Loading...
HomeMy WebLinkAboutCHANGE ORDER - BID - 7433 ROLLAND MOORE PARK RESTROOMS (2)CHANGE ORDER NO.2 Project Title: Rolland Moore playground restroom Contractor: Heath Construction Project Number: Bid 7433 Purchase Order Number: 9125653 Description: I. Reason for Change: Change where the electrical feeds into building. Dp.#e- -%-- S A!r Supp , Order a OV11 2. Description of Change: Bring electrical into south side of building instead of north. 3. Change in Contract Cost: $545.90 4. Change in Contract Time: none ORIGINAL CONTRACT COST $193,300.00 TOTAL APPROVED CHANGE ORDER $ 1,221.00 TOTAL PENDING CHANGE ORDER TOTAL THIS CHANGE ORDER $ 545.90 ADJUSTED CONTRACT COST $195,066.90 (Assuming all change orders approved) ACCEPTED BY:` -' /6� Conti ACCEPTED B)C. Probe REVIEWED BY: Title P / / DATE: //- /Y - i z DATE: DATE: APPROVED BY: DATE: /5 itle: lin'ILt1L� U GLI.�CS' APPROVED BY: DATE: Purchasing Agent over $15,000.00