9—
VENDOR Neenan Archistruction DATE 4-16-14
REQ BY: Brian Hergott
Work Order # OP424311
Billable? Y/N Yes
CHARGE# 254703000.535010.6 (KFCG Funds) TOTAL COST: $99,886.53 - BUYER: John Stephen
CITY DESCRIPTION r b q I -� )- 5'.� 7. COST
Provide labor, materials and equipment for design, construction and installation for the scope of work associated with
change order #5. $99,886.53
Modify the new parking lot for phase III which is to be concrete paving in lieu of asphalt, include pervious paving and landscaping.
Increase weather conditions allowance
Modify new PV system
COMPUTER INPUT INFORMATION:
VENDOR# REQUISITION # DATE ENTERED:
The Neenan Company LLLP
2607 Midpoint Drive,
Fort Collins, CO 80525
archistructions Tel: 970 493-8747 Fax: 970 493-5869
OWNER CHANGE ITEM DETAIL
Project #: 2761 A
Project Name: Fort Collins Senior Center
Project Address: 1200 Raintree Drive
Fort Collins, CO 80526
Status: APP
OCI Date: 03126/2014
Owner CO #: OCO-005
Due to Owner:
Scope Desc:
Source:
Final
Description
Quantity
Amount vendor Name
Weather Conditions
$25,353.00
Subtotal:
$25,353.00
Final
Mark Ups
Quantity
Amount vendor Name
Fee
$1,109.83
Insur, Bond, Warranty
$966.20
Mark Ups Total:
$2,076.03
Total:
$27,429.03
Notes:
Approved By:
The Neenan Company
Date
Owner
Date
The Neenan Company LLLP
2607 Midpoint Drive,
Fort Collins, CO 80525
archistructions Tel: 970 493-8747 Fax: 970 493-5869
OWNER CHANGE ITEM DETAIL
Project #: 2761 A
Project Name: Fort Collins Senior Center
Project Address: 1200 Raintree Drive
Fort Collins, CO 80526
Status: APP
OCI Date: 03/26/2014
Owner CO #: OCO-005
Due to Owner:
Scope Desc: 90 modules on
a single inverter, 24.75kW, turn key system
$72,022 ($2.91m). Source:
$9088 savings.
11.2 % savings with a 3 % decrease in system size and power
output.
Final
Description
Quantity
Amount Vendor Name
Electrical Quote
1 @ $-9088
-$9,088.00
Paint and touch up
1 @ $400
$400.00
Roof Flashing at inverters
1 @ $500
$500.00
buyout savings from 88K
1 @ $-6890
-$6,890.00
Subtotal:
-$15,078.00
Final
Mark Ups
Quantity
Amount Vendor Name
Construction Contingency
-$452.34
Fee
-$660.04
Insur, Bond, Warranty
-$574.63
Mark Ups Total:
$1,687.01
Total:
-$16,765.01
Notes:
Approved By: ,
The Neenan Company
Date
Owner
Date
The Neenan Company LLLP
' ♦ ' 2607 Midpoint Drive,
Fon Collins, CO 80525
archistructions Tel: 970 493-8747 Fax: 970 493-5869
OWNER CHANGE ITEM DETAIL
Project #: 2761A
Project Name: Fort Collins Senior Center
Project Address: 1200 Raintree Drive
Fort Collins, CO 80526
Status: APP
OCI Date: 03/27/2014
Owner CO #: OCO-005
Due to Owner:
Scope Desc:
Source:
Final
Description
Quantity
Amount Vendor Name
Rubber flooring deduct
-$1,951.00
Subtotal:
-$1,951.00
Final
Mark Ups
Quantity
Amount Vendor Name
Construction Contingency
-$58.53
Fee
-$85.41
Insur, Bond, Warranty
-$74.36
Mark Ups Total:
-$218.30
Total:
-$2,169.30
Notes:
Approved By:
The Neenan Company Date
Owner Date
The Neenan Company LLLP
' 1 ' 2607 Midpoint Drive,
Fort Collins, CO 80525
archistructione Tel: 970 493-8747 Fax: 970 493-5869
OWNER CHANGE ITEM DETAIL
Project #:
2761A
Project Name:
Fort Collins Senior Center
Project Address:
1200 Raintree Drive
Fort Collins, CO 80526
Status: APP
OCI Date: 03/27/2014
Owner CO #: OCO-005
- Due to Owner:
Scope Desc:
Source:
Final
Description
Quantity
Amount Vendor Name
Seating reduction
-$2,090.96
Subtotal:
-$2,090.96
Final
Mark Ups
Quantity
Amount vendor Name
Construction Contingency
-$62.73
Fee
-$91.54
Insur, Bond, Warranty
-$79.69
Mark Ups Total:
$233.96
Total:
$2,324.92
Notes:
Approved By:
The Neenan Company Date
Owner Date
CHANGE ORDER NO. 05
PROJECT TITLE: Fort Collins Senior Center Expansion
CONTRACTOR: The Neenan Company LLLP
PROJECT NUMBER: 7440
DESCRIPTION: Add Phase III Parking Lot & Other Scope Items
Fort Collins
In preparing change orders show in order as separate numbered paragraphs the following:
Reason for change: Incorporate additional scope to the project.
2. Description of change?(
m
3. Change in contract cost:
Phase III Parking Lot, weather conditions, landscape allowance and other
4. Change in contract time: Add 15 days for parkinq lot expansion work - July 4, 2014
(Attach additional sheets as required)
ORIGINAL CONTRACT COST
$4,383,702.00
TOTAL APPROVED CHANGE ORDERS
$1,272,009.01
TOTAL PENDING CHANGE ORDERS
$0.00
TOTAL THIS CHANGE ORDER
$99,886.53
TOTAL % OF THIS CHANGE ORDER
2.28%
Total C.O. % of Original Contract
31.30%
ADJUSTED CONTRACT COST
$5,755,597.54
ACCEPTED BY:
ACCEPTED BY:
Project
REVIEWED BY:
APPROVED BY
APPROVED BY
La
Bob Adams - Recreation Department
If over $60,000 - Purchasing Director
cc: City Clerk Project File
Contractor Purchasing
Engineer
Date
Date
Date
6////--
Date
zt +`I
Dat
The Neenan Company LLLP
2607 Midpoint Drive,
Fort Collins, CO 80525
archistructione Tel: 970 493-8747 Fax: 970 493-5869
OWNER CHANGE ORDER
Project #: 2761A Change Order #: OCO-005
Project Name: Fort Collins Senior Center Contract: 2761A
Project Address: 1200 Raintree Drive Change Order Date: 04/04/2014
Fort Collins, CO 80526
Owner: City Of Fort Collins Title: Project adds and deducts
Address: P.O. Box 580
Fort Collins CO 80522
Attn: Brian Hergott
Tel: (970) 221-6804
Fax:
NEENAN and Owner previously entered into an Agreement for the above referenced project. NEENAN and Owner desire to issue a change order
for the Agreement as described below. As modified hereby, the Agreement remains in full force and effect and NEENAN and Owner ratify and
affirm the Agreement in all respects.
Description: 1. Add Phase 3 Parking area(exludes work associated with garden shed) Assumes April 15th Minor
Ammendment Approval, includes 15 day schedule extension for site only.
2. Increase landscape allowance as required per Ramirez Landscaping Bid
3. Add circuit to reception desk
4. Increase weather conditions allowance to match March cost summary
5. Change PV System Spec to SolarWorld Modules, decrease capacity to 24.75KW
6. Deduct for rubber flooring product spec changes (to be RB Rubber 3/8", Loose Laid)
7. Deduct for reduced fixed seating to allow for ADA clearances
Change Item
Change Item Description
Amount
OCI-042
Add Phase 3 parking, 6" unrienforced concrete (no slab or pad for shed)
$78,005.89
OCI-068
Increase Landscape allowance
$15,243.77
OCI-070
Add dedicated circuit, one quad outlet and one phone outlet box to greeting desk.
$467.07
OCI-071
Increase weather conditions allowance
$27,429.03
OCI-072
Change PV spec to Sun World Modules per Bella proposal, City to provide data line to
-$16,765.01
electrical room for BacNet Monitoring
OCI-074
Rubber Flooring Savings Due to Specification Change
-$2,169.30
OCI-076
Deduct for fixed seating reduction
-$2,324.92
Total:
$99,886.53
The Neenan Company LLLP
2607 Midpoint Drive,
Fort Collins, CO 80525
archistructions Tel: 970 493-8747 Fax: 970 493-5869
OWNER CHANGE ORDER
Project #: 2761A Change Order #: OCO-005
Project Name: Fort Collins Senior Center Contract: 2761A
Project Address: 1200 Raintree Drive Change Order Date: 04/04/2014
Fort Collins, CO 80526
The Original Contract Price was..............................................................................................................
$4,383,702.00
Net Change by Previously Authorized Requests and Changes.....................................................................
$1,272,009.01
The Contract Price Prior to This Change Order was..................................................................................
$5,655,711.01
The Contract Price will be Increased By................................................................................................
$99,886.53
The New Contract Price Including This Change Order will be.......................................................................
$5,755,597.54
The Contract Time Will Be Changed By............................................................................................
15 days
The Scheduled Substantial Completion Date as of this Change Order therefore is ...........................................
Site Only 07/04114
ACCEPTED:
The Neenan Company LLLP
By:
Its:
Signed:
By:
Its:
Date:
Neenan Management Company
General Partner
Randolph P. Myers
President & CEO
City Of Fort Collins
By:
Date:
The Neenan Company LLLP
♦ ' 2607 Midpoint Drive,
Fort Collins, CO 80525
archistructions Tel: 970 493-8747 Fax: 970 493-5869
OWNER CHANGE ITEM DETAIL
Project #: 2761 A _
Project Name: Fort Collins Senior Center
Project Address: 1200 Raintree Drive
Fort Collins, CO 80526
OCI-042 Add�P�king, 6" unrienforced concrete{no slab or pad'for shed)
Status: APP OCI Date: 12/31/2013
Owner CO #: OCO-005 Due to Owner: 02/01/2013
Scope Desc: Paving, pervious paving and storm systems, curb 8 gutter, landscaping, parking Source:
lights,
Pricing does not include relocation of shed, or concrete pad for sheds.
Schedule extension is for site work only.
Final
Description Quantity Amount Vendor Name
6" unrienforced concrete paving
7853 @ $3.2
$25,129.60
Barrier Curb
97@$12
$1,164.00
Boulders
1 @ $1600
$1,600.00
Caulking
690 @ $2.8
$1,932.00
Curb in
285 @ $16
$4,560.00
Curb out
317 @ $14
$4,438.00
Electrical
1 @ $900
$900.00
Exterior Signage
12 @ $190
$2,280.00
Fine Grade
7853 @ $.15
$1,177.95
Grading
-1 @ $1273.64
41,273.64
Landscape Allowance
1 @ $6500
$6,500.00
PM/Vehicle
17HR @ $103.5
$1,759.50
Pervious Paving
1650 @ $6.5
$10,725.00
Pole bases
1 @ $525
$525.00
Project coordinator
8HR @ $45
$360.00
Seed Deduct
-10700 @ $.32
-$3,424.00
Site CoordinatorNehicle
88HR @ $93.5
$8,228.00
Storm Allowance (rip rap/fabric)
1 @ $2500
$2,500.00
Striping
1 @ $275
$275.00
Surveyor
1 @ $800
$800.00
The Neenan Company LLLP
' ♦ ' 2607 Midpoint Drive,
Fort Collins, CO 80525
archistructione Tel: 970493-8747 Fax: 970493-5869
OWNER CHANGE ITEM DETAIL
Status:
APP
OCI Date: 12/31/2013
Owner CO #:
OCO-005
Due to Owner: 02/01/2013
Scope Desc:
Paving, pervious paving and stone systems, curb & gutter, landscaping, parking
Source:
lights,
Pricing does not include relocation of shed, or concrete pad for sheds.
Schedule extension is for site work only.
Subtotal: $70,156.41
Final
Mark Ups Quantity Amount Vendor Name
Construction Contingency $2,104.70
Fee $3,071.09
Insur, Bond, Warranty $2,673.69
Mark Ups Total: $7,849.48
Notes: 25-FEB-14 - Pricing pending completion of design
Approved By:
The Neenan Company
Owner
Date
Date
Total: $78,005.89
The Neenan Company LLLP
' ♦ I 2607 Midpoint Drive,
Fort Collins, CO 80525
archistruction3 Tel: 970 493-8747 Fax: 970 493-5869
OWNER CHANGE ITEM DETAIL
Project #: 2761A
Project Name: Fort Collins Senior Center
Project Address: 1200 Raintree Drive
Fort Collins, CO 80526
Status: APP
OCI Date: 03/10/2014
Owner CO M OCO-005
Due to Owner:
Scope Desc: 1. No maintenance contract, all maintenance to be provided by City ($18,000 Source:
value)
2. Rock mulch to be furnished and delivered by the City, installed
by Landscape
Subcontractor
3. No Netafm test area included
4. Reuse existing clock, add small new clock, as show on
drawings
Final
Description Quantity
Amount Vendor Name
Allowance - Retaining Walls
$3,875.00
Landscape Allowance
$16,715.00
TNC Contingency Transfer
-$12,000.00
Temp irrigation -
$5,500.00
Subtotal:
$14,090.00
Final
Mark Ups Quantity
Amount Vendor Name
Fee
$616.79
Insur, Bond, Warranty
$536.98
Mark Ups Total:
$1,153.77
Total:
$15,243.77
Notes:
The Neenan Company LLLP
' 1 I 2607 Midpoint Drive,
Fort Collins, CO 80525
archistruction® Tel: 970 493-8747 Fax: 970 493-5869
OWNER CHANGE ITEM DETAIL
Status: APP OCI Date:
Owner CO #: OCO-005 Due to Owner:
Scope Desc: 1. No maintenance contract, all maintenance to be provided by City ($18,000 Source:
value) W"F' iT S Ak 14fpLe5
2. Rock mulch to be furnished and delivered by the City, installed by Landscape
Subcontractor
3. No Netaliim test area included
4. Reuse existing clock, add small new clock, as show on drawings
Approved By:
The Neenan Company Date
Owner Date
03/10/2014
The Neenan Company LLLP
1 ♦ ' 2607 Midpoint Drive,
Fort Collins, CO 80525
archistructione Tel: 970 493-8747 Fax: 970 493-5869
OWNER CHANGE ITEM DETAIL
Project #:
2761 A
Project Name:
Fort Collins Senior Center
Project Address:
1200 Raintree Drive
Fort Collins, CO 80526
Status: APP
OCI Date: 03/19/2014
Owner CO #: OCO-005
Due to Owner: 03/26/2014
Scope Desc:
Source:
Final
Description
Quantity
Amount Vendor Name
Add dedicated circuit, one quad outlet and one phone
$395.00 Merit Electric Inc.
outlet box to greeting desk.
Subtotal:
$395.00
Final
Mark Ups
Quantity
Amount Vendor Name
Construction Contingency
$11.85
Design Fee
$27.87
Fee
$17.29
Insur, Bond, Warranty
$15.06
Mark Ups Total:
$72.07
Total:
$467.07
Notes:
Approved By:
The Neenan Company Date
Owner Date