HomeMy WebLinkAboutBID - 7506 SPRING CREEK TRAIL CONNECTION CENTER AVE TO MASON TRAILADDENDUM NO. 1
SPECIFICATIONS AND CONTRACT DOCUMENTS
Description of BID 7506: Spring Creek Trail Connection - Centre Ave to Mason Trail
OPENING DATE: 3:00 PM (Our Clock) May 14, 2013
To all prospective bidders under the specifications and contract documents described
above, the following changes/additions are hereby made and detailed in the following
sections of this addendum:
Exhibit 1 – Revised Bid Schedule
Exhibit 2 – General Clarifications
Exhibit 3 – Revised Section 01800 Definition of Bid Items
Exhibit 4 – Replacement Plan Sheets
Please contact John Stephen, CPPO, LEED AP, Senior Buyer at (970) 221-6777 with
any questions regarding this addendum.
RECEIPT OF THIS ADDENDUM MUST BE ACKNOWLEDGED BY A WRITTEN
STATEMENT ENCLOSED WITH THE BID/QUOTE STATING THAT THIS
ADDENDUM HAS BEEN RECEIVED.
Financial Services
Purchasing Division
215 N. Mason St. 2nd Floor
PO Box 580
Fort Collins, CO 80522
970.221.6775
970.221.6707
fcgov.com/purchasing
Addendum 1 – 7506 Spring Creek Trail Connection – Centre Ave to Mason Trail Page 1 of 10
EXHIBIT 1 – REVISED BID SCHEDULE
BID ESTIMATED UNIT ITEM
ITEM # DESCRIPTION QUANTITY UNIT PRICE TOTAL
1 Mobilization 1.00 LS
2 Demolition 1.00 LS
3 Erosion Control 1.00 LS
4 Topsoil Remove/Replace 322.00 CY
5 Unclassified Excavation 118.00 CY
6 Colored Concrete Paving - 5" Thick 11,780.00 SF
7 Colored Concrete Paving - 8" Thick (High Early Mix) 654.00 SF
8 6" Crusher Fines Path 4,003.00 SF
9 8’ Chain Link Fence/Move Existing Gates 86.00 LF
10 Asphalt Trail Removal/Recycle 15,700.00 SF
11 Landscape Restoration 25,325.00 SF
$
(Total Base Bid Written)
TOTAL OF BASE BID
Bid items are described in Section 01800
Addendum 1 – 7506 Spring Creek Trail Connection – Centre Ave to Mason Trail Page 2 of 10
EXHIBIT 2 – GENERAL CLARIFICATIONS
1. Existing Shed (shown on sheet 4, under Exhibit 4) is to be relocated
approximately 30 foot south of existing location, by the contractor.
2. Entire length of existing asphalt trail will be closed off during construction to allow
contractor to remove asphalt trail prior to earthwork and to provide an area for
the stripped topsoil new 12’ concrete trail.
3. City of Fort Collins will provide its own traffic control for existing trail closure and
detour route of Spring Creek Trail.
4. Construction access to the project is to be north, off of Prospect Road by way of
Bay Road, and from the south, off of Drake by way of Red Wing Drive only.
5. VTC has been removed. (See sheet 4, under Exhibit 4)
6. Crusher fines path is to be adjoined to north side of the new concrete trail,
eliminating the 1’ shoulder between the two. (See sheets 4,5,6,& 7, under Exhibit
4)
7. Demolition of existing trees should be taken to City of Fort Collins, Forestry Tree
Disposal Site, which is located south of the intersection of Prospect and
Timberline Roads.
8. Bay Road needs to remain open; both for through traffic and for the Fisheries
and Grounds Operations which take place just south of the bridge. However, a
closure of Bay Road at the bridge will be permitted and the gate on the south part
of the bridge can be shut for that purpose, but it should be for as short of time as
possible. To close it, a closure request needs to be made to CSU Facilities
Management, complete with a map and a traffic control plan.
9. A City of Fort Collins approved 4,000 psi, 48 Hour High-Early Concrete Mix will
be used to pour the widened 8” thick trail crossing at Bay Road.
10. There is no irrigation to establish the revegetated areas. It will rely on Mother
Nature to get it established. If the contractor’s revegetation has been done
according to specifications, and the seed does not properly geminate due to lack
of moisture, the City of Fort Collins will not hold the contractor responsible to
reseed.
11. Substantial Completion will be established by the Project Manager once the new
12’ concrete trail can be opened safely for public use.
12. A City of Fort Collins Floodplain Use Permit has already been established for
construction in the FEMA regulated floodplain. No other permits are required for
construction.
Addendum 1 – 7506 Spring Creek Trail Connection – Centre Ave to Mason Trail Page 3 of 10
13. Bid Item 7 Concrete Paving 8” Thick has changed, to address using a 48 Hour
High-Early Concrete Mix. (See new Section 1800 Definition of Bid Items under
Exhibit 3)
14. Line Item 7 has changed to address High Early Concrete Mix. (See New Bid
Schedule)
Addendum 1 – 7506 Spring Creek Trail Connection – Centre Ave to Mason Trail Page 4 of 10
City of Fort Collins Section 01800 - Definition of Bid Items
Park Planning & Development Division Page 1 of 2
DIVISION 1
SECTION 01800 – DEFINITION OF BID ITEMS
The following items describe the scope of work for this contract and are further clarified through limit-of-work lines,
notes on the drawings and specifications. The work described in each Bid Item may contain work from one or
several technical specifications sections. Contractor shall refer to the technical specifications that apply to the
individual components.
Bid Items 1 – Mobilization
This work includes the mobilization of personnel, equipment and supplies at the project site(s) in preparation for
work on the project, as well as the establishment of the Contractor’s office, buildings and other necessary facilities,
and all other costs incurred or labor and operations which must be performed prior to beginning the other items
under the Contract. This item shall also include marshalling, disassembly and security of all items indicated on the
plans or specifications. Payment will be made as Work progresses. Payment for this item will follow in accordance
with CDOT Standard Specifications for Road and Bridge Construction, Section 626. The total amount for
mobilization shall not exceed five percent (5%) of the total bid.
Bid Items 2 – Demolition
Contractor shall provide all labor and equipment for clearing, grubbing, removing, and disposing of existing trees,
shrubs, existing fencing and debris and other areas shown required by the work. Vegetation and objects designated
to remain shall be preserved free from injury or defacement. Work includes all hauling and fees in accordance with
the drawings and specifications.
Bid Items 3 – Erosion Control
Contractor shall install and maintain erosion control items during construction in accordance with the Drawings and
Specifications including, but not limited to Sections 107 and 208 of the most current CDOT Road & Bridge
Construction Manual, construction entrance, vehicle tracking pad, concrete washout, wattles, etc. in accordance with
the drawings and specifications.
Bid Item 4 – Topsoil Remove/Replace
Contractor shall furnish all labor, materials and equipment to strip, stock, distribute, rough grade, and fine grade (4”
thick) topsoil from limits of grading. Bid amount includes all labor, material and equipment for a complete item in
accordance with the drawings and specifications.
Bid Item 5 – Unclassified Excavation
Contractor shall furnish all labor, materials and equipment for site excavation including stockpiling, distribution,
removal of debris and haul and disposing of all excess material per drawings and specifications.
Bid Items 6 – Colored Concrete Paving – 5” Thick
Contractor shall furnish all labor, materials and equipment to install concrete paving in accordance with the
Drawings and Specifications. The unit price includes sub-grade preparation which consists of ripping soil to 8” and
re-compacting to 95% proctor, installation of 5” thick (4,000 psi) standard concrete with fiber mesh reinforcement,
and integral color additive equaling 2 lbs. per sack of Yosemite Brown color, forming; furnishing and applying
curing compounds; finishing and edging the concrete surfaces; joints and joint materials; furnishing and compacting
base course as required for preparation of a stable sub base; and all other related and necessary materials, work, and
equipment required to construct the flatwork areas in accordance with the drawings and specifications.
Bid Items 7 – Concrete Paving – 8” Thick
Contractor shall furnish all labor, materials and equipment to install concrete paving in accordance with the
Drawings and Specifications. The unit price includes sub-grade preparation which consists of ripping soil to 8” and
re-compacting to 95% proctor, installation of 8” thick City of Fort Collins approved (4,000 psi), 48 Hour High-Early
Concrete Mix with fiber mesh reinforcement, forming; furnishing and applying curing compounds; finishing and
edging the concrete surfaces; joints and joint materials; furnishing and compacting base course as required for
EXHIBIT 3 - REVISED SECTION 01800 DEFINITION OF BID ITEMS
Addendum 1 – 7506 Spring Creek Trail Connection – Centre Ave to Mason Trail Page 5 of 10
City of Fort Collins Section 01800 - Definition of Bid Items
Park Planning & Development Division Page 2 of 2
preparation of a stable sub base; and all other related and necessary materials, work, and equipment required to
construct the flatwork areas in accordance with the drawings and specifications.
Bid Item 8 - 6" Crusher Fines Path
Contractor shall furnish all labor, materials and equipment to install a 6” crusher fines path adjacent to the new 12’
concrete trail. The unit price includes landscape fabric to be placed between the ground and the crusher fines for the
full width of the path in accordance with the drawings and specifications.
Bid Item 9 – 8’ Chain Link Fence/Move Existing Gates
Contractor shall furnish all labor, materials and equipment to install a new 8’ high chain link fence adjacent to the
new 12’ trail and move two (2) existing chain link fence gates in accordance to the drawings and specifications.
Bid Item 10 – Asphalt Trail Removal/Recycle
Contractor shall furnish all labor, materials and equipment to remove and recycle existing asphalt trail and haul to
the City of Fort Collins – Crushing Operations at 1380 Hoffman Mill Road in accordance to the drawings and
specifications.
Bid Items 11 – Landscape Restoration
Contractor shall provide all soil preparation; fine grading; fertilizer; herbicide; seed; labor; hydro-mulching and
equipment to seed any area disturbed during construction in accordance with the drawings and specifications.
END OF SECTION
END OF DIVISION 1
Addendum 1 – 7506 Spring Creek Trail Connection – Centre Ave to Mason Trail Page 6 of 10
Addendum 1 – 7506 Spring Creek Trail Connection – Centre Ave to Mason Trail Page 7 of 10
EXHIBIT 4 - REPLACEMENT PLAN SHEETS
Addendum 1 – 7506 Spring Creek Trail Connection – Centre Ave to Mason Trail Page 8 of 10
Addendum 1 – 7506 Spring Creek Trail Connection – Centre Ave to Mason Trail Page 9 of 10
Addendum 1 – 7506 Spring Creek Trail Connection – Centre Ave to Mason Trail Page 10 of 10