Change Order Form
PROJECT TITLE: River Restoration at Woodward Technology Center Lot 4
BID NUMBER: 7579
CONTRACTOR: Walsh Construction Inc.
CHANGE ORDER NUMBER: 1
In preparing change orders show in order as separate numbered paragraphs the toFlo—wing
1. Reason for change. 2. Description of change.
3. Change in contract cost. 4. Change in contract time.
1 &2. See attached sheet for detail. Additional contact time for Bid Alt#1 Poudre trail completion (open the public) date: March 15
3. The contract cost will not be effected.
Extension of Nine (9) days from March 15 to March 24.
ORIGINAL CONTRACT COST
$1.994.383. 00
TOTAL APPROVED CHANGE ORDERS
$0,00
TOTAL PENDING CHANGE ORDERS
$0.00
TOTAL THIS CHANGE ORDER
$0.00
TOTAL % OF THIS CHANGE ORDER
0.00%
TOTAL C.O. % OF ORIGINAL CONTRACT
0.00%
ADJUSTED CONTRACT COST
$1,994,303.00
(Assuming all change orders approved)
ACCEPTED BY: DATE: 30-1A
IWDIs1%
onstruction, Inc`.7' Imo%
APPROVED BY: 'C � DATE: 3 l $1
(City of Ft. Collins)
APPROVED BY: DATE:
(Purchasing Agent over $50,000)
ca. Contractor
Purchasing
Project File
Wm.T. Welch Company, LLC
a Colorado limited liability company
1315 Oakridge Drive, Suite 100
Fort Collins, CO 80525
Tel: 970/646-2064
March 20, 2014
Mr, Rick Bachand
City of Fort Collins Natural Areas
1745 Hoffman Mill Road
PO Box 580
Fort Collins CO 80522
Project
Management
WTWFor
Structures A
Infrastructure
RE: River Restoration at Woodward Technology Center Lot 4 Bid # 7579
Change Order #1
Dear Mr, Bachand,
Due to unusually severe weather condition we are recommending an extension of the completion date
for.
Bid Alternate Item #1 Poudre trail completion (open the public) date: March 15, 2014 including
adjustments to traffic control duration, temporary construction fence placement/relocation.
Since being given notice to proceed Walsh Construction has worked diligently to meet the goals of this
project including working through poor weather and inefficient site conditions caused by weather.
They have also work in cooperation with the City to resolve issues outside of their control reducing
delays to the project. The following are days lost to adverse weather:
Date
Low
High
1/27/14
15
15
1/28/14
0
20
1/29/14
10
40
1/31/14
20
20
2/1/14
20
25
2/2/14
0
20
2/3/14
5
30
2/5/14
-10
0
2/6/14
-10
0
Reason for Loss Time
Snow
Snow
Snow
Snow
Snow
Snow
Snow
Cold
Cold
Based on this analysis we are recommending the date for completion and opening of the Poudre Trail
be extended Nine (9) days from March 15 to March 24.
No change in contract value is recommended.
Sincerely,,
Erich Purcell
Project Manager
XC: file
John Stokes
John Steven