DESCRIPTION:
Repair of ESD Damaged Curb - BRT Guideway (CEI contra
1. Reason for change:
This change order deducts the value of curb and pavement repair caused by ESD during construction of the
South Transit Center.
2. Description of Change:
ESD, a subcontractor of Growling Bears, accessed the BRT guideway off the South Transit Center site as
they were also working on the Harmony Wal-Mart expansion. When driving over the curb to access the Wal
Mart site, their equipment damaged both concrete curb and paving. Growling Bear refused to repair this
damage. As such, the City requested CEI repair the curb and pavement. The cost for this repair which
should have been borne by ESD and Growling Bear is contained in this change order.
3. Change in Contract Cost:
4. Change in Contract Time: 0 calendar days for substantial completion
0 Icalendar days for final completion
TOTAL APPROVED CHANGE ORDERS
TOTAL PENDING CHANGE ORDERS
TOTAL THIS CHANGE ORDER
TOTAL % OF ORIGINAL CONTRACT, THIS C.O.
TOTAL % OF ORIGINAL CONTRACT, ALL C.O.'S
ADJUSTED CONTRACT COST $4,439,509.74
(Assuming all change orders approved)
ACCEPTED BY:
Contractor's
REVIEW EC
Constructioi
APPROVE[
City Project
APPROVE[
fty y- City Engineer
APPROVED BY:
Purchasing Agent over $60,000
cc: City Clerk Architect
Contractor Engineer
Project File Purchasing
DATE:
DATE: //_ ZZ- a
DATE I(-n - (-�
DATE: /1 -2S-)3
DATE:
maA
November 22, 2013
Ms. Erika Keeton, PE
MAX Project Manager
City of Fort Collins — Engineering Dept
281 N. College Ave.
Fort Collins, CO 80524
RE: South Transit Center
Independent Cost Analysis — Change Order 09
ESD Damaged Curb
MAX Field Construction Office
3000 South College Ave., Suite 201
Fort Collins, CO 80526
fcgov.com/maxconstruction
Delivery by hand
Growling Bear Inc. (GBI) employed a subcontractor named Elevated Structural Decks (ESD) on the South
Transit Center project. During the course of construction (February 2013), ESD traversed the BRT
Guideway job site to access the Wal-Mart site near Harmony and College. They were working on both
job sites simultaneously for different general contractors. When crossing the curb and paving along the
BRT guideway, they damaged the concrete (see attached photos). GBI and ESD refused to repair the
concrete after numerous City requests. As such, the City directed Concrete Express Inc. (CEI) to repair
the curb and pavement. The cost to repair this concrete is attached.
In reviewing the cost for this work, it was based on actual field quantities and BRT contract unit prices.
As such, the cost is verifiable. The cost was determined to be $1,521.90 as outlined in the cost proposal
from CEI.
I recommend a reduction in payment to GBI in the amount shown above based on the costs identified in
the attached CEI change request.
Keith Meyer,
Construction Project Manager
CH2M HILL Team
970-988-8605
keith.mever(a)ditescoseryices.com
Cc: job file
Change Management Checklist
Compliance Category
Date
Reviewed
Reference
Initials
Reviewed for compliance with
11/22/13
Part of the build alternative to
KM
Environmental Assessment
SCC 10.02
Reviewed for construction/safety impacts
2/11/13
Included in traffic control plan for
KM
work in area
Independent cost estimate prepared
11/22/13
As attached to this memo
KM
Reviewed for PCGA grant compliance
11/22/13
Part of Build Alternative
KM
scope is included in SCC 10.02
Reviewed for real estate impacts/needs
2/6/13
Construction inside City
KM
easements for guideway
Reviewed for compliance with design
criteria/ADA
htto://w .access-board.aov/ada-aba/ada-
8/26/13
n/a
KM
standards-dot.cfm
V�
�� s ,L � � cE 7. .� vim"• ' ^ , '. y'.�'�;'q
�i�`t;r,- e ~,Rti�M ` 02/OQ/2a0i11E31 1 l�' DE
ditesco
Date of Estimate: 11/15/2013
Contract Type: Mason Corridor BRT (Hard Bid)
Existing Contract or PO (Y/N): Y
Independent Cost Estimate
Description of Goods (A) or Services (B): A
Scope is to address curb repair damaged by ESD/Growling Bear on MAX BRT contract.
I have obtained the following estimate from;
Published Price List / Past Pricing (date)ICEI Base Bid Unit Prices (MAX-BRT Contract) and Engineer's estimate
Engineering or Technical Estimate (performed by)
Independent Third Party Estimate (performed by)
Other (specify)
Cost Estimate Details:
(Estimate calculated in US Dollars)
Cost of Standard Items
DESCRIPTION
ITEM#
NOTE
QUANTITY
UNIT
UNIT PRICE
TOTAL
Remove curb and gutter
202-00203
Contract
23
LF
4.50
103.50
Curb and gutter Type llB
609-21020
Contract
23
LF
$ 12.90
$ 296.70
Winter protection
-
1
LS
$ 150.00
$ 150.00
Epoxy Rebar Dowels
-
87
LB
$ 4.00
$ 348.00
Traffic control
-
1
LS
$ 250.00
$ 250.00
Concrete pavement extra thickness
oncurb
-
0.65
CY
$ 95.00
$ 61.75
Net Total
$ 1,209.95
Cost of Services, Repairs, or Non -Standard Items
Item/Task:
Materials or Work Description Other Direct
Costs
Lab—or—l—Labor Labor
Rate($) Hours Class
Allocated
Overhead
SG&A' I Profit
I TOTAL
Total
I
is
/f� 'Sefnp. General aM MeiNso-ative Eryenses
Signature of Preparer: •(,I/(�y
ma)t WORK CHANGE DIRECTIVE
TO CONTRACTOR: Concrete Express Inc. (CEI) WCD NO: 101
PROJECT: Mason Corridor — MAX BRT
OWNER: City of Fort Collins — Engineering Department
ENGINEER: Michael Baker Inc.
PROJECT NO: 7332
The following additions, deletions, or revisions to the Work have been ordered and authorized:
(Title of WCD): Guideway Curb and Pavement Repair
This work change directive directs the Contractor to replace damaged curb and guideway paving
south of Harmony Road. This curb was damaged by ESD (a subcontractor to Growling Bear) when
working at the South Transit Center Site. ESD was also working at the Wal-Mart site south of
Harmony when the damage occured. Their crews transported equipment and materials between
Wal-Mart and the STC site along the guideway. During this work, they damaged a section of curb
and paving.
The work shall include supplying equipment, labor and materials to perform the work according to
the MAX BRT project specifications, attached drawings and approved submittals. This work shall be
tracked as time and material and applicable unit prices for the repair.
This change is being initiated by the City as Growling Bear refuses to pay for the damaged
curb/pavement. The City will pay CEI for the repair and withhold the equal cost from Growling
Bear's pay application.
Attachments (List Supporting Documents):
None
It is understood that this Work Change Directive may change the Contract Price and/or Time, and is evidence that the
parties expect a Change Order request for approval to subsequently follow this Work Change Directive.
Ordered By: February 13, 2013
caner Date
Recommended By: �` A/L_ February 13, 2013
Construction MInager Date
Copy: Owner; Engineer; Field File - SharePoint
W CD101—GUIDEWAY CURB REPAIR-02-13-13—DRAFT FOR PRICING PAGE 1 OF 1
t I' ' � h
CEf..
�`.
2113/13
Erika Keeton
Special Projects Engineer
City of Ft. Collins
281 N. College Avenue
Fort Collins, CO 80522-0580
CCR NUMBER:
CEI PROJECT #:
CONTRACT NUMBER:
CONTRACT DATE:
CONTRACT NAME:
161
12-009
7332
Mason Corridor BRT
Td Plfw&e 04&4rED 3y
Esop, ra
G:l e iPtB Soon/
T�f,3Yf/T G�i✓TEL.
DESCRIPTION OF CCR: Pricing to address curb and gutter damages South of Harmony on the
BRT Guildway
LOCATION: South of Harmony East side of BRT
MEMO NO.:
MEMO DATE:
COST CODE:
DESCRIPTION
CITY
UNIT
UNIT PRICE
OT
TOTAL
Flagging
16
HR
$ 24.15
$386.40
Removal of Curb and Gutter
23
LF
$ 8.50
$195.50
#6 Epoxy Bar 12" OC & Epoxy
23
EA
$ 8.00
$184.00
Curb and Gutter Type JIB
23
LF
$ 22.00
$506.00
Winter Protection
1
LS
$ 250.00
$250.00
TOTAL
Concrete Express, Inc., requests 0 days for the above contract modifications.
These are all of the visible effects of the above change we see at this time. We reserve the right to
incorporate other changes as they appear in implementing this change. If you have any questions
regarding this change, please feel free to contact me at 303.562.2000.
$1,521.90
Ryan Dickinson
From: George Latour [glatour@fcgov.com]
Sent: Wednesday, February 13, 2013 10:30 AM
To: Ryan Dickinson; Bobi Jo Meritt
Cc: Keith.Meyer@ditescoservices.com;'tim.hackworth@ch2m.com'; Tarl Bohnet
Subject: FW: Damage to Guide Way C"&G @ STC
Attachments: Picture 065.jpg; Picture 066.jpg; Picture 067.jpg
We went and marked the area to be repaired. It measures 23 feet long basicallyjust removing a 30" section of curb and
gutter. Please provide cost to repair this work.
Thanks
George Latour, CCM
Senior Construction Inspector
City of Fort Collins
480-745-5910
glatour(o)fceov.com
From: Tart Bohnet
Sent: Monday, February 11, 2013 8:26 AM
To: George Latour; 'tim.hackworth@ch2m.com'
Cc: Keith Meyer (Keith.Meyer@ditescoservices.com); Erika Keeton; Tracy Dyer
Subject: Damage to Guide Way C"&G @ STC
Team,
Here are the photos that I took last week. Let me know if you guys need any more information or pictures of the site.
Thanks,
TC