POUDRE TRAIL AT MULBERRY & LEMAY
Federal Aid Project No. STE M455-105
City of Fort Collins Bid No. 7585
PRE-BID CONFERENCE
December 19, 2013
10:00 AM
215 N. Mason Street
Training Room 2E
City of Fort Collins
Park Planning & Development
22
INTRODUCTIONS
• Park Planning & Development:
• Jason Stutzman, P.E. – Project Manager (970) 222-1708
• Engineering:
• Randy Maizland – Project Engineer (970) 218-5658
• Joe Crabill - Construction Inspector (970) 222-1134
• Purchasing:
• John Stephen - Purchasing Agent (970) 221-6777
• Consultant Engineer:
• Interwest Consulting, Skylar Brower – civil design (970) 460-1091
• San Engineering, John J. Migliaccio, PE - structures (303) 503-2593
2
33
ATTENDANCE
• Please be sure to register
• BID OPENING
• When: Monday, January 6, 2014 @ 3:00 P.M.
• Where: 215 North Mason Street (2nd
Floor)
44
VICINITY MAP
3
55
IMPORTANT CONTRACT DATES:
• AWARD CONTRACT
• Approximately January 13, 2014
• PRE-CONSTRUCTION MEETING
• Mandatory Meeting Prior to Start of Construction
• Date to be determined after contract is awarded
• CONSTRUCTION START DATE – Phase 1 work only
• Approximately March 3, 2014 – Phase 1 work ONLY
• Approximately September 1, 2014 – Phase 2 work
• MILESTONE DATE for Phase 1 – Section 520
• SUBTANTIAL COMPLETION
• 270 total calendar days for the project
• FINAL COMPLETION
• 30 Calendar days after Substantial
66
CDOT Local Agency Project
UDBE goal for this project is 0%
Bid proposal must include:
• CDOT 606 Anti-Collusion Affidavit
• CDOT 714 UDBE Assurance
Bids will not be accepted if they do not have these forms
• Fuel Cost Adjustment option
Apparent successful bidder to receive:
• Form 605, Form 621, Form 715, and Form 718
• These forms must be returned by 4:30 pm the following day
(currently Jan 7, 2014)
Monthly payments will not be processed until all documentation
required by CDOT for federally funded projects has been
submitted to the City.
4
77
SUMMARY OF WORK
POUDRE TRAIL AT MULBERRY & LEMAY:
• Clearing and Grubbing
• Removal of Tree
• Removal of Manhole, Pipe, End Section
• Removal of Concrete, Asphalt Mat, Riprap
• Unclassified Excavation
• Borrow (Complete in Place)
• Structure Excavation & Backfill (Class I)
• Topsoil (Remove, Stockpile, Redistribute)
• Erosion Log (12 Inch), Erosion Control Supervisor
• Concrete Washout Structure, Vehicle Tracking Pad
88
SUMMARY OF WORK
POUDRE TRAIL AT MULBERRY & LEMAY: (cont.)
• Reset Structure (Existing 165' Bridge - at Lemay)
• Unload Structure (Existing 165' Bridge - at alt. site)
• Unload Structure (Existing Steel Railing - at alt. site)
• Dewatering
• Seeding (Native), Mulching (Weed Free Hay)
• Aggregate Base Course (Class 5)
• Drilled Caisson (24 inch), (54 inch)
• Repurposed Riprap
• Pedestrian Railing (Steel)
• Concrete Class D
• Reinforcing Steel, Reinforcing Steel (Epoxy Coated)
5
99
SUMMARY OF WORK
POUDRE TRAIL AT MULBERRY & LEMAY: (cont.)
• 24 Inch Reinforce Concrete Pipe, End Section
• 12 Inch Plastic Pipe
• Manhole Slab Base (5 Foot)
• Concrete Sidewalk (6 Inch), Concrete Bikeway (5 Inch), Concrete
Bikeway (Special)
• Construction Surveying
• Structure Temporary Access Road
• Mobilization
• Bridge Girder and Deck Unit - 100'
• Traffic Control
• Flagging, Traffic Control Inspections
• Traffic Control Management - Working Days
1010
Poudre Trail at Mulberry & Lemay
6
1111
PROJECT OVERVIEW
PHASING
• MILESTONE DATE for Phase 1 – Section 520
• All Phase 1 work must be completed and accepted by ENGINEER on or before
April 30, 2014.
• Subject to Liquidated Damages of $1,400 per calendar day
• Phase 2 Work – Section 520
• Phase 2 and all remaining work will ONLY commence upon delivery of the
existing 165’ bridge to the project site, unless approved otherwise in writing
by the ENGINEER.
1212
PROJECT OVERVIEW
• Coordination with utilities and others
– PRPA pole relocation work – T.B.D.
– CDOT bridge replacement project
– Contractor will need to coordinate with any utilities that may be
in the work area.
• Contractor responsible to acquire all appropriate permits and submit
required documentation
• City Flood Plain Use Permit – Provided by Owner, transferred to
Contractor
• Erosion Control
• CDOT Form 205 for each subcontractor
• TCS Diaries, Payrolls etc…
7
1313
HIGHLIGHTS FROM GENERAL CONDITIONS AND
GENERAL REQ’S:
• PROJECT MEETINGS:
• Once a week. Location and time to be determined.
• Agree to weekly quantities
• PROGRESS AND SCHEDULE REVISIONS:
• Prior to construction, initial schedule must be submitted and
approved
• Schedules shall be updated weekly
• The Contractor may be required to submit additional schedules
depending on the progress of the project.
1414
HIGHLIGHTS FROM GENERAL CONDITIONS AND
GENERAL REQ’S:
• Construction Tolerances - Line, Grade and Elevation
The completed project work is subject to FEMA review and acceptance.
All work must be completed to tolerances identified in section 625.
Tolerances must be validated by a Colorado Licensed Professional Land
Surveyor to the ENGINEER’s satisfaction prior to acceptance.
• Record Drawings Plan Set
Contractor will be required to keep and submit record drawings
Contractor must provide a stamped as-built survey, from a CO.
licensed surveyor for approval.
8
1515
Highlights from Specifications
1616
Section 202 Removals
202-00400 Removal of Existing
Bridge
• 9 Trees
• 1 Manhole
• 37 LF of RCP Pipe and 1 FES
• Concrete and asphalt pavement –
Existing trails
• 67 CY Rip-Rap
9
1717
206-Structure Excavation – 449 CY
o Established, plan quantity. Payment will be plan quantity. Any
removals beyond plan limits by contractor will not be paid by
the City unless approved prior to work.
206 Unclassified Excavation
263 CY – Plan quantity Paid
EARTHWORK
1818
SECTION 208 – Erosion Control
Less than an acre of disturbance. No SWMP plan required by the State
however, the contractor is responsible for installation of erosion
control BMP’s as described on the Erosion Control Plan sheets. All
Floodplain Use Permit Restrictions and requirements must be
followed.
Pay Items
– Erosion control logs
– Concrete washout
– Tracking pad
– Erosion control supervisor
10
1919
Phase I – Truck Ramp and Crane
Runway
See Project Specials – Section
621
2020
Phase I – Bridge Foundations
• Bridge Abutments
• Center pier
construction.
• See Phase I
milestone
specifications.
Liquidated damages
$1,400 per day
11
2121
PHASE II
Notice To Proceed Approximately Early September
• Clean up project site
• Install safety fencing
• Maintain traffic control devices
• Maintain erosion control devices
• Coordinate with CDOT on delivery of 165 foot bridge
2222
PHASE II – Setting Bridges
• Take delivery of existing re-purposed 165 foot bridge span
(delivered in two sections) from CDOT Mulberry bridge project
(Approx. late October). City and contractor to inspect and then
contractor takes responsibility.
• Set new fabricated 100 foot bridge span.
• All connection hardware will be inspected. Contractor will need
to supply new elastomeric bearing pads for repurposed bridge.
12
2323
PHASE II – Trail Construction
5 Inch Concrete Trail on 12
Inch Reconditioned Subgrade
5 Inch Concrete Trail on Class I
Compacted Fill
608 – Total of 1,849 SY of concrete
sidewalk and trail construction
2424
SECTION 603/604 – Storm Sewer
• 55 LF – 24 Inch RCP
• 1 EA – FES
• 5 CY – Repurposed Riprap
• 26 LF – 12 Inch SDR 35
• 1 EA – 5 Foot Manhole
13
2525
SECTION 630 – Traffic Control
• Lump Sum traffic
control devices &
setup
•TCM & TCI
• Flagging – Hourly as
approved by the
project engineer or
inspector