HomeMy WebLinkAboutWORK ORDER - RFP - 7175 BRIDGE INSPECTION MAINTENANCE REPAIR AND REPLACEMENT PROGRAM (11)EXHIBIT "A"
WORK ORDER rORPM
PURSUANT TO AN AGREENIENT BETWEEN
THE CITY Or PORT COLLINS
and
MICIIAEL BAKER JR., INC.
DATED: June 20, 2013
Work Order Number: MB10-254902100
Project Title: Bridge Inspection, Maintenance, Repair and Replacement Program
Arthur Ditch Manhole Retrofits at Lake Street and Prospect Road Project
Commencement Date: June 20, 2013
Completion Date: April 30, 20H
Maxinimn Pee: (time and reimbursable directs costs): not to exceed $26,906.97
Project Description: See attached project description.
Scope of Services: See attached scope of service.
Service Provider agrees to perform the services
identified above and on the attached forms in
accordance with the terms and conditions
contained herein and in the Services Agreement
between the parties, in the event of a conflict
between or ambiguity in the terms of the
Services Agreement and this work order
(including the attached farms), the Services
Agreement shall control.
Service Provider
i\
Date: June 20. 2013
Approved By:
Purchasing Agent over $60,000
The attached forms consisting of five (5) pages
are hereby accepted and incorporated herein by
this reference, and Notice to Proceed is hereby
given,
Cit,
By:
bat
Exhibit "A"
WORK ORDER FORM
PURSUANT TO AN AGREEMENT BETWEEN
THE CITY OF FORT COLLINS
AND
MICHAEL BAKER JR., INC.
DATED: June 15, 2013
Work Order No. 10
Purchase Order No.
Project title: Bridge Inspection, Maintenance, Repair and Replacement Program
Arthur Ditch Manhole Retrofits at Lake Street and Prospect Road Project
Commencement Date: June 6, 2013
Completion Date: November 30, 2013
Maximum Fee: $26,906.97
PROJECT DESCRIPTION
The purpose of this project is to provide final design services, including constriction documents, for the
retrofit of the Arthur Ditch Concrete Box Culverts (CBCs) at Lake Street and Prospect Road Fort Collins,
Colorado. The retrofits will provide new manholes in the top slab of these structures for the purposes of
improving personnel, access and safety.
The existing culvert access to the south of Prospect Road is a two -foot diameter manhole with a tapered
transition to an offset four -foot diameter bottom riser section. The existing manhole is located in the top
slab on the western side of the CBC. This manhole is to be replaced with a three-foot diameter manhole
access in the same.area as the existing access, although located on tine eastern side of the culvert.
Currently no culvert access is provided to the north of Prospect Road. A three-foot diameter manhole
access is to. be provided at this location as part of this project. This proposed access is in parking lot
adjacent to a CSU parking garage, a sidewalk, and nearby businesses. The CITY will direct BAKER with
the exact location of this new manhole. The manhole cover will be rated for traffic loading.
At Lake Street, culvert access is already currently provided by a manhole at approximately 50 feet south of
the roadway. An additional access point is to be provided to the north of the roadway, adjacent to CSU
facilities and public walkways through existing embankment fill.
All three manhole retrofits will be similar in nature. A portion of the top slab of the culvert will be removed
and replaced with new manhole accesses.
This scope of work defines the effort required to provide bid documents for the retrofit of the top slab of
the culvert to include manhole access at these locations. No other rehabilitation work is anticipated at this
time.
Exhibit A -Work Order Form —Work Order No.10
Bridge Inspection, Maintenance, Repair and Replacement Program —Arthur Ditch Manhole Retrofit Project
SCOPE OF SERVICES:
The scope of services for this project is to perform design services and prepare construction documents for
the retrofit of the Arthur Ditch Concrete Box Culvert access locations adjacent to Lake Sheet and Prospect
Road. This work includes the replacement of portions of the top slab sections as necessary to accommodate
new manholes.
BAKER will provide design services including: project management, Feld inspection, structural design,
cost estimating, and bidding/construction assistance. All work will be based upon information determined
from the original construction plans, inspection reports, and field inspections.
Services not included in this scope of work include and provided by the CITY, if necessary, are: traffic
control including pedestrian facilities, erosion control, utility identification and coordination, topographical
survey, envirormrental coordination and permitting, and right-of-way services.
Design criteria, standard details, and specifications shall first follow CDOT guidelines and secondly follow
CITY guidelines. Final Construction Documents shall be consistent with CDOT requirements. The design
process will only include one review by the CITY. The final product for this scope is a complete
construction bid package (plans, specification, and estimate) for modifications to the Arthur Ditch Concrete
Box Culverts adjacent to Lake Street and Prospect Road.
I. PROJECT ADMINISTRATION
Upon notice to proceed, BAKER will perform project administration duties throughout the length of the
contract.
A. Invoices will be provided to the CITY on a monthly basis and will include a billing summary and
a progress report for work performed during the billing period.
B. All documents will receive a quality assurance and quality control (QA/QC) review, in accordance
with the BAKER Way Manual, prior to submittal.
C. The following meetings are anticipated:
rr Weekly Status Meetings by Phone
rr One Pre -Design Meeting (Fort Collins)
n One Design Review Meeting (Fort Collins)
TT One Pre -Construction Meeting (Fort Collins)
D. BAKER will prepare documentation of meetings and telephone conversations and provide them to
the CITY for review and recording keeping.
II. FINAL DESIGN
The final design phase includes preparation construction document preparation for the project. Work
elements include:
A. Structural Design — BAKER shall prepare engineering design calculations as necessary.
Independent design calculations shall be prepared in accordance with CDOT guidelines and
procedures. Design calculations shall be submitted to the CITY upon request. A load rating
package and construction field package will not be included in this scope.
June 15, 2013 2 of 5
Exhibit A - Work Order Form — Work Order No.10
Bridge Inspection, Maintenance, Repair and Replocement Progrom —Arthur Ditch Manhole Retrofit
B. Construction Phasing Plan — BAKER will prepare constriction documents assuming no
construction phasing considerations are necessary.
C. Traffic Control Plan — The CITY is responsible for determination of traffic control approach and
all devices, and implementation during construction. BAKER will prepare construction documents
assuming no impacts to adjacent roadways and limited impacts to adjacent sidewalks and parking
lots by use of shoring.
D. Erosion Control Plan — At direction from the CITY, an erosion control plan will not be prepared as
part of the construction documents.
E. Construction Plans — BAKER shall prepare construction plans for the full scope of the project.
This work order includes all work necessary to develop final construction plans. The plans shall be
QC. reviewed prior to submittal to the CITY. Constriction plans shall be prepared in the
Microstation format. The anticipated sheet index of the construction documents include:
IT Cover sheet (x1)
7T General Information (xl)
rt SAQ / Tabulations (xl)
IT General Layout (x2)
rr Removal Details (xl)
rr Culvert/Manhole/Sidewalk Details (x3)
F. Project Specifications — Project specifications will not be provided separately but included in the
plans. All work shall be in accordance with the 2011 Colorado Department of Transportation
(CDOT) Standard Specifications for Road and Bridge Construction as amended in the
construction documents. The construction specifications shall follow CDOT specifications where
applicable and CITY specifications, otherwise.
G. Construction Cost Estimate — BAKER will prepare quantities and an engineer's estimate of
probable construction costs for all work items anticipated on the project.
III. ADVERTISEMENT
The advertisement design phase includes revisions to the final design and construction documents in
response to comments provided by the CITY from the design review. Work elements include:
A. Structural Design — BAKER shall revise the engineering design according to comments from the
CITY. All documents shall be signed and sealed.
B. Contract Documents — BAKER shall revise constriction plans and project specifications
according to comments from the CITY.
C. Construction Cost Estimate — BAKER will prepare quantities and an engineer's estimate of
probable construction costs for all work items anticipated on the project.
June 15, 2013 3 of5
Exhibit A - Work Order Form — Work Order No.10
Bridge Inspection, Maintenance, Repair and Replacement Program —Arthur Ditch Manhole Retrofit Project
D. Assistance with Project Bidding - It is anticipated that a traditional bidding process will be
followed for this project. BAKER will attend a pre -construction meeting with the CITY and
Contractor.
E. Preparation of a Complete Plan Set for Review by the CITY — Prepare a 100% plan set for review
by CITY staff. The plans shall be prepared as a stand-alone construction document. Any
information that would typically be conveyed through project special Provisions will be included
as notes as part of the plan set. Only one CITY review will be provided.
F. Preparation of "For Construction" Plan Set — Prepare a final plan set package that incorporates any
revisions from CITY the review. Plans shall be marked "FOR CONSTRUCTION, (DATE)". All
documents that are signed and sealed.
G. Construction Administration Assistance — BAKER will provide construction administration and
design support services. Construction administration effort may include: RFI responses, as -built
plans, shop drawing review, and design support, amongst others. For estimating purposes, it is
assumed that this work.will require no more than 20 hours of labor from BAKER.
IV. REFERENCES AND DESIGN CRITERIA
The following references and design criteria shall be used throughout all phases of the project:
A. All structural design shall follow the load and resistance factor design (LRFD) methodology.
Design shall be in accordance with the American Association of State Highway and
Transportation Officials (AASHTO) LRFD Bridge Design Specifications, 6th Edition (2012) with
interims througli 2013.
B. Construction document plans shall be prepared in accordance with the latest version of the CDOT
Bridge Detailing Manual.
C. Construction specifications will be prepared in accordance with the 2011 Colorado Department of
Transportation (CDOT) Standard Specifications for Road and Bridge Construction.
V. DELIVERABLES
The following is an estimate of the deliverables required for this project. As the project develops, the
type and number of deliverables may vary. Refer to the detailed discussions above for further detail. All
copies shall be submitted in hard copy and .pdf format; plans are 11x17, all others 8% xl 1, except as
noted otherwise.
Project Administration:
- Monthly progress reports with monthly invoices
- Meeting and telephone conversation documentation
- Quality Control review of all project deliverables prior to their submittal
100% Review
- Review plans
- Draft construction cost estimate
June 15, 2013 4 oJ'5
Exhibit A -Work Order Farm —Work Order No.10
Bridge Inspection, Maintenance, Repair and Replacement Program —Arthur Ditch Manhole Retrofit Project
Advertisement
- "For Construction" plans (1 half-size plan set, electronic PDF files)
- Construction cost estimates
- Final design calculations, signed and sealed (housed at BAKER unless requested otherwise
by the CITY)
VI. SCHEDULE
Construction documents will be completed and submitted to the CITY for review as soon as possible,
but no later than August 31, 2013, unless directed otherwise by the CITY. Construction support
services will extend through Construction as appropriate.