CHANGE ORDER NO.. Kubra
PROJECT TITLE: Authentication Services for Advanced Meter Fort Collins
CONTRACTOR: Kubra
PROJECT NUMBER: NA
PURCHASE ORDER NO.:
DESCRIPTION: Authentication Services for AMFC
1. Reason for Change: The AMFC executive team determined that Utilities would
use an authentication solution proposed by Aclara, in
conjunction with Utilities' a -Bill provider, Kubra.
The strategy, scope of work and costs to complete this
effort have been supplied by Aclara and Kubra in separate
documents. This change is to authorize and provide added
funding for Kubra to add this scope to the existing contract.
2. Description of Change: Addition to scope and added costs for Kubra to provide its
j portion of the authentication services for the Advanced
Meter Fort Collins project, in support of the Aclara Web
Portal implementation.
3. Change in Contract Cost: $37,700
I -
4. Change inaContractACCEPTED BY: DATE:resentative: ;cv wot� cco
s de
ACCEPTED BY� ✓1 �� �• V'-"` "�� DATE yr �D13
Project Manager
REVIEWED BY: DATE:
Title: Light nd Power Operations Manager.
APPROVED BY: DATE: %/ 3 /�
Title: Light and Power Aerations Manager.
�
APPROVED BY: DATE:
Purchasing Agent (over $60,000)
cc: Purchasing
I
STATEMENT O.F;WORK.
DbcWeb CASE: 551597
KUBRA 2
Statement of Work ISOW) I '
This Statement of Work ("SOW') between City of Fort Colliris,and Kubra Data Transfer Ltd. (KUBRA),"as'it relates to this specdic project; is entered into
pursuant.to the Agreement.between KUBRA and City of Fort Collins (the "Agreement'), -and consists of this SOW;' its 'applicable "attachmentsand
'- 4 '
transaction documents refeienced herein, and is effective as of the last signature date below: ~
,City. of fart Collins also.agrees to the hourly bill rate and any contingencies outlined in the "Pricing and Effort' section of this SOW.. As well City of .Fort'
Collins agrees to pay. KUBRA reasonable out-of-pocket expenses, including travel expenses. All additional expenses r0uue written.'docmentation from
KUBRA and must receive prior written approval from City of Fort Collins: City of Fort Collins agrees to. pay KUBRA's fees and expenses within
(30) days of_City of FortCollins receipt of KUBRA's invoice.
Furthermore; all parties acknowledge and understand that the services being delivered hereunder will not commence until full.executiori of this SOW. The
parties agree that"execution and delivery of.this SOW via facsimile or scanned PDF is legal, valid, and binding execution and delive y for all purposes.
Stakeholder Action Name (Print).
KUBRA COE Approval [enter]
KUBRA Sales Approval Ashley Edwards
.City of Fort Authorization and
' Collins- I Approval
''IMPORTANT DATES
Project StartDate Project LI
'To :Be•Deterinmed To Be Determined
'The, Project Start Date will be synonymous with one -of -two comment
the estimate included'in the SOW, being identified as either "Initial" o
Start Date will beaynoriymous with the Requirements Kickoff Meeti
'Estimate, the Project Start Date will be synonymous with the Build G
"All "Final' SOW's.will be presented with an Expiration, Date. The SO
stated expiration date to ensurethat the project schedule and associa
and.staffingwill need to be revisited'which may impact scheduled mil
i
to SOW Expiration" Date 4
TKursday :March .14'2013
milestones within the project schedule dependent upon;the state of
When the SOW is presented with an Initial Estimate, the:Project
ess otherwise stated. Whew the SOW is presentad.with a'Final
icement Milestahe, unless otherwise stated.
t be approved and returned to KUBRA by the end;of-business on the
estones are honored.- Once the SOW has expired; project scheduling
s; project staffing, project costs, and ultimately the project•tIVE:
.Project Management Methoddlogy (PIVIM)
KUBRA 3
Statement of Work (SOW)
PRICING
Fixed Price (where the Implementation Fees within this SOW are fixed)
Total:
Time and Material
Hours
Rate
Not to Exceed
9 Professional Services
260
$145.00
$37,700.00
F Contingency
[hours)
Choose an item.
[hrs'rate]
Other (Travel & Expense, etc...)
[hours]
[set amount)
[set amount]
Total: 260
$37,700.00
I- Gratis
TERMS & CONDITIONS
Hours billed not to exceed the estimated hours without prior written approval
Billing for this SOW will occur in the month following the LIVE of this project
The hourly rate used to calculate the costs are based upon your current contractual rate
ESTIMATE
Initial Estimates are based on a top -down analogous estimating method which considers all information on -hand, expert
Initial F70 judgment, and project historical performance. Initial Estimates are expected to be within +/- 15°% of the final estimate for
standard (non -customized) projects.
Final I" Final Estimates are the result of a completed requirements study (documented in our Business Requirements Document — BR4
systems design, project schedule, and assigned project team.
Phase
Planning
Analysis & Design
Build
Test
Implement
Total
nnar
13
[hours] [comment)
33
[hours] [comment]
91
[hours] i [comment]
104
[hours) [comment]
19 '
[hours] [comment]
260 1 [hours]
Project Management Methodology (PMM)
KUBRA 14
Statement of Work (SOW)
Statement of Scope
City of Fort Collins is looking to integrate Aclara with their web portal. They will have Smart Grid CIS (SGCIS) perform the
authentication, but KUBRA will be responsible for the following:
1. Providing the Key or Token used to confirm user authentication (requirements for establishing account identity will be
handled later in the process) .
2. Migrating all user ID, password, and account information over to SGCIS for the authentication process
3. Migrate City of Fort Collins to the .Net Platform
4. Implement a standard Single Sign On
For more information or clarification, please see the high level architectural overview provided by the City of Fort Collins.
Solutions (check all that apply)
BPO - Legacy
Credit & Collections
r
r
ID Cards
i-doxs Platform
F
r
i-Mobile
-Pay
r
r
Remittance Processing
ENTER Other
r
r
Directories
r
i-doxs Suite
r
i-Pay EFT
r
ENTER Other
r
Document Imaging
r
i-doxs Suite Insurance Edition
r
i-Xchange
r
ENTER Other
r
Document Template Mgr.
-----------
EZ-PAY
r
r
i-doxs Suite Utility Edition 82B
------------
i-doxs Suite Utility Edition 62C
r
r
KUBRABCS
--------------------------
Merchant Acquiring
r
r
ENTER Other
---------
ENTER Other
r
r
i-Connect
i-Direct SEDP
r
r
i-Lockbox
i-Message
r
r
Payment Gateway
Provider Search Websites
r
r
ENTER Other
ENTER Other
r
r
SOW Supporting Documentation
The following documents are considered supporting documents to the agreement outlined in the SOW. The acceptance of this SOW implies a full
understanding and acceptance of all documents listed below.
Document Type
Document Name,
Document Date
Document
Document
_
.
Version :
Source '
Business Requirements Document
AMFC—Authentication_Architecture_v3
Friday, December 14,
3.0
Client
2012
Choose an item.
[enter document title]
Click here to enter a date.
version
Choose an item.
Choose an item.
(enter document title)
lick hereto enter a dat
Ce.
version —
Choose an item.
Choose an item.
[enter document title]
Click here to enter a date.
[version]
Choose an item.
[other doe type] _— -- -
[enter document title]
Click here to enter a date.
[version]
Choose an item.
[other doc type]
[enter document title]
Click here to enter a date.
Iversionl
Choose an item.
Project Change Control Procedures
In the event that changes are required that would alter the scope outlined and agreed upon within this SOW and its supporting documentation, a Scope
Change Request will be initiated.
A high level outline of the process is as follows:
I. A Scope Change Document ("SCd') will be provided by KUBRA, and will be completed by the requesting party with the support and assistance of
our KUBRA Project Lead. The SCd will describe the change, provide the rationale for the change, and the effects (time, costs, staffing, etc...) the
change will have on the project.
2. Approval of the Change Request, as documented within the SCd, must have an appropriate level of approval from both KUBRA and the other party.
3. The SCd is an executable document.
Project Management Methodology (PMM)