HomeMy WebLinkAboutBID - 7501 TURNBERRY ROAD LANDSCAPE & IRRIGATION PROJECTADDENDUM No. 1
SPECIFICATIONS AND CONTRACT DOCUMENTS
Description of BID 7501: Turnberry Road Landscape & Irrigation Project
OPENING DATE: 3:00 PM (Our Clock) April 26, 2013
To all prospective bidders under the specifications and contract documents described
above, the following changes/additions are hereby made and detailed in the following
sections of this addendum:
Exhibit 1 – Revised Bid Tab
Exhibit 2 –Revisions to Bid Tab, Specifications & Drawings
Exhibit 3 - Questions & Answers
Exhibit 4 – Revised Drawings
Please contact John Stephen, CPPO, LEED AP at (970) 221-6779 with any questions
regarding this addendum.
RECEIPT OF THIS ADDENDUM MUST BE ACKNOWLEDGED BY A WRITTEN
STATEMENT ENCLOSED WITH THE BID/QUOTE STATING THAT THIS
ADDENDUM HAS BEEN RECEIVED.
Financial Services
Purchasing Division
215 N. Mason St. 2nd Floor
PO Box 580
Fort Collins, CO 80522
970.221.6775
970.221.6707
fcgov.com/purchasing
EXHIBIT 1 –REVISED BID TAB
Item # Item Description Quantity Unit Unit Cost Total Cost
207-02 Topsoil (Special) - Amend Onsite, Shape, & Fine Grading (Top 6")
(45000+17592+700)*0.5/27) 1,172 CY
212-01 Sod 45,000 SF
212-02 Dryland Seed (soil conditioner, drill seed, crimp straw mulch) 7,000.00 SF
213-01 Mulch (1.5" River Rock, 3" Depth, Fabric Included) 24,478 SF
213-02 Woodchip Mulch (from City Stockpile, Haul and Place only) 700.0 SF
213-03 Mulch (12" River Rock, 18" Deep, Fabric Included) 1,900.0 SF
214-01 Street Trees (Western Catalpa, 2" Cal.) 16 EA
214-02 Street Trees (Skyline Honeylocust, 2"Cal.) 33 EA
214-03 Street Trees (Kentucky Coffee Tree, 2" Cal) 20 EA
214-04 Street Trees (Bur Oak, 2" Cal.) 10 EA
214-05 Street Trees (Chinkapin Oak, 2" Cal.) 9 EA
214-06 Street Trees (Greenspire Linden, 2" Cal.) 26 EA
214-08 Street Trees (Accoloade Elm, 2" Cal.) 9 EA
214-09a Evergreen Tree (Cologreen Juniper 6' height) 13 EA
214-09b Evergreen Tree (Moonglow Juniper 6' height) 14 EA
214-10 Shrubs (5 Gallons) 468 EA
214-11 Ornamental Grasses (1 Gallon) 93 EA
214-12 Perennials (1 Gallon) 185 EA
214-13
Landscape Maintenance - 2 Years for West Parkway South of Richard's Lake
Road Only (Mowing, weeding, mulching, irrigation maintenance & upto 4 winter
waterings per year)
2YEAR
504-01 Versa-Lock Block Landscape Wall (24" Height) (Color TBD)(Complete -in-
place)(Installed per detail) 300 LF
623-01 Irrigation installation for West Parkways (Richard's Lake Road to 500' south of
Country Club Road) 1LS
623-03 Backflow Preventer (installed per ELCO Water District Standards) 1 EA
626-01 Mobilization 1 LS
BID TOTAL:
In Words:
Turnberry Road Landscape and Irrigation Project Bid Tab ‐ REVISED 4/18/2013
EXHIBIT 2 – REVISIONS TO BID TAB, SPECIFICATIONS & DRAWINGS
1. Plan sheets 83 and 84 are replaced with the attached revised plan sheets. The revisions fix an
editing error. The Greenspire Linden trees were incorrectly edited and the Patmore Ash trees were
incorrectly left in place. These sheets revise the plans so that the Patmore Ash trees are replaced
with Kentucky Coffee Trees; the Shademaster Honey locusts trees are replaced with Skymaster
Honey locust trees; and the Greenspire Linden trees are per the original landscape plan. These
quantity modifications are reflected in the attached revised bid tab.
214-02 Street Trees (Skyline Honeylocust, 2"Cal.) 33 EA
214-03 Street Trees (Kentucky Coffee Tree, 2" Cal) 20 EA
214-06 Street Trees (Greenspire Linden, 2" Cal.) 26 EA
2. The Mulch (1.5” River Rock, 3” Depth, Fabric Included) quantity is revised to reflect the quantity
shown on the plan sheets.
213-01 Mulch (1.5" River Rock, 3" Depth, Fabric Included) 24,478 SF
3. Line Items 214-10; 214-11; & 214-12 quantities are revised to reflect the quantity shown on the plan
sheets:
214-10 Shrubs (5 Gallons) 468 EA
214-11 Ornamental Grasses (1 Gallon) 93 EA
214-12 Perrenials (1 Gallon) 185 EA
4. Item 623-02 “Design/Build Irrigation for Maple Hill Parkways” is removed from the contract. Alpine
Landscaping, the irrigation maintenance contractor for Maple Hill HOA will install this system prior
to parkway landscape planting installation.
EXHIBIT 3 – QUESTIONS & ANSWERS
1. Landscape Edging is specified in the Landscape Material Legend on sheets 66
and 68 but the plans do not indicate any locations.
The City does not anticipate installing landscape edging on this project. Any
landscape edging that the City requests will be paid for through change order.
2. Tree counts do not match between the bid tab and the plan sheet quantities.
The bid tab has the correct number of trees and is a combination of the Ripley
designed west parkway and the B&A designed east parkways with bubbled
revisions.
3. ELCO water standards do not require a stop box between the backflow preventer
and the meter. See attached detail below:
4. Can different sod types be used?
The City will allow different sod types in the parkways (areas between sidewalk
and curb). However special attention needs to be taken on the east side
parkway and behind the sidewalk so that sod closely matches existing turf type.
Sod type must also closely resemble the sod type specified.
5. At STA 26+75 there are two green SDR pipes that appear to be conflicting with the
location of the proposed wall, is relocation or removal of these pipes incidental or
associated with this bid?
The two green SDR pipes are storm drain pipe that drain an inlet on the west
side of the frontage road to the inlet in Turnberry Road. The pipes are
approximately 24 inches west of the back of the sidewalk and need to be
protected in place. The City believes the specified wall can be installed between
the exposed pipes and the sidewalk. If a conflict is identified, the City will
address it in the field and if warranted, a change order will be issued.
6. At STA 28 + 50 there is a 12” CMP that appears to be in conflict with the location
of the proposed wall, is removal or relocation of this pipe incidental or associated
with this bid?
The 12” corrugated metal pipe is an abandoned irrigation lateral pipe and can be
partially removed or left in place as required by the wall fabrication. Removal of
any portion of this pipe will not be paid separately and is considered incidental to
the installation of the block wall.
7. For the Bid Schedule Items # 214-10, 214-11, 214-12: what are the varieties of the
plant materials in each item?
The 214-10, 214-11, and 214-12 plant types are defined on plan sheet 66 and 68
on the Ripley designed parkways. The Ripley design sheets are the only
locations for the shrubs, perennials, and ornamental grasses.
8. What is the specification for Dryland Seeding and Mulching?
The dryland seed mix is defined on the bottom of plan sheet 68 of the plans:
Great Basin Wild Rye: 3 lb/acre
Green Needle Grass: 2 lb/acre
Indian Rice Grass: 1 lb/acre
Slender Wheat Grass: 2 lb/acre
Thickspike Wheat Grass: 3 lb/acre
Western Wheat Grass: 4 lb/acre
9. What are the specifications for the aggregate materials associated with the
retaining wall? (Granular leveling pad & Drainage)
Per the Versa-Lock installation instructions, the granular leveling pad should
consist of coarse-grained sand, gravel or crushed stone. The drainage
aggregate is specified as ¾” clear, free draining, angular aggregate.
10. There are several plant lists within the plan sheets. Which ones are correct?
The plant list on plan sheet 79 and 82 do not apply to this project. The Ripley
plant list on sheet 66 and 68 do apply for the plantings that are required on the
Ripley design (sheets 66-68). The remaining trees are not tabulated in the plans,
but they are accounted for on the bid tab. The bid tab has the correct number
and types of trees anticipated on this project. Shrubs, ornamental grasses, and
perennials types are correctly quantified and identified on the Ripley design (plan
sheets 66 & 68).