HomeMy WebLinkAbout102624 PLATTE RIVER POWER AUTHORITY - CONTRACT - PURCHASE ORDER - 9133751INTERGOVERNMENTAL AGREEMENT FOR THE DESIGN AND RELOCATION OF PLAT'TE.RIVER, POWER AUTHORITY TRANSMISSION FACILITIES This, Intergovernmental Agreement for the Design and Relocation of Platte River Power Authority Transmission Facilities is entered on this/.0day of April 2013, between Platte River Power Authority, a political subdivision of the State of Colorado (Platte River), and the City of Fort Collins, a Colorado home rule. municipality (Fort Collins). RECITALS WHEREAS, Platte River owns and operates a 230kV/115kV double circuit overhead transmission line that crosses the Link-N-Greens Golf Course in Fort Collins, and WHEREAS, Woodward, Inc. (Woodward) is considering moving its corporate headquarters facilities to the property currently occupied by Link-N-Greens Golf Course; and WHEREAS, in order to. make the Link-N-Greens Golf Course property useable as a Woodward headquarters complex, approximately 3600 linear feet of the overhead transmission line crossing the Link-N-Green property, specifically the line segment between structures TP-28 on the north and TP-19 on the south (Transmission Facility) will need to be removed and new transmission facilities of a like configuration relocated to a route that runs parallel to Lemay Street (Relocated Transmission Facility); and WHEREAS, construction schedules for Woodward facilities may necessitate the construction and removal of a Temporary Transmission Facility; and WHEREAS, Platte River is willing to remove the Transmission Facility, to construct and remove the Temporary Transmission Facility, and design and construct the Relocated Transmission Facility to accommodate the requirements of Woodward, provided it is reimbursed for the costs associated with this effort; and WHEREAS, Fort Collins is negotiating with Woodward and the Fort Collins Downtown Development Authority to develop a plan for funding of public improvements and related financial incentives and financing arrangements in light of the expected benefits to the Fort Collins community in the event that Woodward constructs its new headquarters facility as described herein; and WHEREAS, subject to the specific terms of this Agreement, Fort Collins is willing to reimburse Platte River the reasonable costs of removal of the Transmission .Facility, the Intergovernmental Agreement for the Design and Relocation of Platte River Power Authority Transmission Facilities Page 1 of 3 reasonable costs of construction and removal of the. Temporary Transmission Facility, if necessary, and the reasonable costs of design and construction of the Relocated Transmission Facility; and WHEREAS, the parties have the authority under C.R.S. § 29-1-203 to enter into intergovernmental agreements provided such agreements are approved by.the legislative body of each party. AGREEMENT 1) Platte River agrees to undertake the removal of the Transmission Facility, the construction and removal of the Temporary Transmission Facility, if necessary, and the design and construction of the Relocated Transmission Facility on the Link-N-Green Golf .Course, in accordance with plans and specifications mutually approved and consistent with the reasonable expectations of the parties (the "Work'). The routes of the Temporary Transmission Facility and the Relocated Transmission Facility are displayed on Exhibit A. The Temporary Transmission Facility and the Relocated Transmission Facility will be constructed overhead. 2) Fort Collins agrees to reimburse Platte River for all reasonable costs incurred in the performance of the Work; provided however that Fort Collins will have no reimbursement obligation unless and until: 1) Fort Collins provides written notice to Platte River that Fort Collins has completed the arrangements necessary for Fort Collins to move forward with the financing or funding of the Work; and 2) Woodward purchases the Link-N-Green property. If the obligation to reimburse Platte River accrues, Fort Collins acknowledges that some of the reimbursable costs were incurred by Platte River prior to the date of this Agreement, but such costs, if reasonable and necessary for the completion of the Work, will be treated as part of the Work and reimbursable hereunder. 3) Platte River will invoice Fort Collins for the costs of the relocation project on a quarterly.basis, invoices payable within thirty (30) days of receipt. Invoices will itemize all costs for which reimbursement is sought. 4) Exhibit B contains an estimate of the costs for the removal of the Transmission Facilities, the construction and removal of the Temporary Transmission Facility; and costs for the design and construction of the Relocated Transmission Facility. Fort Collins acknowledges that Exhibit B is an estimate of anticipated costs, and Intergovernmental Agreement for the Design and Relocation of Platte River Power Authority Transmission Facilities Page 2 of 3 that actual costs may vary: Subject to the limitations set forth herein, Fort Collins is responsible for the reimbursement of all reasonable costs incurred by Platte River to carry out the Work. In the event that Platte River discovers conditions or circumstances that are expected to lead to costs in excess of the estimates contained in Exhibit: B, Platte River will promptly notify FortCollins in writing of such conditions or circumstances and will discuss with Fort Collins such cost impacts and possible mitigation. If the reimbursable costs of the Work exceed $2,000,000.00, Platte River will credit Fort Collins all "PRPA Project Management' expenses, presently estimated to amount to $168,000.00. 5) Financial obligations of Fort Collins payable in future fiscal years shall be subject to the annual appropriation of funds sufficient and intended for the same. Fort Collins will notify Platte River in writing as soon as practicable concerning the appropriation of funds during future fiscal years. Platte River will have no obligation to perform any activity associated with the Work beyond December 31, 2013, unless and until receipt of notice that funds have been appropriated. 6) This is the entire agreement of the parties on this issue. This Agreement may only be modified by a writing executed by both parties. 7) Fort Collins agrees to be the lead agency and take responsibility for all public processes and for obtaining all necessary permits for the work. IN WITNESS WHEREOF, the Parties have caused this Agreement, to be executed the day and year first above written. PLATTE RIVER POWER AUTHORITY ATTEST: By: ��c.•�-c-c. �. By: V General Manager Assistant Secfl CITY OF FORT COLLINS, COLORADO ATTEST: By:9C�(itQi►(J %C%e.(,LRZLt���- By: Mayor City Clerk�*C APPROVED AS TO FORM: Intergovernmental Agreement for the Design and Relocation of Platte River Power Authority Transmission Facilities""' acilities�• `� ��`% Page 3 of 3 fi• Relocated Transmission Facility RPM Existing Transmission Facility Temporary Transmission Facility WOODWARD IGA EXHIBIT A FEBRUARY 27, 2013 February 21, 2013 Woodward IGA Exhibit B 2023 2014 Activity 2nd Qtr 3rd Qtr 4th Qtr 1st Qtr 2nd Qtr 3rd Qtr 4th Qtr Total Exspenses to Date $35,000.00 $35,000.00 Black & Veatch Design $25,000.00 - $25,000.00 $25,000.00 $25,000.00 $10,000.00 $110,000.00 Transmission Towers $281,000.00 $281,000.00 Transmission Hardware $100,000.00 $100,000.00 Transmission Construction $275,000.00 $110,000.00 $385,0pp,00 Removal of Line $65,000.00 $65,000.00 Restoration $20,000.00 $10,000.00 $5,DD0.00 $35,000.00 PRPA Project Management $20,000.00 $20,000.00 $25,000.00 $40,000.00 $40,000.00 $10,000.00 $5,000.00 $160,000.00 Miscellaneous Items $6,0D0.00 $6,000.00 $6,0D0.00 $6,000.00 $6,000.00 $30,000.00 Subtotal $92,88&00 $SS,080.00 $60AS0.00 $785,160.00 $271,080.00 $21,600 00 $10,800 00 $1,297,OSQ00 Order # Vendor/Supplier # OV # Batch # Acct#-_ y2o/ozon3. S2/1N0. •b �F.p