HomeMy WebLinkAboutCHANGE ORDER - RFP - 7071 APP MASON CORRIDOR PROJECT (3)CHANGE ORDER NO. 02 PROJECT TITLE: Mason Corridor - MAX BRT CONTRACTOR: Robert Tully PROJECT NUMBER: APP Construction Agreement PURCHASE ORDER NO.: DESCRIPTION: Anchor Installation for South Transit Center Art Panels 1. Reason for change: This change order adds installation of epoxied anchors to the artist's contract for installation of stone art panels at the South Transit Center. This change is being made as this work was planned for incorporation into the South Transit Center's general contractor's scope of work. However, it was missed during contract document preparation. The construction manager feels it makes better logistical sense for the artist to perform this work and minimizes coordination overlap with the general contractor. 2. Description of Change: This change order installation of epoxied concrete anchors for the various art panel installations at the South Transit Center. The work includes drilling holes for anchor installation, cleaning, supplying and setting rebar or all -thread anchors with Engineer approved epoxy. Installation of the actual granite panels onto the anchors is included in the artist's base scope of work. The same epoxy specified by the Engineer shall be used to anchor the art panels in place. 3. Change in Contract Cost: $3 328 00 4. Change in Contract Time: 61 calendar days. Final completion for this is changed to December 31, 2013 ataz,00u.uu TOTAL APPROVED CHANGE ORDERS $56,697.00 TOTAL PENDING CHANGE ORDERS $0.00 TOTAL THIS CHANGE ORDER $ 3,328.00 TOTAL % OF ORIGINAL CONTRACT, THIS C.O. 1.73% TOTAL % OF ORIGINAL CONTRACT, ALL C.O.'S 31.16% ADJUSTED CONTRACT COST $252,675.00 (Assuming all change orders approved) ACCEPTED BY: Contractor's Rer REVIEWED BY: Construction Manager APPROVED BY: City Project Manager APPROVED BY: APP Representative DATE: 9/24/13 DATE: ?44-13 DATE: I •1 ?j DATE: 7 - 25-/3 APPROVED BY: N Y} DATE: Purchasing Agent over $60,000 cc: City Clerk Artist Contractor Engineer Project File Purchasing TULLY ARTWORKS 733 McKinley Ave., Louisville, CO 80027 720-771-8502 ww.tullyartworks.com PRICE QUOTE ADDITIONAL INSTALLATION ITEMS FOR STC GRANITE RELIEF PANELS: Drilling holes for 96 anchors with template, cleaning holes, epoxy anchors, scaffold setup and moving, cleaning, coordinate with contractor Epoxy Hilti HY150 14 tubes @$50 $700 (96) Stainless 304 5/8" all -thread rods 413 for anchors, cut for embedding 3-1/2" Scaffolding 200 Drill bits 45 Air compressor to blow out holes 190 Labor 14 hrs. @ $80 1120 Labor 14 hrs @ $40 560 Travel 100 Total $3,328 Member —International Sculpture Center DO CHANGE ORDER NO. 2 SUPPORTING DOCUMENTATION Project: Mason Corridor — MAX BRT Art in Public Places Construction Agreement with Robert Tully Purchase Order No. 9126495 Date: September 23, 2013 Description of Change: MAX Field Construction Office 3000 South College Ave., Suite 201 Fort Collins, CO 80526 fcgov.com/maxconstruction This change order adds supply and installation of concrete anchors (epoxy) for mounting granite art panels at the South Transit Center. Installation of anchors will include supply of stainless steel rods, epoxy, drilling anchor holes into cast concrete and setting anchors on the interior and exterior of the South Transit Center building. This change is being initiated by the City of Fort Collins as mounting of the granite art panels was not included in the artist's original contract. This work was intended for the general contractor. However, this work was also left out of their contract. Change in Contract Value: The contract value is being increased by $3,328.00. Please see attached proposal from Robert Tully. Change Order No. 2 Item Number Description Change in Contract Value 1 1 Add installation of concrete anchors for granite art panels 1 $3,328.00 Change in Contract Time: The contract time is being extended to December 31, 2013 to match that of the South Transit Center completion schedule. MAX Field Construction Office 3000 South College Ave., Suite 201 Fort Collins, CO 80526 fcgov.com/maxconstruction Delivery by hand September 20, 2013 Ms. Erika Keeton, PE MAX Project Manager City of Fort Collins — Engineering Dept 281 N. College Ave. Fort Collins, CO 80524 RE: MAX Bus Rapid Transit Project Independent Cost Analysis — Robert Tully Change Order #2 Art Panel Anchors — South Transit Center This change order adds installation of epoxy set anchors for setting of art panels at the South Transit Center. This work is being added to the artist's contract as it was left out of both the artist's scope of work and general contractor's contract. In reviewing this request, the independent cost estimate was prepared using an average labor rate, material quotes and comparable costs from the BRT contract. The independent cost estimate is attached. The independent cost estimate is $4,006.00. As such, I find Robert Tully's pricing for this change in the amount of $3,328.00 to be reasonable for the required increase in scope. As such, I recommend approval of this request for an addition to the contract. KeitF4Mye PE Construction Project Manager CH2M HILL Team 970-988-8605 keith.meyer(a)ditescosery ices.com Cc: job file Change Management Checklist .. ..te Reviewed for compliance with Part of the build alternative; scope Environmental Assessment 9/20/13 of work included in SCC 20.01; KM inside area of influence Included in work area; artist to Reviewed for construction/safety impacts 9/20/13 provide all scaffolding and safety KM items required to meet OSHA regs Independent cost estimate prepared 9/20/13 See attached KM Reviewed for PCGA grant compliance 9/20/13 Part of Build Alternative KM scope is included in SCC 20.01 Reviewed for real estate impacts/needs 9/20/13 Construction inside city owned KM property Reviewed for compliance with design criteria/ADA htto://www.access-board.gov/ada-aba/ada- 9/13/13 n/a KM standards-dot.cfm ffifiesco Independent Cost Estimate Date of Estimate: 9/20/2013 Contract Type: Artist Contract - APP Existing Contract or PO (Y/N): Y Description of Goods (A) or Services (B): B The scope of work is to provide for installation of anchors into concrete columns for installation of granite art panels left out of the artist's and contractor's scope of work. I have obtained the following estimate from; Published Price List / Past Pricing (date) Engineering or Technical Estimate (performed by) Keith Meyer Independent Third Party Estimate (performed by) Other (specify) Misc. Suppliers Cost Estimate Details: (Estimate calculated in US Dollars) Cost of Standard Items DESCRIPTION ITEM # QUANTITY UNIT UNIT PRICE TOTAL Labor for installation NA 40 HR 7 6-500 7 2,600.00 Anchors CEI cost 100 LB $ 1.06 $ 106.00 Epoxy NA 20 EA $ 30.00 $ 600.00 Travel NA 1 LS $ 200.00 $ 200.00 Small tools (allowance) NA 1 LS $ 500.00 $ 500.00 TOTAL I I I 1 4,006.00 Cost of Services, Repairs, or Non -Standard Items Item/Task: Materials or Work Description Other Direct Costs Labor Labor Hours Class Allocated Overhead SG&A` Profit TOTAL $ Total I Is `Selling, General and Adminlslretive Expenses Signature of Preparers System for Award Management Page 1 of 1 Search Results Current Search Terms: robert* Tully* No records found for current search. SAM I System for Award Management 1.0 Note to all Users: This is a Fedml Govemment computer system. Use of this system constitutes consent to mnitoring at all tones. IBM v1.1199.20130801-1829 ® 'USA.9LN<_ Lrr' https://staging.sam.gov/portal/public/SAM/?portal:componentld=d l O l 1732-a781-4ea5-b0... 9/27/2013