HomeMy WebLinkAboutPrebid - BID - 7501 TURNBERRY ROAD LANDSCAPE & IRRIGATION PROJECT1
11
Turnberry Road Landscape and Irrigation
Project
Bid # 7501
PRE-BID CONFERENCE
April 12, 2013
10 A.M.
215 N. Mason Street.
Conference Room 2A
City of Fort Collins
Engineering Dept.
Capital Improvements Program
22
• Engineering: INTRODUCTIONS
Capital Projects Program:
o Dean Klingner – Interim Program Manager 970-218-4962
o Mark Laken - Project Construction Engineer 970-222-3546
o Craig Farver – Project Construction Inspector 970-222-0854
• Purchasing:
– John Stephen - Purchasing Agent 970-221-6777
2
33
ATTENDANCE
• Please be sure to register
• BID OPENING
– When: Friday, April 26, 2013 @ 3:00 P.M.
– Where: 215 North Mason Street (2nd
Floor)
44
3
55
IMPORTANT CONTRACT DATES:
• AWARD CONTRACT
o Bid Opening April 26, 2013 at 3:00 PM
o Award within two to five business days after bid opening
• PRE-CONSTRUCTION MEETING
o Mandatory Meeting Prior to Start of Construction
o Date to be determined after contract is awarded
• CONSTRUCTION START DATE
o Approximately May 10, 2012
o Completion Date Contract
• SUBTANTIAL COMPLETION – June 28, 2013
• FINAL COMPLETION – July 12, 2013
66
CONTRACT DOCUMENTS FOR BID # 7501:
• PLAN SHEETS
– Prepared by Ripley Design, Inc.; Hines Irrigation; and Bromfield &
Associates.
– Sheets 1,50,51, 66-68, 79, 81-84, 101-104
• SPECIFICATION BOOK
– Prepared by City of Fort Collins Engineering and Ripley Design,
Inc.
4
77
SUMMARY OF WORK
Turnberry Landscape and Irrigation Project:
• Install Landscape and Irrigation on the east and
west sides of Turnberry Road between Richard’s
Lake Road and west side of Turnberry Road 500
feet south of Country Club Road
– Landscaped Parkways (Trees, Shrubs,
Perennials, Sod)
– Mulch Beds
– Stacked Block Retaining Walls
– Irrigation
– Landscape Maintenance
• Traffic Control will be provided by City of Fort
Collins
88
HIGHLIGHTS FROM GENERAL
CONDITIONS AND GENERAL REQ’S:
• SUPERINTENDENTS:
o The General Contractor SHALL employ a full time superintendent or jobsite
foreman whose primary responsibility is to monitor and coordinate all
facets of the work
• LIQUIDATED DAMAGES:
o SUBSTANIAL COMPLETION:
• The contractor will need to meet substantial completion requirements
by June 28, 2013. Substantial completion shall be defined as the
completion of all landscape plantings, irrigation, and stacked walls. If
the Contractor goes past the completion date (June 28, 2013), damages
in the amount of six hundred dollars ($600.00) for each calendar day
will be assessed.
o FINAL ACCEPTANCE:
Final acceptance must be met within 14 calendar days of substantial
completion. Liquidated damages in the amount of three hundred
dollars ($300.00) per calendar day will be charged if this schedule has
not been met.
5
99
HIGHLIGHTS FROM GENERAL
CONDITIONS AND GENERAL REQ’S:
• Traffic Control:
– Two way traffic on all roadways will be maintained at all times.
– Traffic Flagging is available, but will be used sparingly and will
need to be coordinated with the City’s Traffic Control
Supervisor.
– The City will setup lane shifts for the work when requested by
the contractor.
1010
HIGHLIGHTS FROM GENERAL
CONDITIONS AND GENERAL REQ’S:
• CONSTRUCTION HOURS:
• Standard Hours of Operation
• 7:00 A.M. thru 6:00 P.M. - Monday thru Friday.
• Given the scope of the proposed improvements,
the City will permit extended working hours
– Extended Hours requests must be made in
writing
6
1111
HIGHLIGHTS FROM GENERAL
CONDITIONS AND GENERAL REQ’S:
PROJECT MEETINGS:
Once a week at the jobsite or City office, time to be
determined.
Schedules shall be updated weekly. The Contractor may be
required to submit additional schedules depending on the
progress of the project.
HAUL ROUTES:
Arterial and Collector streets only. Contractor will not be
allowed to use residential streets to access the site with
trucks hauling materials.
1212
HIGHLIGHTS FROM GENERAL CONDITIONS
AND GENERAL REQ’S:
• SITE CLEAN-UP:
• The construction work shall be kept and accomplished in a
neat, clean and orderly fashion.
• Construction equipment will need to be cleaned to minimize
dirt tracking onto the roadway. Street sweeping will need to
be used in order to minimize tracking and meet EPA storm
water quality requirements.
7
1313
EROSION CONTROL - SWMP
• Contractor will need to coordinate SWMP transfer from Connell
Resources for the portions of the work area impacted by the
landscape installation. SWMP transfers are done through the
Colorado Dept of Public Health and Environment (CDPHE)
• Erosion Control is an incidental cost to the project and will not be paid
separately.
• The Erosion Control Plans provided are not the SWMP.
• Erosion control devices are currently installed and will be handed
over to the Contractor in working condition. Contractor will be
responsible for maintaining devices until devices are removed.
• The Erosion Control Supervisor will meet with the Project Engineer
and Contract Superintendent at least every 14 days and within 24
hours of storm/snowmelt events.
1414
Erosion Control
8
1515
Highlights from Specifications
1616
SECTION 207 – Topsoil (special) Amend
onsite, Shape, & Fine Grading (Top 6”)
• Topsoil is rough graded
• Existing topsoil needs to be
amended onsite and fine
graded prior to sod and
mulch
• City does not anticipate
hauling any topsoil onto the
site or off of the site.
• Cubic Yard quantity
represent the amount of
material to be amended
• Paid per plan quantity
9
1717
SECTION 212 – SOD
• West side parkway
between sidewalk and
curb.
• East side parkway between
sidewalk and curb; also
behind sidewalk.
• Paid per measured
quantity
1818
SECTION 212 – DRYLAND SEED
• West side behind sidewalk
south of Country Club
Road
• Paid per measured
quantity
10
1919
SECTION 213 - MULCHING
• 213-01 - Mulch (1.5” River Rock, 3” Depth, fabric
included)
– Between Sidewalk and frontage road on west
side between Country Club Road and Richard’s
Lake Road
– Paid per measured quantity
2020
SECTION 213 - MULCHING
• 213-02 - Mulch (Organic, Haul and Place only)
– City supplied. City will load trucks, but will not
haul.
– 6’ diameter at all tree locations
• 213-03 – Mulch (12” River Rock, 18” Deep, Fabric
included)
– At property south of Country Club Road, and
south of Richard’s Lake Road
11
2121
SECTION 213 - MULCHING
213-03 – Mulch (12” River
Rock, 18” Deep, Fabric
included)
• At property south of
Country Club Road
• At drainage area at the
southwest corner of
Richard’s Lake Road
2222
SECTION 214 - LANDSCAPING
• 214-01 – Street Trees (Western Catalpa 2” Cal.)
• 214-02 – Street Trees (Skyline Honeylocust 2” Cal.)
• 214-03 – Street Trees (Kentucky Coffee Tree 2” Cal.)
• 214-04 – Street Trees (Bur Oak 2” Cal.)
• 214-05 – Street Trees (Chinkapin Oak 2” Cal.)
• 214-06 – Street Trees (Greenspire Linden 2” Cal.)
• 214-08 – Street Trees (Accoloade Elm 2” Cal.)
• 214-09a – Evergreen (Cologreen 6’ Height)
• 214-09b – Evergreen (Moonglow Juniper 6’ Height)
12
2323
SECTION 214 - LANDSCAPING
• 214-10 – Shrubs (5 Gallon)
• 214-11 – Ornamental Grasses (1 Gallon)
• 214-12 – Perennials (1 Gallon)
2424
SECTION 214 - LANDSCAPING
• Trees installed on both sides of roads in parkways
(between sidewalk and curb)
• Shrubs, ornamental grasses, and perennials
installed in planting areas on west side of road
between sidewalk and frontage road
• High pressure Xcel gas main in west parkway that is
as shallow as 3 feet deep in a few locations and is
mostly between 4 to 6 feet deep.
13
2525
SECTION 214 - LANDSCAPING
• 214-13 – Landscape Maintenance
– Paid 1 Lump Sum over the course of 2 full growing
seasons
– Includes:
• Sprinkler startup, shutdown and maintenance on
the City owned system (west parkway between
Country Club Road and Richard’s Lake Road)
• Weeding and mowing on all west parkways
• Up to 4 winter waterings on west side parkways
2626
SECTION 214 - LANDSCAPING
• Planting Warranty
• Plants are warrantied for 2 growing seasons
• Plant material will be reviewed in Autumn 2013 and
Autumn 2014
• Dead or severely distressed plants identified during
the review will be replaced in Spring 2014 and Spring
2015.
• Stressed plants on east side parkway need to be
documented and brought to City’s attention if the
contractor suspects they are not being watered
properly by HOA’s irrigation system
14
2727
SECTION 504 – STACKED BLOCK WALL
• 504-01 Versa Block Wall
(24” Height) (Color TBD)
– Installed cost
includes granular
leveling pad,
subsurface drain,
drainage aggregate,
compacted backfill,
Versa-lock block and
adhered Versa-lock
capstone
– Paid per measured
lineal foot quantity
2828
SECTION 623 – IRRIGATION SYSTEMS
– Irrigation sleeves have been installed by Connell
Resources throughout the project.
– City Survey will locate all sleeve locations
15
2929
SECTION 623 – IRRIGATION SYSTEMS
• 623-01 Irrigation Installation for west parkways
– Irrigation for west parkway between Richard’s Lake
Road and 500 feet south of Country Club Road
– Per Hines Irrigation design in plans (including
wiring, controller, valves, piping, heads, drip
systems)
– Backflow preventer and connection to ELCO water
meter paid thru separate line item (623-03)
3030
SECTION 623 – IRRIGATION SYSTEMS
• 623-02 Irrigation Installation for Maple Hill parkways
– Irrigation for east parkway between Richard’s Lake Road and
Country Club Road
– Turf irrigation system for parkway
– Turf irrigation system for behind sidewalk (one row of 180
degree heads facing east)
– Installation costs will include installing 8 valve boxes with
valves.
– Installation costs will not include wiring, controller, or
backflow preventer
– Coordination with the Maple Hill HOA will be required
– A design for this system will not be provided.
16
3131
SECTION 623 – IRRIGATION SYSTEMS
• 623-023 Backflow
Preventer (per ELCO
water district
standards)
– 1” Service
– Unit cost includes
all work between
the meter and the
backflow
preventer
3232
SECTION 626 - MOBILIZATION
• 626-01 Mobilization
– Paid Lump Sum (per CDOT)
– Water is available on the jobsite
• Contractor can coordinate with ELCO water district to
install a meter on nearby fire hydrants
• Contractor will be billed for water by ELCO - not
reimbursable thru this contract.
17
3333
SECTION 626 - MOBILIZATION
• Staging Areas:
• City Parks Dept. has a vacant lot one block east of
Turnberry Road south of Maple Hill Drive
• City has vacant right of way on the south side of
Maple Hill that was used as a haul route for the
roadway construction
• City will not allow planting material to be stockpiled
on asphalt surfaces (too hot for the plants)
• Jobsite storage trailers and equipment can be parked
on side streets with parking lanes (Country Club,
Summer Park, Maple Hill, Waterbury, Richard’s Lake)
3434
Thanks For Attending!
• Any Questions or concerns can be addressed to:
– Mark Laken
• Mobile: (970) 222-3546
• Email: mlaken@fcgov.com