project Title: Utilities Customer Service Building — Preconstruclion Phase
Commencement Date: January 26, 2014
Completion Dale: August 30, 2014
Maximum Fee: (lime and reimbursable direct costs): $11.600
Project Description:
Develop a design for the new Customer Service Building to be located on Block 32 to Include working
through SD, DID and CD phases to where the Clly of Fort Collins has Issued a building permit for
construction.
Scope of Services:
The Construction Manager/General Contractor (CM/GC) will collaborate with all consultants and the design
loam to work as an Integrated design team and help maintain the focus and commitment to the Integrated
energy/hlgh performance goals of the project. The CM/GC will assist the project team Wlh cost estimating,
construction methods and approach evaluations, construction sequencing and scheduling and other
construclability considerations during planning and design. The CM/GC will be compensated for their
participation based on approved labor and equipment rates with a cost not to exceed as listed as the Fee.
General condition charges will be allowed as par Exhibit C of the RFP along with the approved rates. Each
Invoice shall have detailed Itemization of each item submitted and be within the not to exceed amount as
listed for each Item In the agreement.
Professional agrees to perform the City of Fort Collins
services identified above and on the Facilities Ppoject Mana : BM
rgotl
attached forms in accordance with the
terms and conditions contained herein By:
and in the Professional Services /
Agreement between the parties. in the Dale: (Ol
event of a conflict between or ambiguity
In the terms of the Professional By:
Services Agreement and this work Director of Purchasing and Risk Management
order (including the attached forms) the (if over $60,000.00)
Professional Services Agreement shall Date:
control. The attached forms consisting AP Muunmin Status. LLCdba Adulrsun
of Nineteen (19) pages are hereby Contractor. & Peterson Construction
accepted and Incorporated herein, by
this reference, and Notice to Proceed is
hereby given. Signature:
Name: Eric P. Kimmclsi uc, Sr. PN
Dale: 6/6/2014