HomeMy WebLinkAboutWORK ORDER - BID - 7382 MAX BRT SOUTH TRANSIT CENTERChange Order No. 4
PROJECT TITLE: South Transit Center
CONTRACTOR: Universal Surety Company
BID NUMBER: 7382
DESCRIPTION:
1. Reason for change: Incorporation of Change Order Proposal #16 into the Contract.
2. Description of change: COP#16 - Electrical work per ASI #1 - $12,630.53.
3. Change In contract costs: $12.630.53
4. Change in contract time: 0 Days
ORIGINAL CONTRACT COST
$4,356,565.70
TOTAL APPROVED CHANGE ORDERS
S20,044.57
TOTAL PENDING CHANGE ORDERS
$0.00
TOTAL THIS CHANGE ORDER
$12.630.53
TOTAL % OF THIS CHANGE ORDER
0.29%
TOTAL C.O. % OF ORIGINAL CONTRACT
0.75%
ADJUSTED CONTRACT COST
$4,389,240.80
REVIEWED BY: :t •g , JC.. _ _ DATE: —
Project -Engineer
ACCEPTED BY: DATE:
Contractors Representative
REVIEWED BY: DATE:
Construction Manager
APPROVED
cc: Contractor
Purchasing
Protect File
-y-• Zr�O 3
DATE:
MAX Field Construction Office
3000 South College Ave., Suite 201
Fort Collins, CO 80526
fcgov.com/maxconstruction
Delivery by hand
June 27, 2013
Ms. Erika Keeton, PE
MAX Project Manager
City of Fort Collins — Engineering Dept
281 N. College Ave.
Fort Collins, CO 80524
RE: MAX Bus Rapid Transit Project — South Transit Center 7382
Independent Cost Analysis — Change Order No. 5
Growling Bear Inc. Change Order Proposal #23
Growling Bear Inc. was requested to provide Change Order Proposal #23 to enable the completion of the
tie-in of the water main within the easement granted by Spradley-Barr for this project. In order to
accomplish the tie-in, the existing backflow preventer on the fire line feeding Spradley-Barr will need to be
removed, along with the vault that it is in so we can tie-in the water line in that space. This change
involves installing a new Reduced Pressure Backflow Preventer that complies with Fort Collins Loveland
Water District requirements, in the fire riser room in the Spradley-Barr facility that will allow us to remove
the existing backflow preventer. With this new backflow device in place we will be able to tie-in the water
line within the easement and complete the water line loop designed into this project without having to go
outside of the existing easement.
The labor, materials and equipment costs proposed by Growling Bear Inc. were evaluated against an
Independent Cost Estimate and are consistent with pricing for similar work. As such, I find the cost of this
Change Order Proposal from Growling Bear Inc. in the amount of $9,604.40 to be reasonable for the
required increase in scope. As such, I recommend acceptance of this additional cost to the contract.
Ron Kechter
Project Engineer
City of Fort Collins
Operational Services - Facilities
Cc: job file
'ZO
June 27, 2013
Ms. Erika Keeton, PE
MAX Project Manager
City of Fort Collins — Engineering Dept
281 N. College Ave.
Fort Collins, CO 80524
RE: MAX Bus Rapid Transit Project — South Transit Center 7382
Independent Cost Analysis — Change Order No. 5
Growling Bear Inc. Change Order Proposal #23
MAX Field Construction Office
3000 South College Ave., Suite 201
Fort Collins, CO 80526
fcgov.com/maxconstruction
Delivery by hand
Growling Bear Inc. was requested to provide Change Order Proposal #23 to enable the completion of the
tie-in of the water main within the easement granted by Spradley-Barr for this project. In order to
accomplish the tie-in, the existing backfow preventer on the fire line feeding Spradley-Barr will need to be
removed, along with the vault that it is in so we can tie-in the water line in that space. This change
involves installing a new Reduced Pressure Backfiow Preventer that complies with Fort Collins Loveland
Water District requirements, in the fire riser room in the Spradley-Barr facility that will allow us to remove
the existing backflow preventer. With this new backflow device in place we will be able to tie-in the water
line within the easement and complete the water line loop designed into this project without having to go
outside of the existing easement.
The labor, materials and equipment costs proposed by Growling Bear Inc. were evaluated against an
Independent Cost Estimate and are consistent with pricing for similar work. As such, I find the cost of this
Change Order Proposal from Growling Bear Inc. in the amount of $9,604.40 to be reasonable for the
required increase in scope. As such, I recommend acceptance of this additional cost to the contract.
a
Ron Kechter
Project Engineer
City of Fort Collins
Operational Services - Facilities
Cc: job file
Change Management Checklist
�541111611c,ITIMM
EMEEM
MEN
Water Resources and Water
Reviewed for compliance with
6/26/13
Quality — EA 3.8.4 - contractor will
RK
Environmental Assessment
comply with all re -vegetation and
erosion control requirements
All of the work Is based upon
Reviewed for constructionlsafety impacts
6/26113
standard construction and safety
RK
practices
Costs were determined to be
reasonable based upon an
Independent cost estimate prepared
6126/13
independent cost esOmate that
RK
was based upon recent
experience with slmilarwork
Reviewed for PCGA grant compliance
6126/13
Part of Build Alternative Scope
RK
included in SCC 30.02
The primary reason for this
Reviewed for real estate impacts/needs
6126/13
changed work is for the project
work to remain inside of existing
RK
easement procured for this project
Reviewed for compliance with design
criteria/ADA
htlA:ltwww.access-board.00vlada-abalada•
6/26113
NIA
RK
standards-dol.dm
of
F,�c`J,M.0-Uns
Independent Cost Estimate
Date of Estimate: 26-Jun-13
Contract Type: Fixed Price
Existing Contract or PO (YIN): Yes
Description Services (8): Change Order Proposal - #16 - Complete electrical work odginally Identified as being on the West side of
the property or By Owner, per ASI #1 and subsequent clarificalions.
1 have obtained the following estimate from:
Engineering or Techinral Eslimale (performed by) - Ron Kechler & Bryan Garrett (City Master Electrician)
Materials or Work Descdpllon
Quantity
Unll
Unit
Cost
TOTAL
Change Order Proposal t116
Add 2 1' conduits from 58 to 1st NE pole
120
LF
S 4.05
S 486.00
Add t 1' conduit from tsl to 2nd NE pole
150
LF
5 4.05
5 607.50
Delete JB's In light le bases
Delete 2- conduit on west & south sides
-4
-285
EA
LF
S 63 00
5 8.14
$ 252.00)
$ 1,749.90
Add 3 2' canduiLs from 58 to 1st SE to
420
LF
5 6,14
5 2.578.80
Add 3 1- conduits from 58 to 1st SE pole
420
1 LF
S 4.05
IS 1.701.00
Add 3 2- conduits from 1st to 2nd SE pole
480
LF
5 6.14
S 2,947.20
Add 2 1"conduiLs from 1st 102nd SE poie
320
LF
5 4.05
S 1,298.00
Add 1 1- conduit from 2nd SE polato MonumentSign
100
LF
S 4.05
5 405.00
Add 1 2- conduit from 2nd SE pole to Century Link Pedestal
160
LF
S 6.14
$ 982,40
Add 2 2' condulls from 2nd SE pWo 10 vault at comer of Fossil & Fairway
700
LF
5 6.14
$ 4,298.00
Add 6• sand from 55 to 2nd SE pole
4
CY
S 12.50
S 50.00
Add 18' oownit from 5B to 2nd SE pole
to
CY
S 6o.o0
Electrical Subtotal
S 14,430.00
GBI Mark-up on Subcontractor Work @ 5%
S 721.50
' Subcontractor Total
5 15,151.50
GBI Costs
Type SV Vault & Lid
1
EA
$1.044.46
S 1.044.46
Freight
1
EA
5 250.00
S 250.D0
Install Type SV Vault
Equipment Operator
4
HR
5 26.DD
S 104,00
Skid Steer
4
HR
S 45.00
5 180.00
Superintendent
a
HR
5 au.00
5 640.00
rolecl Manager
GBI Subtotal
S 2.558.46
GBt Marx -up an own Work @ 15%
S 383.77
GBI Total
S 2.942.23
GBI and Subcontractor Total
S 18.093,73
Bond 1%
5 180.94
i ena nsurance
of
Signature of Preparer. (_ Pa,,,,, A ,. s
c v
MAX Field Construction Office
3000 South College Ave., Suite 201
Fort Collins, CO 80526
fcgov.com/maxconstruction
Delivery by hand
June 26, 2013
Ms. Erika Keeton, PE
MAX Project Manager
City of Fort Collins — Engineering Dept
281 N. College Ave.
Fort Collins, CO 80524
RE: MAX Bus Rapid Transit Project — South Transit Center 7382
Independent Cost Analysis — Change Order No. 4
Growling Bear Inc. Change Order Proposal #16
Growling Bear Inc. was requested to provide Change Order Proposal #16 in response to AS] #1 and
subsequent clarifications. This request changed the route of the fiber optic conduits from the west side of
the building in order to utilize the trenches already being dug to the light poles in the parking tot on the
east side of the building. This request also Included all of the conduits needed for the installation of the
security cameras mounted on the light poles, a feed to the monument sign and a feed to the emergency
phone tower. This request also included conduits going to the Century Link pedestal and to an added
vault at the corner of Fairway and Fossil for the completion of the fiber optic loop for the entire MAX
Project. Additionally, sand and flow fill were added to the trench containing the fiber optic conduits as
they ran under the parking lot. This routing of the fiber optic conduits also provided the avenue for
providing connectivity to the College and Fairway traffic from a Traffic vault located at Harmony Road.
The labor, materials and equipment costs proposed by Growling Bear Inc. were evaluated against an
Independent Cost Estimate and are consistent with pricing for similar work. As such, I find the cost of this
Change Order Proposal from Growling Bear Inc. in the amount of $1Z630.53 to be reasonable for the
required increase in scope. As such, 1 recommend acceptance of this additional cost to the contract.
a -4�"'Q'
Ron Kechter
Project Engineer
City of Fort Collins
Operational Services - Facilities
Cc: job file
Change Management Checklist
Visual Impacts EA 3.15.3 —
Reviewed for compliance with
Disturbed areas will be re -
Environmental Assessment
6126/13
vegetated; Air Quality EA
RK
3.6.5/Noise EA 3.7.3 — contractor
will comply with all requirements
All of the work is based upon
Reviewed for construction/safety Impacts
6/26113
standard construction and safety
RK
practices
Costs were determined to be
reasonable based upon an
Independent cost estimate prepared
6126/13
independent cost estimate
RK
prepared in conjunction with our
City Master Electrician using an
estimating guide
Reviewed for PCGA grant compliance
6/26113
Part of Build Alternative Scope
RK
Included in SCC 30.02
Fiber optic conduits and a data
Reviewed for real estate impacts/needs
6/26113
vault are being placed in existing
RK
right-of-way; All other work is on
City owned property
Reviewed for compliance with design
criteria/ADA
httoJ/wnw.access-board.govtada-abalada-
6/26113
N/A
RK
§tpndards-dotcftn
Change Order No. 5
PROJECT TITLE: South Transit Center
CONTRACTOR: Growling Bear Inc.
BID NUMBER: 7382
DESCRIPTION:
1. Reason for change: Incorporation of Change Order Proposal #23 into the Contract.
2. Description of change: COP#23 - Backflow/Pressure Reducer - $9,604.40
3. Change in contract costs: $9,604.40
4. Change in contract time: 0 Days
ORIGINAL CONTRACT COST
$4,356,565.70
TOTAL APPROVED CHANGE ORDERS
$20,044.57
TOTAL PENDING CHANGE ORDERS
$12,630.53
TOTAL THIS CHANGE ORDER
$9,604.40
TOTAL % OF THIS CHANGE ORDER
0.22%
TOTAL C.O. % OF ORIGINAL CONTRACT
0.97%
ADJUSTED CONTRACT COST
$4,398,845.20
REVIEWED BY:
ACCEPTED BY:
0-4- (2-q-ALs �E �Q.N i��- DATE: Z 7
Facilities Project Manager
Contractor's Representative
REVIEWED BY:
Manager
APPROVED BY: (:
cc: Contractor
Purchasing
Project File
DATE: 7i
DATE: !-n-13
DATE:
Growling Bear Construction Inc. PROPOSED CHANGE ORDER
No. 00023
2330 4tlr Ave Phone: 970-353-6964
Greelev. CO 80631 Fax: 970-353-6974
TITLE: Backtlow/Pressure Reducer
PROJECT: FC South Transit
TO: Attn: Ron Kechter
M
Fort Collins South Transit Center
4915 Fossil Blvd
Fort Collins, CO 80525
To:
DESCRIPTION OF PROPOSAL
DATE: 5/24/2013
JOB:
CONTRACT NO:
From: Number:
Proposal for minor modifications to the Fire Sprinkler System at Spradley-Barr Ford. Scope is primarily for installation of a new 6"
reduced pressure backflow device in the Fire Control room so that the existing backflow device can be abandoned in the vault outside
of the building (to facilitate a new water main connection). The proposal from Flow Fire Protection, Inc., is attached and is hereby
incorporated into this Change Order Proposal, including all exclusions listed. Flow Fire Protection proposal dated 5/22/2013 in the
amount of: $6,900.00
Growling Bear Staffing costs: $1,940.00
GBI Mark-up on Subcontractor (5ro): $345.00
GBI Mark-up on self -performed work: $291.00
Proposal Sub -total: $9,476.00
Additional Bond (1% rate): $94.76
Additional Insurance: $33.64
Proposal Total: $9,604.40
Please provide a Change Order for this scope of work at your earliest convenience.
Proposal specifically excludes other costs associated with the water main extension (connection) that are not shown on the contract
documents.
Unit Cost: $0.00
Unit Tax: $0.00
Lump Sum: $9,604.40
Lump Tax: $0.00
Total: $9,604.40
APPROVAL:
By: �e / .0 _ By:
Gene Leach Ron Kechter
Date: s�z/�j Date:
u�:wn o
Change Order Proposal #23
Fire Sprinkler System modification (back flow) at Spradley-Barr
FFP Flow Fire Protection Proposal: $6,900.00
Growling Bear Costs
Superintendent (to date)
12 $80.00 $960.00
Superintendent- additional coordination required
8 $80.00 $640.00
Project Manager
4 $85.00 $340.00
$1,940.00
GBI Mark-up - subcontractor - 5%
$345.00
GBI Mark-up - self performed 15%
$291.00
Sub -total:
$9,476.00
Additional Bond
1% $94.76
Additional Insurance $3.55/$1000
$33.64
Proposal Total: $9,604.40
rd ,y �qr
Flow Fire Protection, Inc.
Change Order Pricing
3054 Lake Canal Ct Unit 100 — Fort Collins, CO
Office (970) 494-1817 - Fax (970) 493-7157 page I of 1
Date: May 22, 2013
To: Growling Bear Construction
Attention: Gene & Pat
Reference: Spradley Barr
Specification Section - Fire Sprinkler System modification Change Order Pricing
Thank you for the opportunity to provide your company with pricing for the above referenced project. The price has been
based on the below scope inclusions/exclusions.
Add a new 6 reduce pressure backflow device to the existing fire sprinkler system. New tamper switches
to be tied into the existing tampers. Certification of the new backflow device will be performed. The air gap is
to be piped to the exterior or to an adequate floor drain. The existing fire sprinkler system will need to have
calculations done to verified that the installation of the new device will not affect the operation of the system.
Included:
1. The system would be modified to the latest version of NFPA 13
2. Material and installation based on minimum requirements of NFPA 13 & FCLWD
Exclusions:
1. Alarms, Detection, Remote Annunciator or Central Station Monitoring
2. IRI, Factory Mutual, or other HRP insurers requirements more stringent than NFPA standard(s) cited above
3. Cutting and patching
4. Changing of any existing pipe if the calculations show that piping will need to be changed out.
5. Removal of the existing backflow device that is located in the vault.
6. Asbestos Abatement or working under asbestos conditions
7. Flushing of the underground pipe
8. Capture or chlorination of water drained from system out of exterior drains or related permits if applicable
9. Off hours or night work
Change Order Total----- $6,900.00
Thank you for the opportunity to quote this project to your firm.
don't hesitate to contact me.
Sincerely, �„�„
`eta„ ,1, o"�,'. an
Tony Lyman
Construction Manager
Flow Fire Protection
Accepted By:
Title:
If you have any questions regarding this proposal please
This Bid is valid For 30 Days. Should this bid be accepted please notify our offices by signing and returning a copy of this proposal by either fax or mail. By
signing the above acknowledgement, this endorsement confirms full authorization to sign for the Purchaser, and accepts General Terms and Conditions as if
written herein.
City of
Fort Collins
Date of Estimate: 11-Jun-13
Independent Cost Estimate
Contract Type: Fixed Price
Existing Contract or PO (Y/N): Yes
Description Services (B): Change Order Proposal - #23 - Install 6" Backflow/Pressure Reducer at Spradley-
Barr so we can remove the backflow in the vault and connect the water line loop
tie-in to the FCLWD main line going out to College Avenue.
I have obtained the following estimate from:
Engineering or Techincal Estimate (performed by) - Ron Kechter
Materials or Work Description
Quantity
Unit
Unit
Cost
TOTAL
Change Order Proposal #23
Flow Fire Protection Costs
Procure 6" RPBF
1
EA
$ 5,210.00
$ 5,210.00
Miscellaneous Materials
1
EA
$ 250.00
$ 250.00
Install 6" RPBF
16
HR
$ 68.00
$ 1,088.00
Test System
2
HR
$ 68.00
$ 136.00
Design
4
68.00
272.00
Flow Fire Protection Subtotal
$ 6,956.00
GBI Mark-up on Subcontractor Work @ 5%
$ 347.80
Subcontractor Total
$ 7,303.80
GBI Costs
Superintendent
20
HR
$ 80.00
$ 1,600.00
Project Manager
4
HR
85.00
340.00
GBI Subtotal
$ 1,940.00
GBI Mark-up on own Work @ 15%
$ 291.00
GBI Total
$ 2,231.00
GBI and Subcontractor Total
$ 9,534.80
Bond @ 1 %
$ 95.35
Additional nsurance @ 3.55 000
33.85
ota
Signature of Preparer C1z cI P .F+ Q7,,!