ADDENDUM NO. 1
SPECIFICATIONS AND CONTRACT DOCUMENTS
Description of BID 7568: Bryan Avenue Bridge Replacement
OPENING DATE: 3:00 PM (Our Clock) November 12, 2013
To all prospective bidders under the specifications and contract documents described
above, the following changes/additions are hereby made and detailed in the following
sections of this addendum:
Exhibit 1 – Revised Bid Schedule
Exhibit 2 – Clarifications & Revisions
Please contact John Stephen, CPPO, LEED AP, Senior Buyer at (970) 221-6777 with
any questions regarding this addendum.
RECEIPT OF THIS ADDENDUM MUST BE ACKNOWLEDGED BY A WRITTEN
STATEMENT ENCLOSED WITH THE BID/QUOTE STATING THAT THIS
ADDENDUM HAS BEEN RECEIVED.
Financial Services
Purchasing Division
215 N. Mason St. 2nd Floor
PO Box 580
Fort Collins, CO 80522
970.221.6775
970.221.6707
fcgov.com/purchasing
Addendum 1 – 7568 Bryan Ave Bridge Replacement Page 2 of 6
EXHIBIT 1 – REVISED BID SCHEDULE
ITEM NO. DESCRIPTION UNIT QUANTITY UNIT COST TOTAL
201-00000 CLEARING AND GRUBBING L S 1 $ -
202-00010 REMOVAL OF TREE EACH 2 $ -
202-00019 REMOVAL OF INLET EACH 1 $ -
202-00019 REMOVAL OF PIPE LF 50 $ -
202-00200 REMOVAL OF SIDEWALK SY 87 $ -
202-00203 REMOVAL OF CURB AND GUTTER LF 67 $ -
202-00210 REMOVAL OF CONCRETE PAVEMENT SY 45 $ -
202-00220 REMOVAL OF ASPHALT MAT SY 356 $ -
202-00705 REMOVAL OF LIGHT STANDARD EA 1 $ -
202-01000 REMOVAL OF FENCE LF 28 $ -
202-04000 REMOVAL OF EXISTING BRIDGE LS 1 $ -
203-00100 MUCK EXCAVATION CY 173 $ -
206-00000 STRUCTURE EXCAVATION CY 491 $ -
206-00065 STRUCTURE BACKFILL (FLOWFILL) CY 46 $ -
206-00100 STRUCTURE BACKFILL (CLASS 1) CY 298 $ -
206-01750 SHORING (AREA 1) L S 1 $ -
208-00005 EROSION LOG (12 INCH) LF 165 $ -
208-00034 GRAVEL BAG LF 40 $ -
208-00045 CONCRETE WASHOUT STRUCTURE EACH 1 $ -
208-00050 STORM DRAIN INLET PROTECTION EACH 2
208-00070 VEHICLE TRACKING PAD EACH 1 $ -
208-00103 REMOVAL AND DISPOSAL OF SEDIMENT (LABOR) HR 40
208-00106 SWEEPING (SEDIMENT REMOVAL) HR 5
208-00107 REMOVAL OF TRASH HR 5
208-00205 EROSION CONTROL SUPERVISOR HR 120 $ -
211-03005 DEWATERING LS 1
212-00005 SEEDING (NATIVE) ACRE 0.02 $ -
212-00032 SOIL CONDITIONING ACRE 0.5 $ -
212-00100 TREE RETENTION AND PROTECTION LS 1 $ -
213-00002 MULCHING (WEED FREE HAY) ACRE 0.02 $ -
216-00041 SOIL RETENTION BLANKET (STRAW/COCONUT) SY 444 $ -
Addendum 1 – 7568 Bryan Ave Bridge Replacement Page 3 of 6
304-06000 AGGREGATE BASE COURSE (CLASS 6) TON 72 $ -
403-32721 HOT MIX ASPHALT (GRADING SG) (75) (PG 58-28) TON 40 $ -
403-33721 HOT MIX ASPHALT (GRADING S) (75) (PG 58-28) TON 42 $ -
406-00700 TEMPORARY PAVEMENT SY 285 $ -
412-00800 CONCRETE PAVEMENT (8-INCH) SY 100 $ -
420-00507 GEOTEXTILE PAVING FABRIC SY 75 $ -
506-00000 RIP RAP CY 38 $ -
509-70000 STAINLESS STEEL ANGLE (SPECIAL) LF 228 $ -
514-00100 HAND RAIL LF 6 $ -
514-00200 PEDESTRIAN RAILING (STEEL) LF 38 $ -
514-01020 PEDESTRIAN RAILING (TIMBER) LF 58 $ -
601-03030 CONCRETE CLASS D (BOX CULVERT) CY 50 $ -
601-03050 CONCRETE CLASS D (WALL) CY 114 $ -
601-40008 MOSS ROCK VENEER SF 1,200 $ -
601-40009 MOSS ROCK CAP LF 94 $ -
601-40400 STRUCTURAL CONCRETE STAIN SY 369 $ -
602-00020 REINFORCING STEEL (EPOXY COATED) LB 34,061 $ -
603-50008 8 INCH PVC PIPE (SDR 35) LF 39 $ -
603-72020 25 X 7.33 FOOT CONCRETE 3-SIDED CULVERT (PRECAST) LF 39 $ -
603-72021 26 X 7.33 FOOT CONCRETE 3-SIDED CULVERT TOP SLAB (PRECAST) LF 39
604-19800 CONCRETE CATCH BASIN (2 FOOT X 2 FOOT) EA 2 $ -
604-19801 INLET FRAME AND GRATE (24 INCHES) EA 2 $ -
608-00006 CONCRETE SIDEWALK (6 INCH) SY 207 $ -
608-00300 COLOR STAINING AND SEALING (SPECIAL) SY 56 $ -
613-00105 1 INCH ELECTRICAL CONDUIT LF 20 $ -
613-00300 3 INCH ELECTRICAL CONDUIT LF 555 $ -
613-01050 1/2 INCH ELECTRICAL CONDUIT (PLASTIC) LF 36 $ -
613-01100 1 INCH ELECTRICAL CONDUIT (PLASTIC) LF 200 $ -
613-10000 WIRING LS 1 $ -
613-13000 LUMINAIRE (LED) EA 4 $ -
613-34140 LIGHT STANDARD METAL (14 FOOT) EA 4 $ -
613-50010 PHOTOELECTRIC CELL EA 1 $ -
620-00020 SANITARY FACILITY EA 1 $ -
626-00005 MOBILIZATION L S 1 $ -
Addendum 1 – 7568 Bryan Ave Bridge Replacement Page 4 of 6
630-00000 FLAGGING HOUR 260 $ -
630-00007 TRAFFIC CONTROL INSPECTION DAY 51 $ -
630-00012 TRAFFIC CONTROL MANAGEMENT DAY 145 $ -
630-70000 CONSTRUCTION ZONE TRAFFIC CONTROL LS 1 $ -
630-80359 PORTABLE MESSAGE SIGN PANEL DAY 84 $ -
TOTAL BID (FOR PERFORMANCE AND PAYMENT BONDS, AND UDBE GOALS) $ -
700-70010 F/A MINOR CONTRACT REVISIONS FA 1 $80,000.00 $ 80,000.00
700-70011 F/A PARTNERING FA 1 $2,500.00 $ 2,500.00
700-70016 F/A FUEL COST ADJUSTMENT FA 1 $3,000.00 $ 3,000.00
700-70019 F/A ASPHALT CEMENT COST ADJUSTMENT FA 1 $5,000.00 $ 5,000.00
TOTAL ADDITIONAL COSTS $ 90,500.00
TOTAL BASE BID
TOTAL BASE BID IN WORDS (CONTRACT VALUE):
ADDITIONAL COSTS
Addendum 1 – 7568 Bryan Ave Bridge Replacement Page 5 of 6
EXHIBIT B – CLARIFICATIONS & REVISIONS
I. Project and Bidding Clarifications
A. Remove the term “(Arthurs Ditch)” from Bid Item 201-00000 Clearing and
Grubbing. This bridge replacement occurs on the Larimer No. 2 Canal.
B. Temporary paving during cold weather months has been specified as
being recycled asphalt base in Bid Item 406-00700. Contractor may use
HMA, WMA or other APPROVED equal material at no additional cost to
the City. Contractor is responsible for maintaining temporary pavement as
directed by the project engineer in a manner that provides adequate
protection on the bridge deck and a reasonable driving surface.
C. Revision to Section 105 HMA Pavement Smoothness does NOT apply to
this project. There will be no HRI Category II smoothness requirements.
However, all LCUASS asphalt patching standards will be applicable.
D. Eliminate the plan note on Sheet 10 of the plans indicating a waterproofing
membrane on top of the bridge deck. No waterproofing membrane is
required. However, joint wrapping is required and included in the precast
box culvert specifications and shown in the detail on Sheet 16 of the
plans.
E. The City will provide all construction surveying for the project including
confirmation of final grades as required by Note 25 on Sheet 27 of the
plans.
F. The Larimer Canal No. 2 ditch has historically been turned back on for
service no sooner than April 15th. However, it is the contractors
responsibility to coordinate with the Larimer Canal No. 2 ditch company
regarding any conflicts in the construction schedule.
G. Because the entire existing bridge is to be demolished under full road
closure, no stamped, engineered demolition plan is required for removal of
the existing bridge.
H. Dewatering – Bid Item 211-03005. The intent of this bid item is for
dewatering of storm water runoff and nuisance flows. However, the
specification for dewatering does include measures for treatment and or
disposal if necessary but not expected. No additional payment for
dewatering will be provided so please bid accordingly.
I. The City will coordinate and pay for all materials testing required for the
project.
J. Bid Item 630-70000 – Construction Zone Traffic Control. All construction
traffic control devices are inclusive in the Lump Sum bid. A list of devices
has been provided on Sheet 26 of the Plans FOR INFORMATION ONLY.
Additional devices may be needed and the bid should include temporary
barriers as shown on Sheet 15 of the Plans and Phase 2 Notes
(Construction Phasing Plan) that will be required for safety during
Addendum 1 – 7568 Bryan Ave Bridge Replacement Page 6 of 6
construction. No additional payment will be made for setting, adjusting or
relocating barriers to facilitate construction phasing under this Lump Sum
pay item.
K. Bid Item 630-70000 – Construction Zone Traffic Control. Traffic control
management, inspections and flagging are NOT included in the
Construction Zone Traffic Control lump sum bid item as written in the
specifications. TCM, TCI and Flagging will be measured and paid
separately by line items provided in the bid form.
L. All removals of concrete and pavement on the slopes of the canal shall be
included and paid for by the lump sum bid for removal of the existing
bridge. No additional payment will be made for removal of concrete and
ditch slope paving.
II. Revisions to the Plans/Bid Tab:
A. The City is beginning to transition from the use of PG 58-28 asphalt binder
to PG 64-22 or the asphalt binder. The two asphalt line items have been
adjusted to the following:
Hot Mix Asphalt (Grading S)(75)(PG 64-22)
Hot Mix Asphalt (Grading SG)(75)(PG 64-22)
Quantities for the above have not changed.
B. A new line item has been added to the project under section 202-04000:
Removal of Existing Bridge 1 LS
This line item was inadvertently left out of the bid schedule. Project special
specifications are provided.
III. Revisions to the Project Contract Documents:
A. The following has been added to Section 00520 AGREEMENT
Article 3.3.2(3) – A full road closure for demolition of the existing
bridge structure and resetting of the new precast bridge structure is
limited to no more than 21 Days. Liquidated Damages in the
amount of $2,000 per day will be assessed beyond the 21 Days.
The contractor is required to re-open the road to a single travel lane
northbound into the park at least 12 feet wide no more than 21 days
after full road closure and the single travel lane must remain in
place until substantial completion is met at which time Bryan
Avenue shall be re-opened to traffic in both directions. The 21 day
time count will begin when the road is fully closed for removals and
demolition.