Loading...
HomeMy WebLinkAboutCHANGE ORDER - PURCHASE ORDER - 9125295CHANGE ORDER NO. 1 PROJECT TITLE: DWRF 2012 Primary Clarifier Repair & Lighting Replacement CONTRACTOR: Hydro Construction Company, Inc. P.O. NUMBER: 9125295 VENDOR NUMBER: 109420 CHARGE NUMBER: 5030373617.563040.6 DESCRIPTION In preparing change orders show inorder as separate numbered paragraphs the following: 1. Reason for change. 2. Description of change. 3. Change in contract cost. 4. Change in contract time 1. Requested work completed under budget 2. N/A 3.-$5,990.77 4. No change in contract time. (Attach additional sheets as required) ORIGINAL CONTRACT COST TOTAL APPROVED CHANGE ORDERS TOTAL PENDING CHANGE ORDERS TOTAL THIS CHANGE ORDER TOTAL % OF ORIGINAL CONTRACT, THIS CO: TOTAL % OF ORIGINAL CONTRACT, ALL CO'S: ADJUSTED CONTRACT COST (Assuminia all chance orders anoroved) ACCEPTED BY: REVIEWED BY: APPROVED BY: (font or representative) (Prof (Chief Engineer) APPROVED BY: (Water kesources and Treatment Ops Manager) APPROVED BY: (Pur asing Agent Over $34,WM) 60,E $295,874.00 $0.00 $0.00 ($5,990.77) -2.07% -0.34% $289,883.23 DATE: DATE: DATE: DATE: Ll -4( — L.? DATE: L'1 ` / 7 - / CC: Purchasing NOTE: Signature of Contractor indicates Contractor Project File agreement herewithin, including any adjustment in contract sum or contract time. Application for Payment PROJECT: DWRF 2912 Primary Clarifier Repair & Lighting Replacement Page 1 of 2 OWNER: City of Fort Collins - Utilities CONTRACTOR: Hydro Construction Co., Inc. APPLICATION NUMBER: 5 - FINAL 700 Wood Street 301 E. Lincoln Ave. APPLICATION DATE: 4/l/2013 Fort Collins, CO 80522 Fort Collins, CO 80524 PERIOD BEGINNING: 1/l/2013 ENGINEER: NIA PERIOD ENDING: 313112013 PO NUMBER: 9125295 CHANGE ORDERS: PAY APPLICATION: RETAINAGE: NUMBER DATE AMOUNT Application is made for Payment as shown below in connection with the Contract. The present status of the account for this Contract is as follows. Original Contract Amount: $ 295,874.00 Retainage to Date: $ 14,793.70 Net Change by Change Order: $0.00 Retainage Previous: $ 14.793.70 Revised Current Contract Amount: $295,874.00 Ch a in Retainage: $ - Total Work Completed and Stored to Date: $ 289,883.23 Less Previous Payment: $ Amount due this Pay Application (before retamage): $ 15.315. 6 Less Retainage: $ 14,793 0 Net Change by Change Order: $0.00 AMOUNT DUE THIS APPLICATION: $ 521 96 Change Order %: 0.00 CERTIFICATION: The undersigned CONTRACTOR certifies that all obligations of CONTRACTOR incurred in connection with the WORK have been satisfied as required in paragraph 14.3 of the General Conditions of the Contract. The above Amount Due this Application is requested by 4CORACTOR. Date: g Payment of the above Amount Due This Application is recommended by the ENGINEER. n V -1 7 / Date: B NIA `�'`j� -5 : f Payment of the above Amount Due This�AppplicatigVha; been review y the OWNER'S Project Manager. `-' IV Date: By: Payment of the ve Amount Due This Application is approved by the OWNER. ate: By: 12-Oi-274 Application for Payment PROJECT: DWRF 2012 Primary Clarifier Repair & Lieht ng Replacement OWNER: City of Fort Collins - Utilities CONTRACTOR: Hydro Construction Co., Inc. 700 Wood Street 301 E. Lincoln Ave. Fort Collins. CO 80522 Fort Collins, CO 80524 ENGINEER: N/A SCHEDULE OF VALUES Page 2 of 2 APPLICATION NUMBER: 5 - FINAL APPLICATION DATE: 04101/13 PERIOD BEGINNING: 01/01113 PERIOD ENDING: 03/31/13 PO NUMBER: 9125295 Item ff Job Code It Description Cty. UOM Contract Summary Billed This Period Billed Previous Billed Total to Date Stored Materials Total Billed & Stored to Date Cost Remaining Billed Percent Complete Unit Price Total Amount Qty. Amount City. Amount Qty. Amount 1 Bond & Insurance 1 LS $4,586.00 $ 4,586.00 0% $ - 102% $ 4,655.00 102% $ 4,655.00 $ - $ 4,655.00 $ (69.00) 102% 2 General Conditions 1 LS $6,209.00 $ 6,209.00 73% $ 4,539.89 0% $ - 73% $ 4,539.89 $ - $ 4,539.89 $ 1,669.11 73% 3 MSR Wells 1 LS $5,316.00 $ 5,316.00 0% $ - 0% $ - 0% $ - $ - $ - $ 5,316.00 0% 4 Primary Clarifier Repair 1 LS $91,674.00 $ 91.674.00 0% $ - 107% $ 98.052.33 107% $ 98,052.33 $ - $ 98,052.33 $ (6,378.33) 107% 4 PRPA Valve &Meter 1 LS $11.869.00 $ 11.869.00 0% $ - 1% $ 104.24 1% $ 104.24 $ - $ 104.24 $ 11.764.76 1% 4 DWRF Site Lighting 1 LS $140.051.00 $ 140,051.00 -4% $ (5,805.85) 100% $ 140.051.00 96% $ 134,245.15 $ - $ 134,245.15 $ 5,805.85 96% Sub -Totals: $ 259,705.00 1 0% $ (1,265.96) 94% $ 242,862.57 93% $ 241,596.611 $ 241,596.611 $ 18,108.39 93% Fixed Fee charges: $ 36,169.00 6% $ 2,170.30 94% $ 33.998.70 100% $ 36,169.00 $ 36,169.00 $ - 100% GRAND SUB -TOTALS: Pendinq Issues: 1 Channel Prep for Inspection 1 LS 2 West Channel Sandblasting 1 LS 3 East Channel Sandblasting i LS 4 Metal Recycling i LS 5 Lincoln St. Ga e 1 LS Pending issues Sub -Totals: $ 295,874.00 $ 904.34 $ 276.861.27 $ 277,765.61 $ 277.765.61 $ 5,990.77 94 % $5,500.00 $ 5.500.00 0% $ - 100% $ 5.500.00 1009/6 $ 5,500.00 $ - $ 5,500.00 $ - 100% $3,500.00 $ 3,500.00 0% $ - 100% $ 3.500.00 100% $ 3,500.00 $ - $ 3,500.00 $ - 100% $3,500.00 $ 3,500.00 0% $ - 100% $ 3,500.00 100% $ 3,600.00 $ - $ 3,500.00 $ - 100% ($2,733.50) $ (2,733.50) 100% $ (2,733.50) 0% $ - 100% $ (2.733.50) $ - $ (2,733,50) $ - 100% $2.351.12 $ 2.351.12 100% $ 2,351.12 0% $ 100% $ 2.351.12 $ $ 2,351.12 $ 100% $ 12.117.62 $ (382.38) $ 12,500.00 $ 12,117.62 $ 12,117.62 $ PAY APPLICATION TOTALS: $ 295,874.00 $ 521.96 $ 289,361.27 $ 289,883.23 $ 289,883.23