HomeMy WebLinkAboutCHANGE ORDER - RFP - 7507 APP SENIOR CENTER EXPANSIONCHANGE ORDER NO. 1
PROJECT TITLE: Senior Center Project "
CONTRACTOR: Ken Bernstein
PROJECT NUMBER:
PURCHASE ORDER NO.: 9136547
DESCRIPTION: APP Design Contract ā Senior Center Project
1. Reason for change: The artist needs additional time to design the gate which is connected to
the art element (bench) for this project. This is for design only. The City of Fort Collins will
contract to engineer, fabricate and install with other contractors.
2. Description of Change: Additional money will be added to the APP Design Contract
3. Change in Contract Cost: This change will add $500 to the contract.
4. Change in Contract Time: This will extend the Final Design for the Gate to January 31, 2014
ORIGINAL CONTRACT COST $4,000
TOTAL APPROVED CHANGE ORDERS
TOTAL PENDING CHANGE ORDERS
TOTAL THIS CHANGE ORDER $500
TOTAL % OF ORIGINAL CONTRACT, THIS C.O.: %
TOTAL % OF ORIGINAL CONTRACT, ALL C.O.'S: %
ADJUSTED CONTRACT COST $4,500
(Assuming all change orders approved)