Loading...
HomeMy WebLinkAboutCHANGE ORDER - BID - 7382 MAX BRT SOUTH TRANSIT CENTER (2)3 Change Order No. 6 PROJECT TITLE: South Transit Center CONTRACTOR: Growling Bear Inc. BID NUMBER: 7382 DESCRIPTION: 1. Reason for change: Incorporation of Change Order Proposal #5 into the Contract. 2. Description of change: COP#5 - Additional Off -site Utility Costs - $6,810.56. Please see attached spreadsheet 3. Change in contract costs: $6,810.56 4. Change in contract time: 0 Days ORIGINAL CONTRACT COST $4,356,565.70 TOTAL APPROVED CHANGE ORDERS $20,044.57 TOTAL PENDING CHANGE ORDERS $22,234.93 TOTAL THIS CHANGE ORDER $6,810.56 TOTAL % OF THIS CHANGE ORDER 0.16% TOTAL C.O. % OF ORIGINAL CONTRACT 1.13% ADJUSTED CONTRACT COST $4,405,655.76 REVIEWED BY: DATE: 6 1 - 7^ 113 ACCEPTED BY: DATE: Contractor's Representative REVIEWED BY: Manager APPROVED BY: (l; REPRESENTATIVE cc: Contractor Purchasing Project File DATE: ��� � 13 DATE: (� ' • �T— COP #5 - Additional Off -site Utility Costs Item Description City GBI 5 13 2013 Costs Proposal Difference Resolution of RFI #18 - Existing Inlet Conflicts $ 1,242.30 $ 1,242.30 Kehn shut down costs $ 621.92 $ 621.92 None Kehn additional potholing $ 458.34 $ 458.34 None Conflict at Storm Manhole 1 & Modifications $ 2,337.62 $ 2,682.62 Kehn STMH1 conflict shutdown $ 621.92 $ 621.92 None Kehn STMH1 modify manhole $ 1,410.79 $ 1,710.79 5CY Flowfill Kehn additional paving repair costs $ 1,740.00 $ 2,610.00 10T Asphalt Additional Traffic Control NCTC - 23 days @ $144/day $ 3,312.00 $ 3,312.00 None NCTC - 23 days @ $60/day $ 1,380.00 $ 1,380.00 None NCTC- Additional Barricades $ 480.00 $ 695.00 # Barricades Credit for Raising the Profile of Storm Line A Station 1+17.80 to 3+84.99 58 CY Less Excavation/Flowfill Reduced Excavation/Flowfill - 58 CY @ $70/CY * $ (4,060.00) $ - Station 0+27.30 to 1+17.80 28 CY Less Excavation/Flowfill Reduced Excavation/Flowfill - 28 CY @ $70/CY ** $ (1,960.00) $ - Subcontractor Subtotal $ 4,471.92 $ 11,921.92 GBI Mark-up on Subcontractor Work $ 223.60 $ 596.10 Subcontract Subtotal $ 4,695.51 $ 12,518.01 GBI Staff Costs Superintendent $ 1,200.00 $ 1,200.00 None Project Engineer $ 320.00 $ 320.00 None Project Manager $ 240.00 $ 480.00 Less PM Time GBI Staff Costs Subtotal $ 1,760.00 $ 2,000.00 GBI Mark-up on Self -performed Work - 15% $ 264.00 $ 300.00 GBI Subtotal $ 2,024.00 $ 2,300.00 Cumulative Total $ 6,719.51 $ 14,818.01 Additional Bond @ 1% $ 67.20 1 $ 148.18 Additional Insurance @ 3.55/10001 $ 23.85 1 1 $ 52.60 Total $ 6,810.56 $ 15,018.80 * Profile Raised 1.36 feet - 4.5' wide X 255' long X 1.36' high = 1561 CF or 58 CY ** Profile Raised 1.87 feet - 4.5' wide X 90.5' long X 1.87' high = 762 CIF or 28 CY $10/CY Excavation + $60/CY Flow Fill = $70/CY July 24, 2013 Ms. Erika Keeton, PE MAX Project Manager City of Fort Collins — Engineering Dept 281 N. College Ave. Fort Collins, CO 80524 RE: MAX Bus Rapid Transit Project — South Transit Center 7382 Independent Cost Analysis — Change Order No. 6 Growling Bear Inc. Change Order Proposal #5 MAX Field Construction Office 3000 South College Ave., Suite 201 Fort Collins, CO 80526 fcgov.com/maxconstruction Delivery by hand Growling Bear Inc. provided Change Order Proposal #5 as a preliminary estimate of costs for the conflicts encountered with installation of Storm Drain Profile A on 11/26/12. After numerous discussions relative to this subject with GBI, we provided a letter response on February 20, 2013 that outlined many concerns with their proposal and removed the lowering of the water main at Storm Sewer Manhole #2 from this proposal (attached). We then received a revised Change Order Proposal #5 that provided some reductions and an explanation of the Superintendent and Operator concern that we accepted, but their proposal was still much higher than our determined costs, since they did not provide reductions for items that were clearly justified, based upon the construction that actually took place (please see attached). As you can see, we did agree with the costs presented by Don Kehn Construction, but the appropriate deductions for items that were clearly reduced by the construction that actually happened in the field were not provided, even though they were succinctly requested. I attempted to incorporate these costs in a proposed Change Order #2 on 5/1/13, but they were rejected by Gary Shironaka by his letter of 5/16/13. We have taken the appropriate deductions in the City costs and we believe they are fair and reasonable. The costs proposed by Growling Bear Inc. were evaluated against our City determined costs in the Independent Cost Estimate and we believe that the City costs should be the basis for the Contract Change. As such, I find the City costs for this Change Order in the amount of $6,810.56 to be reasonable for the required increase in scope. As such, I recommend acceptance of this additional cost to the contract. (JT , , ": t ". - � �'- -. � Ron Kechter Project Engineer City of Fort Collins Operational Services - Facilities Cc: job file art` Y`I� Independent Cost Estimate Date of Estimate: 13-May-13 Contract Type: Fixed Price Existing Contract or PO (Y/N): Yes Description Services (B): Change Order Proposal - #5 - This work was for the resolution of off - site utility conflicts with Storm Line Profile A running down Fossil Blvd. The City is in basic agreement with the GBI costs presented with the exception of: 5CY less flowfill; 10T less asphalt; less barricades; 58 CY less excavation/flowfill at Station 1+17.80 to 3+84.99; 28 CY less excavation/flowfill at Stations0+27.30 to 1+17.80; and 3 hours less PM time. I have obtained the following estimate from: Engineering or Techincal Estimate (performed by) - Ron Kechter COP #5 - Additional Off -site Utility Costs Item Description City Costs GBI Proposal Difference Resolution of RFI #18 - Fxistinq Inlet Conflicts $1,242.30 $1,242.30 Kehn shut down costs $621.92 $621.92 None Kehn additional potholing $458.34 $458.34 None Conflict at Storm Manhole 1 8 Modifications $2,337.62 $2,682.62 Kehn STMH1 conflict shutdown $621.92 $621.92 None Kehn STMH1 modify manhole $1.410.79 $1,710.79 5CY Less Flowfill Kehn additional paving repair costs $1,740.00 $2.610.00 10T Less Asphalt Additional Traffic Control NCTC - 23 days @ $144/day $3,312.00 $3.312.00 None NCTC - 23 days @ $60/day $1,380.00 $1,380.00 None NCTC -Additional Barricades $480.00 $695.00 # Barricades Credit for Raising the Profile of Storm Line A Station 1+17.80 to 3+84.99 58 CY Less Excavation/Flowfill Reduced Excavation/Flowfill - 58 CY @ $701CY ($4,060.00) S- Station 0+27.30 to 1+17.80 28 CY Less Excavation/Flowfill Reduced Excavation/Flowfill - 28 CY @ $70/CY ($1,960.00) $- Subcontractor Subtotal $4,471.92 $11.921.92 GBI Mark-up on Subcontractor Work $223.60 $596.10 Subcontract Subtotal $4,695,51 $12,518.01 GBI Staff Costs Superintendent $1,200.00 $1,200.00 None Project Engineer $320.00 $320.00 None Project Manager $240.00 $480.00 3 Hours Less PM Time GBI Staff Costs Subtotal $1.760.00 $2,000.00 GBI Mark-up on Self -performed Work - 15% $264.00 $300.00 GBI Subtotal $2.024.00 1 1 $2,300.00 Cumulative Total $6,719.51 $14,818.01 Additional Bond @ 1% $67.20 1 $148.18 Additional Insurance @ 3.5511000 $23.85 1 $52.60 Total 1 $6,810.56 1 $15,U18.8U ' Profile Raised 1.36 feet - 4.5' wide X 255' long X 1.36' high = 1561 CF or 58 CY Profile Raised 1.87 feet - 4.5' wide X 90.5' long X 1.87' high = 762 CF or 28 CY $10/CY Excavation + $60/CY Flow Fill = $70/CY Signature of Preparer. P1 a,- n T=2 o Ya Change Order No. 7 PROJECT TITLE: South Transit Center CONTRACTOR: Growling Bear Inc. BID NUMBER: 7382 DESCRIPTION: 1. Reason for change: Incorporation of Change Order Proposal #8 into the Contract. 2. Description of change: COP#8/WCD01/COP#18 -Water Line Lowering - $22,229.00. Please see attached spreadsheet. 3. Change in contract costs: $22,229.00 4. Change in contract time: 0 Days ORIGINAL CONTRACT COST $4,356,565.70 TOTAL APPROVED CHANGE ORDERS $20,044.57 TOTAL PENDING CHANGE ORDERS $29,045.49 TOTAL THIS CHANGE ORDER $22,229.00 TOTAL % OF THIS CHANGE ORDER 0.51 % TOTAL C.O. % OF ORIGINAL CONTRACT 1.64% ADJUSTED CONTRACT COST $4,427,884.76 REVIEWED BY: DATE: Facilities Project Manager ACCEPTED BY: DATE: Contractor's Representative REVIEWED BY: DATE: Construc n Manager APPROVED BY: l� DATE: OWNER'S KEPkSENTATIVE cc: Contractor Purchasing Project File Change Order Proposal #8 - Water Line Lowering Resolving Conflict w/ 4 30 2013 Storm Line Profile A at SMH #2 - Reconciliation of WCD 01 Costs Description Cost GBI Costs Materials & Labor for lowering w/ markup - Kehn $ 13,826.45 $ 13,826.45 Additional asphalt patching - 30 tons @ $87.00/ton $ 2,610.00 $ 3,480.00 Pipe crew re -mobilization $ 600.00 $ 1,200.00 Additional traffic control measures - NCTC $ 1,175.00 $ 1,175.00 Subcontractor Subtotal $ 18,211.45 $ 19,681.45 GBI Mark-up on Subcontractor work @ 5% $ 910.57 $ 984.07 Subtotal $ 19,122.02 $ 20,665.52 Additional Bond @ 1% $ 191.22 $ 206.66 Additional Insurance @ $3.55/$1000 $ 67.88 $ 73.36 Total $ 19,381.13 $ 20,945.54 Additional Asphalt patching - 37 tons @ $87.00/ton Reduced Amount of Flow Fill - 30 CY @ &60.00/CY Added Cost for Pipe Crew Re -mobilization Added Cost for Traffic Control - NCTC Temporary Toilet Facilities - Gallegos Sanitation Additional Subcontractor Subtotal GBI Mark-up on Subcontractor work @ 5% Additional Bond @ 1% Additional Insurance @ $3.55/$1000 Subtotal Additional Subtotal Final Total $ 3,219.00 $ (11800.00) $ 492.00 $ 155.00 $ 610.00 $ 2,676.00 $ 133.80 $ 2,809.80 $ 28.10 $ 9.97 $ 2,847.87 $ 22,229.00 $ 29,217.65 COP #18 t July 26, 2013 Ms. Erika Keeton, PE MAX Project Manager City of Fort Collins — Engineering Dept 281 N. College Ave. Fort Collins, CO 80524 RE: MAX Bus Rapid Transit Project — South Transit Center 7382 Independent Cost Analysis — Change Order No. 7 Growling Bear Inc. Change Order Proposals #8 & #18 MAX Field Construction Office 3000 South College Ave., Suite 201 Fort Collins, CO 80526 fcgov.com/maxconstruction Delivery by hand Growling Bear Inc. provided Change Order Proposal #8 as a preliminary estimate of costs for the conflict with the FCLWD water line encountered with installation of Storm Drain Profile A on 2/1/13 that included a 16 day project delay and compensation. In our letter dated February 22, 2013 we stated that we were in general agreement with the construction costs and provided Work Change Directive 01. The 16 day delay and compensation were denied in this letter. The 16 day delay and compensation was later included in Change Order Proposal #12 along with a total time extension request of 95 days. This was the matter taken through mediation and is pending arbitration. Accordingly we then worked with only the estimate of construction costs, which totaled $20,945.54, including bonds and insurance. We disagreed with the amount of asphalt and costs for pipe crew remobilization so our costs totaled $19381.13, as outlined in our letter of February 28.2013. Once the work was complete we reconciled quantities and found that 37 addition tons of asphalt were used and 30 tons less of flow fill were used. Concurrently we received Change Order Proposal (COP) #18, dated 4/25/13, that turned out to be a whole new proposal for these costs that included items not even mentioned in the original proposal. Using information that we gleaned from the field and some of the pertinent information from COP #18, we came up with a reconciled cost total of $22,229.00, as shown in the attached Independent Cost Estimate (ICE). This ICE clearly shows the additional items inserted by GBI that weren't even part of the original proposal. I attempted to incorporate these costs in a proposed Change Order #2 on 5/1/13, but they were rejected by Gary Shironaka by his letter of 5/16/13. We have taken the appropriate additions and deductions in the City costs and we believe they are fair and reasonable. The costs proposed by Growling Bear Inc. were evaluated against our City determined costs in the Independent Cost Estimate and we believe that the City costs should be the basis for the Contract Change. As such, I find the City costs for this Change Order in the amount of $22,229.00 to be reasonable for the required increase in scope. As such, I recommend acceptance of this additional cost to the contract. Ron Kechter Project Engineer City of Fort Collins Operational Services - Facilities Cc: job file ForIndependent Cost Estimate Date of Estimate: 30-Apr-13 Contract Type: Fixed Price Existing Contract or PO (Y/N): Yes Description Services (8): Change Order Proposal - #8 - This work was for the lowering of the FCLWD water line in conflict with Storm Line Profile A at Storm Manhole #2. During the orginal evaluation, the City was in basic agreement with the GBI costs presented with the exception of: The amount of additional asphalt patching and pipe crew remobilization costs. Once the work was completed, the City reconciled the cost through observation of what actually happened in the field. GBI at that point provided a completely new proposal, COP #18, that introduced costs never before presented. I have obtained the following estimate from: Engineering or Techincal Estimate (performed by) - Ron Kechler Change Order Proposal #8 8 #18 - Water Line Lowering Resolving Conflict w/ Storm Line Profile A at SMH #2 - Reconciliation of WCD 01 Costs Description Cit Costs GBI Costs #8 GBI Costs #18 Materials 8 Labor for lowering w/ markup - Kehn $13,826.45 $13,826.45 $ 12,047.86 Additional asphalt patching - 30 tons @ $87.00/ton $2,610.00 $3,480.00 $ 6,525.00 Pipe crew re -mobilization $600.00 $1,200.00 $ 1,092.00 Asphalt Crew Mobilization $ 1,591.92 Additional traffic control measures -NCTC $1,175.00 $1,175.00 $ 1,330.00 Subcontractor 10%Markup $0.00 $0.00 $ 2,125.67 Subcontractor Subtotal $18,211.45 $19.681.45 $ 24,712.45 GBI Mark-up on Subcontractor work @ 5% $910.57 $984.07 $ 1,235.62 Subtotal $19,122.02 $20,665.52 $ 25,948.07 Additional Bond @ 1% $191.22 $206.66 $ 259.48 Additional Insurance @ $3.55/$1000 $67.88 $73.36 $ 92.12 Original Totals $19,381.13 $20.945.54 $ 26,299.67 Reconciliation Additional Asphalt patching - 37 tons @ $87.00/ton $3,219.00 included Above Reduced Amount of Flow Fill - 30 CY @ 860.00/CY ($1,800.00) $ Added Cost for Pipe Crew Re -mobilization $492.00 Included Above Added Cost for Traffic Control - NCTC $155.00 Included Above Temporary Toilet Facilities- Gallegos Sanitation $610.00 $ 610.00 Additional Subcontractor Subtotal $2,676.00 $ 610.00 GBI Mark-up on Subcontractor work @ 5% $133.80 $ 30.50 Subtotal $2,809.80 $ 640.50 GBI Costs Superintendent- 18.7 hours @ $80.00 $ 1,496.00 Project Manager - 5.3 hours @ $85.00 $ 450.50 GBI Mark-up on Self -performed work @ 15°/, $ 291.98 GBI Subtotal $ 2,238.48 Subtotal $2,809.80 $ 2,878.98 Additional Bond @ 1% $28.10 $ 28.79 Additional Insurance @ $3.55/$1000 $9.97 $ 10.22 Additional Subtotal $2,847.87 Is 2,917.99 Final ota $22.229.00 29,217.65 Signature of Preparer: Z,i\ �Qo