HomeMy WebLinkAboutBID - 5932 MASON STREET HARMONY ROAD SPRING CREEK BIKE PSPECIFICATIONS AND CONTRACT DOCUMENTS
for
Mason Street/Harmony Road/Spring Creek
Bike/Pedestrian Trail
Bid No. 5932
PURCHASING DIVISION
215 North N Mason Street, 2nd Floor, Fort Collins
August 30, 2005 – 3:00 (Our Clock)
07/2001 Section 00020 Page 2
CONTRACT DOCUMENTS TABLE OF CONTENTS
Section Pages
BID INFORMATION
00020 Notice Inviting Bids 00020-1 - 00020-2
00100 Instruction to Bidders 00100-1 - 00100-9
00300 Bid Form 00300-1 - 00300-3
00400 Supplements to Bid Forms 00400-1
00410 Bid Bond 00410-1 - 00410-2
00420 Statements of Bidders Qualifications 00420-1 - 00420-3
00430 Schedule of Major Subcontractors 00430-1
CONTRACT DOCUMENTS
00500 Agreement Forms 00500-1
00510 Notice of Award 00510-0
00520 Agreement 00520-1 - 00520-6
00530 Notice to Proceed 00530-1
00600 Bonds and Certificates 00600-1
00610 Performance Bond 00610-1 - 00610-2
00615 Payment Bond 00615-1 - 00615-2
00630 Certificate of Insurance 00630-1
00635 Certificate of Substantial Completion 00635-1
00640 Certificate of Final Acceptance 00640-1
00650 Lien Waiver Release(Contractor) 00650-1 - 00650-2
00660 Consent of Surety 00660-1
00670 Application for Exemption Certificate 00670-1 - 00670-2
CONDITIONS OF THE CONTRACT
00700 General Conditions 00700-1 - 00700-34
Exhibit GC-A GC-A1 - GC-A2
00800 Supplementary Conditions 00800-1 - 00800-2
00900 Addenda, Modifications, and Payment 00900-1
00950 Contract Change Order 00950-1 - 00950-2
00960 Application for Payment 00960-1 - 00960-4
SPECIFICATIONS
GEOTECHNICAL ENGINEERING STUDY
07/2001 Section 00020 Page 3
SECTION 00020
INVITATION TO BID
07/2001 Section 00020 Page 1
SECTION 00020
INVITATION TO BID
Date: July 29, 2005
Sealed Bids will be received by the City of Fort Collins (hereinafter referred
to as OWNER), at the office of the Purchasing Division, 3:00 P.M., our clock,
on August 30, 2005, for the Mason Street/Harmony Road/Spring Creek
Bike/Pedestrian Trail; BID NO. 5932. If delivered, they are to be delivered
to 215 North Mason Street, 2nd Floor, Fort Collins, Colorado, 80524. If mailed,
the mailing address is P. O. Box 580, Fort Collins, CO 80522-0580.
At said place and time, and promptly thereafter, all Bids that have been duly
received will be publicly opened and read aloud.
The job limits for the Mason Street Bike/Pedestrian Project from Harmony Road
to Spring Creek Trail are from Harmony Road northward to the Spring Creek
Trail connection. The improvements will include: installation of: 2.62 miles
of 12’ wide Portland concrete trail, three steel pedestrian bridges, two
concrete box culverts, curb and gutter, Portland concrete pavement, asphalt
patching, grubbing, landscaping, and fence installation. The project occurs
within the Burlington Northern-Santa Fe Railroad (BNSF) Right of Way and will
require specific BNSF safety and security training for all primary contractor
and sub-contractor employees working within the BNSF Right of Way.
The City will provide surveying. The Contractor will provide traffic control.
The Contractor will be required to work with our traffic control supervisor.
Material Testing will be provided by the City and performed by CTL Thompson,
Inc.
All Bids must be in accordance with the Contract Documents on file with The
City of Fort Collins, 215 North Mason St., 2nd floor, Fort Collins, Colorado
80524.
Contract Documents will be available August 1, 2005.
Copies of the Contract Documents, complete with Construction Specifications
and Drawings, may be obtained from Purchasing Division at 215 North Mason St.,
2nd floor, Fort Collins, Colorado, 80524 upon payment of a refundable fee of
Fifty Dollars ($50.00) per set. No partial sets will be issued.
The Contract Documents and Construction Drawings may be examined at:
1. City of Fort Collins, Purchasing Division.
2. Dodge Plan Room, 1114 W. 7th Ave., Suite 100, Denver, Colorado.
3. Reed Construction Data, 11397 W. Radcliffe Dr. Littleton Colorado.
4. Builders Exchange, 223 South Link Lane, Fort Collins, Colorado.
5. Construction News Service, 4775 Centennial Blvd Ste 150, Colorado
Springs, Colorado.
A prebid conference and job walk with representatives of prospective Bidders
will be held at, on August 11, 2005, at 1:00 P.M.,at 215 N. Mason, Community
Room in Fort Collins.
DATE: August 30, 2005
CITY OF FORT COLLINS
PLANHOLDERS LIST FOR
BID #5932
BID NAME: Mason Street/Harmony Road/Spring Creek Bike/Pedestrian Trail
Flatiron
10090 I-25 Frt. Rd.
Longmont, CO 80504
PH 720-494-8111
FAX 303-776-0072
Wheeler consolidated, Inc.
9330 James Ave. SO
Bloomington, MN 55431
PH 800-328-3986 x226
FAX 952-929-2909
Korby Landscape
PO Box 989
Wellington, CO 80549
PH 970-568-7633
FAX 970-568-7635
ECI
2526 E. Hwy. 402
Loveland, CO 80539
PH 970-669-6291
FAX 970-669-8411
Big R Manufacturing, LLC
PO Box 1290
Greeley, CO 80632-1290
PH 970-356-9600
GL Hoff
1815 W. 12th St.
Loveland, CO 80537
PH 970-669-3255
FAX 970-663-1566
Lawson Construction Co.
PO Box 1318
Longmont, CO 80501
PH 303-444-8680
FAX 303-938-9955
American Eagle Industries, Inc.
691 First St. Unit B
Nunn, CO 80648
PH 970-897-2880
FAX 970-897-2879
Steadfast Bridges
4021 Gault Ave. S.
Fort Payne, AL 35967
PH 800-749-7515
FAX 256-845-9750
TLM Constructors
1013 67th Ave. Ct.
Greeley, CO 80633
PH 970-346-8323
FAX 970-346-8324
ABCO Contracting Co., Inc.
2180 E. 47th Pl.
Denver, CO 80229
PH 303-288-4140
FAX 303-288-4036
Northstar Concrete, Inc.
Gap Constructors
4505 Inlet Ct.
Fort Colllins, CO 80526
PH 970-214-1192
FAX 970-207-1608
Excel Sheet Metal, Inc.
12001 Shoemaker Ave.
Santa Fe Springs, CA 90670
PH 800-548-0054
FAX 562-944-4025
Hall-Irwin Construction
301 Centennial Dr.
Milliken, CO
PH 970-587-6951
Vogel Concrete
1313 Blue Spruce Dr.
Fort Collins, CO 80524-3506
PH 970-484-3880
Mountain Constructors
PO Box 405
Platteville, CO 80651
PH 970-785-6161
FAX 970-785-2515
Weekly Plan-it
6820 N. Franklin
Loveland, CO 80538
PH 970-593-1171
FAX 970-593-1171
Native-Scopes of CO, Inc.
1613 E. Olive Ct., Unit E
Fort Collins, CO 80524
PH 970-494-1613
FAX 970-494-1613
Korby Landscape
PO Box 989
Wellington, CO 80549-0989
PH 970-568-7633
FAX 970-568-7635
Concrete Works
1260 Rock Creek Cir.
Lafayette, CO 80026
PH 303-665-2933
Bridge America, Inc.
PO Box 907
Alexandria, MN 56308
PH 320-763-5600
FAX 320-763-5672
J-2 Contracting Company
929 38th Ave., Ct. #106
Greeley, CO 80634
Ph 970-392-0694
Arapahoe Utilities & Infrastructure
14251 E. Fremont Ave., Ste E
Englewood, CO 80112
PH 303-690-8888
FAX 303-690-2180
Weld County Construction
PO 67
Pierce, CO 80650
PH 970-834-2631
DATE: August 2, 2005
CITY OF FORT COLLINS
PLANHOLDERS LIST FOR
BID #5932
BID NAME: Mason Street/Harmony Road/Spring Creek Bike/Pedestrian Trail
ADDITIONAL PLAN HOLDERS WHO HAVE DOWNLOADED THE PLANS FROM THE WEB
ARE LISTED AT: https://secure2.fcgov.com/bso/external/bidAckList.sdo?bidId=5932
Flatiron
10090 I-25 Frt. Rd.
Longmont, CO 80504
PH 720-494-8111
FAX 303-776-0072
Administrative Services
Purchasing Divison
215 North Mason Street y 2nd Floor y P.O. Box 580 y Fort Collins, CO 80522-0580 y (970) 221-6775 y Fax (970) 221-6707
www.fcgov.com
ADDENDUM No. 1
SPECIFICATIONS AND CONTRACT DOCUMENTS
Description of Bid: 5932 Mason Street/Harmony Road/Spring Creek Bike/Pedestrian Trail
OPENING DATE: 3:00 P.M. (Our Clock) August 30, 2005
To all prospective bidders under the specifications and contract documents described above,
the following changes are hereby made.
I. Clarification on Railroad Safety and Security Training for Material Suppliers and
Sub-Contractors: It is not necessary for Material Suppliers to have the Railroad Safety
and Security Training. Sub-contractors do not need Railroad Safety and Security
training so long as there are Primary Contractor employees (that are required to have
the Railroad Safety and Security Training) on the job site.
II. Railroad Flagging will be arranged and paid for by The City of Fort Collins. Page
71 of the Contract in the Special Provisions will be revised as follows: under “Railroad
Flagging”:
a. “The Contractor shall notify the Railroad in writing 10 days prior to beginning and
48 hours prior to stopping any work that will require protective services. The
Contractor shall notify the Railroad five days prior to canceling protective
services.” is revised to read: The City of Fort Collins shall notify the Railroad
in writing 10 days prior to beginning and 48 hours prior to stopping any
work that will require protective services. The City of Fort Collins shall
notify the Railroad five days prior to canceling protective services.
b. “ The Railroad will bill the Contractor monthly at the current rates of pay for
flagging services furnished and the Contractor shall pay the Railroad within 30
days after the receipt of bills. The Department will reimburse the Contractor
under the planned force account item “Railroad Flagging” is revised to read: The
Railroad will bill the City of Fort Collins monthly at the current rates of pay
for flagging services furnished and the City of Fort Collins shall pay the
Railroad within 30 days after the receipt of bills. The Department will not
reimburse the Contractor under the planned force account item “Railroad
Flagging”
III. Item 607 – Fence (Plastic) shall be 48” high lightweight orange safety “crowd control”
plastic (high density polyethylene) fencing (Resinet SL24-48100-O, or equal). The post
shall be metal studded “tee” line post spaced at 16 feet. The fencing shall be securely
tied to the post, and shall be removed as directed by the engineer.
IV. Pedestrian Bridge #1 Wingwall Elevation Correction: There is a discreprency on the
top of the East wing wall elevations for Pedestrian Bridge #1 on plan sheets 11 and 12.
The correct eastside wing wall elevation is: 5041.54’. The appropriate correction to
sheet number 12 should be made and noted on your construction plan sets.
V. Sheet #10 Summary of Quantities Correction: The table on sheet 10 of the plan set
incorrectly references Pedestrian Bridge 3 as being the 42’0” structure and Pedestrian
Bridge 4 as being the 50’0” structure. Pedestrian Bridge #3 is the 50’0” structure and
Pedestrian Bridge 4 is the 42’0” structure.
VI. Sheet #10 Structure Descriptions Revisions: The “Structure Descriptions” incorrectly
describe Pedestrian Bridge 3 and Pedestrian Bridge 4 as being a 59’8” Prefabricated
Steel Truss Bridges. The correct descriptions are:
Pedestrian Bridge 3
50’0” PREFABRICATED STEEL TRUSS BRIDGE, CONCRETE DECK, ON CAST
IN-PLACE ABUTMENTS OVER NEW MERCER DITCH, FORT COLLINS,
COLORADO 14’0’ WIDTH, RAILING TO RAILING (15’0” OUT-TO-OUT)
Pedestrian Bridge 4
42’0” PREFABRICATED STEEL TRUSS BRIDGE, CONCRETE DECK, ON CAST
IN-PLACE ABUTMENTS OVER LARIMER COUNTY NO.2 DITCH, FORT COLLINS,
COLORADO 11’6’ WIDTH, RAILING TO RAILING (12’6” OUT-TO-OUT)
VII. Clarification on Safety Fencing along Easements: Revisions of Section 104 in the
Specifications Book states under the “Limits of Construction” that all easements and
work areas need to be fenced. This only applies to locations where the trail comes into
contact with existing sidewalks and roadways. You will also need to safety fence any
holes and drop-offs with safety fence. All these uses should be covered by your traffic
control line item.
VIII. Clarification on Interim Milestone Dates: There are no interim milestone dates, as the
contract is written. On a side note, the successful bidder will have to time his
construction so that it coincides with the New Mercer Channel and Larimer County Ditch
#2 shut-off date of October 15 and turn on date of March 15.
IX. Clarification on Health and Safety Management in the event that hazardous
material are encountered: In the event of encountering hazardous materials on the
jobsite, the City of Fort Collins will overrun Item 250 -Health and Safety Officer (HSO)
quantity for Health and Safety Management. An argument would need to be made for
us to justify force account work for the HSO. However, upon encountering hazardous
materials onsite, we would need to look at the problem and there may very well be
legitimate force account work related to moving and/or disposing of the material. Based
on the environmental report that was done, we are not anticipating hazardous materials
onsite.
X. Clarification on Note 23 in the General Notes on the plans: The primary contractor
will keep track of all changes on a master set of drawings in red ink. It will be The City of
Fort Collins’ responsibility to coordinate it's surveying services with Felsburg, Holt and
Ullvig to get the storm sewer verification and any other as-built field elevations/locations
and make electronic as-built updates to the plans.
XI. Clarification on Note 36 in the General Notes on the plans: Note 36 states: “In
Streets where more than one cut is made, an overlay of the entire street width, including
the patched are may be required.” This provision is for locations where there are more
than utility crossings in close proximity to each other. This situation does not occur on
this project and therefore the statement does not apply to this project.
RECEIPT OF THIS ADDENDUM MUST BE ACKNOWLEDGED BY A WRITTEN STATEMENT
ENCLOSED WITH THE BID/QUOTE STATING THAT THIS ADDENDUM HAS BEEN
RECEIVED.
Administrative Services
Purchasing Divison
215 North Mason Street y 2nd Floor y P.O. Box 580 y Fort Collins, CO 80522-0580 y (970) 221-6775 y Fax (970) 221-6707
www.fcgov.com
ADDENDUM No. 1
SPECIFICATIONS AND CONTRACT DOCUMENTS
Description of Bid: 5932 Mason Street/Harmony Road/Spring Creek Bike/Pedestrian Trail
OPENING DATE: 3:00 P.M. (Our Clock) August 30, 2005
To all prospective bidders under the specifications and contract documents described above,
the following changes are hereby made.
I. Clarification on Railroad Safety and Security Training for Material Suppliers and
Sub-Contractors: It is not necessary for Material Suppliers to have the Railroad Safety
and Security Training. Sub-contractors do not need Railroad Safety and Security
training so long as there are Primary Contractor employees (that are required to have
the Railroad Safety and Security Training) on the job site.
II. Railroad Flagging will be arranged and paid for by The City of Fort Collins. Page
71 of the Contract in the Special Provisions will be revised as follows: under “Railroad
Flagging”:
a. “The Contractor shall notify the Railroad in writing 10 days prior to beginning and
48 hours prior to stopping any work that will require protective services. The
Contractor shall notify the Railroad five days prior to canceling protective
services.” is revised to read: The City of Fort Collins shall notify the Railroad
in writing 10 days prior to beginning and 48 hours prior to stopping any
work that will require protective services. The City of Fort Collins shall
notify the Railroad five days prior to canceling protective services.
b. “ The Railroad will bill the Contractor monthly at the current rates of pay for
flagging services furnished and the Contractor shall pay the Railroad within 30
days after the receipt of bills. The Department will reimburse the Contractor
under the planned force account item “Railroad Flagging” is revised to read: The
Railroad will bill the City of Fort Collins monthly at the current rates of pay
for flagging services furnished and the City of Fort Collins shall pay the
Railroad within 30 days after the receipt of bills. The Department will not
reimburse the Contractor under the planned force account item “Railroad
Flagging”
III. Item 607 – Fence (Plastic) shall be 48” high lightweight orange safety “crowd control”
plastic (high density polyethylene) fencing (Resinet SL24-48100-O, or equal). The post
shall be metal studded “tee” line post spaced at 16 feet. The fencing shall be securely
tied to the post, and shall be removed as directed by the engineer.
IV. Pedestrian Bridge #1 Wingwall Elevation Correction: There is a discreprency on the
top of the East wing wall elevations for Pedestrian Bridge #1 on plan sheets 11 and 12.
The correct eastside wing wall elevation is: 5041.54’. The appropriate correction to
sheet number 12 should be made and noted on your construction plan sets.
V. Sheet #10 Summary of Quantities Correction: The table on sheet 10 of the plan set
incorrectly references Pedestrian Bridge 3 as being the 42’0” structure and Pedestrian
Bridge 4 as being the 50’0” structure. Pedestrian Bridge #3 is the 50’0” structure and
Pedestrian Bridge 4 is the 42’0” structure.
VI. Sheet #10 Structure Descriptions Revisions: The “Structure Descriptions” incorrectly
describe Pedestrian Bridge 3 and Pedestrian Bridge 4 as being a 59’8” Prefabricated
Steel Truss Bridges. The correct descriptions are:
Pedestrian Bridge 3
50’0” PREFABRICATED STEEL TRUSS BRIDGE, CONCRETE DECK, ON CAST
IN-PLACE ABUTMENTS OVER NEW MERCER DITCH, FORT COLLINS,
COLORADO 14’0’ WIDTH, RAILING TO RAILING (15’0” OUT-TO-OUT)
Pedestrian Bridge 4
42’0” PREFABRICATED STEEL TRUSS BRIDGE, CONCRETE DECK, ON CAST
IN-PLACE ABUTMENTS OVER LARIMER COUNTY NO.2 DITCH, FORT COLLINS,
COLORADO 11’6’ WIDTH, RAILING TO RAILING (12’6” OUT-TO-OUT)
VII. Clarification on Safety Fencing along Easements: Revisions of Section 104 in the
Specifications Book states under the “Limits of Construction” that all easements and
work areas need to be fenced. This only applies to locations where the trail comes into
contact with existing sidewalks and roadways. You will also need to safety fence any
holes and drop-offs with safety fence. All these uses should be covered by your traffic
control line item.
VIII. Clarification on Interim Milestone Dates: There are no interim milestone dates, as the
contract is written. On a side note, the successful bidder will have to time his
construction so that it coincides with the New Mercer Channel and Larimer County Ditch
#2 shut-off date of October 15 and turn on date of March 15.
IX. Clarification on Health and Safety Management in the event that hazardous
material are encountered: In the event of encountering hazardous materials on the
jobsite, the City of Fort Collins will overrun Item 250 -Health and Safety Officer (HSO)
quantity for Health and Safety Management. An argument would need to be made for
us to justify force account work for the HSO. However, upon encountering hazardous
materials onsite, we would need to look at the problem and there may very well be
legitimate force account work related to moving and/or disposing of the material. Based
on the environmental report that was done, we are not anticipating hazardous materials
onsite.
X. Clarification on Note 23 in the General Notes on the plans: The primary contractor
will keep track of all changes on a master set of drawings in red ink. It will be The City of
Fort Collins’ responsibility to coordinate it's surveying services with Felsburg, Holt and
Ullvig to get the storm sewer verification and any other as-built field elevations/locations
and make electronic as-built updates to the plans.
XI. Clarification on Note 36 in the General Notes on the plans: Note 36 states: “In
Streets where more than one cut is made, an overlay of the entire street width, including
the patched are may be required.” This provision is for locations where there are more
than utility crossings in close proximity to each other. This situation does not occur on
this project and therefore the statement does not apply to this project.
RECEIPT OF THIS ADDENDUM MUST BE ACKNOWLEDGED BY A WRITTEN STATEMENT
ENCLOSED WITH THE BID/QUOTE STATING THAT THIS ADDENDUM HAS BEEN
RECEIVED.
SPECIFICATIONS AND CONTRACT DOCUMENTS
for
Mason Street/Harmony Road/Spring Creek
Bike/Pedestrian Trail
Bid No. 5932
PURCHASING DIVISION
215 North N Mason Street, 2nd Floor, Fort Collins
August 30, 2005 – 3:00 (Our Clock)
07/2001 Section 00020 Page 2
CONTRACT DOCUMENTS TABLE OF CONTENTS
Section Pages
BID INFORMATION
00020 Notice Inviting Bids 00020-1 - 00020-2
00100 Instruction to Bidders 00100-1 - 00100-9
00300 Bid Form 00300-1 - 00300-3
00400 Supplements to Bid Forms 00400-1
00410 Bid Bond 00410-1 - 00410-2
00420 Statements of Bidders Qualifications 00420-1 - 00420-3
00430 Schedule of Major Subcontractors 00430-1
CONTRACT DOCUMENTS
00500 Agreement Forms 00500-1
00510 Notice of Award 00510-0
00520 Agreement 00520-1 - 00520-6
00530 Notice to Proceed 00530-1
00600 Bonds and Certificates 00600-1
00610 Performance Bond 00610-1 - 00610-2
00615 Payment Bond 00615-1 - 00615-2
00630 Certificate of Insurance 00630-1
00635 Certificate of Substantial Completion 00635-1
00640 Certificate of Final Acceptance 00640-1
00650 Lien Waiver Release(Contractor) 00650-1 - 00650-2
00660 Consent of Surety 00660-1
00670 Application for Exemption Certificate 00670-1 - 00670-2
CONDITIONS OF THE CONTRACT
00700 General Conditions 00700-1 - 00700-34
Exhibit GC-A GC-A1 - GC-A2
00800 Supplementary Conditions 00800-1 - 00800-2
00900 Addenda, Modifications, and Payment 00900-1
00950 Contract Change Order 00950-1 - 00950-2
00960 Application for Payment 00960-1 - 00960-4
SPECIFICATIONS
GEOTECHNICAL ENGINEERING STUDY
07/2001 Section 00020 Page 3
SECTION 00020
INVITATION TO BID
07/2001 Section 00020 Page 1
SECTION 00020
INVITATION TO BID
Date: July 29, 2005
Sealed Bids will be received by the City of Fort Collins (hereinafter referred
to as OWNER), at the office of the Purchasing Division, 3:00 P.M., our clock,
on August 30, 2005, for the Mason Street/Harmony Road/Spring Creek
Bike/Pedestrian Trail; BID NO. 5932. If delivered, they are to be delivered
to 215 North Mason Street, 2nd Floor, Fort Collins, Colorado, 80524. If mailed,
the mailing address is P. O. Box 580, Fort Collins, CO 80522-0580.
At said place and time, and promptly thereafter, all Bids that have been duly
received will be publicly opened and read aloud.
The job limits for the Mason Street Bike/Pedestrian Project from Harmony Road
to Spring Creek Trail are from Harmony Road northward to the Spring Creek
Trail connection. The improvements will include: installation of: 2.62 miles
of 12’ wide Portland concrete trail, three steel pedestrian bridges, two
concrete box culverts, curb and gutter, Portland concrete pavement, asphalt
patching, grubbing, landscaping, and fence installation. The project occurs
within the Burlington Northern-Santa Fe Railroad (BNSF) Right of Way and will
require specific BNSF safety and security training for all primary contractor
and sub-contractor employees working within the BNSF Right of Way.
The City will provide surveying. The Contractor will provide traffic control.
The Contractor will be required to work with our traffic control supervisor.
Material Testing will be provided by the City and performed by CTL Thompson,
Inc.
All Bids must be in accordance with the Contract Documents on file with The
City of Fort Collins, 215 North Mason St., 2nd floor, Fort Collins, Colorado
80524.
Contract Documents will be available August 1, 2005.
Copies of the Contract Documents, complete with Construction Specifications
and Drawings, may be obtained from Purchasing Division at 215 North Mason St.,
2nd floor, Fort Collins, Colorado, 80524 upon payment of a refundable fee of
Fifty Dollars ($50.00) per set. No partial sets will be issued.
The Contract Documents and Construction Drawings may be examined at:
1. City of Fort Collins, Purchasing Division.
2. Dodge Plan Room, 1114 W. 7th Ave., Suite 100, Denver, Colorado.
3. Reed Construction Data, 11397 W. Radcliffe Dr. Littleton Colorado.
4. Builders Exchange, 223 South Link Lane, Fort Collins, Colorado.
5. Construction News Service, 4775 Centennial Blvd Ste 150, Colorado
Springs, Colorado.
A prebid conference and job walk with representatives of prospective Bidders
will be held at, on August 11, 2005, at 1:00 P.M.,at 215 N. Mason, Community
Room in Fort Collins.
DATE: August 30, 2005
CITY OF FORT COLLINS
PLANHOLDERS LIST FOR
BID #5932
BID NAME: Mason Street/Harmony Road/Spring Creek Bike/Pedestrian Trail
Flatiron
10090 I-25 Frt. Rd.
Longmont, CO 80504
PH 720-494-8111
FAX 303-776-0072
Wheeler consolidated, Inc.
9330 James Ave. SO
Bloomington, MN 55431
PH 800-328-3986 x226
FAX 952-929-2909
Korby Landscape
PO Box 989
Wellington, CO 80549
PH 970-568-7633
FAX 970-568-7635
ECI
2526 E. Hwy. 402
Loveland, CO 80539
PH 970-669-6291
FAX 970-669-8411
Big R Manufacturing, LLC
PO Box 1290
Greeley, CO 80632-1290
PH 970-356-9600
GL Hoff
1815 W. 12th St.
Loveland, CO 80537
PH 970-669-3255
FAX 970-663-1566
Lawson Construction Co.
PO Box 1318
Longmont, CO 80501
PH 303-444-8680
FAX 303-938-9955
American Eagle Industries, Inc.
691 First St. Unit B
Nunn, CO 80648
PH 970-897-2880
FAX 970-897-2879
Steadfast Bridges
4021 Gault Ave. S.
Fort Payne, AL 35967
PH 800-749-7515
FAX 256-845-9750
TLM Constructors
1013 67th Ave. Ct.
Greeley, CO 80633
PH 970-346-8323
FAX 970-346-8324
ABCO Contracting Co., Inc.
2180 E. 47th Pl.
Denver, CO 80229
PH 303-288-4140
FAX 303-288-4036
Northstar Concrete, Inc.
Gap Constructors
4505 Inlet Ct.
Fort Colllins, CO 80526
PH 970-214-1192
FAX 970-207-1608
Excel Sheet Metal, Inc.
12001 Shoemaker Ave.
Santa Fe Springs, CA 90670
PH 800-548-0054
FAX 562-944-4025
Hall-Irwin Construction
301 Centennial Dr.
Milliken, CO
PH 970-587-6951
Vogel Concrete
1313 Blue Spruce Dr.
Fort Collins, CO 80524-3506
PH 970-484-3880
Mountain Constructors
PO Box 405
Platteville, CO 80651
PH 970-785-6161
FAX 970-785-2515
Weekly Plan-it
6820 N. Franklin
Loveland, CO 80538
PH 970-593-1171
FAX 970-593-1171
Native-Scopes of CO, Inc.
1613 E. Olive Ct., Unit E
Fort Collins, CO 80524
PH 970-494-1613
FAX 970-494-1613
Korby Landscape
PO Box 989
Wellington, CO 80549-0989
PH 970-568-7633
FAX 970-568-7635
Concrete Works
1260 Rock Creek Cir.
Lafayette, CO 80026
PH 303-665-2933
Bridge America, Inc.
PO Box 907
Alexandria, MN 56308
PH 320-763-5600
FAX 320-763-5672
J-2 Contracting Company
929 38th Ave., Ct. #106
Greeley, CO 80634
Ph 970-392-0694
Arapahoe Utilities & Infrastructure
14251 E. Fremont Ave., Ste E
Englewood, CO 80112
PH 303-690-8888
FAX 303-690-2180
Weld County Construction
PO 67
Pierce, CO 80650
PH 970-834-2631
DATE: August 2, 2005
CITY OF FORT COLLINS
PLANHOLDERS LIST FOR
BID #5932
BID NAME: Mason Street/Harmony Road/Spring Creek Bike/Pedestrian Trail
ADDITIONAL PLAN HOLDERS WHO HAVE DOWNLOADED THE PLANS FROM THE WEB
ARE LISTED AT: https://secure2.fcgov.com/bso/external/bidAckList.sdo?bidId=5932
Flatiron
10090 I-25 Frt. Rd.
Longmont, CO 80504
PH 720-494-8111
FAX 303-776-0072
Administrative Services
Purchasing Divison
215 North Mason Street y 2nd Floor y P.O. Box 580 y Fort Collins, CO 80522-0580 y (970) 221-6775 y Fax (970) 221-6707
www.fcgov.com
ADDENDUM No. 1
SPECIFICATIONS AND CONTRACT DOCUMENTS
Description of Bid: 5932 Mason Street/Harmony Road/Spring Creek Bike/Pedestrian Trail
OPENING DATE: 3:00 P.M. (Our Clock) August 30, 2005
To all prospective bidders under the specifications and contract documents described above,
the following changes are hereby made.
I. Clarification on Railroad Safety and Security Training for Material Suppliers and
Sub-Contractors: It is not necessary for Material Suppliers to have the Railroad Safety
and Security Training. Sub-contractors do not need Railroad Safety and Security
training so long as there are Primary Contractor employees (that are required to have
the Railroad Safety and Security Training) on the job site.
II. Railroad Flagging will be arranged and paid for by The City of Fort Collins. Page
71 of the Contract in the Special Provisions will be revised as follows: under “Railroad
Flagging”:
a. “The Contractor shall notify the Railroad in writing 10 days prior to beginning and
48 hours prior to stopping any work that will require protective services. The
Contractor shall notify the Railroad five days prior to canceling protective
services.” is revised to read: The City of Fort Collins shall notify the Railroad
in writing 10 days prior to beginning and 48 hours prior to stopping any
work that will require protective services. The City of Fort Collins shall
notify the Railroad five days prior to canceling protective services.
b. “ The Railroad will bill the Contractor monthly at the current rates of pay for
flagging services furnished and the Contractor shall pay the Railroad within 30
days after the receipt of bills. The Department will reimburse the Contractor
under the planned force account item “Railroad Flagging” is revised to read: The
Railroad will bill the City of Fort Collins monthly at the current rates of pay
for flagging services furnished and the City of Fort Collins shall pay the
Railroad within 30 days after the receipt of bills. The Department will not
reimburse the Contractor under the planned force account item “Railroad
Flagging”
III. Item 607 – Fence (Plastic) shall be 48” high lightweight orange safety “crowd control”
plastic (high density polyethylene) fencing (Resinet SL24-48100-O, or equal). The post
shall be metal studded “tee” line post spaced at 16 feet. The fencing shall be securely
tied to the post, and shall be removed as directed by the engineer.
IV. Pedestrian Bridge #1 Wingwall Elevation Correction: There is a discreprency on the
top of the East wing wall elevations for Pedestrian Bridge #1 on plan sheets 11 and 12.
The correct eastside wing wall elevation is: 5041.54’. The appropriate correction to
sheet number 12 should be made and noted on your construction plan sets.
V. Sheet #10 Summary of Quantities Correction: The table on sheet 10 of the plan set
incorrectly references Pedestrian Bridge 3 as being the 42’0” structure and Pedestrian
Bridge 4 as being the 50’0” structure. Pedestrian Bridge #3 is the 50’0” structure and
Pedestrian Bridge 4 is the 42’0” structure.
VI. Sheet #10 Structure Descriptions Revisions: The “Structure Descriptions” incorrectly
describe Pedestrian Bridge 3 and Pedestrian Bridge 4 as being a 59’8” Prefabricated
Steel Truss Bridges. The correct descriptions are:
Pedestrian Bridge 3
50’0” PREFABRICATED STEEL TRUSS BRIDGE, CONCRETE DECK, ON CAST
IN-PLACE ABUTMENTS OVER NEW MERCER DITCH, FORT COLLINS,
COLORADO 14’0’ WIDTH, RAILING TO RAILING (15’0” OUT-TO-OUT)
Pedestrian Bridge 4
42’0” PREFABRICATED STEEL TRUSS BRIDGE, CONCRETE DECK, ON CAST
IN-PLACE ABUTMENTS OVER LARIMER COUNTY NO.2 DITCH, FORT COLLINS,
COLORADO 11’6’ WIDTH, RAILING TO RAILING (12’6” OUT-TO-OUT)
VII. Clarification on Safety Fencing along Easements: Revisions of Section 104 in the
Specifications Book states under the “Limits of Construction” that all easements and
work areas need to be fenced. This only applies to locations where the trail comes into
contact with existing sidewalks and roadways. You will also need to safety fence any
holes and drop-offs with safety fence. All these uses should be covered by your traffic
control line item.
VIII. Clarification on Interim Milestone Dates: There are no interim milestone dates, as the
contract is written. On a side note, the successful bidder will have to time his
construction so that it coincides with the New Mercer Channel and Larimer County Ditch
#2 shut-off date of October 15 and turn on date of March 15.
IX. Clarification on Health and Safety Management in the event that hazardous
material are encountered: In the event of encountering hazardous materials on the
jobsite, the City of Fort Collins will overrun Item 250 -Health and Safety Officer (HSO)
quantity for Health and Safety Management. An argument would need to be made for
us to justify force account work for the HSO. However, upon encountering hazardous
materials onsite, we would need to look at the problem and there may very well be
legitimate force account work related to moving and/or disposing of the material. Based
on the environmental report that was done, we are not anticipating hazardous materials
onsite.
X. Clarification on Note 23 in the General Notes on the plans: The primary contractor
will keep track of all changes on a master set of drawings in red ink. It will be The City of
Fort Collins’ responsibility to coordinate it's surveying services with Felsburg, Holt and
Ullvig to get the storm sewer verification and any other as-built field elevations/locations
and make electronic as-built updates to the plans.
XI. Clarification on Note 36 in the General Notes on the plans: Note 36 states: “In
Streets where more than one cut is made, an overlay of the entire street width, including
the patched are may be required.” This provision is for locations where there are more
than utility crossings in close proximity to each other. This situation does not occur on
this project and therefore the statement does not apply to this project.
RECEIPT OF THIS ADDENDUM MUST BE ACKNOWLEDGED BY A WRITTEN STATEMENT
ENCLOSED WITH THE BID/QUOTE STATING THAT THIS ADDENDUM HAS BEEN
RECEIVED.
Administrative Services
Purchasing Divison
215 North Mason Street y 2nd Floor y P.O. Box 580 y Fort Collins, CO 80522-0580 y (970) 221-6775 y Fax (970) 221-6707
www.fcgov.com
ADDENDUM No. 1
SPECIFICATIONS AND CONTRACT DOCUMENTS
Description of Bid: 5932 Mason Street/Harmony Road/Spring Creek Bike/Pedestrian Trail
OPENING DATE: 3:00 P.M. (Our Clock) August 30, 2005
To all prospective bidders under the specifications and contract documents described above,
the following changes are hereby made.
I. Clarification on Railroad Safety and Security Training for Material Suppliers and
Sub-Contractors: It is not necessary for Material Suppliers to have the Railroad Safety
and Security Training. Sub-contractors do not need Railroad Safety and Security
training so long as there are Primary Contractor employees (that are required to have
the Railroad Safety and Security Training) on the job site.
II. Railroad Flagging will be arranged and paid for by The City of Fort Collins. Page
71 of the Contract in the Special Provisions will be revised as follows: under “Railroad
Flagging”:
a. “The Contractor shall notify the Railroad in writing 10 days prior to beginning and
48 hours prior to stopping any work that will require protective services. The
Contractor shall notify the Railroad five days prior to canceling protective
services.” is revised to read: The City of Fort Collins shall notify the Railroad
in writing 10 days prior to beginning and 48 hours prior to stopping any
work that will require protective services. The City of Fort Collins shall
notify the Railroad five days prior to canceling protective services.
b. “ The Railroad will bill the Contractor monthly at the current rates of pay for
flagging services furnished and the Contractor shall pay the Railroad within 30
days after the receipt of bills. The Department will reimburse the Contractor
under the planned force account item “Railroad Flagging” is revised to read: The
Railroad will bill the City of Fort Collins monthly at the current rates of pay
for flagging services furnished and the City of Fort Collins shall pay the
Railroad within 30 days after the receipt of bills. The Department will not
reimburse the Contractor under the planned force account item “Railroad
Flagging”
III. Item 607 – Fence (Plastic) shall be 48” high lightweight orange safety “crowd control”
plastic (high density polyethylene) fencing (Resinet SL24-48100-O, or equal). The post
shall be metal studded “tee” line post spaced at 16 feet. The fencing shall be securely
tied to the post, and shall be removed as directed by the engineer.
IV. Pedestrian Bridge #1 Wingwall Elevation Correction: There is a discreprency on the
top of the East wing wall elevations for Pedestrian Bridge #1 on plan sheets 11 and 12.
The correct eastside wing wall elevation is: 5041.54’. The appropriate correction to
sheet number 12 should be made and noted on your construction plan sets.
V. Sheet #10 Summary of Quantities Correction: The table on sheet 10 of the plan set
incorrectly references Pedestrian Bridge 3 as being the 42’0” structure and Pedestrian
Bridge 4 as being the 50’0” structure. Pedestrian Bridge #3 is the 50’0” structure and
Pedestrian Bridge 4 is the 42’0” structure.
VI. Sheet #10 Structure Descriptions Revisions: The “Structure Descriptions” incorrectly
describe Pedestrian Bridge 3 and Pedestrian Bridge 4 as being a 59’8” Prefabricated
Steel Truss Bridges. The correct descriptions are:
Pedestrian Bridge 3
50’0” PREFABRICATED STEEL TRUSS BRIDGE, CONCRETE DECK, ON CAST
IN-PLACE ABUTMENTS OVER NEW MERCER DITCH, FORT COLLINS,
COLORADO 14’0’ WIDTH, RAILING TO RAILING (15’0” OUT-TO-OUT)
Pedestrian Bridge 4
42’0” PREFABRICATED STEEL TRUSS BRIDGE, CONCRETE DECK, ON CAST
IN-PLACE ABUTMENTS OVER LARIMER COUNTY NO.2 DITCH, FORT COLLINS,
COLORADO 11’6’ WIDTH, RAILING TO RAILING (12’6” OUT-TO-OUT)
VII. Clarification on Safety Fencing along Easements: Revisions of Section 104 in the
Specifications Book states under the “Limits of Construction” that all easements and
work areas need to be fenced. This only applies to locations where the trail comes into
contact with existing sidewalks and roadways. You will also need to safety fence any
holes and drop-offs with safety fence. All these uses should be covered by your traffic
control line item.
VIII. Clarification on Interim Milestone Dates: There are no interim milestone dates, as the
contract is written. On a side note, the successful bidder will have to time his
construction so that it coincides with the New Mercer Channel and Larimer County Ditch
#2 shut-off date of October 15 and turn on date of March 15.
IX. Clarification on Health and Safety Management in the event that hazardous
material are encountered: In the event of encountering hazardous materials on the
jobsite, the City of Fort Collins will overrun Item 250 -Health and Safety Officer (HSO)
quantity for Health and Safety Management. An argument would need to be made for
us to justify force account work for the HSO. However, upon encountering hazardous
materials onsite, we would need to look at the problem and there may very well be
legitimate force account work related to moving and/or disposing of the material. Based
on the environmental report that was done, we are not anticipating hazardous materials
onsite.
X. Clarification on Note 23 in the General Notes on the plans: The primary contractor
will keep track of all changes on a master set of drawings in red ink. It will be The City of
Fort Collins’ responsibility to coordinate it's surveying services with Felsburg, Holt and
Ullvig to get the storm sewer verification and any other as-built field elevations/locations
and make electronic as-built updates to the plans.
XI. Clarification on Note 36 in the General Notes on the plans: Note 36 states: “In
Streets where more than one cut is made, an overlay of the entire street width, including
the patched are may be required.” This provision is for locations where there are more
than utility crossings in close proximity to each other. This situation does not occur on
this project and therefore the statement does not apply to this project.
RECEIPT OF THIS ADDENDUM MUST BE ACKNOWLEDGED BY A WRITTEN STATEMENT
ENCLOSED WITH THE BID/QUOTE STATING THAT THIS ADDENDUM HAS BEEN
RECEIVED.
FAX 970-834-2631
DBE Manufacturing & Supply
431 5th St.
Greeley, CO 80631
PH 970-302-0777
FAX 970-304-1199
Dean Contracting
34711 W. Cty. Rd. 23
Windsor, CO 80550
PH 970-686-0351
FAX 970-686-5630
PO Box Y
Berthoud, CO 80513
PH 970-532-0805
Dumar Contractor
PO Box 532
Greeley, CO 80632
PH 970-356-5660
Fax 970-356-5661
Continental Bridge, Inc.
8301 State Hwy. 29 N.
Alexandria, MN 56308
PH 320-852-7500
FAX 320-852-7067
FAX 970-834-2631
DBE Manufacturing & Supply
431 5th St.
Greeley, CO 80631
PH 970-302-0777
FAX 970-304-1199
Dean Contracting
34711 W. Cty. Rd. 23
Windsor, CO 80550
PH 970-686-0351
FAX 970-686-5630
PO Box Y
Berthoud, CO 80513
PH 970-532-0805
Dumar Contractor
PO Box 532
Greeley, CO 80632
PH 970-356-5660
Fax 970-356-5661
Continental Bridge, Inc.
8301 State Hwy. 29 N.
Alexandria, MN 56308
PH 320-852-7500
FAX 320-852-7067