HomeMy WebLinkAboutCHANGE ORDER - BID - 7426 TRANSFORT MAINTENANCE FACILITY EXPANSION (6)I Change Order No:'t3) eD5 CONTRACTOR: Heath Construction BID NUMBER: 7426 DESCRIPTION: 1. Reason for change: Incorporation of Pricing Change Request (PCR) #11 Into the Contrail 2. Description of change: PCR#11 - Provide Methane Detedlon for the Transfort Maintenance Facility Addition and the Chassis Wash Addition. 3. Change In contract costs: 519,548.52 4. Change In contract Nme: 19 Days ORIGINAL CONTRACT COST $2,156.000.00 TOTAL APPROVED CHANGE ORDERS $141,875.36 TOTAL PENDING CHANGE ORDERS $0.0 TOTAL THIS CHANGE ORDER $19.548.52 — TOTAL % OF THIS CHANGE ORDER 0.911E TOTAL C.O. % OF ORIGINAL CONTRACT 7.49% ADJUSTED CONTRACT COST $2,317,423.88 REVIEWED BY: ACCEPTED REVIEWED APPROVED cc ca osaw p,rdmft PmtW FOG DATE: t! 4 3 DATE: 9- /6 — �3 DATE: lq - 1 ✓ MAX Field Construction Office 3000 South College Ave., Suite 201 Fort Collins, CO 80526 fcgov.com/maxconstruction Delivery by hand September 5, 2013 Ms. Erika Keeton, PE MAX Project Manager City of Fort Collins — Engineering Dept 281 N. College Ave. Fort Collins, CO 80524 RE: MAX Bus Rapid Transit Project — Transfort Maintenance Facility Expansion 7426 Independent Cost Analysis — Change Order No. 6 Heath Construction Pricing Change Request #11 Heath Construction was requested to provide Pricing Change Request #11 in order to provide a Methane Detection system for the addition and chassis wash. This system was an addition to the existing system placed in the Transfort Maintenance Facility in 2010. We were able to use existing ports in the system controller to add the six detectors in the addition, since the original system was sized to accommodate the addition. The detectors for the chassis wash addition had to be more capable units that will provide stand-alone capability that feeds back to the main control panel. A couple of iterations of the Pricing Change Request (PCR) were provided by the contractor in an effort to get the pricing in line. The contractor was then able to provide a proposal that was acceptable and PCR #11 was sent to me on August 281h. This PCR provides all of the components necessary for a complete Methane Detection System for the Transfort Maintenance Facility. Since this work will be done late in the project and the projected completion date is after the current Substantial Completion date, Heath Construction has requested a time extension of 19 days to complete this work, which I fully support. The labor, materials and equipment costs proposed by Heath Construction were evaluated against an Independent Cost Estimate and are consistent with pricing for similar work. As such, I find the cost of this Proposed Change Request #11 from Heath Construction converted into Change Order No. 6 in the amount of $19,548.52 to be reasonable for the required increase in scope. As such, I recommend acceptance of this additional cost to the contract and the 19 day time extension. Ron Kechter Project Engineer City of Fort Collins Operational Services - Facilities Cc: job file System for Award Management Page 1 of 1 R. C. HEATH CONSTRUCTION CO. DUNS: 096341062 CAGE Code: 4LGA6 Status: Active Entity Overview Entity Information Name: R. C. HEATH CONSTRUCTION CO. Doing Business As: HEATH CONSTRUCTION CO Business Type: Business or Organization POC Name: None Specified Registration Status: Active Expiration Date:03/28/2014 Exclusions Active Exclusion Records? No SAM I System for Award Mamge m 1.0 Note to all Users: This is a Federal Govemment computer system. Use of this systern constitutes consent to monitoring at all times. 141 RACQUE11TE DR FORT COLLINS, CO, 80524-3244, UNITED STATES IBM v1.1149.20130801-1829 www2 ® IUSACA .gov https://www.sam.gov/portal/public/SAM/?portal:componentld=fb67166e-75 d6-44cc-b77f—... 9/30/2013 Fort Collins Independent Cost Estimate Date of Estimate: 12-Aug-13 Contract Type: Fixed Price Existing Contract or PO (Y/N): Yes Description Services (B): Provide all labor, materials and equipment to install methane detection in the addition and in the chassis wash. The detectors in the addition will be tied to the existing main panel and tied to two new horn strobes. The detectors in the chassis wash will be stand alone and tied to one new horn strobe. I have obtained the following estimate from: Engineering or Techincal Estimate (performed by) - Ron Kechter B Transfort Maintenance Facilitv Exoansion Materials or Work Description Quantity Unit Unit Cost *** TOTAL Change Order #6 - PCR No. 11 Methane Detectors - Tie to Existing - Add. 6 EA $ 825.00 $ 4,950.00 Methane Detectors - Stand Alone - CW 2 EA $ 1,045.00 $ 2,090.00 Horn - Strobe Units 3 EA $ 350.00 $ 1,050.00 Methane Detection System Engineering 1 LS $ 625.00 $ 625.00 Programming 1 LS $ 500.00 $ 500.00 Miscellaneous Materials 1 LS $ 500.00 $ 500.00 Installation Labor 60 HR $ 75.00 $ 4,500.00 Cable & Installation 1200 LF $ 1.25 $ 1,500.00 Lifts P&D 1 LS $ 800.00 $ 800.00 Subcontractor Subtotal $ 16,515.00 Subcontractor Mark-up @ 15% $ 2,477.25 Subcontractor Total $ 18,992.25 Bond @ 1% $ 165.15 Overhead ro it o ota *** Unit Cost Based Upon Recent Experience Signature of Preparers _(j?�n Heath construction Job: Project No. 1280531 Title: Extend Methane Gas Detection Sysytem Project Transfod To: Attn: Ron Kechter City of Fort Collins - Facilities Management 281 N. CollegeAve. Fort Collins, CO 80524 DESCRIPTION OF PROPOSAL Provide labor mtd materials to extmM the e:tating methane ges detection System. GC'S Forces Pricing Change Request No. 11 Back Up Irdomtation Originating Document: o.e.tisauet Originating Document Date: a/1412013 PCO Date: 8/27/2013 Item Description TWO ON I Unit nit I Labor Material Equip subcontractor Other I Total 1 Rose Electric S 1.00 LS 0.00 0.00 0.00 18 442.00 0.00 $ 18 442.00 2 S 1.00 Ea 0.00 0.00 0.00 0.00 0.00 $ 3 S 1.00 LF 0.00 0.00 0.00 0.00 0.00 $ 4 S 1.00 EA 0.00 0.00 0.00 0.00 0.00 $ 5 S 1.00 Ea 0.00 0.00 0.00 0.00 0.00 $ a 7 0.00 0.00 0.00 0.00 0.00 $ 8 0.00 0.00 0.00 0.00 0.00 $ 9 0.001 0.00 0.00 0.00 0.00 $ 10 1 0.00 0.00 0.00 0.001 0.00 $ 11 0.00 O.DO 0.01) 0.00 0.00 $ 12 0.00 O.Do 0.00 0.00 0.00 $ 13 0.00 0.00 0.00 0.00 0.00 $ 14 0.00 0.00 0.00 0.00 0.00 $ 15 Additional General Conditions O 0.00 Days 0.00 0.00 0.00 0.00 0.00 $ 16 GC Carpenter Labor/fonnan-Addition L 0.00 hr 68.00 0.00 0.00 0.00 0.00 0.00 $ 17 GC Carpenter Labodforman-Chassis L 0.00 hr 68.00 0.00 0.00 0.00 0.00 0.00 $ 18 GC Project Management L 0.00 hr 0.00 0.00 0.00 0.00 0.00 0.00 $ 19 0.001 0.00 0.00 0.00 21 Subtotal 0.00 0.00 0.001 18,442.00 0.00 $ 18442.00 23 Sales Tax NA % O.I)D% 0.00 $ 24 Bond Premium O 18 442.00 % 1.00% $ 164.42 25 LiabilityInsurance O 10 442.00 % 0.63% $ 26 Builders Risk O 18 442.00 % 0.39% 28 ISubtotal 0.00 S 184.42 30 Labor Burden O 0.00% 1 0.00 32 Subtotal 0.00 $ 34 Overhead O 18 442.00 it 3.00% 553.26 553.26 Profit 1 O 18442.00 2.00% 1 368.84 368A4 35 36 Subtotal 0.00 0.001 0.001 0.001 0.00 $ 922.10 Note: 1e Addxtonal days of time an, requested as a mutt of We Merge. Total Cost S 19,548.52 Issued By: Reviewed By: Approved By: Paul L Ehrlich Jr., Project Manager Ron Kschtsr Project Architect Heath Construction City of Fort Collins Alter Ungle Massey Date Data ELLCTQIC August 14, 2013 Reference: Transfort Facility Ft. Collins, Colorado Paul The following delineates the inclusions, exclusions, and assumptions made during our cost estimate for the above referenced project. We are pleased to submit for your review and consideration our proposal to perform the additional electrical work on the above referenced project. This cost estimate is based on time and material work orders. Also included is the cost for the methane detection. Inclusions: 1.) All applicable sales taxes 0.0% 2.) Supply and install cable for each detector for each sensor. 3.) Clean up of our identifiable debris to dumpsters provided, serviced, and maintained by others. 4.) Supply and install methane detectors as submitted by Wilson/Mohr. 5.) Install new sensors. 6.) Install new cable from existing gas monitor station to new Watt Stopper cabinet. 7.) Install two new monitors in wash bay and six in new building. 8.) Supply and install supports for new cable. 9.) Supply man lift. 10.) Supply and install . 11.) Testing. 12.) Supply and install two horn/strobes in new building. 13.) Supply and install one new horNstrobe in wash bay area. Exclusions: 1.) Overtime. 2.) Permit fees and inspection fees. 3.) Sheet rock cut, patch repair and painting. 4.) Any and all raceway. 5.) Any and all modifications to existing gas monitor panel. Clarification: