HomeMy WebLinkAboutCHANGE ORDER - BID - 7362 RADIANT NEIGHBORHOOD PARK (6)CHANGE ORDER NO. #5
PROJECT TITLE:
Radiant Park
CONTRACTOR:
Designscapes
PROJECT NUMBER:
7362
PURCHASE ORDER NO.:
DESCRIPTION:
Construction changes
1. Reason for change: addition of 112 " rock , binder, quick clips, cell fabric and shipping to gravel pave area -
wind plaza, additional class 6 at 4" depth under pavers - earth plaza, additional annual
rye seed to blue gramma mix; testing failures paid back to city (see attached summary)
2. Description of Change: addition of 1/2 " rock , binder, quick clips, cell fabric and shipping
to gravel pave area —wind plaza, additional class 6 at 4" depth
under pavers - earth plaza, additional annual rye seed to blue
gramma mix, testing failures paid back to city (see attached
summary)
3. Change in Contract Cost: $6,767.13
4. Change in Contract Time: 0
ORIGINAL CONTRACT COST
$1,345,034.40
TOTAL APPROVED CHANGE ORDER
($14,410.45)
TOTAL PENDING CHANGE ORDER
TOTAL THIS CHANGE ORDER
$6,767.13
TOTAL % OF ORIGINAL CONTRACT, THIS C.O.
0.50%
TOTAL % OF ORIGINAL CONTRACT, ALL C.O.'S
-0.57%
ADJUSTED CONTRACT COST
$1,337,391.08
ACCEPTED BY: / DATE: 1,211 Z
Contractor's Representative
ACCEPTED BY: DATE:
Project Manager
REVIEWED BY: DATE:
Title:
APPROVED BY: DATE:
Title:
APPROVED BY: DATE:
Purchasing Agent over $30,000
cc: City Clerk Architect
Contractor Engineer
Project File Purchasing