HomeMy WebLinkAboutBID - 5998 LPATH BERM EROSION PROTECTION MEASURESSPECIFICATIONS
AND
CONTRACT DOCUMENTS
FOR
LPATH Berm Erosion Protection Measures
BID NO. 5998
PURCHASING DIVISION
215 NORTH MASON STREET, 2ND FLOOR, FORT COLLINS
October 19, 2006 – 3:00 P.M. (OUR CLOCK)
CONTRACT DOCUMENTS TABLE OF CONTENTS
Section Pages
BID INFORMATION
00020 Notice Inviting Bids 00020-1 - 00020-2
00100 Instruction to Bidders 00100-1 - 00100-9
00300 Bid Form 00300-1 - 00300-3
00400 Supplements to Bid Forms 00400-1
00410 Bid Bond 00410-1 - 00410-2
00420 Statements of Bidders Qualifications 00420-1 - 00420-3
00430 Schedule of Major Subcontractors 00430-1
CONTRACT DOCUMENTS
00500 Agreement Forms 00500-1
00510 Notice of Award 00510-0
00520 Agreement 00520-1 - 00520-6
00530 Notice to Proceed 00530-1
00600 Bonds and Certificates 00600-1
00610 Performance Bond 00610-1 - 00610-2
00615 Payment Bond 00615-1 - 00615-2
00630 Certificate of Insurance 00630-1
00635 Certificate of Substantial Completion 00635-1
00640 Certificate of Final Acceptance 00640-1
00650 Lien Waiver Release(Contractor) 00650-1 - 00650-2
00660 Consent of Surety 00660-1
00670 Application for Exemption Certificate 00670-1 - 00670-2
CONDITIONS OF THE CONTRACT
00700 General Conditions 00700-1 - 00700-34
Exhibit GC-A GC-A1 - GC-A2
00800 Supplementary Conditions 00800-1 - 00800-2
00900 Addenda, Modifications, and Payment 00900-1
00950 Contract Change Order 00950-1 - 00950-2
00960 Application for Payment 00960-1 - 00960-4
SPECIFICATIONS
DIVISION 1 - GENERAL REQUIREMENTS
01010 SUMMARY OF WORK
01140 CONTRACTOR’S USE OF PREMISES
01145 SPECIAL PROJECT PROCEDURES
01180 UTILITY SOURCES
01270 MEASUREMENT AND PAYMENT
07/2001 Section 00020 Page 2
01310 PROJECT MEETINGS
01320 CONSTRUCTION SCHEDULES
01330 SUBMITTALS
01425 STANDARD REFRENCES
01450 MATERIALS TESTING
01555 TRAFFIC REGULATION
01635 SUBSTITUTIONS AND PRODUCT OPTIONS
01650 MATERIAL DELIVERY, STORAGE, AND HANDLING
01710 SITE CONDITIONS
01715 TREE, LANDSCAPE, VEGETATION, AND WETLAND PROTECTION
01720 FIELD ENGINEERING AND SURVEYING
01745 ENVIRONMENTAL CONTROLS
01780 CONTRACT CLOSE-OUT
DIVISION 2 - SITE WORK
02230 CLEARING AND GRUBBING
02235 NATIVE SOIL
02236 TOPSOIL
02240 WATER CONTROL AND DEWATERING
02315 EXCAVATION AND EMBANKMENT
02370 EROSION AND SEDIMENT CONTROL
02371 GEOTEXTILE FABRIC FOR CONCRETE BLOCK REVETMENT
02375 RIPRAP
02376 CONCRETE RUBBLE
02700 CONCRETE BLOCK REVETMENT SYSTEM SPECIFICATIONS FOR OVERTOPPING
APPLICATIONS
02921 GROUND PREPARATION FOR SEEDING
DIVISION 3 - CONCRETE
03110 STRUCTURAL CAST-IN-PLACE CONCRETE FORMS
03210 REINFORCING STEEL
03310 STRUCTURAL CONCRETE
03320 CONSTRUCTION JOINTS
03350 CONCRETE FINISHING
03390 CONCRETE CURING
03615 GROUT
APPENDIX A
GEOTECHNICAL ENGINEERING REPORT
07/2001 Section 00020 Page 3
SECTION 00020
INVITATION TO BID
07/2001 Section 00020 Page 1
SECTION 00020
INVITATION TO BID
Date: SEPTEMBER 25, 2006
Sealed Bids will be received by the City of Fort Collins (hereinafter referred
to as OWNER), at the office of the Purchasing Division, 3:00 P.M., our clock,
on OCTOBER 10, 2006, for the LPATH Berm Erosion Protection Measures ; BID NO.
5998. If delivered, they are to be delivered to 215 North Mason Street, 2nd
Floor, Fort Collins, Colorado, 80524. If mailed, the mailing address is P. O.
Box 580, Fort Collins, CO 80522-0580.
At said place and time, and promptly thereafter, all Bids that have been duly
received will be publicly opened and read aloud.
The Contract Documents provide for the construction of LPATH Berm Erosion
Protection Measures; The project includes the removal of existing fence, the
removal of existing trees and concrete rubble, and the installation of erosion
control measures. The project also includes the excavation and transportation
of fill material and the placement of fill material. The installation of
concrete block revetment mats, the installation of concrete sills, buried
riprap, and the preparation of all disturbed areas for revegetation.
Questions concerning the scope of the bid should be directed to Project
Manager Jin Wang, (970) 221-6605 X7733.
Questions regarding bid submittal or process should be directed to John D.
Stephen, CPPO, CPPB, Senior Buyer (970) 221-6777.
All Bids must be in accordance with the Contract Documents on file with The
City of Fort Collins, 215 North Mason St., 2nd floor, Fort Collins, Colorado
80524.
Contract Documents will be available September 28, 2006.
A prebid conference and job walk with representatives of prospective Bidders
will be held at 10:00 a.m., on October 5, 2006, at 215 N. Mason St.,
Conference Room 2E in Fort Collins.
07/2001 Section 00020 Page 2
The Contract Documents and Construction Drawings may be examined online at:
1. City of Fort Collins BuySpeed: https://secure2.fcgov.com/bso/login.jsp
2. Mercury-LDO Reprographics: www.mercury-ldo.com
Copies of the Contract Documents, complete with Construction Specifications
and Drawings, may be viewed and purchased at:
1. Mercury LDO Reprograhics:
• FORT COLLINS: 422 S. Link Lane, Ft. Collins, CO 80524
Ph: 970-484-1201, Fax: 970-221-0404
• ENGLEWOOD: 9632 E. Arapahoe, Englewood, CO. 80112
Ph: 303-790-7169, Fax: 303-792-2936
• DENVER: 860 Bryant Street, Denver, CO. 80204
Ph: 303-893-8701, Fax: 303-893-0617
• COLORADO SPRINGS:11 E Las Vegas, Colorado Springs, CO. 80903
Ph: 719-231-8121, Fax: 719-633-5710
• LODO: 1660 Wynkoop Ste. 130, Denver, CO. 80202
Ph: 303-785-2520, Fax: 303-785-2522
• BOULDER: 2575 Pearl St. Unit C., Boulder, CO. 80302
Ph: 303-539-1350, Fax: 303-539-1356
2. Builders Exchange, 223 South Link Lane, Fort Collins, Colorado.
07/2001 Section 00020 Page 3
Construction Document Ordering Instructions
(Download a complete PlanWell 4.0 Ordering Guide from www.planwell.com)
1. GO TO: www.mercury-ldo.com
2. SELECT: Denver Links: “Plan Well”
3. SELECT: Public Planroom: “GO”
4. SELECT: the desired “Project Number” from the list
07/2001 Section 00020 Page 4
5. CLICK: “Most Current Set” to View the list of
documents available for the project
6. CLICK: Sheet No. to view
7. CLICK: to add a specific document to your
“Shopping Cart”
8. CLICK: to place the order for printing
9. REGISTER –or- LOGIN
10. SELECT: Process-Media, Output Size and Binding options
11. ENTER: Job Number and PO information then click Next.
12. REVIEW: Recipient information.
13. ENTER: Quantities
14. CLICK: the down arrow to populate order.
15. SELECT: Delivery options and Due time.
16. ENTER: Your phone number in the special instructions
box.
17. CLICK: Next.
18. REVIEW order
19. CLICK: SUBMIT
Planwell contacts:
Marie Owens 970-484-1201, mowens@mercury-ldo.com
David Bacon-720-220-7683, dbacon@mercury-ldo.com
07/2001 Section 00020 Page 5
Prospective Bidders are invited to present their questions relative to this
Bid proposal at this meeting.
Bids will be received as set forth in the Bidding Documents.
The Work is expected to be commenced within the time as required by Section
2.3 of General Conditions. Substantial Completion of the Work is required as
specified in the Agreement.
The successful Bidder will be required to furnish a Performance Bond and a
Payment Bond guaranteeing faithful performance and the payment of all bills
and obligations arising from the performance of the Contract.
No Bid may be withdrawn within a period of forty-five (45) days after the date
fixed for opening Bids.
The OWNER reserves the right to reject any and all Bids, and to waive any
informalities and irregularities therein.
Bid security in the amount of not less than 5% of the total Bid must accompany
each Bid in the form specified in the Instructions to Bidders.
Sales Prohibited/Conflict of Interest: No officer, employee, or member of City
Council, shall have a financial interest in the sale to the City of any real
or personal property, equipment, material, supplies or services where such
officer or employee exercises directly or indirectly any decision-making
authority concerning such sale or any supervisory authority over the services
to be rendered. This rule also applies to subcontracts with the City.
Soliciting or accepting any gift, gratuity favor, entertainment, kickback or
any items of monetary value from any person who has or is seeking to do
business with the City of Fort Collins is prohibited
City of Fort Collins
By ______________________________________
James B. O'Neill, II, CPPO, FNIGP
Purchasing/Risk Management Director
Plan Holders List
Bid 5998 LPATH Berm Erosion Protection Measures
Updated 10/16/06
SPECIFICATIONS
AND
CONTRACT DOCUMENTS
FOR
LPATH Berm Erosion Protection Measures
BID NO. 5998
PURCHASING DIVISION
215 NORTH MASON STREET, 2ND FLOOR, FORT COLLINS
October 19, 2006 – 3:00 P.M. (OUR CLOCK)
CONTRACT DOCUMENTS TABLE OF CONTENTS
Section Pages
BID INFORMATION
00020 Notice Inviting Bids 00020-1 - 00020-2
00100 Instruction to Bidders 00100-1 - 00100-9
00300 Bid Form 00300-1 - 00300-3
00400 Supplements to Bid Forms 00400-1
00410 Bid Bond 00410-1 - 00410-2
00420 Statements of Bidders Qualifications 00420-1 - 00420-3
00430 Schedule of Major Subcontractors 00430-1
CONTRACT DOCUMENTS
00500 Agreement Forms 00500-1
00510 Notice of Award 00510-0
00520 Agreement 00520-1 - 00520-6
00530 Notice to Proceed 00530-1
00600 Bonds and Certificates 00600-1
00610 Performance Bond 00610-1 - 00610-2
00615 Payment Bond 00615-1 - 00615-2
00630 Certificate of Insurance 00630-1
00635 Certificate of Substantial Completion 00635-1
00640 Certificate of Final Acceptance 00640-1
00650 Lien Waiver Release(Contractor) 00650-1 - 00650-2
00660 Consent of Surety 00660-1
00670 Application for Exemption Certificate 00670-1 - 00670-2
CONDITIONS OF THE CONTRACT
00700 General Conditions 00700-1 - 00700-34
Exhibit GC-A GC-A1 - GC-A2
00800 Supplementary Conditions 00800-1 - 00800-2
00900 Addenda, Modifications, and Payment 00900-1
00950 Contract Change Order 00950-1 - 00950-2
00960 Application for Payment 00960-1 - 00960-4
SPECIFICATIONS
DIVISION 1 - GENERAL REQUIREMENTS
01010 SUMMARY OF WORK
01140 CONTRACTOR’S USE OF PREMISES
01145 SPECIAL PROJECT PROCEDURES
01180 UTILITY SOURCES
01270 MEASUREMENT AND PAYMENT
07/2001 Section 00020 Page 2
01310 PROJECT MEETINGS
01320 CONSTRUCTION SCHEDULES
01330 SUBMITTALS
01425 STANDARD REFRENCES
01450 MATERIALS TESTING
01555 TRAFFIC REGULATION
01635 SUBSTITUTIONS AND PRODUCT OPTIONS
01650 MATERIAL DELIVERY, STORAGE, AND HANDLING
01710 SITE CONDITIONS
01715 TREE, LANDSCAPE, VEGETATION, AND WETLAND PROTECTION
01720 FIELD ENGINEERING AND SURVEYING
01745 ENVIRONMENTAL CONTROLS
01780 CONTRACT CLOSE-OUT
DIVISION 2 - SITE WORK
02230 CLEARING AND GRUBBING
02235 NATIVE SOIL
02236 TOPSOIL
02240 WATER CONTROL AND DEWATERING
02315 EXCAVATION AND EMBANKMENT
02370 EROSION AND SEDIMENT CONTROL
02371 GEOTEXTILE FABRIC FOR CONCRETE BLOCK REVETMENT
02375 RIPRAP
02376 CONCRETE RUBBLE
02700 CONCRETE BLOCK REVETMENT SYSTEM SPECIFICATIONS FOR OVERTOPPING
APPLICATIONS
02921 GROUND PREPARATION FOR SEEDING
DIVISION 3 - CONCRETE
03110 STRUCTURAL CAST-IN-PLACE CONCRETE FORMS
03210 REINFORCING STEEL
03310 STRUCTURAL CONCRETE
03320 CONSTRUCTION JOINTS
03350 CONCRETE FINISHING
03390 CONCRETE CURING
03615 GROUT
APPENDIX A
GEOTECHNICAL ENGINEERING REPORT
07/2001 Section 00020 Page 3
SECTION 00020
INVITATION TO BID
07/2001 Section 00020 Page 1
SECTION 00020
INVITATION TO BID
Date: SEPTEMBER 25, 2006
Sealed Bids will be received by the City of Fort Collins (hereinafter referred
to as OWNER), at the office of the Purchasing Division, 3:00 P.M., our clock,
on OCTOBER 10, 2006, for the LPATH Berm Erosion Protection Measures ; BID NO.
5998. If delivered, they are to be delivered to 215 North Mason Street, 2nd
Floor, Fort Collins, Colorado, 80524. If mailed, the mailing address is P. O.
Box 580, Fort Collins, CO 80522-0580.
At said place and time, and promptly thereafter, all Bids that have been duly
received will be publicly opened and read aloud.
The Contract Documents provide for the construction of LPATH Berm Erosion
Protection Measures; The project includes the removal of existing fence, the
removal of existing trees and concrete rubble, and the installation of erosion
control measures. The project also includes the excavation and transportation
of fill material and the placement of fill material. The installation of
concrete block revetment mats, the installation of concrete sills, buried
riprap, and the preparation of all disturbed areas for revegetation.
Questions concerning the scope of the bid should be directed to Project
Manager Jin Wang, (970) 221-6605 X7733.
Questions regarding bid submittal or process should be directed to John D.
Stephen, CPPO, CPPB, Senior Buyer (970) 221-6777.
All Bids must be in accordance with the Contract Documents on file with The
City of Fort Collins, 215 North Mason St., 2nd floor, Fort Collins, Colorado
80524.
Contract Documents will be available September 28, 2006.
A prebid conference and job walk with representatives of prospective Bidders
will be held at 10:00 a.m., on October 5, 2006, at 215 N. Mason St.,
Conference Room 2E in Fort Collins.
07/2001 Section 00020 Page 2
The Contract Documents and Construction Drawings may be examined online at:
1. City of Fort Collins BuySpeed: https://secure2.fcgov.com/bso/login.jsp
2. Mercury-LDO Reprographics: www.mercury-ldo.com
Copies of the Contract Documents, complete with Construction Specifications
and Drawings, may be viewed and purchased at:
1. Mercury LDO Reprograhics:
• FORT COLLINS: 422 S. Link Lane, Ft. Collins, CO 80524
Ph: 970-484-1201, Fax: 970-221-0404
• ENGLEWOOD: 9632 E. Arapahoe, Englewood, CO. 80112
Ph: 303-790-7169, Fax: 303-792-2936
• DENVER: 860 Bryant Street, Denver, CO. 80204
Ph: 303-893-8701, Fax: 303-893-0617
• COLORADO SPRINGS:11 E Las Vegas, Colorado Springs, CO. 80903
Ph: 719-231-8121, Fax: 719-633-5710
• LODO: 1660 Wynkoop Ste. 130, Denver, CO. 80202
Ph: 303-785-2520, Fax: 303-785-2522
• BOULDER: 2575 Pearl St. Unit C., Boulder, CO. 80302
Ph: 303-539-1350, Fax: 303-539-1356
2. Builders Exchange, 223 South Link Lane, Fort Collins, Colorado.
07/2001 Section 00020 Page 3
Construction Document Ordering Instructions
(Download a complete PlanWell 4.0 Ordering Guide from www.planwell.com)
1. GO TO: www.mercury-ldo.com
2. SELECT: Denver Links: “Plan Well”
3. SELECT: Public Planroom: “GO”
4. SELECT: the desired “Project Number” from the list
07/2001 Section 00020 Page 4
5. CLICK: “Most Current Set” to View the list of
documents available for the project
6. CLICK: Sheet No. to view
7. CLICK: to add a specific document to your
“Shopping Cart”
8. CLICK: to place the order for printing
9. REGISTER –or- LOGIN
10. SELECT: Process-Media, Output Size and Binding options
11. ENTER: Job Number and PO information then click Next.
12. REVIEW: Recipient information.
13. ENTER: Quantities
14. CLICK: the down arrow to populate order.
15. SELECT: Delivery options and Due time.
16. ENTER: Your phone number in the special instructions
box.
17. CLICK: Next.
18. REVIEW order
19. CLICK: SUBMIT
Planwell contacts:
Marie Owens 970-484-1201, mowens@mercury-ldo.com
David Bacon-720-220-7683, dbacon@mercury-ldo.com
07/2001 Section 00020 Page 5
Prospective Bidders are invited to present their questions relative to this
Bid proposal at this meeting.
Bids will be received as set forth in the Bidding Documents.
The Work is expected to be commenced within the time as required by Section
2.3 of General Conditions. Substantial Completion of the Work is required as
specified in the Agreement.
The successful Bidder will be required to furnish a Performance Bond and a
Payment Bond guaranteeing faithful performance and the payment of all bills
and obligations arising from the performance of the Contract.
No Bid may be withdrawn within a period of forty-five (45) days after the date
fixed for opening Bids.
The OWNER reserves the right to reject any and all Bids, and to waive any
informalities and irregularities therein.
Bid security in the amount of not less than 5% of the total Bid must accompany
each Bid in the form specified in the Instructions to Bidders.
Sales Prohibited/Conflict of Interest: No officer, employee, or member of City
Council, shall have a financial interest in the sale to the City of any real
or personal property, equipment, material, supplies or services where such
officer or employee exercises directly or indirectly any decision-making
authority concerning such sale or any supervisory authority over the services
to be rendered. This rule also applies to subcontracts with the City.
Soliciting or accepting any gift, gratuity favor, entertainment, kickback or
any items of monetary value from any person who has or is seeking to do
business with the City of Fort Collins is prohibited
City of Fort Collins
By ______________________________________
James B. O'Neill, II, CPPO, FNIGP
Purchasing/Risk Management Director
SECTION 00100
INSTRUCTIONS TO BIDDERS
12/03 Section 00100 Page 1
SECTION 00100
INSTRUCTIONS TO BIDDERS
1.0 DEFINED TERMS
Terms used in these Instructions to Bidders which are defined in the
Standard General Conditions of the Construction Contract (No. 1910-8,
1990 ed.) have the meanings assigned to them in the General Conditions.
The term "Bidder" means one who submits a Bid to OWNER, as distinct from
a sub-bidder, who submits a Bid to Bidder. The terms "Successful Bidder"
means the lowest, qualified, responsible and responsive Bidder to whom
OWNER (on basis of OWNER's evaluation as hereinafter provided) makes an
award. The term "Bidding Documents" includes the Advertisement or
Invitation to Bid, Instructions to Bidders, the Bid Form, and the
proposed Contract Documents (including all Addenda issued prior to
receipt of Bids).
2.0 COPIES OF BIDDING DOCUMENTS
2.1. Complete sets of Bidding Documents may be obtained as stated in the
Invitation to Bid. No partial sets will be issued. The Bidding
Documents may be examined at the locations identified in the Invitation
to Bid.
2.2. Complete sets of Bidding Documents shall be used in preparing Bids;
neither OWNER nor Engineer assumes any responsibility for errors or
misinterpretations resulting from the use of incomplete sets of Bidding
Documents.
2.3. The submitted Bid proposal shall include Sections 00300, 00410,
00420, and 00430 fully executed.
2.4. OWNER and Engineer, in making copies of Bidding Documents available
on the above terms, do so only for the purpose of obtaining Bids on the
Work and do not confer a license or grant for any other use.
3.0 QUALIFICATION OF BIDDERS
3.1 To demonstrate qualifications to perform the Work, each Bidder must
submit at the time of the Bid opening, a written statement of
qualifications including financial data, a summary of previous
experience, previous commitments and evidence of authority to conduct
business in the jurisdiction where the Project is located. Each Bid must
contain evidence of Bidder's qualification to do business in the state
where the Project is located or covenant to obtain such qualification
prior to award of the contract. The Statement of Qualifications shall be
prepared on the form provided in Section 00420.
12/03 Section 00100 Page 2
3.2. In accordance with Section 8-160 of the Code of the City of Fort
Collins in determining whether a bidder is responsible, the following
shall be considered: (1) The ability, capacity and skill of the bidder to
perform the contract or provide the services required, (2) whether the
bidder can perform the contract or provide the service promptly and
within the time specified without delay or interference, (3) the
character, integrity, reputation, judgment, experience and efficiency of
the bidder, (4) the quality of the bidder's performance of previous
contracts or services, (5) the previous and existing compliance by the
bidder with laws and ordinances relating to the contract or service, (6)
the sufficiency of the financial resources and ability of the bidder to
perform the contract or provide the service, (7) the quality,
availability and adaptability of the materials and services to the
particular use required, (8) the ability of the bidder to provide future
maintenance and service for the use of the subject of the contract, and
(9) any other circumstances which will affect the bidder's performance of
the contract.
3.3. Each Bidder may be required to show that he has handled former Work
so that no just claims are pending against such Work. No Bid will be
accepted from a Bidder who is engaged on any other Work which would
impair his ability to perform or finance this Work.
3.4 No Bidder shall be in default on the performance of any other
contract with the City or in the payment of any taxes, licenses or other
monies due to the City.
4.0 EXAMINATION OF CONTRACT DOCUMENTS AND SITE
4.1. It is the responsibility of each Bidder, before submitting a Bid,
to (a) examine the Contract Documents thoroughly, (b) visit the site to
familiarize himself with local conditions that may in any manner affect
cost, progress or performance of the Work, (c) familiarize himself with
federal, state and local laws, ordinances, rules and regulations that may
in any manner affect cost, progress or performance of the Work, (d) study
and carefully correlate Bidder's observations with the Contract
Documents, and (e) notify Engineer of all conflicts, errors or
discrepancies in the Contract Documents.
4.2. Reference is made to the Supplementary Conditions for
identification of: Subsurface and Physical Conditions SC-4.2.
4.3. The submission of a Bid will constitute an incontrovertible
representation by Bidder that Bidder has complied with every requirement
of this Article 4, that without exception the Bid is premised upon
performing and furnishing the Work required by the Contract Documents and
such means, methods, techniques, sequences or procedures of construction
as may be indicated in or required by the Contract Documents, and that
12/03 Section 00100 Page 3
the Contract Documents are sufficient in scope and detail to indicate and
convey understanding of all terms and conditions for performance and
furnishing of the Work.
5.0 INTERPRETATIONS AND ADDENDA.
5.1. All questions about the meaning or intent of the Bidding Documents are to
be submitted in writing to the Engineer and the OWNER. Interpretation or
clarifications considered necessary in response to such questions will be
issued only by Addenda. Questions received less than seven days prior to
the date for opening of the Bids may not be answered. Only questions
answered by formal written Addenda will be binding. Oral and other
interpretations or clarifications will be without legal effect.
5.2. All questions concerning the scope of this project should be
directed to the Engineer. Questions regarding submittal of bids should
be directed to the City of Fort Collins' Purchasing Division.
5.3. Addenda may also be issued to modify the Bidding Documents as
deemed advisable by OWNER or Engineer.
5.4. Addenda will be mailed or delivered to all parties recorded by the
OWNER as having received the Bidding documents.
6.0 BID SECURITY
6.1. Each Bid must be accompanied by Bid Security made payable to OWNER
in the amount stated in the Invitation to Bid. The required security
must be in the form of a certified or bank cashier's check payable to
OWNER or a Bid Bond on the form enclosed herewith. The Bid Bond must be
executed by a surety meeting the requirements of the General Conditions
for surety bonds.
6.2. The Bid Security of the successful Bidder will be retained until
such Bidder has executed the Agreement and furnished the required
contract security, whereupon Bid Security will be returned. If the
successful Bidder fails to execute and deliver the Agreement and furnish
the required contract security within 15 days of the Notice of Award,
OWNER may annul the Notice of Award and the Bid Security of that Bidder
will be forfeited. The Bid Security of other Bidders whom OWNER believes
to have reasonable chance receiving the award may be retained by OWNER
until the earlier of the seventh day after the effective date of the
Agreement or the thirty-first day after the Bid Opening, whereupon Bid
Security furnished by such Bidders will be returned. Bid Security with
Bids which are not competitive will be returned within seven days after
the Bid opening.
7.0 CONTRACT TIME.
12/03 Section 00100 Page 4
The number of days within which, or the date by which the Work is to be
substantially complete and also completed and ready for Final Payment
(the Contract Times) are set forth in the Agreement.
8.0 LIQUIDATED DAMAGES.
Provisions for liquidated damages are set forth in the Agreement.
9.0 SUBSTITUTE ("OR EQUAL") MATERIAL AND EQUIPMENT
The Contract, if awarded, will be on the basis of material and equipment
described on the Drawings or specified in the Specifications without
consideration of possible substitute or "or equal" items. Whenever it is
indicated on the Drawings or specified in the Specifications that a
substitute or "or equal" item of material or equipment may be furnished
or used by CONTRACTOR if acceptable to Engineer, application for such
acceptance will not be considered by Engineer until after the "effective
date of the Agreement". The procedure for submittal of any such
application by CONTRACTOR and consideration by Engineer is set forth in
the General Conditions which may be supplemented in the General
Requirements.
10.0 SUBCONTRACTORS, SUPPLIERS AND OTHERS
10.1. Each Bidder shall submit at the Bid opening to OWNER a list of
principal subcontractors he proposes to use in the Work. Refer to
Section 00430 contained within these Documents.
10.2. If OWNER or Engineer after due investigation has reasonable
objection to any proposed Subcontractor, either may, before the Notice of
Award is given, request the apparent successful Bidder to submit an
acceptable substitute without an increase in Bid price. If the apparent
successful Bidder declines to make any substitution, OWNER may award the
contract to the next lowest responsive and responsible Bidder that
proposes to use acceptable subcontractors. Subcontractors, suppliers,
other persons or organization listed and to whom OWNER or Engineer does
not make written objection prior to the giving of the Notice of Award
will be deemed acceptable to OWNER and ENGINEER subject to revocation of
such acceptance after the effective date of the Agreement as provided in
the General Conditions.
10.3. CONTRACTOR shall not be required to employ any subcontractor,
supplier or other persons or organizations against whom he has reasonable
objection. The use of subcontractors listed by the Bidder and accepted
by OWNER prior to the Notice of Award will be required in the performance
of the Work.
11.0 BID FORM.
12/03 Section 00100 Page 5
11.1. A copy of the Bid Form is bound in the Contract Documents which
may be retained by the Bidder. A separate unbound copy is enclosed for
submission with the Bid.
11.2. Bid Forms must be complete in ink or typed. All lump sum prices
on the form must be stated in words and numerals; in case of conflict,
words will take precedence. Unit prices shall govern over extensions of
sums.
11.3. Bids by corporations must be executed in the corporate name by the
president or a vice-president (or other appropriate officer accompanied
by evidence of authority to sign) and the corporate seal shall be affixed
and attested by the secretary or an assistant secretary. The corporate
address and state of incorporation shall be shown below the corporate
name.
11.4. Bids by partnerships must be executed in the partnership name and
signed by a partner, his title must appear under his signature and the
official address of the partnership must be shown below the signature.
11.5. Bids by joint venture shall be signed by each participant in the
joint venture or by an authorized agent of each participant. The full
name of each person or company interested in the Bid shall be listed on
the Bid Form.
11.6. The Bid shall contain an acknowledgement of receipt of all Addenda
(the numbers of which must be filled in on the Bid Form).
11.7. No alterations in Bids, or in the printed forms therefore, by
erasures, interpolations, or otherwise will be acceptable unless each
such alteration is signed or initialed by the Bidder; if initialed, OWNER
may require the Bidder to identify any alteration so initialed.
11.8. The address and telephone number for communications regarding the
Bid shall be shown.
12.0 BID PRICING.
Bids must be priced as set forth in the Bid Schedule or Schedules.
13.0 SUBMISSION OF BIDS.
13.1. Bids shall be submitted at the time and place indicated in the
Invitation to Bid and shall be enclosed in an opaque sealed envelope
marked with the Project title, Bid No., and name and address of the
Bidder and accompanied by the Bid Security, Bid Form, Bid Bond, Statement
of Bidders Qualifications, and Schedule of Subcontractors as required in
Section 00430. If the Bid is sent through the mail or other delivery
system, the sealed envelope shall be enclosed in a separate envelope with
12/03 Section 00100 Page 6
the notation "BID ENCLOSED" on the face of it.
13.2. Bids shall be deposited at the designated location prior to the
time and date for receipt of Bids indicated in the Invitation to Bid, or
any extension thereof made by addendum. Bids received after the time and
date for receipt of Bids will be returned unopened. Bidder shall assume
full responsibility for timely delivery at the location designated for
receipt of Bids.
13.3. Oral, telephonic, telegraphic, or facsimile Bids are invalid and
will not receive consideration.
13.4. No Bidder may submit more than one Bid. Multiple Bids under
different names will not be accepted from one firm or association.
14.0 MODIFICATION AND WITHDRAWAL OF BIDS.
14.1. Bids may be modified or withdrawn by an appropriate document duly
executed (in a manner that a Bid must be executed) and delivered to the
place where Bids are to be submitted at any time prior to the opening of
Bids.
14.2. Bids may also be modified or withdrawn in person by the Bidder or
an authorized representative provided he can prove his identity and
authority at any time prior to the opening of Bids.
14.3. Withdrawn Bids may be resubmitted up to the time designated for
the receipt of Bids provided that they are then fully in conformance with
these Instructions to Bidders.
15.0 OPENINGS OF BIDS.
Bids will be opened and (unless obviously non-responsive) read aloud
publicly as indicated in the Invitation to Bid. An abstract of the
amounts of the Base Bids and major alternates (if any) will be made
available after the opening of Bids.
16.0 BIDS TO REMAIN OPEN SUBJECT TO ACCEPTANCE.
All Bids shall remain open for forty-five (45) days after the day of the
Bid Opening, but OWNER may, in his sole discretion, release any Bid and
return the Bid Security prior to that date.
17.0 AWARD OF CONTRACT.
17.1. OWNER reserves the right to reject any and all Bids, to waive any
and all informalities not involving price, time or changes in the Work,
to negotiate contract terms with the Successful Bidder, and the right to
12/03 Section 00100 Page 7
disregard all nonconforming, nonresponsive, unbalanced or conditional
Bids. Also, OWNER reserves the right to reject the Bid of any Bidder if
OWNER believes that it would not be in the best interest of the Project
to make an award to that Bidder, whether because the Bid is not
responsive or the Bidder is unqualified or of doubtful financial ability
or fails to meet any other pertinent standard or criteria established by
OWNER. Discrepancies between the indicated sum of any column of figures
and the correct sum thereof will be resolved in favor of the correct sum.
17.2. In evaluating Bids, OWNER will consider the qualifications of the
Bidders, whether or not the Bids comply with the prescribed requirements,
and such alternates, unit prices and other data, as may be requested in
the Bid Form or prior to the Notice of Award.
17.3. OWNER may consider the qualification and experience of
Subcontractors, Suppliers, and other persons and organizations proposed
for those portions of the Work as to which the identity of
Subcontractors, Suppliers, and other persons and organizations is
submitted as requested by OWNER. OWNER also may consider the operating
costs, maintenance requirements, performance data and guarantees of major
items of materials and equipment proposed for incorporation in the Work
when such data is required to be submitted prior to the Notice of Award.
17.4. OWNER may conduct such investigations as OWNER deems necessary to
assist in the evaluation of any Bid and to establish the responsibility,
qualifications and financial ability of the Bidder's proposed
Subcontractors, Suppliers and other persons and organizations to do the
Work in accordance with the Contract Documents to OWNER's satisfaction
within the prescribed time.
17.5. If the Contract is to be awarded, it will be awarded to the lowest
responsive and responsible Bidder whose evaluation by OWNER indicates to
OWNER that the award will be in the best interest of the OWNER. Award
shall be made on the evaluated lowest base bid excluding alternates. The
basis for award shall be the lowest Bid total for the Schedule or, in the
case of more than one schedule, for sum of all schedules. Only one
contract will be awarded.
17.6. If the Contract is to be awarded, OWNER will give the Successful
Bidder a Notice of Award within forty-five (45) days after the date of
the Bid opening.
18.0 CONTRACT SECURITY.
The General Conditions and the Supplementary Conditions set forth OWNER's
requirements as to performance and other Bonds. When the Successful
Bidder delivers the executed Agreement to the OWNER, it shall be
accompanied by the required Contract Security.
12/03 Section 00100 Page 8
19.0 SIGNING OF AGREEMENT.
When OWNER gives a Notice of Award to the Successful Bidder, it will be
accompanied by the required number of unsigned counterparts of the
Agreement with all other written Contract Documents attached. Within
fifteen (15) days thereafter, CONTRACTOR shall sign and deliver the
required number of counterparts of the Agreement and attached documents
to OWNER with the required Bonds. Within ten (10) days thereafter, OWNER
shall deliver one fully signed counterpart to CONTRACTOR. Each
counterpart is to be accompanied by a complete set of the Drawings with
appropriate identification.
20.0 TAXES.
OWNER is exempt from Colorado State Sales and Use Taxes on materials and
equipment to be incorporated in the Work. Said taxes shall not be
included in the Contract Price. Reference is made to the General and
Supplementary Conditions.
21.0 RETAINAGE.
Provisions concerning retainage are set forth in the Agreement.
22.0 PURCHASING RESTRICTIONS.
Purchasing restrictions: The Bidder's authorized signature of this Bid
assures the Bidder's compliance with the City's purchasing restrictions.
A copy of the resolutions are available for review in the Purchasing and
Risk Management Division or the City Clerk's office.
A. Cement Restrictions: City of Fort Collins Resolution 91-121
requires that suppliers and producers of cement or products
containing cement to certify that the cement was not made in cement
kilns that burn hazardous waste as a fuel.
23.0 COLLUSIVE OR SHAM BIDS.
Any Bid deemed by the City in its sole discretion to be a collusive or
sham Bid will be rejected and reported to authorities as such. Your
authorized signature of this Bid assures that such Bid is genuine and is
not a collusive or sham Bid.
24.0 BID RESULTS.
For information regarding results for individual Bids send a self-
addressed, self-stamped envelope and a Bid tally will be mailed to you.
Bid results will be posted in the Purchasing office seven (7) days after
the Bid Opening.
12/03 Section 00100 Page 9
END OF SECTION
SECTION 00300
BID FORM
SECTION 00300
BID FORM
PROJECT: 5998 LPATH Berm Erosion Protection Measures
Place
Date
1. In compliance with your Invitation to Bid dated
, and subject to all conditions thereof, the undersigned
a (Corporation, Limited Liability Company, Partnership, Joint Venture, or
Sole Proprietor) authorized to do business in the State of Colorado
hereby proposes to furnish and do everything required by the Contract
Documents to which this refers for the construction of all items listed
on the following Bid Schedule or Bid Schedules.
2. The undersigned Bidder does hereby declare and stipulate that this
proposal is made in good faith, without collusion or connection with any
other person or persons Bidding for the same Work, and that it is made in
pursuance of and subject to all the terms and conditions of the
Invitation to Bid and Instructions to Bidders, the Agreement, the
detailed Specifications, and the Drawings pertaining to the Work to be
done, all of which have been examined by the undersigned.
3. Accompanying this Bid is a certified or cashier's check or standard Bid
bond in the sum of ______________________________________________________
($ ) in accordance with the Invitation To Bid
and Instructions to Bidders.
4. The undersigned Bidder agrees to execute the Agreement and a Performance
Bond and a Payment Bond for the amount of the total of this Bid within
fifteen (15) calendar days from the date when the written notice of the
award of the contract is delivered to him at the address given on this
Bid. The name and address of the corporate surety with which the Bidder
proposes to furnish the specified performance and payment bonds is as
follows: _________________________________________________________.
5. All the various phases of Work enumerated in the Contract Documents with
their individual jobs and overhead, whether specifically mentioned,
included by implication or appurtenant thereto, are to be performed by
the CONTRACTOR under one of the items listed in the Bid Schedule,
irrespective of whether it is named in said list.
6. Payment for Work performed will be in accordance with the Bid Schedule or
Bid Schedules subject to changes as provided in the Contract Documents.
7. The undersigned Bidder hereby acknowledges receipt of Addenda No.
_______through .
7/96 Section 00300 Page 2
8. BID SCHEDULE (Base Bid)Lump Sum
Item Description Unit Estimated Unit Item
Number Quantity Cost ($) Cost ($)
1 Mobilization LS 1
2 Traffic / Access Control LS 1
3 Clearing and Grubbing LS 1
4 Construction Dewatering (North Spill and River Riprap
Location) LS 1
5 Remove Concrete Rubble SF 10350
6 Fence Removal/Resetting (Wood Fence) LF 100
7 Silt Fence LF 3845
8 Straw Bale – Sediment and Erosion Control Structure EA 8
9 Unclassified Excavation (Quantity Assumed 15% shrinkage in
Borrow Site material) CY 9068
10 Muck Excavation CY 200
11 Native Soil (Over Revetment Mat Only) CY 1040
12 Embankment (Complete In Place) without Haul - South Spill
Only CY 1652
13 Embankment (Complete In Place) with Haul - Both Spill
Locations CY 9738
North Spill = 7416 CY, South Spill = 2322 CY ---- ----
14 Concrete Sill (Complete In Place) CY 170
15 Concrete Block Revetment Mat - North Spill SF 27453
16 Concrete Block Revetment Mat (Including drainage layer) -
South Spill SF 28640
17 Riprap (Class 12) TON 1560
18 4" to 8" Crushed Concrete Rubble (Quantity Assumed 20%
extra for voids) TON 1968
19 1-1/2" Washed Rock (Quantity Assumed 35% shrinkage) TON 818
20 Landscape - Tree Removal (> 12" Diameter) EA 15
21 Ground Preparation for Seeding AC 9
22 Topsoil (Delivery and Stockpile only - No Installation) CY 200
TOTAL COST
Total Cost in Words:___________________________________________________Dollars
7/96 Section 00300 Page 3
9. PRICES
The foregoing prices shall include all labor, materials, transportation,
shoring, removal, dewatering, overhead, profit, insurance, etc., to cover
the complete Work in place of the several kinds called for.
Bidder acknowledges that the OWNER has the right to delete items in the Bid
or change quantities at his sole discretion without affecting the Agreement
or prices of any item so long as the deletion or change does not exceed
twenty-five percent (25%) of the total Agreement Price.
RESPECTFULLY SUBMITTED:
________________________________ __________________
Signature Date
________________________________
Title
________________________________
License Number (If Applicable)
(Seal - if Bid is by corporation)
Attest:___________________________
Address _____________________________________
_____________________________________
Telephone _____________________________________
7/96 Section 00410 Page 1
SECTION 00400
SUPPLEMENTS TO BID FORMS
00410 Bid Bond
00420 Statement of Bidder's Qualifications
00430 Schedule of Subcontractors
7/96 Section 00410 Page 2
SECTION 00410
BID BOND
KNOW ALL MEN BY THESE PRESENTS: that we, the undersigned
as Principal, and as Surety, are
hereby held and firmly bound unto the City of Fort Collins, Colorado, as
OWNER, in the sum of $ ______________________ for the
payment of which, well and truly to be made, we hereby jointly and severally
bind ourselves, successors, and assigns.
THE CONDITION of this obligation is such that whereas the Principal has
submitted to the City of Fort Collins, Colorado the accompanying Bid and
hereby made a part hereof to enter into a Construction Agreement for the
construction of Fort Collins Project, 5998 LPATH Berm Erosion Protection
Measures.
NOW THEREFORE,
(a) If said Bid shall be rejected, or
(b) If said Bid shall be accepted and the Principal shall execute and deliver
a Contract in the form of Contract attached hereto (properly completed in
accordance with said Bid) and shall furnish a BOND for his faithful
performance of said Contract, and for payment of all persons performing
labor or furnishing materials in connection therewith, and shall in all
other respects perform the Agreement created by the acceptance of said
Bid, then this obligation shall be void; otherwise the same shall remain
in force and effect, it being expressly understood and agreed that the
liability of the Surety for any and all claims hereunder shall, in no
event, exceed the penal amount of this obligation as herein stated.
The Surety, for value received, hereby stipulates and agrees that the
obligations of said Surety and its BOND shall be in no way impaired or
affected by any extension of the time within which the OWNER may accept such
Bid; and said Surety does hereby waive notice of any such extension.
Surety Companies executing bonds must be authorized to transact business in
the State of Colorado and be accepted by the OWNER.
7/96 Section 00410 Page 3
IN WITNESS WHEREOF, the Principal and the Surety have hereunto set their hands
and seals this day of , 20__, and such of them as are
corporations have caused their corporate seals to be hereto affixed and these
presents to be signed by their proper officers, the day and year first set
forth above.
PRINCIPAL SURETY
Name:_____________________________ __________________________________
Address:__________________________ __________________________________
__________________________________ __________________________________
By:_______________________________ By: ______________________________
Title: ___________________________ Title:____________________________
ATTEST:
By:_______________________________
(SEAL) (SEAL)
7/96 Section 00420 Page 1
SECTION 00420
STATEMENT OF BIDDER'S QUALIFICATIONS
All questions must be answered and the data given must be clear and
comprehensive. This statement must be notarized. If necessary, questions may
be answered on separate attached sheets. The Bidder may submit any additional
information he desires.
1. Name of Bidder: _________________________________________________
2. Permanent main office address: __________________________________
3. When organized: _________________________________________________
4. If a corporation, where incorporated: ___________________________
5. How many years have you been engaged in the contracting business
under your present firm or trade name?___________________________
6. Contracts on hand: (Schedule these, showing the amount of each
contract and the appropriate anticipated dates of completion.)
_________________________________________________________________
_________________________________________________________________
_________________________________________________________________
_________________________________________________________________
7. General character of Work performed by your company:
_________________________________________________________________
_________________________________________________________________
8. Have you ever failed to complete any Work awarded to you?________
If so, where and why?____________________________________________
_________________________________________________________________
9. Have your ever defaulted on a contract?__________________________
If so, where and why?____________________________________________
_________________________________________________________________
10. Are you debarred by any government agency? ______________________
If yes list agency name._________________________________________
7/96 Section 00420 Page 2
11. List the more important projects recently completed by your company,
stating the approximate cost of each, and the month and year completed,
location and type of construction.
_________________________________________________________________________
_________________________________________________________________________
_________________________________________________________________________
12. List your major equipment available for this contract.
_________________________________________________________________________
_________________________________________________________________________
_________________________________________________________________________
13. Experience in construction Work similar in importance to this
project:
_________________________________________________________________________
_________________________________________________________________________
_________________________________________________________________________
14. Background and experience of the principal members of your organization,
including officers:
_________________________________________________________________________
_________________________________________________________________________
_________________________________________________________________________
15. Credit available: $______________________________________________________
16. Bank reference:__________________________________________________________
17. Will you, upon request, fill out a detailed financial statement and
furnish any other information that may be required by the OWNER?
_________________________________________________________________________
18. Are you licensed as a General CONTRACTOR?________________________________
If yes, in what city, county and state? __________________________What
class, license and numbers?______________________________________________
19. Do you anticipate subcontracting Work under this
Contract?_________________
If yes, what percent of total contract?__________________________________
and to whom?_____________________________________________________________
20. Are any lawsuits pending against you or your firm at this time?__________
IF yes, DETAIL___________________________________________________________
_________________________________________________________________________
7/96 Section 00420 Page 3
21. What are the limits of your public liability? DETAIL
_________________________________________________________________________
What company?____________________________________________________________
22. What are your company's bonding limitations?_____________________________
_________________________________________________________________________
23. The undersigned hereby authorizes and requests any person, firm or
corporation to furnish any information requested by the OWNER in
verification of the recital comprising this Statement of Bidder's
Qualifications.
Dated at ________________ this ______ day of __________________, 20__.
_____________________________________________
Name of Bidder
By:__________________________________________
Title:_______________________________________
State of________________________
)
County of_______________________
___________________________________being duly sworn deposes and says that he
is ______________________of_____________________________ and that
(name of organization)
the answers to the foregoing questions and all statements therein contained
are true and correct.
Subscribed and sworn to before me this _______ day of
____________, 20__.
___________________________________
Notary Public
___________________________________
___________________________________
My commission expires _____________________________.
7/96 Section 00430 Page 1
SECTION 00430
SCHEDULE OF SUBCONTRACTORS
List all subcontractors for the work items listed below and all subcontractors
performing over 15% of the contract.
ITEM SUBCONTRACTOR
______________________________ _______________________________
______________________________ _______________________________
______________________________ _______________________________
______________________________ _______________________________
______________________________ _______________________________
______________________________ _______________________________
______________________________ _______________________________
______________________________ _______________________________
______________________________ _______________________________
______________________________ _______________________________
______________________________ _______________________________
______________________________ _______________________________
______________________________ _______________________________
______________________________ _______________________________
______________________________ _______________________________
______________________________ _______________________________
______________________________ _______________________________
______________________________ _______________________________
SECTION 00500
AGREEMENT FORMS
00510 Notice of Award
00520 Agreement
00530 Notice to Proceed
9/12/01 Section 00510 Page 1
SECTION 00510
NOTICE OF AWARD
Date:
TO:
PROJECT: 5998 LPATH Berm Erosion Protection Measures
OWNER: CITY OF FORT COLLINS
(hereinafter referred to as "the OWNER")
You are hereby notified that your Bid dated ___________, 20__ for the above
project has been considered. You are the apparent successful Bidder and have
been awarded an Agreement for Bid 5998 LPATH Berm Erosion Protection Measures;
The project includes the removal of existing fence, the removal of existing
trees and concrete rubble, and the installation of erosion control measures.
The project also includes the excavation and transportation of fill material
and the placement of fill material. The installation of concrete block
revetment mats, the installation of concrete sills, buried riprap, and the
preparation of all disturbed areas for revegetation.
The Price of your Agreement is ________________________________________________
_______________________________________________________________________________
Three (3) copies of each of the proposed Contract Documents (except Drawings)
accompany this Notice of Award. Three (3) sets of the Drawings will be
delivered separately or otherwise made available to you immediately.
You must comply with the following conditions precedent within fifteen (15)
days of the date of this Notice of Award, that is by _________, 20__.
1. You must deliver to the OWNER three (3) fully executed counterparts of
the Agreement including all the Contract Documents. Each of the Contract
Documents must bear your signature on the cover of the page.
2. You must deliver with the executed Agreement the Contract Security
(Bonds) as specified in the Instructions to Bidders, General Conditions
(Article 5.1) and Supplementary Conditions.
Failure to comply with these conditions within the time specified will entitle
OWNER to consider your Bid abandoned, to annul this Notice of Award and to
declare your Bid Security forfeited.
Within ten (10) days after you comply with those conditions, OWNER will return
to you one (1) fully-signed counterpart of the Agreement with the Contract
Documents attached.
City of Fort Collins
OWNER
By:________________________________________
James B. O’Neill, II, CPPO, FNIGP
Director of Purchasing & Risk Management
9/12/01 Section 00520 Page 1
SECTION 00520
AGREEMENT
THIS AGREEMENT is dated as of the day of in the
year of 20__ and shall be effective on the date this AGREEMENT is signed by
the City.
The City of Fort Collins (hereinafter called OWNER) and
(hereinafter called CONTRACTOR)
OWNER and CONTRACTOR, in consideration of the mutual covenants hereinafter set
forth, agree as follows:
ARTICLE 1. WORK
CONTRACTOR shall complete all Work as specified or indicated in the Contract
Documents. The Project for which the Work under the Contract Documents may be
the whole or only a part is defined as the construction of the LPATH Berm
Erosion Protection Measures, Bid 5998, The project includes the removal of
existing fence, the removal of existing trees and concrete rubble, and the
installation of erosion control measures. The project also includes the
excavation and transportation of fill material and the placement of fill
material. The installation of concrete block revetment mats, the installation
of concrete sills, buried riprap, and the preparation of all disturbed areas
for revegetation and is generally described in Section 01010.
ARTICLE 2. ENGINEER
The Project has been designed by Anderson Consulting Engineers Inc., who is
hereinafter called ENGINEER and who will assume all duties and
responsibilities and will have the rights and authority assigned to ENGINEER
in the Contract Documents in connection with completion of the Work in
accordance with the Contract Documents.
ARTICLE 3. CONTRACT TIMES
3.1 The Work shall be Substantially Complete March 23, 2007 as provided
in the General Conditions and completed and ready for Final Payment and
Acceptance in accordance with the General Conditions March 30, 2007.
3.2. Liquidated Damages. OWNER and CONTRACTOR recognize that time is of
the essence of this Agreement and that OWNER will suffer financial loss if the
Work is not completed within the times specified in paragraph 3.1. above, plus
any extensions thereof allowed in accordance with Article 12 of the General
Conditions.
They also recognize the delays, expenses and difficulties involved in proving
in a legal proceeding the actual loss suffered by OWNER if the Work is not
completed on time. Accordingly, instead of requiring any such proof, OWNER
and CONTRACTOR agree that as liquidated damages for delay (but not as penalty)
CONTRACTOR shall pay OWNER the amounts set forth hereafter.
9/12/01 Section 00520 Page 2
1) Substantial Completion:
Seven Hundred Fifty Dollars ($750) for each calendar day or
fraction thereof that expires after March 23, 2007 the day for
Substantial Completion of the Work until the Work is Substantially
Complete.
2) Final Acceptance:
After Substantial Completion, Five Hundred Dollars ($500) for each
calendar day or fraction thereof that expires after March 30, 2007
the day for Final Payment and Acceptance until the Work is ready
for Final Payment and Acceptance.
ARTICLE 4. CONTRACT PRICE
4.1. OWNER shall pay CONTRACTOR for performance of the Work in
accordance with the Contract Documents in current funds as follows: ($ ),
$ Dollars, in accordance with Section 00300, attached and incorporated
herein by this reference.
ARTICLE 5. PAYMENT PROCEDURES
CONTRACTOR shall submit Applications for Payment in accordance with
Article 14 of the General Conditions. Applications for Payment will be
processed by ENGINEER as provided in the General Conditions.
5.1. PROGRESS PAYMENTS. OWNER shall make progress payments on account
of the Contract Price on the basis of CONTRACTOR's Application for Payment as
recommended by ENGINEER, once each month during construction as provided
below. All progress payments will be on the basis of the progress of the Work
measured by the schedule of values established in paragraph 2.6 of the General
Conditions and in the case of Unit Price Work based on the number of units
completed, and in accordance with the General Requirements concerning Unit
Price Work.
5.1.1. Prior to Substantial Completion, progress payments will be in the
amount equal to the percentage indicated below, but, in each case, less the
aggregate of payments previously made and less such amounts as ENGINEER shall
determine, or OWNER may withhold, in accordance with paragraph 14.7 of the
General Conditions. 90% of the value of Work completed until the Work has
been 50% completed as determined by ENGINEER, when the retainage equals 5% of
the Contract Price, and if the character and progress of the Work have been
satisfactory to OWNER and ENGINEER, OWNER on recommendation of ENGINEER, may
determine that as long as the character and progress of the Work remain
satisfactory to them, there will be no additional retainage on account of Work
completed in which case the remaining progress payments prior to Substantial
Completion will be in an amount equal to 100% of the Work completed. 90% of
materials and equipment not incorporated in the Work (but delivered, suitably
stored and accompanied by documentation satisfactory to OWNER as provided in
paragraph 14.2 of the General Conditions) may be included in the application
for payment.
9/12/01 Section 00520 Page 3
5.1.2. Upon Substantial Completion payment will be made in an amount
sufficient to increase total payments to CONTRACTOR to 95% of the Contract
Price, less such amounts as ENGINEER shall determine or OWNER may withhold in
accordance with paragraph 14.7 of the General Conditions or as provided by
law.
5.2. FINAL PAYMENT. Upon Final Completion and Acceptance of the Work in
accordance with paragraph 14.13 of the General Conditions, OWNER shall pay the
remainder of the Contract Price as recommended by ENGINEER as provided in said
paragraph 14.13.
ARTICLE 6. CONTRACTOR'S REPRESENTATION
In order to induce OWNER to enter into this Agreement, CONTRACTOR makes
the following representations:
6.1. CONTRACTOR has familiarized himself with the nature and extent of
the Contract Documents, Work, site, locality, and with all local conditions
and Laws and Regulations that in any manner may affect cost, progress,
performance or furnishing of the Work.
6.2. CONTRACTOR has studied carefully all reports of explorations and
tests of subsurface conditions and drawings of physical conditions which are
identified in the Supplementary Conditions as provided in paragraph 4.2 of the
General Conditions.
6.3. CONTRACTOR has obtained and carefully studied (or assumes
responsibility for obtaining and carefully studying) all such examinations,
investigations, explorations, tests, reports, and studies (in addition to or
to supplement those referred to in paragraph 6.2 above) which pertain to the
subsurface or physical condition at or contiguous to the site or otherwise may
affect the cost, progress, performance or furnishing of the Work as CONTRACTOR
considers necessary for the performance or furnishing of the Work at the
Contract Price, within the Contract Times and in accordance with the other
terms and conditions of the Contract Documents, including specifically the
provisions of paragraph 4.2 of the General Conditions; and no additional
examinations, investigations, explorations, tests, reports, studies or similar
information or data are or will be required by CONTRACTOR for such purposes.
6.4. CONTRACTOR has reviewed and checked all information and data shown
or indicated on the Contract Documents with respect to existing Underground
Facilities at or contiguous to the site and assumes responsibility for the
accurate location of said Underground Facilities. No additional examinations,
investigations, explorations, tests, reports, studies or similar information
or data in respect of said Underground Facilities are or will be required by
CONTRACTOR in order to perform and furnish the Work at the Contract Price,
within the Contract Times and in accordance with the other terms and
conditions of the Contract Documents, including specifically the provision of
paragraph 4.3. of the General Conditions.
9/12/01 Section 00520 Page 4
6.5. CONTRACTOR has correlated the results of all such observations,
examinations, investigations, tests, reports and data with the terms and
conditions of the Contract Documents.
6.6. CONTRACTOR has given ENGINEER written notice of all conflicts,
errors or discrepancies that he has discovered in the Contract Documents and
the written resolution thereof by ENGINEER is acceptable to CONTRACTOR.
ARTICLE 7. CONTRACT DOCUMENTS
7.1 The Contract Documents which comprise the entire Agreement between
OWNER and CONTRACTOR concerning the Work consist of the General Conditions,
Supplementary Conditions, those items included in the definition of “Contract
Documents” in Article 1.10 of the General Conditions, and such other items as
are referenced in this Article 7, all of which are incorporated herein by this
reference.
7.2 Forms for use by CONTRACTOR in performing the Work and related
actions in carrying out the terms of this Agreement are deemed Contract
Documents and incorporated herein by this reference, and include, but are not
limited to, the following:
7.2.1 Certificate of Substantial Completion
7.2.2 Certificate of Final Acceptance
7.2.3 Lien Waiver Releases
7.2.4 Consent of Surety
7.2.5 Application for Exemption Certificate
7.2.6 Application for Payment
7.3 Drawings, consisting of a cover sheet and sheets numbered as
follows:
Index of Sheet
Sheet
No.
Index
No.
Description
1 1 COVER SHEET
2 C1 PROJECT INFORMATION
3 C2 NORTH SPILL-DEMOLITION, UTILITIES, AND SURVEY CONTROL
4 C3 SOUTH SPILL-DEMOLITION, UTILITIES, AND SURVEY CONTROL
5 C4 NORTH SPILL AND BORROW SITE-INGRESS/EGRESS, STAGING, AND
TRAFFIC CONTROL PLAN
6 C5 SOUTH SPILL-INGRESS/EGRESS, STAGING, AND TRAFFIC CONTROL PLAN
7 C6 NORTH SPILL-PLAN AND PROFILE
8 C7 NORTH SPILL-GRADING AND CROSS SECTION LOCATIONS
9 C8 NORTH SPILL-BERM CROSS SECTIONS
10 C9 NORTH SPILL-BERM CROSS SECTIONS
11 C10 NORTH SPILL-RIPRAP CROSS SECTIONS
12 C11 SOUTH SPILL-PLAN AND PROFILE
13 C12 SOUTH SPILL-PLAN AND PROFILE
14 C13 SOUTH SPILL-BERM CROSS SECTIONS
15 C14 SOUTH SPILL-BERM CROSS SECTIONS
16 C15 SOUTH SPILL-BERM CROSS SECTIONS
17 C16 NORTH SPILL-CONCRETE BLOCK REVETMENT MAT LAYOUT PLAN
18 C17 SOUTH SPILL-CONCRETE BLOCK REVETMENT MAT LAYOUT PLAN
19 C18 NORTH SPILL-EROSION CONTROL PLAN
9/12/01 Section 00520 Page 5
20 C19 SOUTH SPILL-EROSION CONTROL PLAN
21 C20 BORROW SITE-GRADING AND EROSION CONTROL PLAN
22 C21 CONCRETE REVETMENT MAT DETAIL
23 C22 MISCELLANEOUS DETAIL
24 L1 NORTH SPILL-LANDSCAPE AND REVEGETATION PLAN
25 L2 SOUTH SPILL-LANDSCAPE AND REVEGETATION PLAN
26 L3 SOUTH SPILL-LANDSCAPE AND REVEGETATION PLAN
27 L4 BORROW AREA-LANDSCAPE AND REVEGETATION PLAN
28 L5 NORTH SPILL CONSTRUCTION AREA-LANDSCAPE AND REVEGETATION PLAN
29 L6 SOUTH SPILL CONSTRUCTION AREA-LANDSCAPE AND REVEGETATION PLAN
30 D1 POSSIBLE DEWATERING SCENARIOS
The Contract Drawings shall be stamped "Final for Construction" and dated.
Any revisions made shall be clearly identified and dated.
7.4. Addenda Numbers to , inclusive.
7.5. The Contract Documents also include all written amendments and
other documents amending, modifying, or supplementing the Contract Documents
pursuant to paragraphs 3.5 and 3.6 of the General Conditions.
7.6. There are no Contract Documents other than those listed or
incorporated by reference in this Article 7. The Contract Documents may only
be amended, modified or supplemented as provided in paragraphs 3.5 and 3.6 of
the General Conditions.
ARTICLE 8. MISCELLANEOUS
8.1. Terms used in this Agreement which are defined in Article I of the
General Conditions shall have the meanings indicated in the General
Conditions.
8.2. No assignment by a party hereto of any rights under or interests in
the Contract Documents will be binding on another party hereto without the
written consent of the party sought to be bound; and specifically but not
without limitations, moneys that may become due and moneys that are due may
not be assigned without such consent (except to the extent that the effect of
this restriction may be limited by law), and unless specifically stated to the
contrary in any written consent to an assignment no assignment will release or
discharge that assignor from any duty or responsibility under the Contract
Document.
8.3. OWNER and CONTRACTOR each binds itself, its partners, successors,
assigns and legal representatives to the other party hereto, its partners,
successors, assigns and legal representatives in respect to all covenants,
Agreement and obligations contained in the Contract Document.
OWNER: CITY OF FORT COLLINS CONTRACTOR:
By: ____________________________ By:_______________________________
JAMES B. O’NEILL II, CPPO, FNIGP
9/12/01 Section 00520 Page 6
DIRECTOR OF PURCHASING __________________________________
AND RISK MANAGEMENT
Title:____________________________
Date:___________________________ Date:_____________________________
(CORPORATE SEAL)
Attest: ________________________ Attest:___________________________
City Clerk
Address for giving notices: Address for giving notices:
P. O. Box 580 __________________________________
Fort Collins, CO 80522 __________________________________
LICENSE NO.:______________________
Approved as to Form
_______________________________
Assistant City Attorney
7/96 Section 00530 Page 1
SECTION 00530
NOTICE TO PROCEED
Description of Work: 5998 LPATH Berm Erosion Protection Measures
To:
This notice is to advise you:
That the contract covering the above described Work has been fully executed by
the CONTRACTOR and the OWNER.
That the required CONTRACTOR's Performance Bond and Payment Bond have been
received by the OWNER.
That the OWNER has approved the said Contract Documents.
Therefore, as the CONTRACTOR for the above described Work, you are hereby
authorized and directed to proceed within ( ) calendar days from
receipt of this notice as required by the Agreement.
Dated this day of , 20__.
The dates for Substantial Completion and Final Acceptance shall be ,
and , 20__, respectively.
City of Fort Collins
OWNER
By:
Title:
ACKNOWLEDGMENT OF NOTICE
Receipt of the above Notice to Proceed is hereby acknowledged this
day of , 20__.
CONTRACTOR:
By:
Title:
SECTION 00600
BONDS AND CERTIFICATES
00610 Performance Bond
00615 Payment Bond
00630 Certificate of Insurance
00635 Certificate of Substantial Completion
00640 Certificate of Final Acceptance
00650 Lien Waiver Release (CONTRACTOR)
00660 Consent of Surety
00670 Application for Exemption Certificate
7/96 Section 00610 Page 1
SECTION 00610
PERFORMANCE BOND
Bond No.
KNOW ALL MEN BY THESE PRESENTS: that
(Firm)
(Address)
(an Individual), (a Partnership), (a Corporation), hereinafter referred to as
the "Principal" and
(Firm)
(Address)
hereinafter referred to as "the Surety", are held and firmly bound unto City
of Fort Collins, 300 Laporte Ave, Fort Collins, Colorado 80522 a (Municipal
Corporation) hereinafter referred to as the "OWNER", in the penal sum of
in lawful money of the United States,
for the payment of which sum well and truly to be made, we bind ourselves,
successors and assigns, jointly and severally, firmly by these presents.
THE CONDITIONS OF THIS OBLIGATION are such that whereas the Principal entered
into a certain Agreement with the OWNER, dated the day of ,
20__, a copy of which is hereto attached and made a part hereof for the
performance of The City of Fort Collins project, 5998 LPATH Berm Erosion
Protection Measures.
NOW, THEREFORE, if the Principal shall well, truly and faithfully perform its
duties, all the undertakings, covenants, terms, conditions and agreements of
said Agreement during the original term thereof, and any extensions thereof
which may be granted by the OWNER, with or without Notice to the Surety and
during the life of the guaranty period, and if the Principal shall satisfy all
claims and demands incurred under such Agreement, and shall fully indemnify
and save harmless the OWNER from all cost and damages which it may suffer by
reason of failure to do so, and shall reimburse and repay the OWNER all outlay
and expense which the OWNER may incur in making good any default then this
obligation shall be void; otherwise to remain in full force and effect.
7/96 Section 00610 Page 2
PROVIDED, FURTHER, that the said Surety, for value received, hereby stipulates
and agrees that no change, extension of time, alteration or addition to the
terms of the Agreement or to the Work to be performed thereunder or the
Specifications accompanying the same shall in any way affect its obligation on
this bond; and it does hereby waive notice of any such change, extension of
time, alteration or addition to the terms of the Agreement or to the Work or
to the Specifications.
PROVIDED, FURTHER, that no final settlement between the OWNER and the
CONTRACTOR shall abridge the right of any beneficiary hereunder, whose claim
may be unsatisfied.
PROVIDED, FURTHER, that the Surety Company must be authorized to transact
business in the State of Colorado and be acceptable to the OWNER.
IN WITNESS WHEREOF, this instrument is executed in three (3) counterparts,
each one of which shall be deemed an original, this day of ,
20__.
IN PRESENCE OF: Principal
______________________________ ________________________________________
______________________________ ________________________________________
(Title)
________________________________________
(Address)
(Corporate Seal)
IN PRESENCE OF: Other Partners
_____________________________ By:_____________________________________
_____________________________ By:_____________________________________
IN PRESENCE OF: Surety
_____________________________ By:_____________________________________
_____________________________ By:_____________________________________
(Address)
(Surety Seal)
NOTE: Date of Bond must not be prior to date of Agreement.
If CONTRACTOR is Partnership, all partners should execute Bond.
7/96 Section 00615 Page 1
SECTION 00615
PAYMENT BOND
Bond No.
KNOW ALL MEN BY THESE PRESENTS: that
(Firm)
(Address)
(an Individual), (a Partnership), (a Corporation), hereinafter referred to as
the "Principal" and
(Firm)
(Address)
hereinafter referred to as "the Surety", are held and firmly bound unto the
City of Fort Collins, 300 Laporte Ave., Fort Collins, Colorado 80522 a
(Municipal Corporation) hereinafter referred to as "the OWNER", in the penal
sum of in lawful money of the
United States, for the payment of which sum well and truly to be made, we bind
ourselves, successors and assigns, jointly and severally, firmly by these
presents.
THE CONDITIONS OF THIS OBLIGATION are such that whereas the Principal entered
into a certain Agreement with the OWNER, dated the day of ,
20__, a copy of which is hereto attached and made a part hereof for the
performance of The City of Fort Collins project, 5998 LPATH Berm Erosion
Protection Measures.
NOW, THEREFORE, if the Principal shall make payment to all persons, firms,
subcontractors, and corporations furnishing materials for or performing labor
in the prosecution of the Work provided for in such Agreement and any
authorized extension or modification thereof, including all amounts due for
materials, lubricants, repairs on machinery, equipment and tools, consumed,
rented or used in connection with the construction of such Work, and all
insurance premiums on said Work, and for all labor, performed in such Work
whether by subcontractor or otherwise, then this obligation shall be void;
otherwise to remain in full force and effect.
7/96 Section 00615 Page 2
PROVIDED, FURTHER, that the said Surety, for value received, hereby stipulates
and agrees that no change, extension of time, alteration or addition to the
terms of the Agreement or to the Work to be performed thereunder or the
Specifications accompanying the same shall in any way affect its obligation on
this bond; and it does hereby waive notice of any such change, extension of
time, alteration or addition to the terms of the Agreement or to the Work or
to the Specifications.
PROVIDED, FURTHER, that no final settlement between the OWNER and the
CONTRACTOR shall abridge the right of any beneficiary hereunder, whose claim
may be unsatisfied.
PROVIDED, FURTHER, that the Surety Company must be authorized to transact
business in the State of Colorado and be acceptable to the OWNER.
IN WITNESS WHEREOF, this instrument is executed in three (3) counterparts,
each one of which shall be deemed an original, this day of ,
20__.
IN PRESENCE OF: Principal
______________________________ By:___________________________________
______________________________ ______________________________________
(Title)
______________________________________
(Address)
(Corporate Seal)
IN PRESENCE OF: Other Partners
______________________________ ______________________________________
______________________________ ______________________________________
IN PRESENCE OF: Surety
______________________________ By:___________________________________
______________________________ By:___________________________________
(Address)
(Surety Seal)
NOTE: Date of Bond must not be prior to date of Agreement.
If CONTRACTOR is Partnership, all partners should execute Bond.
7/96 Section 00630 Page 1
SECTION 00630
CERTIFICATE OF INSURANCE
CONTRACTOR shall insert his own standard form for Certificate of Insurance.
7/96 Section 00635 Page 1
SECTION 00635
CERTIFICATE OF SUBSTANTIAL COMPLETION
TO: CITY OF FORT COLLINS
(OWNER)
DATE OF SUBSTANTIAL COMPLETION: PROJECT TITLE: 5998 LPATH Berm Erosion
Protection Measures
_____________________________
PROJECT OR SPECIFIED PART SHALL LOCATION: Fort Collins, Colorado
INCLUDE:
OWNER: City of Fort Collins
____________________________
____________________________ CONTRACTOR: ______________________________
____________________________
CONTRACT DATE:____________________________
The Work performed under this contract has been inspected by authorized
representatives of the OWNER, CONTRACTOR, and the ENGINEER and the project (or
specified part of the project, as indicated above) is hereby declared to be
substantially completed on the above date.
A tentative list of items to be completed or corrected is appended hereto.
This list may not be exhaustive, and the failure to include an item on it does
not alter the responsibility of the CONTRACTOR to complete all the Work in
accordance with the Contract Documents.
_________________________________ ________________________________________
ENGINEER AUTHORIZED REPRESENTATIVE DATE
The CONTRACTOR accepts the above Certificate of Substantial Completion and
agrees to complete and correct the items on the tentative list within the time
indicated.
________________________________ By: ________________________________________
CONTRACTOR AUTHORIZED REPRESENTATIVE DATE
The OWNER accepts the project or specified area of the project as
substantially complete and will assume full possession of the project or
specified area of the project at 12:01 a.m., on . The
responsibility for heat, utilities, security, and insurance under the Contract
Documents shall be as set forth under "Remarks" below.
CITY OF FORT COLLINS, COLORADO By: ________________________________________
OWNER AUTHORIZED REPRESENTATIVE DATE
REMARKS:
7/96 Section 00640 Page 1
SECTION 00640
CERTIFICATE OF FINAL ACCEPTANCE
, 20__
TO:
Gentlemen:
You are hereby notified that on the day of , 20__, the City of
Fort Collins, Colorado, has accepted the Work completed by
for the City of Fort Collins project, 5998 LPATH Berm Erosion Protection
Measures.
A check is attached hereto in the amount of $________________________ as Final
Payment for all Work done, subject to the terms of the Contract Documents
which are dated ________________.
In conformance with the Contract Documents for this project, your obligations
and guarantees will continue for the specified time from the following
date:___________________________.
Sincerely,
OWNER: City of Fort Collins
By:
Title:
ATTEST:
Title:
7/96 Section 00650 Page 1
SECTION 00650
LIEN WAIVER RELEASE
(CONTRACTOR)
TO: City of Fort Collins, Colorado (OWNER)
FROM: (CONTRACTOR)
PROJECT: 5998 LPATH Berm Erosion Protection Measures
1. The CONTRACTOR acknowledges having received payment, except retainage
from the OWNER for all work, labor, skill and material furnished,
delivered and performed by the CONTRACTOR for the OWNER or for anyone in
the construction, design, improvement, alteration, addition or repair of
the above described project.
2. In consideration of such payment and other good and valuable
consideration, the receipt and adequacy of which are hereby acknowledged,
the CONTRACTOR voluntarily waives all rights, claims and liens, including
but not limited to, mechanic's liens, Miller Act claims (40 U.S.C.A. 270
a and b), stop notices, equitable liens and labor and material bond
rights which the CONTRACTOR may now or may afterward have, claim or
assert for all and any work, labor, skill or materials furnished,
delivered or performed for the construction, design, improvement,
alteration, addition or repair of the above described project, against
the OWNER or its officers, agents, employees or assigns, against any fund
of or in the possession or control of the OWNER, against the project or
against all land and the buildings on and appurtenances to the land
improved by the project.
3. The CONTRACTOR affirms that all work, labor and materials, furnished,
delivered or performed to or for the construction, design, improvement,
alteration, addition or repair of the project were furnished, delivered
or performed by the CONTRACTOR or its agents, employees, and servants, or
by and through the CONTRACTOR by various Subcontractors or materialmen or
their agents, employees and servants and further affirms the same have
been paid in full and have released in full any and all existing or
possible future mechanic's liens or rights or claims against the project
or any funds in the OWNER'S possession or control concerning the project
or against the OWNER or its officers, agents, employees or assigns
arising out of the project.
4. The CONTRACTOR agrees to defend and hold harmless the OWNER, the lender,
if any, and the Surety on the project against and from any claim
hereinafter made by the CONTRACTOR'S Subcontractors, materialmen,
employees, servants, agents or assigns against the project or against the
OWNER or its officers, employees, agents or assigns arising out of the
7/96 Section 00650 Page 2
project for all loss, damage and costs, including reasonable attorneys
fees, incurred as a result of such claims.
5. The parties acknowledge that the description of the project set forth
above constitutes and adequate description of the property and
improvements to which this Lien Waiver Release pertains. It is further
acknowledged that this Lien Waiver Release is for the benefit of and may
be relied upon by the OWNER, the lender, if any, and Surety on any labor
and material bonds for the project.
Signed this day of , 20__.
CONTRACTOR
By:
Title:
ATTEST:
Secretary
STATE OF COLORADO )
)ss.
COUNTY OF LARIMER )
Subscribed and sworn to before me this day of
20__, by
Witness my hand and official seal.
My Commission Expires: .
Notary Public
7/96 Section 00660 Page 1
SECTION 00660
CONSENT OF SURETY
TO: City of Fort Collins, Colorado
(hereinafter referred to as the "OWNER")
CONTRACTOR:
PROJECT: 5998 LPATH Berm Erosion Protection Measures
CONTRACT DATE:
In accordance with the provisions of the Contract between the OWNER and the
CONTRACTOR as indicated above, for
(Surety)
on bond of
hereby approves of the Final Payment to the CONTRACTOR, and agrees that Final
Payment to the CONTRACTOR shall not relieve the Surety Company of any of its
obligations to the OWNER, as set forth in the said Surety Company's Bond.
IN WITNESS WHEREOF, the Surety Company has hereunto set its hand this
day of , ____ .
(Surety Company)
By
ATTACH: Power of Attorney and Certificate of Authority of Attorney(s)-in-
Fact.
Section 00670 Page 1
SECTION 00670
APPLICATION FOR EXEMPTION CERTIFICATE
Section 00670 Page 2
SECTION 00700
GENERAL CONDITIONS
SE
SECTION 00800
SUPPLEMENTARY CONDITIONS
7/96 Section 00800 Page 1
SECTION 00800
SUPPLEMENTARY CONDITIONS
Conditions of the Contract
These Supplementary Conditions amend or supplement the General Conditions of
the Construction Contract (EJCDC General Conditions 1910-8, 1990 edition with
City of Fort Collins modifications) and other provisions of the Contract
Documents as indicated below.
SC-4.2 Subsurface and Physical Conditions:
A. Add the following language to paragraph 4.2.1 of the General
Conditions.
4.2.1.1.1 The following report(s) of exploration and tests of
subsurface conditions at the site of the Work:
Geotechnical Investigation
Cache La Poudre River
Controlled Spill Structures
Fort Collins, Colorado
Contractor may rely upon the accuracy of the technical data
contained in the geotechnical documents, but not upon nontechnical
data, interpretations or opinions contained therein or upon the
completeness of any information in the report.
B. 4.2.1.2.1 No drawing of physical conditions in or relating to
existing surface or subsurface structures (except Underground
Facilities referred to in Paragraph 4.3) which are at or contiguous
to the site have been utilized by the Engineer in preparation of
the Contract Documents, except the following:
SC-5.4.8 Limits of Liability
A. Add the following language at the end of paragraph 5.4.8.
The limits of liability for the insurance required by the paragraph
numbers of the General Conditions listed below are as follows:
7/96 Section 00800 Page 2
5.4.1 and 5.4.2
Coverage A - Statutory Limits
Coverage B - $100,000/$100,000/$500,000
5.4.3 and 5.4.5 Commercial General Liability policy will have limits of
$1,000,000 combined single limits (CSL). This policy will include
coverage for Explosion, Collapse, and Underground coverage unless waived
by the Owner.
5.4.6 The Comprehensive Automobile Liability Insurance policy will have
limits of $1,000,000 combined single limits (CSL).
5.4.9 This policy will include completed operations coverage/product
liability coverage with limits of $1,000,000 combined single limits
(CSL).
9/99
SECTION 00900
ADDENDA, MODIFICATIONS AND PAYMENT
00950 Contract Change Order
00960 Application for Payment
9/99 Section 00950 Page 1
SECTION 00950
CHANGE ORDER NO.
PROJECT TITLE: 5998 LPATH Berm Erosion Protection Measures
CONTRACTOR:
PROJECT NUMBER:
DESCRIPTION:
1. Reason for change:
2. Description of Change:
3. Change in Contract Cost
4. Change in Contract Time:
__
ORIGINAL CONTRACT COST $ .00
TOTAL APPROVED CHANGE ORDER 0.00
TOTAL PENDING CHANGE ORDER 0.00
TOTAL THIS CHANGE ORDER 0.00
TOTAL % OF THIS CHANGE ORDER
TOTAL C.O.% OF ORIGNINAL CONTRACT
ADJUSTED CONTRACT COST $ 0.00
(Assuming all change orders approved) _
ACCEPTED BY: DATE:
Contractor's Representative
ACCEPTED BY: DATE: __
Project Manager
REVIEWED BY: DATE:
Title:
APPROVED BY: DATE:
Title:
APPROVED BY: DATE:
Purchasing Agent over $30,000
cc: City Clerk Contractor
Project File Architect
Engineer Purchasing
9/997/96 Section 00960 Page 1
Section 00960
APPLICATION FOR PAYMENT PAGE 1 OF 4
OWNER: City of Fort Collins
PROJECT: 5998 LPATH Berm
Erosion Protection Measures APPLICATION NUMBER:
APPLICATION DATE:
PERIOD BEGINNING:
ENGINEER: CONTRACTOR: PERIOD ENDING:
PROJECT NUMBER:
CHANGE ORDERS Application is made for Payment as shown below in connection with Contract
NUMBER DATE AMOUNT
The present status of the account for this Contract is as
follows:
1
2 Original Contract Amount:
3 Net Change by Change Order:
Current contract Amount: $0.00
Total Completed and Stored to Date:
Less Previous Applications:
Amount Due this Application - Before Retainage: $0.00
Less Retainage:
Net Change by Change Order $0.00 AMOUNT DUE THIS APPLICATION: $0.00
CERTIFICATION:
The undersigned CONTRACTOR certifies that all obligations of CONTRACTOR incurred in connection with
the Work have been satisfied as required in Paragraph 14.3. of the General Conditions of the Contract.
The above Amount Due This Application is requested by the
CONTRACTOR.
Date: By:
Payment of the above Amount Due This Application is recommended by the ENGINEER.
Date: By:
Payment of the above Amount Due This Application has been reviewed by the OWNER'S Project Manager.
Date: By:
Payment of the above Amount Due This Application is approved by the OWNER.
7/96 Section 00960 Page 2
Date: By:
CONTRACT AMOUNTS
APPLICATION FOR
PAYMENT PAGE 2 OF 4
Work
Completed
Work
Completed
Work
Completed Stored
Bid
This
Month
Previous
Periods
To
Date Materials Total
Item This Earned Percent
Number Description Quantity Units
Unit
Price Amount Qty. Amount Qty. Amount Qty. Amount Period To Date Billed
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
7/96 Section 00960 Page 3
TOTALS $0.00 $0.00 $0.00 $0.00 $0.00
CHANGE ORDERS APPLICATION FOR PAYMENT PAGE 3 OF 4
Work Completed
Work
Completed
Work
Completed Stored
Bid
This
Month
Previous
Periods
To
Date Materials Total
Item This Earned Percent
Number Description Quantity Units
Unit
Price Amount Qty. Amount Qty. Amount Qty. Amount Period
To
Date Billed
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
TOTALS CHANGE ORDERS $0.00 $0.00 $0.00 $0.00 $0.00
7/96 Section 00960 Page 4
PROJECT TOTALS $0.00 $0.00 $0.00 $0.00 $0.00
STORED MATERIALS
SUMMARY PAGE 4 OF 4
On Hand Received Installed On Hand
Item Invoice Previous This This This
Number Number Description Application Period Period Application
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
TOTALS $0.00 $0.00 $0.00 $0.00
LPATH Berm Erosion
Protection Measures
DIVISION 1 - GENERAL REQUIREMENTS
SECTION 01010 SUMMARY OF WORK
SECTION 01140 CONTRACTOR’S USE OF PREMISES
SECTION 01145 SPECIAL PROJECT PROCEDURES
SECTION 01180 UTILITY SOURCES
SECTION 01270 MEASUREMENT AND PAYMENT
SECTION 01310 PROJECT MEETINGS
SECTION 01320 CONSTRUCTION SCHEDULES
SECTION 01330 SUBMITTALS
SECTION 01425 STANDARD REFERENCES
SECTION 01450 MATERIALS TESTING
SECTION 01555 TRAFFIC REGULATION
SECTION 01635 SUBSTITUTIONS AND PRODUCT
OPTIONS
SECTION 01650 MATERIAL DELIVERY, STORAGE,
AND HANDLING
SECTION 01710 SITE CONDITIONS
SECTION 01715 TREE, LANDSCAPE, VEGETATION,
AND WETLAND PROTECTION
SECTION 01720 FIELD ENGINEERING AND SURVEYING
SECTION 01745 ENVIRONMENTAL CONTROLS
SECTION 01780 CONTRACT CLOSEOUT
LPATH Berm Erosion 01010-1 Summary of Work
Protection Measures
SECTION 01010
SUMMARY OF WORK
PART 1 GENERAL
1.01 SECTION INCLUDES
Furnish all labor and install all materials for the LPATH Berm Erosion Protection Measures,
including but not limited to the following items:
The project includes the removal of existing fence, the removal of existing trees and concrete
rubble, and the installation of erosion control measures. The project also includes the
excavation and transportation of fill material and the placement of fill material. The
installation of concrete block revetment mats, the installation of concrete sills, buried riprap,
and the preparation of all disturbed areas for revegetation.
1.02 QUALIFICATIONS
The CONTRACTOR must show proof to have completed at least 3 projects involving
dewatering or concrete block revetment mat.
1.03 WORK SEQUENCE
A. The Work Sequence is to be submitted as part of the construction schedule required
in Section 01320. Construction of the project shall begin within seven (7) calendar
days of the date of Notice to Proceed unless approved by the ENGINEER.
The date of beginning and the time for completion of the work are essential
conditions of the Contract Documents and the work embraced shall be commenced
on a date specified in the Notice to Proceed.
The CONTRACTOR will proceed with the work at such rate of progress to
ensure full completion within the contract time. It is expressly understood and
agreed, by and between the CONTRACTOR and the OWNER that the contract
time for the completion of the work described herein is a reasonable time, taking into
consideration the climatic and other factors prevailing in the locality of the work.
Every effort shall be made by the CONTRACTOR to complete the project
within the "Contract Time" shown in the proposal. The "Contract Time"
anticipates "Normal" weather and climate conditions in and around the vicinity of
the Project site during the times of year that the construction will be carried out.
Extensions of time based upon weather conditions shall be granted only if the
CONTRACTOR demonstrates clearly that such conditions were "unusually
severe," would not have been reasonably anticipated, and that such conditions
adversely affected the CONTRACTOR’s work and thus required additional time to
complete the work.
The following specifies the procedure for the determination of time extensions for
unusually severe weather. The listing below defines the anticipated number of
calendar days lost to adverse weather for each month and is based upon National
Oceanic and Atmospheric Administration (NOAA) or similar data for the geographic
location of the project.
LPATH Berm Erosion 01010-2 Summary of Work
Protection Measures
Monthly Anticipated Calendar Days Lost to Adverse Weather Conditions
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
(7) (4) (4) (4) (6) (3) (4) (2) (3) (3) (2) (5)
The above schedule of anticipated adverse weather will constitute the base line for
monthly (or portion thereof) weather time evaluations. Upon acknowledgment of the
Notice to Proceed and continuing throughout the contract on a monthly basis, actual
adverse weather days and the impact of adverse weather days that delay the work
will be recorded on a day-to-day basis. It is assumed that the work will be carried
out Mondays through Fridays (holidays excepted) unless an approved construction
schedule or written authorization from the OWNER indicates otherwise. The number
of days of delayed work due to adverse weather or the impact thereof will then be
compared to the monthly adverse weather schedule above.
An actual adverse weather day must prevent work for 50 percent or more of the
CONTRACTOR’s workday, delay work critical to the timely completion of the
project, and be documented by the CONTRACTOR. The City Representative
observing the construction shall determine on a daily basis whether or not work can
proceed or if work is delayed due to adverse weather or the effects thereof. The
CONTRACTOR shall notify the ENGINEER in writing of any disagreement as to
whether or not work can proceed on a given date, within 2 calendar days of that date.
The OWNER will use the above written notification in determining the number of
working days for which work was delayed during each month.
At the end of each month, if the number of working days for which work was
delayed due to adverse weather exceeds that shown in the above schedule, a Change
Order will be executed which increases the Contract Time. The number of work
days delayed due to adverse weather or the impact thereof will then be converted to
Calendar Days based on the contract completion day and date. This conversion
assumes a 5-day work week, Mondays through Fridays, holidays excepted; should
the CONTRACTOR have authorization to work weekends and/or holidays, then the
method of conversion of workdays to calendar days would take this into
consideration. The contract time period will then be increased by the number of
calendar days calculated above and a new contract completion day and date will be
set.
The CONTRACTOR’s schedule must reflect the above-anticipated adverse weather
delays on all weather-dependent activities.
While extensions of time shall be granted for "unusually severe" weather or climate
conditions, the OWNER shall make no monetary compensation for any costs to the
CONTRACTOR arising out of such delays. The CONTRACTOR shall comply with
the portions of the Contract Documents relating to his project schedule and
amendments thereto which result from the "unusually severe" weather condition.
Breakdowns in equipment or lack of performance by the CONTRACTOR will not be
considered justification for an extension of time. Liquidated damages will be
assessed as delineated elsewhere.
LPATH Berm Erosion 01010-3 Summary of Work
Protection Measures
The CONTRACTOR shall not be charged with liquidated damages or any excess
cost when the delay in completion of the work is due to the following, and the
CONTRACTOR has promptly given written notice of such delay to the OWNER or
ENGINEER.
1. To any preference, priority, or allocation order duly issued by the OWNER.
2. To unforeseeable causes beyond the control and without the fault or
negligence of the CONTRACTOR, including but not restricted to, acts of
God, or of the public enemy, acts of the OWNER, acts of another
CONTRACTOR in the performance of a contract with the OWNER, fires,
floods, epidemics, quarantine restrictions, strikes, freight embargoes, and
abnormal and unforeseeable weather as provided above.
3. To any delays of Subcontractors occasioned by any of the causes specified in
paragraphs 1 and 2, above.
Other than the conditions above, CONTRACTOR is permitted to start the work at
any location within the project site.
The CONTRACTOR shall adhere to the construction traffic control requirements
delineated in Section 01555 and on the Drawings.
1.04 UNDERGROUND UTILITIES
A. It shall be the responsibility of the CONTRACTOR to verify the existence and
location of all underground utilities along the route of the work and to coordinate the
construction schedules with these utility owners.
B. Known utilities and structures adjacent to or encountered in the work are shown on
the Drawings. The locations shown are taken from existing records and the best
information available from existing utility plans and from field potholing, however,
it is expected that there may be some discrepancies and omissions in the locations
and quantities of utilities and structures shown. Those shown are for the
convenience of the CONTRACTOR only, and no responsibility is assumed by either
the OWNER or the ENGINEER for their accuracy or completeness.
C. The CONTRACTOR shall field verify all utilities and coordinate construction with
utility owners prior to starting construction. The CONTRACTOR shall be
responsible for protecting utilities during construction and scheduling utility
adjustments to eliminate conflict with progress of the work.
D. The CONTRACTOR shall notify the ENGINEER immediately of any field condition
not consistent with the contract documents.
E. The CONTRACTOR will be responsible for repairing or paying for the repairs to
any damaged utilities.
PART 2 PRODUCTS (Not Applicable)
LPATH Berm Erosion 01010-4 Summary of Work
Protection Measures
PART 3 EXECUTION (Not Applicable)
END OF SECTION
LPATH Berm Erosion 01140-1 Contractor’s Use of Premises
Protection Measures
SECTION 01140
CONTRACTOR’S USE OF PREMISES
PART 1 GENERAL
1.01 SECTION INCLUDES
A. The CONTRACTOR may use the OWNER’s property designated within the
construction limits shown on the Drawings for equipment and materials as long as he
confines his operations to those permitted by local laws, ordinance and permits and
meets the following requirements:
1. Do not unreasonably encumber site with materials or equipment.
2. Assume full responsibility for protection and safekeeping of products stored
on premised.
3. Move any stored products which interfere with operations of the OWNER.
4. Obtain and pay for use of additional storage or work areas needed for
operations.
1.02 LIMITS OF CONSTRUCTION
A. The CONTRACTOR must maintain all of his construction activities within the
OWNER’s property and/or construction easements and limits of the project, or other
stated areas, unless permits and/or written permission are obtained by the
CONTRACTOR, from appropriate authorities or private property owners, outside of
these areas. Contractor to fence all easements and work areas. The temporary
permits must be secured and paid for by the CONTRACTOR at no extra cost to the
OWNER. Any temporary permits secured must be in writing and a copy of same
provided to the ENGINEER.
1.03 SECURITY
A. The CONTRACTOR shall at all times be responsible for the security of his facilities
and equipment. The OWNER will not take responsibility for missing or damaged
equipment, tools, or personal belongings of the CONTRACTOR.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
END OF SECTION
LPATH Berm Erosion 01140-2 Contractor’s Use of Premises
Protection Measures
THIS PAGE INTENTIONALLY LEFT BLANK.
LPATH Berm Erosion 01145-1 Special Project Procedures
Protection Measures
SECTION 01145
SPECIAL PROJECT PROCEDURES
PART 1 GENERAL
1.01 SECTION INCLUDES
A. General construction requirements and special considerations relating to the elements
of construction of the LPATH Berm Erosion Protection Measures. Specific
descriptions of the work are provided for the following sections of the project:
1) Construction of the North and South spills.
2) Removal of fill material from borrow sites South of the Blue Gill Pond, and
North of Prospect Road.
1.02 RELATED SECTIONS
A. Section 00520 – Agreement
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION
3.01 CONSTRUCTION TRAFFIC CONTROL
A. The CONTRACTOR, with input and cooperation from the OWNER, will prepare the
construction traffic control plans and specifications for construction of the project.
The traffic control plan shall be submitted at least 7 days prior to the start of traffic
control activities. Any changes to the approved traffic control plan will need to be
submitted to the City of Fort Collins Traffic Department at least 48 hours prior to
instituting the proposed changes.
B. The CONTRACTOR shall provide to the City of Fort Collins Traffic Department a
detailed construction schedule for the work, including production rates, estimated
closure times for streets and intersections, if any, and material delivery and haul
routes.
C. Section 01555 Traffic Regulation is provided as a guide to items of work the
CONTRACTOR will be responsible for, and that may not be specifically referenced
in the construction traffic control plan. Such items include providing access to fire
hydrants, access for emergency services, and provision of warning signs and lights
around the work zone, especially during non-work periods.
3.03 NATURAL AREAS
Due to the project being located entirely within a city designated natural area the
CONTRACTOR shall abide by the rules and regulations set forth by the City of Fort Collins
Natural Resources Department.
END OF SECTION
LPATH Berm Erosion 01145-2 Special Project Procedures
Protection Measures
THIS PAGE INTENTIONALLY LEFT BLANK.
LPATH Berm Erosion 01180-1 Utility Sources
Protection Measures
SECTION 01180
UTILITY SOURCES
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Names and telephone numbers of affected agencies and utilities in the area are listed
below for the CONTRACTOR’s convenience. The CONTRACTOR assumes all
responsibility of contacting these agencies and verification of telephone numbers.
1. Water
a. City of Fort Collins (970) 221-6700
b. Fort Collins – Loveland Water District (970) 226-3104
c. East Larimer Water District (970) 493-2044
2. Sanitary Sewer - City of Fort Collins (970) 221-6700
- Boxelder Sanitation District (970) 498-0604
3. Stormwater - City of Fort Collins (970) 221-6700
4. Natural Resources – City of Fort Collins (970) 221-6600
5. Park Planning – City of Fort Collins (970) 221-6360
6. Electrical
a. City of Fort Collins (970) 224-6157
b. Platte River Power Authority (PRPA) (970) 226-4000
c. Western Area Power Administration (WAPA) (970) 461-7298
d. Poudre Valley Rural Electric Association (PVREA) (970) 226-1234
e. Public Service Company (PSC) / Xcel Energy (800) 895-1999
7. Engineering – City of Fort Collins (970) 221-6605
8. Traffic – City of Fort Collins (970) 224-6062
9. Gas - Xcel Energy (800) 895-2999
10. Telephone - Qwest (970) 222-2414
11. Cable TV - Comcast (970) 484-7166
12. One-Call Utility Locates 1 (800) 922-1987
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
END OF SECTION
LPATH Berm Erosion 01180-2 Utility Sources
Protection Measures
THIS PAGE INTENTIONALLY LEFT BLANK.
LPATH Berm Erosion 01270-1 Measurement and Payment
Protection Measures
SECTION 01270
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.01 SECTION INCLUDES
A. The work performed under this Agreement shall be paid for on both a Unit Price
basis and Lump Sum basis for individual line items at the rates for the respective
items on the Bid Schedule. The quantities provided on the Bid Schedule are only
estimates of the actual quantities of the work to be performed, and are only included
for purposes of making the award and establishing a basis for estimating the probable
cost of the Work. The actual amounts of work performed and materials furnished for
unit price bid items may differ from the estimated quantities. The basis of payment
for work and materials bid as a unit price will be the actual amount of approved work
done and materials furnished.
Payment shall be made only for those items included in the Bid Schedule. All costs
incurred shall comply with the provisions of these Specifications and shall be
included in the unit price bid for the associated items in the Bid Schedule. Except as
may be otherwise stipulated, no material, labor or equipment will be furnished by the
OWNER. The quantity of work which will be considered for payment is the actual
number of units completed in accordance with all relative Specifications. This basis
of measurement and payment for each proposal item will be described below. The
following provides a general listing of contract bid items along with a brief summary
of the work and materials included, but not limited to, in the unit price or lump sum
price for each bid item. Refer to the Specifications and Drawings for additional
information.
1.02 PAY ITEMS
1. Mobilization
No unit measurement for payment will be made for any of the work,
materials and equipment required for mobilization and field overhead. This
work consists of the mobilization of personnel, equipment and supplies at the
project site in preparation for work on the project. This item shall include the
establishment of the CONTRACTOR’S offices, buildings and other
necessary facilities, and all other costs incurred or labor and operations
which must be performed prior to beginning the other items under the
Contract. This item shall also include temporary fencing around project
work and driving areas, and any other fencing/security items as deemed
necessary by the CONTRACTOR. This item also includes obtaining
permits and CONTRACTOR testing. This item may also include provision
of required bonds, insurance and preparation of the project schedule. The
removal of the CONTRACTOR's equipment, supplies, excess materials, and
cleanup of the site are also included in this item.
Payment will be made as the work progresses. Fifty percent (50%) of the
lump sum bid price will be paid at the time of the first monthly progress
payment. An additional thirty percent (30%) will be paid when one-half the
original contract amount is earned. The remaining twenty percent (20%) will
LPATH Berm Erosion 01270-2 Measurement and Payment
Protection Measures
be paid upon final acceptance of the project. The total amount for
mobilization shall not exceed five percent (5%) of the total bid.
Pay Item Pay Unit
Mobilization LS
2. Traffic / Access Control
No unit measurement for payment shall be made for any of the materials,
work, and equipment required. The payment shall be total compensation for
all labor, equipment, materials, maintenance, and all incidentals necessary to
prepare, implement, and maintain the approved Traffic Control Plan in
accordance with the Drawings and accepted Traffic Control Plan. The work
also includes but is not limited to the installation and maintenance of all
required barricades and signs.
Payment will be made as work progresses. Fifty percent (50%) of the lump
sum bid price will be paid when twenty five (25%) of the original contract
amount has been earned; an additional thirty percent (30%) will be paid
when fifty percent (50%) of the original contract amount has been earned;
and the remaining twenty percent (20%) will be paid upon final acceptance
of the project.
Pay Item Pay Unit
Traffic / Access Control LS
3. Clearing and Grubbing
No measurement for payment shall be made for any of the materials, work,
and equipment required. Payment will be made as work progresses on a
percentage lump sum basis.
The payment shall be total compensation for all labor, equipment, materials,
maintenance, and all incidentals necessary to prepare, implement, and
conduct the clearing and grubbing, in accordance with the Drawings and
Specifications, including all costs associated with the disposing of materials
off-site.
Pay Item Pay Unit
Clearing and Grubbing LS
4. Construction Dewatering (North Spill and River Riprap Location)
No unit measurement for payment will be made for this work. Work
includes all equipment, temporary power, labor and materials for
implementation of measures to control surface water and groundwater. Pay
item also includes all work necessary to obtain the required Stormwater
Management Permit and the Construction Dewatering Permit from the
LPATH Berm Erosion 01270-3 Measurement and Payment
Protection Measures
Colorado Department of Health. Also included are all equipment, labor and
materials for evaluation, design, construction, and monitoring of dewatering.
Payment shall be made based on the percentage of all work completed at the
time of each Progress Payment.
Pay Item Pay Unit
Construction Dewatering (North Spill and River LS
Riprap Location)
5. Remove Concrete Rubble
The measurement for removal of this item will be made on a unit basis. The
unit price bid for this item shall be full compensation for removing, hauling
and disposal of such items including existing concrete rubble, and all other
work necessary to remove these items in accordance with the Drawings and
Specifications. Replacement of riprap, trees, or vegetation outside of the pay
lines due to the CONTRACTOR’s failure to protect existing, undisturbed
materials shall not be paid for and shall be replaced at the CONTRACTOR’s
expense.
Pay Item Pay Unit
Remove Concrete Rubble SF
6. Fence Removal/Resetting (Wood Fence)
The measurement for payment of this item will be the total number of linear
feet of fence removed, stored, re-installed and accepted by the ENGINEER.
No payment will be made for items installed as the result of negligence or
unauthorized operations by the CONTRACTOR. The CONTRACTOR shall
supply and install any new materials required to remove, store, and re-install
the fence in its original location. Posts, rails and hardware shall be salvaged
and re-installed, provided that they are in condition acceptable to the
ENGINEER.
The unit bid price per linear foot shall include all of the CONTRACTOR’S
costs of whatsoever nature. The bid price shall include: removing, storing,
and re-installing all posts, rails, and appurtenances, all additional materials,
including wire and concrete; excavation, fill, compaction; and all other
related and necessary materials, work, and equipment required to construct
the work.
Pay Item Pay Unit
Fence Removal/Resetting (Wood Fence) LF
LPATH Berm Erosion 01270-4 Measurement and Payment
Protection Measures
7. Silt Fence
The measurement for payment of silt fence will be the actual number of
linear feet of silt fence installed. The work includes all equipment, labor,
materials, maintenance, and all incidentals necessary to prepare, implement,
maintain, remove the silt fence upon completion of construction, repair and
reseed ground along fence line, in accordance with the Drawings.
Pay Item Pay Unit
Silt Fence LF
8. Straw Bale – Sediment and Erosion Control Structure
The measurement for payment of straw bales will be on a unit basis.
Payment will be made for each bale furnished and placed. The work
includes all equipment, labor, materials, maintenance and all incidentals
necessary to prepare, implement, maintain, and ultimately remove the straw
bales in accordance with the Drawings and Specifications.
Pay Item Pay Unit
Straw Bale – Sediment and Erosion Control Structure EA
9. Unclassified Excavation
10. Muck Excavation
11. Native Soil (Over Revetment Mat Only)
12. Embankment (Complete In Place) without Haul
13. Embankment (Complete In Place) with Haul
The measurement for payment of unclassified excavation will be the total
number of cubic yards of material excavated according to the final Drawings.
Unclassified excavation shall consist of excavation of all materials on the site
to final grades, excluding the bid items listed in Section 02220. Excavation
of unsuitable material will only be paid for if it is found to be unsuitable in
its original state. Unclassified excavation shall be measured from the
drawings and cross sections, and the plan quantity will be paid for by the
cubic yard.
Muck excavation shall include excavation of unsuitable material and haul
and disposal of unsuitable material. Muck excavation shall also include the
cost of materials used to replace muck excavation. Muck excavation of
material from rain or weather damage will not be paid for and is entirely the
CONTRACTOR’S responsibility. This item will be measured in the field
and will be paid for by the cubic yard.
If unsuitable subgrade is encountered and the ENGINEER directs the
CONTRACTOR to overexcavate the material, the CONTRACTOR shall use
LPATH Berm Erosion 01270-5 Measurement and Payment
Protection Measures
uniformly graded 1 1/2” rock. This item will be measured in the field and
will be paid by the cubic yard per ticket of material used.
Native Soil shall include stripping existing vegetation, temporarily
stockpiling, load, haul and placement of topsoil within all designated areas of
the construction site. This item shall be measured in the field and the volume
calculated by the area multiplied by the depth, as determined by the
ENGINEER with no allowance for shrinkage or swell, and shall be paid for
by the cubic yard.
Embankment (Complete In Place) without Haul shall include all excavated
material, which is placed as embankment and compacted to final grades as
specified in Section 02315. This item shall include placement and
compaction of excavated material that has been determined as suitable from
the on-site excavations. This item will be measured from the drawings and
cross sections and the plan quantity will be paid for by the cubic yard.
Embankment (Complete In Place) with Haul shall include all excavated
material, which is placed as embankment and compacted to final grades as
specified in Section 02315. This item shall include haul, placement and
compaction of excavated material that has been determined as suitable from
the on-site excavations. This item will be measured from the drawings and
cross sections and the plan quantity will be paid for by the cubic yard.
Pay Item Pay Unit
Unclassified Excavation CY
Muck Excavation CY
Native Soil (Over Revetment Mat Only) CY
Embankment (Complete In Place) without Haul CY
Embankment (Complete In Place) with Haul CY
14. Concrete Sill (Complete In Place)
The measurement for payment of the concrete sill shown on the Drawings,
will be the total amount of cubic yards dimensioned on the Drawings,
completed in place, and accepted. No measurement for payment will be
made for items placed outside of the dimensions as shown on the Drawings
unless directed by the ENGINEER.
The unit price bid per cubic yard shall include all of the CONTRACTOR’s
costs of whatsoever nature. The price bid shall include: excavation;
furnishing and placing the concrete and steel reinforcement; forming;
furnishing and applying curing compounds; finishing the edging the concrete
surfaces; joints and joint materials; furnishing and compacting all materials
required for preparation of a stable subbase; backfilling; and, all other related
and necessary materials, work, and equipment required to construct the
concrete sill in accordance with the Drawings and Specifications. No
measurement for payment shall be made for replacement of materials
damaged by the CONTRACTOR in his operations.
LPATH Berm Erosion 01270-6 Measurement and Payment
Protection Measures
Pay Item Pay Unit
Concrete Sill (Complete In Place) CY
15. Concrete Block Revetment Mat – North Spill
The measurement for payment for this item will be by the actual number of
square feet in place. The unit price bid per square foot of Concrete Block
Revetment Mat for the North Spill shall include all of the CONTRACTOR’s
costs of whatsoever nature including: furnishing all labor, materials,
equipment, and any other incidentals to Concrete Block Revetment Mat in
accordance with the Contract Documents, complete-in-place; haul from the
suppliers source; placement of revetment mat to design dimensions;
excavation and embankment; subgrade preparation; compaction; furnishing
and placement of filter fabric; grout; reinforcing bar; steel cable; anchors;
and, any other miscellaneous items and work shown or reasonably implied
on the Drawings and in the Specifications for this work, and elsewhere in the
Contract Documents.
Pay Item Pay Unit
Concrete Block Revetment Mat – North Spill SF
16. Concrete Block Revetment Mat (Including Drainage Layer) – South Spill
The measurement for payment for this item will be by the actual number of
square feet in place. The unit price bid per square foot of Concrete Block
Revetment Mat for the North Spill shall include all of the CONTRACTOR’s
costs of whatsoever nature including: furnishing all labor, materials,
equipment, and any other incidentals to Concrete Block Revetment Mat in
accordance with the Contract Documents, complete-in-place; haul from the
suppliers source; placement of revetment mat to design dimensions;
excavation and embankment; subgrade preparation; compaction; furnishing
and placement of filter fabric; furnishing and placement of ¾” crushed rock
drainage layer; grout; reinforcing bar; steel cable; anchors; and, any other
miscellaneous items and work shown or reasonably implied on the Drawings
and in the Specifications for this work, and elsewhere in the Contract
Documents.
Pay Item Pay Unit
Concrete Block Revetment Mat SF
(Including Drainage Layer) – South Spill
LPATH Berm Erosion 01270-7 Measurement and Payment
Protection Measures
17. Riprap (Class 12)
The measurement for payment of riprap will be the total number of tons of
riprap required to be placed as specified on the Drawings or as otherwise
directed by the ENGINEER. Measurement does not include the thickness of
the bedding.
The unit price bid per ton of riprap placed shall include all of the
CONTRACTOR’s costs of whatsoever nature. The item shall include:
furnishing, transporting, and placing all riprap; excavation, compaction,
backfilling, removal and disposal of excavations and debris; Type II bedding
material; geotextile fabric; compacted fill required to bury riprap; and all
other related and necessary materials, work, and equipment required to place
the riprap in accordance with the Drawings and Specifications.
Pay Item Pay Unit
Riprap (Class 12) TON
18. 4” to 8” Crushed Concrete Rubble
The measurement for payment of 4” to 8” crushed concrete rubble will be the
total number of tons of concrete rubble required to be placed as specified on
the Drawings or as otherwise directed by the ENGINEER.
The unit price bid per ton of concrete rubble placed shall include all of the
CONTRACTOR’s costs of whatsoever nature. The item shall include:
furnishing, transporting, and placing all concrete rubble; excavation,
compaction, backfilling, removal and disposal of excavations and debris; and
all other related and necessary materials, work, and equipment required to
place the concrete rubble in accordance with the Drawings and
Specifications.
Pay Item Pay Unit
4” to 8” Crushed Concrete Rubble TON
19. 1-1/2” Washed Rock
The measurement for payment of 1-1/2” washed rock will be the total
number of tons of washed rock required to be placed as specified on the
Drawings or as otherwise directed by the ENGINEER.
The unit price bid per ton of washed rock placed shall include all of the
CONTRACTOR’s costs of whatsoever nature. The item shall include:
furnishing, transporting, and placing all washed rock; excavation,
compaction, backfilling, removal and disposal of excavations and debris; and
all other related and necessary materials, work, and equipment required to
place the washed rock in accordance with the Drawings and Specifications.
LPATH Berm Erosion 01270-8 Measurement and Payment
Protection Measures
Pay Item Pay Unit
1-1/2” Washed Rock TON
20. Landscape-Tree Removal (>12” Diameter)
The measurement and payment for Tree Removal will be the total number of
trees removed as shown on the bid schedule and measured and accepted by
the ENGINEER in accordance with the Drawings and Specifications. The
ENGINEER will mark all trees to be removed and paid for under this item.
All other miscellaneous tree and shrub removal shall be included in Clearing
and Grubbing. Payment will be made upon completion of the work in
accordance with the Drawings and Specifications.
The unit price bid for each item shall include all of the CONTRACTOR’s
cost of whatsoever nature to complete the tree removal including: furnishing
and transporting all materials, labor, and equipment; excavation and removal
of tree and stump and root system; backfilling and compaction; and, all other
related and necessary materials, work, and equipment required to perform the
work in accordance with the Drawings and Specifications.
Pay Item Pay Unit
Landscape-Tree Removal (>12” Diameter) EA
21. Ground Preparation for Seeding
The measurement for payment of this item will be the total number of acres
of disturbed ground prepared for seeding and accepted by the ENGINEER.
No payment will be made for prepared ground outside of the limit of
disturbance.
The unit bid price per acre shall include all of the CONTRACTOR’S costs of
whatsoever nature. The bid price shall include: watering, disking, and the
preparation of disturbed ground to receive grass seed and shrubs; and all
other related and necessary materials, work, and equipment required to
conduct the work.
Pay Item Pay Unit
Ground Preparation for Seeding AC
22. Topsoil (Delivery and Stockpile only - No Installation)
The measurement for payment of topsoil will be the total number of cubic
yards of material delivered to the site. This item shall include delivery of the
material and placement at various locations within the site. The final
location of these delivery sites will be at the direction of the ENGINEER.
LPATH Berm Erosion 01270-9 Measurement and Payment
Protection Measures
Pay Item Pay Unit
Topsoil (Delivery and Stockpile only - No Installation) CY
END OF SECTION
LPATH Berm Erosion 01270-10 Measurement and Payment
Protection Measures
THIS PAGE INTENTIONALLY LEFT BLANK.
LPATH Berm Erosion 01310-1 Project Meetings
Protection Measures
SECTION 01310
PROJECT MEETINGS
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Pre-Construction Conference: A Pre-Construction Conference will be held after
Notice of Award and before the Notice to Proceed, the date, time and location will be
determined after Notice of Award.
The conference shall be attended by:
1. CONTRACTOR and CONTRACTOR’s Superintendent
2. CONTRACTOR’s Subcontractors
3. ENGINEER
4. OWNER
5. Others as requested by the CONTRACTOR, OWNER, or ENGINEER.
Unless previously submitted to the OWNER, the CONTRACTOR shall bring to the
conference a tentative schedule of the construction project, including the scheduled
shop drawings and other submittals.
The purpose of the conference is to designate responsible personnel and establish a
working relationship. Matters requiring coordination will be discussed and
procedures for handling such matters established. The agenda will include:
1. CONTRACTOR’s tentative Schedule
2. Permit applications and submittals, including 402 Permit, Erosion and
Sediment Control Plan, and Traffic Control Plan
3. Transmittal, review and distribution of CONTRACTOR’s submittals
4. Processing applications for payment
5. Maintaining record documents
6. Critical work sequencing
7. Field decision and change orders
8. Use of premises, office and storage areas, staging area, security,
housekeeping, and OWNER’s needs
9. CONTRACTOR’s assignment of safety and first aid
LPATH Berm Erosion 01310-2 Project Meetings
Protection Measures
B. Construction Progress Meetings: Progress meetings will be conducted weekly or at
some other frequency, if approved by the OWNER, ENGINEER and
CONTRACTOR. These meetings shall be attended by the OWNER, the
ENGINEER, the CONTRACTOR’s representative and any others invited by these
people.
The meeting will be conducted by the ENGINEER and the ENGINEER will arrange
for keeping the minutes and distributing the minutes to all persons in attendance.
The agenda of these project meetings will include construction progress, the status of
submittal reviews, the status of information requests, critical work sequencing,
review of strategies for connections into existing facilities, status of field orders and
change orders, and any general business.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
END OF SECTION
LPATH Berm Erosion 01320-1 Construction Schedules
Protection Measures
SECTION 01320
CONSTRUCTION SCHEDULES
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Prepare detailed schedule of all construction operations and procurements to be reviewed
by parties attending the preconstruction conference.
Schedule shall be approved by the OWNER and ENGINEER prior to Notice to Proceed.
1.02 FORMAT AND SUBMISSIONS
A. Prepare construction and procurement schedules in a graphic format suitable for
displaying scheduled and actual progress. The construction schedule shall clearly identify
the critical path for the project and shall also identify all critical procurement items.
B. Submit four (4) copies of each schedule to the OWNER and ENGINEER for review.
The ENGINEER will return one copy to the CONTRACTOR with revisions suggested or
necessary for coordination of the Work with the needs of the OWNER or others.
1.03 CONTENT
A. Construction Progress Schedule
1. Show the complete work sequence of construction by activity and location.
2. Show the dates for the beginning and completion of major task items. At a
minimum, show the following items:
• Removal of trees and concrete rubble.
• Installation of concrete sills for the North and South spills.
• Placement of fill for the North and South spills
• Installation of the concrete revetment mats and backfill for the North and
South spills.
• Placement of the buried riprap in the Cache la Poudre River.
• Seeding/Mulching and placement of erosion control mat (By others).
3. Show projected percentage of completion for each item as of the first day of the
month.
B. Report of delivery of equipment and materials.
1. Show delivery status of critical and major items of equipment and materials.
2. Include a schedule which includes the critical path for Shop Drawings, tests, and
other submittal requirements for equipment and materials.
LPATH Berm Erosion 01320-2 Construction Schedules
Protection Measures
1.04 PROGRESS REVISIONS
A. Submit revised schedules and reports when changes are foreseen, when requested by
OWNER or ENGINEER, and with each application for progress payment.
B. Show changes occurring since previous submission.
1. Actual progress of each item to date.
2. Revised projections of progress and completion.
C. Provide a narrative report as needed to define:
1. Anticipated problems, recommended actions, and their effects on the schedule.
2. The effect of changes on schedules of others.
1.05 OWNER'S RESPONSIBILITY
A. OWNER's review is only for the purpose of checking conformity with the Contract
Documents and assisting CONTRACTOR in coordinating the Work with the needs of the
Project.
B. It is not to be construed as relieving CONTRACTOR from any responsibility to
determine the means, methods, techniques, sequences and procedures of construction as
provided in the General Conditions.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
END OF SECTION
LPATH Berm Erosion 01330-1 Submittals
Protection Measures
SECTION 01330
SUBMITTALS
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Requirements:
1. Where required by the Specifications, the CONTRACTOR shall submit
descriptive information that will enable the ENGINEER to determine
whether the CONTRACTOR’s proposed materials, equipment, methods of
work are in general conformance to the design concept and in accordance
with the Drawings and Specifications. The information submitted may
consist of drawings, specifications, descriptive data, certificates, samples, test
results, product data, and such other information, all as specifically required
in the Specifications. In some instances, specified submittal information
describes some, but not all features of the material, equipment, or method of
work.
2. The CONTRACTOR shall be responsible for the accuracy and completeness
of the information contained in each submittal and shall assure that the
material, equipment, or method of work shall be as described in the
submittal. The CONTRACTOR shall verify that all features of all products
conform to the requirements of the Drawings and Specifications. The
CONTRACTOR shall ensure that there is no conflict with other submittals
and notify the ENGINEER in each case where its submittal may affect the
work of another CONTRACTOR or the OWNER. The CONTRACTOR
shall ensure coordination of submittals among the related crafts and
subcontractors.
3. Submittals will be reviewed for overall design intent and returned to
CONTRACTOR with action to be indicated by the ENGINEER. It shall be
the CONTRACTOR’s responsibility to assure that previously accepted
documents are destroyed when they are superseded by a resubmittal as such.
4. It shall be the CONTRACTOR’s responsibility to ensure that required items
are corrected and resubmitted. Any work done before approval shall be at
the CONTRACTOR’s own risk.
B. Submittal Procedure:
1. Unless a different number is called for in the individual sections, six (6)
copies of each submittal and sample are required, four (4) of which will be
retained by the ENGINEER. The CONTRACTOR shall receive two (2)
copies in return. Faxed submittals will not be accepted.
2. Submittals that are related to or affect each other shall be forwarded
simultaneously as a package to facilitate coordinated review. Uncoordinated
submittals will be rejected.
LPATH Berm Erosion 01330-2 Submittals
Protection Measures
3. If the items or system proposed are acceptable but the major part of the
individual drawings or documents are incomplete or require revision, the
submittal will be returned with requirements for completion.
4. The right is reserved for the ENGINEER to require submittals in addition to
those called for in individual sections.
5. Submittals regarding material and equipment shall be submitted directly to
the ENGINEER and will be accompanied by a transmittal form. A separate
form shall be used for each specific item, class of material, equipment, and
items specified in separate discrete sections for which the submittal is
required. Submittals for various items shall be made with a single form
when the items taken together constitute a manufacturer’s package or are so
functionally related that expediency indicates checking or review of the
group or package as a whole.
6. A unique number, sequentially assigned, shall be noted on the transmittal
form accompanying each item submitted. Original submittal numbers shall
have the following format: “XXX-Y;” where “XXX” is the originally
assigned submittal number and “Y” is a sequential letter assigned for
resubmittals (i.e., A, B, or C being the first, second and third resubmittals,
respectively). Submittal 25B, for example, is the second resubmittal of
Submittal 25.
7. If the CONTRACTOR proposes to provide material, equipment, or method
of work that deviates from the Contract Documents, it shall indicate so under
“deviations” on the transmittal form accompanying the submittal copies.
8. Submittals that do not have all the information required to be submitted,
including deviations, are not acceptable and will be returned without review.
C. Review Procedure:
1. Submittals are specified for those features and characteristics of materials,
equipment, and methods of operation that can be selected based on the
CONTRACTOR’s judgment of their conformance to the requirements of the
Drawing and Specifications. Other features and characteristics are specified
in a matter that enables the CONTRACTOR to determine acceptable options
without submittals. The review procedure is based on the CONTRACTOR’s
guarantee that all features and characteristics not requiring submittals
conform to the Drawings and Specifications. Review shall not extend to
means, methods, techniques, sequences, or procedures of construction or to
verifying quantities, dimensions, weights or gages, or fabrication processes
(except where specifically indicated or required by the Specifications) of
separate items, and as such, will not indicate approval of the assembly in
which the item functions.
2. Unless otherwise specified, within twenty-one (21) calendar days after
receipt of the submittal, the ENGINEER will review the submittal and return
copies. The returned submittal will indicate one of the following actions:
LPATH Berm Erosion 01330-3 Submittals
Protection Measures
a. If the review indicates that the material, equipment, or work method
complies with the Specifications, submittal copies will be marked
“NO EXCEPTIONS TAKEN”. In this event, the CONTRACTOR
may begin to implement the work method or incorporate the material
or equipment covered by the submittal.
b. If the review indicates limited corrections are required, copies will be
marked “FURNISH AS NOTED”. The CONTRACTOR may begin
implementing the work method or incorporating the material and
equipment covered by the submittal in accordance with the noted
corrections. Where submittal information will be incorporated in
Operation and Maintenance data, a corrected copy shall be provided.
c. If the review indicates that the submittal is insufficient or contains
incorrect data, copies will be marked “REVISE AND RESUBMIT”.
Except at its own risk, the CONTRACTOR shall not undertake work
covered by this submittal until it has been revised, resubmitted and
returned marked either “NO EXCEPTIONS TAKEN” or “FURNISH
AS NOTED”.
d. If the review indicates that the material, equipment, or work method
do not comply with the Specifications, copies of the submittal will be
marked “REJECTED”. Submittals with deviations that have not
been identified clearly may be rejected. Except at its own risk, the
CONTRACTOR shall not undertake the work covered by such
submittals until a new submittal is made and returned marked either
”NO EXCEPTIONS TAKEN” or “FURNISH AS NOTED”.
D. Drawing:
1. The term “shop drawings” includes drawings, diagrams, layouts, schematic,
descriptive literature, illustrations schedules performance and test data, and
similar materials furnished by CONTRACTOR to explain in detail specific
portions of the work required by the Contract
2. CONTRACTOR shall coordinate all such drawings, and review them for
legibility, accuracy, completeness and compliance with contract requirements
and shall indicate this approval thereon as evidence of such coordination and
review. Shop drawing submitted to the ENGINEER without evidence of
CONTRACTOR’s approval will be returned for resubmission.
3. Shop drawing shall be clearly identified with the name and project number of
this contract, and references to applicable specification paragraphs and
contract drawings. When catalog pages are submitted, applicable items shall
be clearly identified.
4. CONTRACTOR shall stamp his approval on shop drawings prior to
submission to the ENGINEER as indication of his checking and verification
of dimensions and coordination with interrelated items. Stamp shall read:
“(CONTRACTOR’s Name) represents that we have determined and
verified all field dimensions and measurements, field construction
LPATH Berm Erosion 01330-4 Submittals
Protection Measures
criteria, materials, catalog numbers and similar data, and that we
have checked with the requirements of the Specifications and
Drawings, the Contract Documents, and General Conditions”.
Marks on drawings by CONTRACTOR shall not be in red. Any marks by
CONTRACTOR shall be duplicated on all copies submitted.
5. If shop drawings show variations from contract requirements,
CONTRACTOR shall describe such variations in writing, separate from the
drawings, at time of submission. All such variations must be approved by
the ENGINEER. If ENGINEER approves any such variations, he shall
issue an appropriate contract modification, except that, if the variation is
minor and does not involve a change in price or in time of performance, a
modification need not be issued.
6. Should the CONTRACTOR propose any item on his shop drawings or
incorporate an item into the work, and that item should subsequently prove to
be defective or otherwise unsatisfactory, (regardless of the ENGINEER’s
preliminary review), the CONTRACTOR shall, at his own expense, replace
the item with another item that will perform satisfactorily.
E. Certificates:
For those items called for in individual sections, furnish six (6) certificates of
compliance from manufacturers or suppliers certifying that materials or equipment
being furnished under the Contract comply with the requirements of these
Specifications.
F. Samples:
Samples shall be sufficient in size to clearly illustrate functional characteristics and
full range of color, texture, and pattern.
G. Effect of Review of CONTRACTOR’s Submittals:
Review of drawings, data, methods of work, or information regarding materials or
equipment the CONTRACTOR proposes to provide, shall not relieve the contractor
of its responsibility for errors therein and shall not be regarded as an assumption of
risks or liability by the ENGINEER or the OWNER, or by any officer or employee
thereof, and the CONTRACTOR shall have no claim under the Contract on account
of the failure or partial failure, of the method of work, material, or equipment so
reviewed. A mark of “NO EXCEPTIONS TAKEN” or “FURNISH AS NOTED”
shall mean that the OWNER has no objection to the CONTRACTOR, upon its own
responsibility, using the plan or method of work proposed, or providing the materials
or equipment proposed.
LPATH Berm Erosion 01330-5 Submittals
Protection Measures
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
END OF SECTION
LPATH Berm Erosion 01330-6 Submittals
Protection Measures
THIS PAGE INTENTIONALLY LEFT BLANK.
LPATH Berm Erosion 01425-1 Standard References
Protection Measures
SECTION 01425
STANDARD REFERENCES
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Reference to standards, specifications, manuals, or codes of any technical society,
organization, or association, or to the laws or regulations of any governmental
authority, whether such reference be specific or by implication, shall mean the latest
standard specification, manual, code, or laws or regulations in effect at the time of
opening of Bids, except as may be otherwise specifically stated. However, no
provision of any referenced standard, specifications manual or code (whether or not
specially incorporated by reference in the Contact Documents) shall be effective to
change the duties and responsibilities of OWNER, CONTRACTOR, or ENGINEER,
or any of their consultants, agents or employees from those set forth in the Contract
Documents, nor shall it be effective to assign to ENGINEER, or any of
ENGINEER’s Consultants, agents, or employees, any duty or authority to supervise
or direct the furnishing or performance of the Work.
Whenever used in the Contract Documents, the following abbreviations will have the
meanings listed:
AASHTO American Association of State Highway and Transportation
Officials
444 North Capital Street, N.W., Suite 225
Washington, DC 20001
ACI American Concrete Institute
P. O. Box 19150
Detroit, MI
ACPA American Concrete Pipe Association
AISC American Iron and Steel Construction
AISI American Iron and Steel Institute
ANSI American National Standards Institute, Inc.
1430 Broadway
New York, NY 10017
AREMA American Railway Engineering
and Maintenance-of-Way Association
8201 Corporate Drive, Suite 1125
Landover, MD 20785
ASCE American Society of Civil Engineers
345 East 47th Street
New York, NY 10017
LPATH Berm Erosion 01425-2 Standard References
Protection Measures
ASTM American Society of Testing and Materials
1916 Race Street
Philadelphia, PA 19103
BOCA Building Officials and Code Administrators
17926 Halstead
Homewood, IL 60430
CISPI Cast Iron Soil Pipe Institute
CRSI Concrete Reinforcing Steel Institute
180 North LaSalle Street
Chicago, IL 60601
CSI Construction Specifications Institute
DIPRA Ductile Iron Pipe Research Associations
EPA Environmental Protection Agency
FEDSPEC Federal Specifications
General Services Administration
Specification and Consumer Information
Distribution Branch
Washington Navy Yard, Building 197
Washington, DC 20407
FEDSTDS Federal Standards (see FEDSPEC)
ICBO International Conference of Building Officials
5360 South Workman Mill Road
Whittier, CA 90601
MILSPEC Military Specifications
Naval Publications and Forms Center
5801 Tabor Avenue
Philadelphia, PA 19120
NIST National Institute of Standards and Technology
NPC National Plumbing Code
NSC National Safety Council
OSHA Occupational Safety and Health Act
U.S. Department of Labor
Occupational and Health Administration
San Francisco Regional Office
450 Golden Gate Avenue, Box 30617
PCA Portland Cement Association
PCI Prestressed Concrete Institute
LPATH Berm Erosion 01425-3 Standard References
Protection Measures
PS Products Standards Section - U.S. Depart. of Commerce
SSPC Steel Structures Painting Council
SSPWC Standard Specifications for Public Works Construction
Building News, Inc.
3055 Overhead Avenue
Los Angeles, CA 90034
TCA Title Council of America
UBC Uniform Building Code
Published by ICBO
UL Underwriter’s Laboratory
207 East Ohio Street
Chicago, IL 60611
UMC Uniform Mechanical Code
Published by ICBO
UPC Uniform Plumbing Code
Published by IAPMO
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
END OF SECTION
LPATH Berm Erosion 01425-4 Standard References
Protection Measures
THIS PAGE INTENTIONALLY LEFT BLANK.
LPATH Berm Erosion 01450-1 Materials Testing
Protection Measures
SECTION 01450
MATERIALS TESTING
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Provide such equipment and facilities as are required for conducting field tests and
for collecting and forwarding samples. Do not use any materials or equipment
represented by samples until tests, if required, have been made and the materials or
equipment found to be acceptable. Any product which becomes unfit for use after
approval thereof shall not be incorporated into the work.
B. Tests shall be made by an accredited testing laboratory selected by the OWNER.
Except as otherwise provided, sampling and testing of all materials and the laboratory
methods and testing equipment shall be in accordance with the latest standards and
tentative methods of the American Society for Testing Materials (ASTM), and the
American Association of Highway and Transportation Officials (AASHTO).
C. Where additional or specific information concerning testing methods, sample sizes,
etc., is required, such information is included under the applicable sections of the
Specifications. Any modification of, or elaboration on, these test procedures which
may be included for specific materials under their respective sections in the
Specifications shall take precedence over these procedures.
1.02 OWNER’S RESPONSIBILITIES
A. The OWNER shall be responsible for and shall pay all costs in connection with the
following testing:
1. Soils compaction tests.
2. Trench backfill.
3. Tests not called for by the Specifications of materials delivered to the site.
4. Concrete tests.
1.03 CONTRACTOR’S RESPONSIBILITIES
A. In addition to those inspections and tests called for in the General Conditions,
CONTRACTOR shall also be responsible for and shall pay all costs in connection
with testing required for the following:
1. Concrete materials and mix designs.
2. Gradation tests for embedment, fill and backfill materials.
3. All performance and field testing specifically called for by the Specifications.
LPATH Berm Erosion 01450-2 Materials Testing
Protection Measures
4. All retesting for work or materials found defective or unsatisfactory, including
tests covered under 1.02 above.
5. Water quality testing required by discharge permits.
1.04 TRANSMITTAL OF TEST REPORTS
Written reports of tests and engineering data furnished by CONTRACTOR for ENGINEER’s
review of materials and equipment proposed to be used in the work shall be submitted as
specified for Shop Drawings.
The testing laboratory retained by the OWNER will furnish three (3) copies of a written
report of each test performed by laboratory personnel in the field or laboratory. Two (2)
copies of each test report will be transmitted to the ENGINEER and one (1) copy to the
CONTRACTOR within seven (7) days after each test is completed.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
END OF SECTION
LPATH Berm Erosion 01555-1 Traffic Regulation
Protection Measures
SECTION 01555
TRAFFIC REGULATION
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Conformance: City of Fort Collins Work Area Traffic Control Handbook, Manual of
Uniform Traffic Control Devices (U.S. Department of Transportation), or applicable
statutory requirements of authority having jurisdiction. Fort Collins Handbook takes
precedence over Manual of Uniform Traffic Control Devices.
B. Operations on or about traffic areas and provisions for regulating traffic will be subject to the
regulation of governmental agencies having jurisdiction over the affected areas.
C. Keep traffic areas free of excavated material, construction equipment, pipe, and other
materials and equipment.
D. Keep fire hydrants and water control valves free from obstruction and available for use at all
times.
E. Conduct operations in a manner to avoid unnecessary interference with public and private
roads and drives.
1.02 TRAFFIC CONTROL PLAN
A. The Traffic Control Plan is to be used as a guideline for the CONTRACTOR. Adjustments to
the approved plan may be required by the OWNER based on actual traffic operation.
B. Traffic control shall be provided by the CONTRACTOR.
1.03 FLAGMEN
A. Required where necessary to provide for public safety, or the regulation of traffic, or by
jurisdictional authorities.
B. Shall be properly equipped and certified by ATSSA.
1.04 WARNING SIGNS AND LIGHTS
A. Provide barricades and warning signs for:
1. Open trenches and other excavations.
2. Obstructions, such as material piles, equipment (moving or parked), piled
embankment.
B. Illuminate by means of warning lights all barricades and obstructions from sunset to
sunrise.
LPATH Berm Erosion 01555-2 Traffic Regulation
Protection Measures
C. Protect roads and driveways by effective barricades on which are placed acceptable
warning signs.
D. Barricades and warning signs must be acceptable to the ENGINEER.
1.05 PARKING
A. The CONTRACTOR shall designate parking areas with the approval of the OWNER for
the use of all construction workers and others performing work or furnishing services in
connection with the project so as avoid interference with public traffic, OWNER's
operations, or construction activities.
1.06 ROADWAY USAGE BETWEEN OPERATIONS
A. At all times when work is not actually in progress, CONTRACTOR shall make passable
and shall open to traffic such portions of the project and temporary roadways or portions
thereof as may be agreed upon between CONTRACTOR and OWNER and all authorities
having jurisdiction over any properties involved.
1.07 WORK AREA SAFETY
A. The CONTRACTOR shall maintain a safe work area and protect area residents,
motorists, bicyclists, pedestrians, and children from work area hazards.
B. The CONTRACTOR shall provide all work area safety control devices, such as
barricades and safety fence around all excavations and drop-offs.
C. Work area safety control devices will not be paid for separately. Cost for this equipment
should be included in the unit costs for the work items which will require work area
safety control devices.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
END OF SECTION
LPATH Berm Erosion 01635-1 Substitutions and
Protection Measures Product Options
SECTION 01635
SUBSTITUTIONS AND PRODUCT OPTIONS
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Description:
1. This section describes the procedure required by the CONTRACTOR for
product substitutions.
2. Requests for Substitution:
a. Base all bids on materials, equipment and procedures specified.
b. Certain types of equipment and kinds of material are described in
specifications by means of trade names and catalog numbers, and/or
manufacturer’s names. Where this occurs, it is not intended to
exclude from consideration such types of equipment and kinds of
material bearing other trade names, catalog numbers and/or
manufacturer’s names, capable of accomplishing purpose of types of
equipment or kinds of material specifically indicated.
c. Other types of equipment and kinds of material may be acceptable to
the OWNER and ENGINEER.
d. Types of equipment, kinds of material and methods of construction,
if not specifically indicated must be approved in writing by
ENGINEER and the OWNER.
3. Submission of Requests for Substitution:
a. After Notice to Proceed, the OWNER/ENGINEER will consider
written requests for substitutions of products, materials, systems or
other items.
b. The ENGINEER reserves the right to require substitute items to
comply color and pattern-wise with base specified items, if necessary
to secure “design intent”.
c. Submit six (6) copies of request for substitution. Include in request:
1) Complete data substantiating compliance of proposed
substitute with Contract Documents.
2) For products:
i. Product identification, including manufacturer’s
name.
ii. Manufacturer’s literature, marked to indicate
specific model, type, size, and options to be
LPATH Berm Erosion 01635-2 Substitutions and
Protection Measures Product Options
considered: Product description; performance and
test data; reference standards; difference in power
demand; dimensional differences for specified unit.
iii. Name and address of similar projects on which
product was used, date of installation, and field
performance data.
3) For construction methods:
i. Detailed description of proposed method.
ii. Drawings illustrating methods.
4) Itemized comparison of proposed substitution with product
or method specified.
5) Data relating to changes in construction schedule.
6) Relation to separate contracts.
7) Accurate cost data on proposed substitution in comparison
with product or method specified.
d. In making request for substitution, or in using an approved substitute
item, Supplier/Manufacturer represents:
1) He has personally investigated proposed product or method,
and has determined that it is equal or superior in all respects
to that specified and that it will perform function for which it
is intended.
2) He will provide same guarantee for substitute item as for
product or method specified.
3) He will coordinate installation of accepted substitution into
work, to include building modifications if necessary, making
such changes as may be required for work to be complete in
all aspects.
4) He waives all claims for additional costs related to
substitution which subsequently become apparent.
4. Substitutions:
a. Request sufficiently in advance to avoid delay in construction.
LPATH Berm Erosion 01635-3 Substitutions and
Protection Measures Product Options
5. CONTRACTOR’s Option:
a. For products specified only by reference standards, select any
product meeting standards by any manufacturer, indicate selected
type in submission.
b. For products specified by naming several products or manufacturers,
select any product and manufacturer named, indicate selected type in
submission.
c. For products specified by naming one or more products, but
indicating option of selecting equivalent products by stating “or
equivalent” after specified product, CONTRACTOR must submit
request, as required for substitution, for any product not specifically
named.
6. Rejection of Substitution or Optional Item:
a. Substitutions and/or options will not be considered if:
1) They are indicated or implied on shop drawings, or project
data submittals, without formal request submitted in
accordance with this section.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
END OF SECTION
LPATH Berm Erosion 01635-4 Substitutions and
Protection Measures Product Options
THIS PAGE INTENTIONALLY LEFT BLANK.
LPATH Berm Erosion 01650-1 Material Delivery,
Protection Measures Storage, and Handling
SECTION 01650
MATERIAL DELIVERY, STORAGE,
AND HANDLING
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Equipment, products and materials shall be shipped, handled, stored, and installed in
ways which will prevent damage to the items. Damaged items will not be permitted
as part of the work except in cases of minor damage that have been satisfactorily
repaired and are acceptable to the ENGINEER.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
END OF SECTION
LPATH Berm Erosion 01650-2 Material Delivery,
Protection Measures Storage, and Handling
THIS PAGE INTENTIONALLY LEFT BLANK.
LPATH Berm Erosion 01710-1 Site Conditions
Protection Measures
SECTION 01710
SITE CONDITIONS
PART 1 GENERAL
1.01 SECTION INCLUDES
A. General:
1. The CONTRACTOR acknowledges that he has satisfied himself as to the nature
and location of the work, the general and local conditions, particularly those
bearing upon access to the site; handling, storage, and disposal of materials;
availability of water, electricity and roads; uncertainties of weather, river stages,
water flow rates and levels in irrigation ditches and canals or similar physical
conditions at the site; the conformation and conditions of the ground; the
equipment and facilities needed preliminary to and during the execution of the
work; and all other matters which can in any way affect the work or the cost
thereof under this Contract.
2. The CONTRACTOR further acknowledges that he has satisfied himself as to the
character, quality and quantity of surface and subsurface materials to be
encountered from his inspection of the site and from reviewing any available
records of exploratory work furnished by the OWNER or included in these
Documents. Failure by the CONTRACTOR to acquaint himself with the
physical conditions of the site and all the available information will not relieve
him from responsibility for properly estimating the difficulty or cost of
successfully performing the work.
3. The CONTRACTOR warrants that as a result of his examination and
investigation of all the aforesaid data that he can perform the work in a good and
workmanlike manner and to the satisfaction of the OWNER. The OWNER
assumes no responsibility for any representations made by any of its officers or
agents during or prior to the execution of this Contract, unless (1) such
representations are expressly stated in the Contract, and (2) the Contract
expressly provides that the responsibility therefore is assumed by the OWNER.
PART 2 PRODUCTS
2.01 INFORMATION ON SITE CONDITIONS
A. Any information obtained by the ENGINEER regarding site conditions, subsurface
information, groundwater elevations, existing construction of site facilities, and similar
data will be available for inspection, as applicable, at the office of the ENGINEER upon
request. Such information is offered as supplementary information only. Neither the
ENGINEER nor the OWNER assumes any responsibility for the completeness or
interpretation of such supplementary information.
1. Differing Subsurface Conditions:
a. In the event that the subsurface or latent physical conditions are found
materially different from those indicated in these Documents, and
LPATH Berm Erosion 01710-2 Site Conditions
Protection Measures
differing materially from those ordinarily encountered and generally
recognized as inherent in the character of work covered in these
Contract Documents, the CONTRACTOR shall promptly, and before
such conditions are disturbed, notify the ENGINEER in writing of such
changed conditions.
b. The ENGINEER will investigate such conditions promptly and
following this investigation, the CONTRACTOR shall proceed with the
work, unless otherwise instructed by the ENGINEER. If the
ENGINEER finds that such conditions do so materially differ and cause
an increase or decrease in the cost of or in the time required for
performing the work, the ENGINEER will recommend to the OWNER
the amount of adjustment in cost and time he considers reasonable. The
OWNER will make the final decision on all Change Orders to the
Contract regarding any adjustment in cost or time for completion.
2. Underground Utilities:
a. Known utilities and structures adjacent to or encountered in the work are
shown on the Drawings. The locations shown are taken from existing
records and the best information available from existing utility plans,
however, it is expected that there may be some discrepancies and
omissions in the locations and quantities of utilities and structures
shown. Those shown are for the convenience of the CONTRACTOR
only, and no responsibility is assumed by either the OWNER or the
ENGINEER for their accuracy or completeness.
PART 3 EXECUTION
3.01 GENERAL
A. Where the CONTRACTOR's operations could cause damage or inconvenience to
railway, telegraph, telephone, television, oil, gas, electricity, water, sewer, or irrigation
systems, the operations shall be suspended until all arrangements necessary for the
protection of these utilities and services have been made by the CONTRACTOR.
B. Notify all utility offices which are affected by the construction operation at least 48 hours
in advance. Under no circumstances expose any utility without first obtaining permission
from the appropriate agency. Once permission has been granted, locate, expose, and
provide temporary support for all existing underground utilities.
C. The CONTRACTOR shall protect all utility poles from damage. If interfering power
poles, telephone poles, guy wires, or anchors are encountered, notify the ENGINEER and
the appropriate utility company at least 48 hours in advance of construction operations to
permit the necessary arrangements for protection or relocation of the interfering structure.
D. The CONTRACTOR shall be solely and directly responsible to the owner and operators
of such properties for any damage, injury, expense, loss, inconvenience, delay, suits,
actions, or claims of any character brought because of any injuries or damage which may
result from the construction operations under this Contract.
LPATH Berm Erosion 01710-3 Site Conditions
Protection Measures
E. Neither the OWNER nor its officers or agents shall be responsible to the
CONTRACTOR for damages as a result of the CONTRACTOR's failure to protect
utilities encountered in the work.
F. If the CONTRACTOR while performing the Contract discovers utility facilities not
identified in the Drawings or Specifications, he shall immediately notify the OWNER,
utility, and the ENGINEER in writing.
G. In the event of interruption to domestic water, sewer, storm drain, or other utility services
as a result of accidental breakage due to construction operations, promptly notify the
proper authority. Cooperate with said authority in the restoration of service as promptly
as possible and bear all costs of repair.
H. The CONTRACTOR shall replace, at his own expense, any and all other existing utilities
or structures removed or damaged during construction, unless otherwise provided for in
these Contract Documents or ordered by the ENGINEER.
3.02 INTERFERING STRUCTURES
A. The CONTRACTOR shall take necessary precautions to prevent damage to existing
structures whether on the surface, aboveground, or underground. An attempt has been
made to show major structures on the Drawings. The completeness and accuracy cannot
be guaranteed, and it is presented simply as a guide to avoid known possible difficulties.
3.03 FIELD RELOCATION
A. During the progress of construction, it is expected that minor relocations of the work will
be necessary. Such relocations shall be made only by direction of the ENGINEER. If
existing structures are encountered that prevent the construction, and that are not properly
shown on the Drawings, notify the ENGINEER before continuing with the construction
in order that the ENGINEER may make such field revision as necessary to avoid conflict
with the existing structures. If the CONTRACTOR shall fail to so notify the ENGINEER
when an existing structure is encountered, and shall proceed with the construction despite
the interference, he shall do so at his own risk.
3.04 EASEMENTS
A. Where portions of the work are located on public or private property, easements and
permits will be obtained by the OWNER. Easements will provide for the use of the
property for construction purposes to the extent indicated on the easements. Copies of
these easements and permits are available upon request to the OWNER. It shall be the
CONTRACTOR's responsibility to determine the adequacy of the easement obtained in
every case and to abide by all requirements and provisions of the easement. The
CONTRACTOR shall confine his construction operations to within the easement limits
or make special arrangements with the property owners or appropriate public agency for
the additional area required. Any damage to property, either inside or outside the limits
of the easements provided by the OWNER, shall be the responsibility of the
CONTRACTOR as specified herein. The CONTRACTOR shall remove, protect, and
replace all fences or other items encountered on public or private property. Before final
payment will be authorized by the ENGINEER, the CONTRACTOR will be required to
furnish the OWNER with written releases from property owners or public agencies where
LPATH Berm Erosion 01710-4 Site Conditions
Protection Measures
side agreements or special easements have been made by the CONTRACTOR or where
the CONTRACTOR's operations, for any reason, have not been kept within the
construction right-of-way obtained by the OWNER.
B. It is anticipated that the required easements and permits will be obtained before
construction is started. However, should the procurement of any easement or permit be
delayed, the CONTRACTOR shall schedule and perform the work around these areas
until such a time as the easement or permit has been secured.
3.05 LAND MONUMENTS
A. The CONTRACTOR shall notify the ENGINEER of any existing Federal, State, City,
County, and private land monuments encountered. Private monuments shall be
preserved, or replaced by a licensed surveyor at the CONTRACTOR's expense. When
Government monuments are encountered, the CONTRACTOR shall notify the
ENGINEER at least two (2) weeks in advance of the proposed construction in order that
the ENGINEER will have ample opportunity to notify the proper authority and reference
these monuments for later replacement.
END OF SECTION
LPATH Berm Erosion 01715-1 Tree, Landscape, Vegetation,
Protection Measures and Wetland Protection
SECTION 01715
TREE, LANDSCAPE, VEGETATION, AND WETLAND PROTECTION
PART 1 GENERAL
1.01 SECTION INCLUDES
A. The work for this section consists of protecting existing trees, landscape, wetlands and
adjacent vegetation. The CONTRACTOR must take special care to avoid damaging
existing trees and vegetation in areas that do not need to be disturbed to complete
construction.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION
3.01 SUBMITTAL REQUIREMENTS
A. The CONTRACTOR shall submit a plan for on-site haul of materials prior to
construction. The plans shall include points of access to and from the site and shall show
a workable system of on-site haul routes that protect existing landscaped and wetland
areas. This plan shall be submitted to the ENGINEER for his review and comment prior
to the commencement of any work. The plan will be discussed with the CONTRACTOR
to insure protection of existing vegetation, but the ENGINEER shall not dictate haul
routes or construction methods to the CONTRACTOR. Note that the Natural Resources
Department may dictate haul routes within the city designated Natural area.
3.02 CONSTRUCTION REQUIREMENTS
A. Protected areas will be marked in the field, one time, by the OWNER and ENGINEER.
No access of construction vehicles or workers on foot is permitted through protected
areas. No material shall be stockpiled; no equipment shall be parked or repaired within
these areas.
B. Trees and vegetation to be saved that do not fall within the limits of protected areas shall
be marked one time in the field by the OWNER and ENGINEER. The CONTRACTOR
shall erect fencing if there is risk of damage caused by construction operations. Vehicular
and pedestrian traffic shall be limited to performing work in areas marked. Through
traffic, and stock piling of equipment and materials are not permitted within marked
areas.
C. No construction roads are to be created within the drop lines of any trees or other
vegetation designated to be saved without approval of the ENGINEER.
D. All trees which will be preserved, but are within the limits of construction, must be
protected from all damage associated with construction. A sturdy, physical barrier
(florescent orange in color) must be fixed in place around each tree for the duration of
construction. This barrier will be placed no closer than 6 feet from the trunk, or the drip
line, whichever is greater. The barrier itself must be fixed so it cannot be moved easily,
but the material can be flexible, such as orange snow fence attached to T-posts driven into
the ground, and must act as an effective deterrent to deliberate or accidental damage of
each tree. Actual materials and location of barrier must be approved by the OWNER’s
LPATH Berm Erosion 01715-2 Tree, Landscape, Vegetation,
Protection Measures and Wetland Protection
representatives (i.e. Utilities and City Forester) and ENGINEER.The cost of these tree
protection measures are to be borne solely by the CONTRACTOR.
E. The movement or storage of equipment, material, debris, or fill within these required
protective barriers is completely prohibited.
F. Any trees damaged during construction shall be immediately repaired by an approved tree
surgeon. Any tree judged by the ENGINEER to be damaged beyond repair shall be
removed at the CONTRACTOR’s expense. For each tree erroneously removed or
damaged beyond repair, an assessment shall be immediately withheld from the
CONTRACTOR’s progress payments. This assessment shall be equal to the value of the
tree prior to damage. This assessment shall be determined by a tree appraiser, selected by
the OWNER and paid for by the CONTRACTOR. The cost for hiring the appraiser shall
also be withheld from the CONTRACTOR’s progress payments.
In addition to the paying of the assessment, the CONTRACTOR shall replace each
damaged tree per OWNER’S standards for tree mitigation.
G. The CONTRACTOR shall pay an assessment if he disturbs any grasses, shrubs and/or
cattails located within the protected areas. The assessment shall not exceed one dollar
($1.00) per square foot of disturbance, and will be immediately withheld from the
CONTRACTOR’s progress payments.
In addition to the paying of the assessment, the damaged vegetation shall be replaced with
an equal value per square foot of damage. Replacements shall be planted in accordance
with the provisions outlined in these Specifications. Damaged wetland areas shall be
replaced and then seeded with a wetland seed mix in accordance with these Specifications
or as directed by the ENGINEER.
END OF SECTION
LPATH Berm Erosion 01720-1 Field Engineering
Protection Measures and Surveying
SECTION 01720
FIELD ENGINEERING AND SURVEYING
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Surveying:
1. The OWNER will provide construction surveying for the project. City
Survey Crews will perform the surveying required.
2. The CONTRACTOR must submit a survey request form to the City
Surveyors a minimum of 48 hours prior to needing surveying.
3. If the requested surveying cannot be accomplished in the time frame
requested by the CONTRACTOR, the survey personnel shall notify the
CONTRACTOR with the date on which the requested work will be
completed.
4. Should a sudden change in the CONTRACTOR’s operations or schedule
require the survey personnel to work overtime, the CONTRACTOR shall pay
the additional overtime expense.
5. The CONTRACTOR shall protect all survey monuments and construction
stakes. If it is unavoidable to remove a survey monument or construction
stakes, the CONTRACTOR is responsible for notifying the Surveyor and
allowing enough time for the monuments or stakes to be relocated. The
CONTRACTOR will be responsible for the cost of restaking construction
stakes and for the cost of reestablishing a destroyed monument.
6. The CONTRACTOR shall be responsible for transferring the information
from the construction staked to any necessary forms and for constructing all
pipelines, drainage ways, pavements, inlets, walls, and other structures in
accordance with the information on the stakes and grade sheets supplied by
the OWNER.
B. Supervision: The CONTRACTOR shall have supervision, knowledge of the project
requirements and proper installation, and construction procedures, available in the
field at all times that work is progressing.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
END OF SECTION
LPATH Berm Erosion 01720-2 Field Engineering
Protection Measures and Surveying
THIS PAGE INTENTIONALLY LEFT BLANK.
LPATH Berm Erosion 01745-1 Environmental Controls
Protection Measures
SECTION 01745
ENVIRONMENTAL CONTROLS
PART 1 GENERAL
1.01 SECTION INCLUDES
A. The work of this section consists of obtaining permits and providing environmental
controls consistent with regulatory permits through the duration of the work required
under this project.
PART 2 PRODUCTS
2.01 MATERIALS
A. Dust Control: Dust control agents may be necessary in addition to wetting down
with water. Dust control agents may be used only after prior approval by the
OWNER.
PART 3 EXECUTION
3.01 Dust Control Application:
A. The CONTRACTOR shall execute work by methods to minimize raising dust from
construction operations.
B. The CONTRACTOR shall provide and apply dust control at all times, including
evenings, holidays and weekends, as required to abate dust nuisance on and about the
site that is a direct result of construction activities. The use of non-approved
chemicals, oil, or similar palliatives will not be allowed. Dust control agents may be
used only after prior approval of the OWNER. The CONTRACTOR shall be
required to provide sufficient quantities of equipment and personnel for dust control
sufficient to prevent dust nuisance on and about the site.
C. The OWNER will have authority to order dust control work whenever in its opinion
it is required, and there shall be no additional cost to the OWNER. The
CONTRACTOR shall be expected to maintain dust control measures effectively
whether the OWNER or ENGINEER specifically orders such Work.
3.02 PRESERVATION OF NATURAL FEATURES
A. Confine operations as much as possible. Exercise special care to maintain natural
surroundings in an undamaged condition. Within the work limits, barricade trees,
rock outcroppings, and natural features to be preserved.
3.03 HOUSEKEEPING
A. Keep project neat, orderly, and in a safe condition at all times. Store and use
equipment, tools, and materials in a manner that does not present a hazard.
LPATH Berm Erosion 01745-2 Environmental Controls
Protection Measures
Immediately remove all rubbish. Do not allow rubbish to accumulate. Provide on-
site containers for collection of rubbish and dispose of it at frequent intervals during
progress of work.
3.04 DISPOSAL
A. Disposal of Waste (Unsuitable) Materials: All material determined by the
ENGINEER to be waste will be disposed of in approved landfill in a manner meeting
all regulations. Dispose of waste materials, legally, at public or private dumping
areas. Do not bury wastes inside of the limits of construction. All costs for dump
fees, permits, etc., to be borne by the CONTRACTOR.
B. Disposal of Garbage and Other Construction Materials: Provide sanitary
containers/dumpsters and haul away contents such that no overflow exists.
C. Excess excavation shall become the property of the CONTRACTOR and shall be
legally disposed of by him outside the limits of construction to an approved disposal
site. Excess excavated material suitable for backfill shall not be disposed of until all
backfill operations are complete.
D. The CONTRACTOR is to immediately inform ENGINEER of any hazardous
materials encountered during construction. Dispose of waste materials legally at
private or public facilities.
3.05 BURNING
A. No burning of debris will be permitted.
3.06 WATER CONTROL
A. The project work is located within a natural drainage course is subject to periodic
flooding due to rainfall and snowmelt, flows for adjacent developed areas and storm
water pipes and ground water flows from saturated soils or other ground water
sources. Refer to Section 02240 for Water Control and Dewatering requirements.
3.07 NOISE CONTROL
A. All mechanical equipment shall be equipped with the best available mufflers to
reduce noise. The CONTRACTOR shall be responsible for obtaining any necessary
permits and shall limit noise to the permitted levels. Noise level monitoring shall be
performed by the CONTRACTOR as necessary to show that the permitted levels are
not being exceeded.
3.08 PERMITS
A. All work must be performed in accordance with all applicable regulatory permits.
It shall be the responsibility of the CONTRACTOR to obtain a Groundwater
Discharge (402) Permit from the Colorado Department of Public Health and
Environment for any dewatering operations that will be discharged into any
LPATH Berm Erosion 01745-3 Environmental Controls
Protection Measures
drainageways, open channels, or irrigation ditches. The CONTRACTOR shall be
responsible for any testing required under the 402 Permit.
It shall also be the responsibility of the CONTRACTOR to apply for and obtain a
State of Colorado Stormwater Discharge Permit. All costs for this permit shall be the
responsibility of the CONTRACTOR.
B. The OWNER will obtain the following permits:
• (None)
C. It shall be the responsibility of the CONTRACTOR to prepare and obtain an
approved Erosion and Sediment Control Plan from the OWNER. The
CONTRACTOR must obtain all other applicable permits.
END OF SECTION
LPATH Berm Erosion 01745-4 Environmental Controls
Protection Measures
THIS PAGE INTENTIONALLY LEFT BLANK.
LPATH Berm Erosion 01780-1 Contract Closeout
Protection Measures
SECTION 01780
CONTRACT CLOSEOUT
PART 1 GENERAL
1.01 SECTION INCLUDES
A. The following project closeout procedure defines the responsibilities of the
CONTRACTOR, OWNER, and ENGINEER in closing the project:
Step 1: CONTRACTOR advises the ENGINEER in writing that he has reached
"Substantial Completion" and provides a list of items to be completed or corrected.
Closeout may be conducted by areas or portions of the work if requested by the
OWNER.
Step 2: ENGINEER inspects the work to determine if it is substantially complete,
and issues a Certificate of Substantial Completion plus a "Punch List" of items to be
completed or corrected.
Substantial Completion - Definition
1. Reference General Conditions, Substantial Completion
Step 3: CONTRACTOR completes and/or corrects all punch list items and notifies
the ENGINEER in writing that his work is ready for final inspection. At this time, a
final application for payment is submitted.
Step 4: ENGINEER makes final inspection. When the work is found to be
acceptable under the Contract Documents, and the Contract fully performed, the
ENGINEER will issue a final Certificate for Payment.
B. Final Paperwork:
Prior to Final Payment and Acceptance, the CONTRACTOR shall deliver the
following items to the ENGINEER:
1. CONTRACTOR's Two-Year Correction Period.
2. All Guarantees, Warranties and Submittals, as specified.
3. Receipts for Extra Materials Delivered to the OWNER.
4. Final Application for Payment.
5. Consent of Surety to Final Payment.
6. CONTRACTOR's Affidavit of Release of Liens.
7. Releases from Property Owners for Special Easements.
8. Project Record Documents.
LPATH Berm Erosion 01780-2 Contract Closeout
Protection Measures
9. Red-lined as-built drawings (a.k.a. “Drawings of Record” or “Record
Drawings”).
C. Definition for Substantial Completion
1. All of the following work must be completed:
a. North and South spills completed including concrete sills, concrete
block revetment mats, and backfilling.
b. All cut/fill work along the top of the berm at both spill locations
completed.
c. All final grading completed at the borrow sites.
d. All buried riprap in place, and all ground preparation completed.
D. Definition for Final Completion
1. All Work must be complete for Final Completion.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
END OF SECTION
LPATH Berm Erosion
Protection Measures
DIVISION 2 – SITE WORK
SECTION 02230 CLEARING AND GRUBBING
SECTION 02235 NATIVE SOIL
SECTION 02236 TOPSOIL
SECTION 02240 WATER CONTROL AND DEWATERING
SECTION 02315 EXCAVATION AND EMBANKMENT
SECTION 02370 EROSION AND SEDIMENT CONTROL
SECTION 02371 GEOTEXTILE FABRIC FOR CONCRETE
BLOCK REVETMENT
SECTION 02375 RIPRAP
SECTION 02376 CONCRETE RUBBLE
SECTION 02700 CONCRETE BLOCK REVETMENT SYSTEM
SPECIFICATIONS FOR OVERTOPPING
APPLICATIONS
SECTION 02921 GROUND PREPARATION FOR SEEDING
LPATH Berm Erosion 02230-1 Clearing and Grubbing
Protection Measures
SECTION 02230
CLEARING AND GRUBBING
PART 1 GENERAL
1.01 SECTION INCLUDES
A. This work consists of clearing, grubbing, removing, and disposing of vegetation and
debris within the limits of the project site as shown on the Drawings and as required
by the Work. Vegetation and objects designated to remain shall be preserved free
from injury or defacement.
1.02 RELATED SECTIONS
A. Section 02315 - Excavation and Embankment
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION
3.01 CONSTRUCTION REQUIREMENTS
A. The OWNER will designate all trees, shrubs, plants, and other objects to remain.
Any object that is designated to remain and is damaged shall be repaired or replaced
as directed by the OWNER, at the CONTRACTOR’s expense.
Clearing and grubbing shall extend to the toe of fill or the top of cut slopes, unless
otherwise designated. All surface objects, trees, stumps, roots, and other protruding
obstructions not designated to remain shall be cleared and grubbed, including
mowing, as required. Undisturbed stumps, roots, and nonperishable solid objects
located two feet or more below subgrade or embankment slope may remain in place.
In areas to be rounded at the tops of backslopes, stumps shall be removed to at least
two feet below the surface of the final slope line.
Except in areas to be excavated, all holes resulting from the removal of obstructions
shall be backfilled with suitable material and compacted in accordance with Section
02315.
No material or debris shall be disposed of within the project limits.
All cleared timber shall be removed from the project and shall become the property
of the CONTRACTOR. All trimming shall be done in accordance with good tree
surgery practices. The maximum tree diameter included for removal in this section
shall be 12 inches.
The CONTRACTOR shall scalp the areas within the excavation or embankment
grading limits. Scalping shall include the removal from the ground surface of
sawdust, and other vegetation matter.
END OF SECTION
LPATH Berm Erosion 02230-2 Clearing and Grubbing
Protection Measures
THIS PAGE INTENTIONALLY LEFT BLANK.
LPATH Berm Erosion 02235-1 Native Soil
Protection Measures
SECTION 02235
NATIVE SOIL
PART 1 GENERAL
1.01 SECTION INCLUDES
A. This work consists of stripping, salvaging and stockpiling native soil, and excavating
suitable native soil from stockpiles, contractor sources, available sources, or from the
approved natural ground cover to place on designated areas. It shall include the placing
of native soil upon constructed cut and fill slopes after grading operations are
completed.
1.02 RELATED SECTIONS
A. Section 02230 – Clearing and Grubbing
B. Section 02315 – Excavation and Embankment
PART 2 PRODUCTS
2.01 MATERIALS
A. Native soil shall consist of loose friable loam free of subsoil, refuse, stumps, roots,
rocks, brush, weeds, heavy clay, hard clods, toxic substances, or other material which
would be detrimental to its use on the project. Native soil shall consist of natural on-
site ground cover or hauled material from off-site sources.
Wetland native soil material shall consist of moist organic soil, including any existing
wetland vegetation and seeds, to be excavated from areas as directed by the
ENGINEER or OWNER.
PART 3 EXECUTION
3.01 CONSTRUCTION REQUIREMENTS
A. Native soil within the limits of the project shall be salvaged prior to beginning hauling,
excavating, or fill operations by excavating and stockpiling the material at designated
locations in a manner that will minimize sediment damage, and not obstruct natural
drainage. Native soil shall be placed directly upon completed cut and fill slopes
whenever conditions and the progress of construction will permit.
B. No soil stockpile shall exceed ten (10) feet in height. All soil stockpiles shall be
protected from sediment transport by surface roughening, watering, and perimeter silt
fencing. Any soil stockpile remaining after 30 days shall be seeded and mulched.
C. Native soil shall be placed at locations and to the thickness provided in the Contract
Documents and shall be keyed to the underlying material by the use of harrows, rollers,
or other suitable equipment.
LPATH Berm Erosion 02235-2 Native Soil
Protection Measures
D. Water shall be applied to the native soil as designated in the Contract Documents, in a
fine spray by nozzles or spray bars so the native soil areas will not be washed or
eroded.
E. Salvaged native soil exceeding the quantity required under the Contract shall be
disposed of at the CONTRACTOR’s expense.
F. Wetland native soil material shall be excavated from designated areas to a minimum
depth of 18 inches, or as otherwise designated. The CONTRACTOR shall prepare the
relocation site to elevations specified and approved by the ENGINEER prior to
excavating the wetlands. If the ENGINEER determines that this is not possible, then
the CONTRACTOR shall stockpile the material in an approved area, to remain
undisturbed until the relocation site has been prepared. Storage time within the
stockpile shall be as short as possible. If deemed necessary by the ENGINEER, the
stockpile will be protected in such a manner to preserve the wetland seed bank.
Wetland native soil material shall be placed over the prepared relocation areas to a
depth of 18 inches, or as otherwise designated.
END OF SECTION
LPATH Berm Erosion 02236-1 Topsoil
Protection Measures
SECTION 02236
TOPSOIL
PART 1 GENERAL
1.01 SECTION INCLUDES
A. This work consists of delivering topsoil to the site. It shall include the placing of topsoil
in approved stockpiles.
1.02 RELATED SECTIONS
A. Section 02230 – Clearing and Grubbing
B. Section 02315 – Excavation and Embankment
PART 2 PRODUCTS
2.01 MATERIALS
A. Topsoil shall consist of loose friable loam free of subsoil, refuse, stumps, roots, rocks,
brush, weeds, heavy clay, hard clods, toxic substances, or other material which would
be detrimental to its use on the project. Topsoil shall consist of hauled material from
off-site sources.
PART 3 EXECUTION
3.01 CONSTRUCTION REQUIREMENTS
A. Topsoil shall be delivered to the site and place in approved stockpile locations.
B. No soil stockpile shall exceed ten (10) feet in height. All soil stockpiles shall be
protected from sediment transport by surface roughening, watering, and perimeter silt
fencing. Any soil stockpile remaining after 30 days shall be seeded and mulched.
END OF SECTION
LPATH Berm Erosion 02236-2 Topsoil
Protection Measures
THIS PAGE INTENTIONALLY LEFT BLANK.
LPATH Berm Erosion 02240-1 Water Control and Dewatering
Protection Measures
SECTION 02240
WATER CONTROL AND DEWATERING
PART 1 GENERAL
1.01 SECTION INCLUDES
A. The work of this section consists of controlling groundwater, site drainage, and storm
flows during construction. The CONTRACTOR is cautioned that the work involves
construction in and around drainage channels, local streams or rivers, and areas of local
drainage. These areas are subject to frequent periodic inundation.
1.02 RELATED SECTIONS
A. Section 02315 – Excavation and Embankments
PART 2 PRODUCTS
2.01 MATERIALS
A. On-site materials may be used within the limits of construction to construct temporary
dams and berms. The materials such as plastic sheeting, sand bags, and storm sewer
pipe may also be used if desired by the CONTRACTOR.
PART 3 EXECUTION
3.01 CONSTRUCTION REQUIREMENTS
A. General: For all excavation, the CONTRACTOR shall provide suitable equipment and
labor to remove water, and he shall keep the excavation dewatered so that construction
can be carried on under dewatered conditions where required by the Drawings and
Specifications. Water control shall be accomplished such that no damage is done to
adjacent channel banks or structures. The CONTRACTOR is responsible for
investigating and familiarizing himself with all site conditions that may affect the work
including surface water, level of groundwater and the time of year the work is to be
done. All excavations made as part of dewatering operations shall be backfilled with
the same type material as was removed and compacted to 95% of Maximum Standard
Proctor Density (ASTM D698) except where replacement by other materials and/or
methods are required. The cost for this excavation and backfilling shall be included in
the Construction Dewatering bid item.
The CONTRACTOR shall conduct his operation in such a manner that storm or other
waters may proceed uninterrupted along their existing drainage courses. By submitting
a bid, the CONTRACTOR acknowledges that he has investigated the risk arising from
such waters and has prepared his bid accordingly, and assumes all of said risk.
At no time during construction shall the CONTRACTOR affect existing surface or
subsurface drainage patterns of adjacent property. Any damage to adjacent property
resulting from the CONTRACTOR’s alteration of surface or subsurface drainage
patterns shall be repaired by the CONTRACTOR at no additional cost to the OWNER.
CONTRACTOR shall remove all temporary water control facilities when they are no
longer needed or at the completion of the project.
LPATH Berm Erosion 02240-2 Water Control and Dewatering
Protection Measures
Pumps and generators used for dewatering and water control shall be quiet equipment
enclosed in sound deadening devices.
B. Surface Water Control: Surface water control generally falls in to the following
categories:
1. Normal low flows along the channel;
2. Storm/flood flows along the channel;
3. Flows from existing storm drain pipelines; and,
4. Local surface inflows not conveyed by pipelines.
The CONTRACTOR shall coordinate, evaluate, design, construct, and maintain
temporary water conveyance systems. These systems shall not worsen flooding, alter
major flow paths, or worsen flow characteristics during construction. The
CONTRACTOR is responsible to ensure that any such worsening of flooding does
not occur. The CONTRACTOR is solely responsible for determining the methods
and adequacy of water control measures.
At a minimum, the CONTRACTOR will be responsible for diverting the quantity of
surface flow around the construction area so that the excavations will remain free of
surface water for the time it takes to install these materials, and the time required for
curing of any concrete or grout. The CONTRACTOR is cautioned that the minimum
quantity of water to be diverted is for erosion control and construction purposes and
not for general protection of the construction-site. It shall be the CONTRACTOR's
responsibility to determine the quantity of water which shall be diverted to protect his
work from damage caused by storm water.
The CONTRACTOR shall, at all times, maintain a flow path for all channels.
Temporary structures such as berms, sandbags, pipeline diversions, etc., may be
permitted for the control of channel flow, as long as such measures are not a major
obstruction to flood flows, do not worsen flooding, or alter historic flow routes.
C. Groundwater Control: The CONTRACTOR shall install adequate measures to
maintain the level of groundwater below the foundation subgrade elevation and
maintain sufficient bearing capacity for all structures, pipelines, earthwork, and rock
work. Such measures may include, but are not limited to, installation of perimeter
subdrains, pumping from drilled holes or by pumping from sumps excavated below
the subgrade elevation. The foundation bearing surfaces are to be kept dewatered
and stable until the structures or other types of work are complete and backfilled.
Disturbance of foundation subgrade by CONTRACTOR operations shall not be
considered as originally unsuitable foundation subgrade and shall be repaired at
CONTRACTOR’s expense.
Any temporary dewatering trenches or well points shall be restored following
dewatering operations to reduce permeability in those areas as approved by the
ENGINEER.
CONTRACTOR is to restore any areas disturbed by the dewatering operations to
their original condition.
LPATH Berm Erosion 02240-3 Water Control and Dewatering
Protection Measures
D. Contaminated Groundwater Control: CONTRACTOR shall not discharge
contaminated water exceeding local, State and/or Federal limits to above ground
channels or watercourses.
END OF SECTION
LPATH Berm Erosion 02240-4 Water Control and Dewatering
Protection Measures
THIS PAGE INTENTIONALLY LEFT BLANK.
LPATH Berm Erosion 02315-1 Excavation and Embankment
Protection Measures
SECTION 02315
EXCAVATION AND EMBANKMENT
PART 1 GENERAL
1.01 SECTION INCLUDES
A. This work shall consist of excavation, embankment fill, disposal of excess material,
shaping, and compaction of all material encountered within the limits of work,
including excavation and backfill for structures. The excavation shall include, but is
not limited to, the native soils which must be excavated for the project work. All work
shall be completed in accordance with these Specifications and the lines and grades on
the Drawings.
1.02 DEFINITIONS
A. Unclassified Excavation shall consist of the excavation of all materials on site to final
grades, excluding the bid items included in Section 02220. Excavation of unsuitable
material will only be paid for if it is found to be unsuitable in its original state.
B. Muck Excavation shall consist of the removal and disposal of mixtures of soils and
organic matter not suitable for foundation material and replacement with approved
material. Material damaged due to rain or weather will not be paid for as Muck
excavation and is entirely the responsibility of the CONTRACTOR.
C. Rock Excavation shall consist of igneous, metamorphic and sedimentary rock which
cannot be excavated without the use of rippers, and all boulders or other detached
stones each having a volume of 1/2 cubic yard or more, as determined by physical or
visual measurement. It shall also include replacement with approved material as
required.
D. Embankment (Complete in Place): shall consist of placing all excavated material,
except material being hauled and disposed, as embankment and compacted to final
grades as specified in the Contract Documents and on the Drawings.
1.03 DESCRIPTION
A. This work shall consist of excavation, disposal, placement, and compaction of all
material encountered within the limits of the work, and not being completed under
some other item, necessary for the construction of the project in accordance with the
Specifications and the lines, grades, and typical cross-sections shown on the
Drawings. All excavation will be classified, “unclassified excavation”, or “muck
excavation” or “rock excavation”, as hereafter described. All embankment will be
classified “embankment material” as hereafter described.
1.04 RELATED SECTIONS
A. Section 02230 – Clearing and Grubbing
B. Section 02240 – Water Control and Dewatering
LPATH Berm Erosion 02315-2 Excavation and Embankment
Protection Measures
1.05 QUALITY ASSURANCE
A. Final topography and/or cross-sections will be surveyed of areas that are to finished
grade and compared to the design section for accuracy. Final grade shall match
design grades within the tolerances discussed in PART 3 EXECUTION.
PART 2 PRODUCTS
2.01 MATERIALS
A. Embankment material may consist of approved material acquired from excavations
or material hauled from outside the project limits. Suitable material identified on-site
shall be used first for embankments and backfill. Excess excavated native soils which
are not used as embankment or backfill shall become the property of the
CONTRACTOR and shall be disposed of off-site by the CONTRACTOR, in a
location acceptable to the ENGINEER.
B. Muck excavation encountered in all areas shall also include the replacement of
excavated muck with uniformly graded rock, riprap, on-site or imported soils, or
other material whichever is most suitable for the specific situation encountered. The
ENGINEER will determine which type of aggregate or other material which shall be
used after observing the specific site conditions.
PART 3 EXECUTION
3.01 GENERAL EXCAVATION/EMBANKMENT
A. General: The excavation and embankment for the project work shall be finished to
reasonably smooth and uniform surfaces. Variation from the subgrade plane shall not
be more than .08 feet in soil or more than .08 feet above or .50 below in rock. Where
bituminous or concrete surfacing materials are to be placed directly on the subgrade,
the subgrade plane shall not vary more than 0.04 feet. Materials shall not be wasted
without permission of the ENGINEER. Excavation operations shall be conducted so
that material outside of the limits of slopes will not be disturbed. Prior to beginning
grading operations in any area, all necessary clearing and grubbing in that area shall
have been performed in accordance with Section 02230 of these Specifications.
When the CONTRACTOR’s excavating operations encounter remains of pre-historic
people’s dwelling sites or artifacts of historical or archaeological significance, the
operations, shall be temporarily discontinued. The ENGINEER will contact
archaeological authorities to determine the disposition thereof. When directed, the
CONTRACTOR shall excavate the site in such a manner as to preserve the artifacts
encountered and shall remove them for delivery to the custody of the proper state
authorities. Such excavation will be considered and paid for as extra work.
B. Excavation:
1. Unclassified: All excess suitable material excavated from the project site
and not used for embankment shall be removed from the project site and
become the property of the CONTRACTOR. Where material encountered
LPATH Berm Erosion 02315-3 Excavation and Embankment
Protection Measures
within the limit of the work is considered unsuitable for embankment (fills)
on any portion of this project work, such material shall be excavated as
directed by the ENGINEER and replaced with suitable fill material. All
unsuitable excavated material from excavation consisting of any type of
debris (surface or buried), excavated rock, bedrock or rocks larger than 6
inches in diameter and boulders shall be hauled from the project site and
disposed of. Debris is defined as “anything that is not earth which exists at
the job site”.
2 . Muck: Where excavation to the finished grade section results in a subgrade
or slopes of unsuitable soil, the ENGINEER may require the
CONTRACTOR to remove the unsuitable materials and backfill to the
finished graded section with approved material. Disposal of the material
shall be at the CONTRACTOR’s expense.
Good surface drainage shall be provided around all permanent cuts to direct
surface runoff away from the cut face.
3. Rock: Unless otherwise specified, rock shall be excavated to a minimum
depth of 0.5 feet below subgrade within the limits of the channel area, and
the excavation shall be backfilled with material shown on the Drawings or as
designated by the ENGINEER. Disposal of material and replacement with
suitable approved material shall be at the CONTRACTOR’s expense.
C. Embankment Construction: Embankment construction shall consist of constructing
all fill areas, including preparation of the areas upon which they are to be placed, and
the placing and compacting of embankment material in holes, pits and other
depressions within the project area. Only approved materials shall be used in the
construction of embankments and backfills.
Approved materials shall consist of clean on-site cohesive soils or approved imported
soils. On-site cohesive soils are suitable for use as compacted fill provided the
following recommendations are met:
Percent Finer by Weight
Gradation (ASTM C136)
½-Inch 100
3/8-Inch 70 – 100
No. 4 Sieve 50 – 100
No. 200 Sieve 60 (min)
• Liquid Limit 35 (max)
• Plasticity Index 20 (max)
• In-Situ Coefficient of Permeability 1x10-6 cm/sec
Excavation and Embankment will only be paid when a significant change in grade is
required, as determined by the ENGINEER. Minor cuts and fills will be considered
incidental to the work, and will not be paid for separately under this section.
LPATH Berm Erosion 02315-4 Excavation and Embankment
Protection Measures
On-site cohesive soils or imported soils should be placed and compacted in
horizontal lifts, using equipment and procedures that will produce recommended
moisture contents and densities throughout the lift and embankment height. On-site
or imported cohesive soils should be compacted within a moisture content range of
2% below, to 2% above optimum moisture content and compacted to 95% of the
Maximum Standard Proctor Density (ASTM D698).
When embankment is to be placed and compacted on hillsides, or when new
embankment is to be compacted against existing embankments, or when embankment
is built 1/2 width at a time, the slopes that are steeper than 4:1 when measured
longitudinally or at right angles to the adjacent ground shall be continuously benched
over those areas where it is required as the work is brought up in layers. Benching
shall be well keyed and where practical a minimum of 8 feet. Each horizontal cut
shall begin at the intersection of the original ground and the vertical sides of the
previous cuts. Material thus cut out shall be recompacted along with the new
embankment material at the CONTRACTOR’s expense.
The ground surface underlying all fills shall be carefully prepared by removing all
organic matter, scarification to a depth of 8 inches and recompacting to 95% of the
Maximum Standard Proctor Density (ASTM D698) at optimum moisture content +
or - 2% prior to fill placement.
Embankment material shall be placed in horizontal layers not exceeding 8 inches
(loose measurement) and shall be compacted to 95% of the Maximum Standard
Proctor Density (ASTM D698) at optimum moisture content + or - 2%. Effective
spreading equipment shall be used on each lift to obtain uniform thickness prior to
compacting. As the compaction of each layer progresses, continuous leveling and
manipulating will be required to assure uniform density.
For embankments which serve as berms, the downstream portion shall be “keyed”
into the subsurface soils a minimum of 3 feet to enhance the stability of the slope.
Materials which are removed from excavations beneath the water table may be over
the optimum moisture content and will require that they be dried out prior to reusing
them.
Cross hauling or other action as appropriate will be ordered when necessary to insure
that the best available material is placed in critical areas of embankments, including
the top 2 feet of all embankments. No additional payment will be made for cross
hauling ordered by the ENGINEER.
Frozen materials shall not be used in construction of embankments.
During the construction of channels, the channel bottom shall be maintained in such
condition that it will be well drained at all times.
Excavation or Embankment (Fill), and Structural Backfill work either completed or
in a stage of completion that is either eroded or washed away or becomes unstable
due to either rains, snow, snow melt, channel flows or lack of proper water control
shall be either removed and replaced, recompacted or reshaped as directed by the
LPATH Berm Erosion 02315-5 Excavation and Embankment
Protection Measures
ENGINEER and in accordance with the Drawings and Specifications at the
CONTRACTOR’s sole expense. Removed unsuitable materials shall be hauled away
and disposed of at the CONTRACTOR’s expense. Placing of replacement materials
for removed unsuitable materials shall be purchased, placed and compacted at the
CONTRACTOR’ expense.
D. Proof rolling with a heavy rubber tired roller will be required, if designated on the
Drawings or when ordered by the ENGINEER. Proof rolling shall be done after
specified compaction has been obtained. Areas found to be weak and those areas
which failed shall be ripped, scarified, wetted if necessary, and recompacted to the
requirements for density and moisture at the CONTRACTOR’s expense.
Proof rolling shall be done with equipment and in a manner acceptable to the
ENGINEER. Proof rolling as shown on the Drawings or as ordered by the
ENGINEER shall not be measured and paid for separately, but shall be included in
the unit prices bid for the work.
3.02 EXCAVATION AND BACKFILL FOR STRUCTURES
A. Poor foundation material for any of the work shall be removed, by the
CONTRACTOR, as directed by the ENGINEER. The CONTRACTOR will be
compensated for removal and replacement of such materials in accordance with
Muck Excavation.
The CONTRACTOR is cautioned that construction equipment may cause the natural
soils to pump or deform while performing excavation work inside and on footings,
structural floor slabs, or other structure foundation areas.
Foundation materials which are: a) saturated by either surface or subsurface flows
due to the lack of adequate water control or dewatering work by the
CONTRACTOR; b) frozen for any reason; or, c) that are disturbed by the
CONTRACTOR’s work or caused to become unacceptable for foundation material
purposes by means of the CONTRACTOR’s equipment, manpower, or methods of
work shall be removed and replaced by the CONTRACTOR at his expense.
Dewatering should not be conducted by pumping from inside footing, structural floor
slab, or other structure foundation limits. This may decrease the supporting capacity
of the soils.
Care should be taken when excavating the foundations to avoid disturbing the
supporting materials. Excavation by either hand or careful backhoe soil removal,
may be required in excavating the last few inches of material to obtain the subgrade
of any item of the concrete work.
Any over-excavated subgrades that are due to the CONTRACTOR’s actions, shall be
brought back to subgrade elevations by the CONTRACTOR and at his expense in the
following manner:
LPATH Berm Erosion 02315-6 Excavation and Embankment
Protection Measures
1. For over-excavations of 2 inches or less, either: Backfill and compact with
an approved granular materials; backfill with 1/2 inch crushed rock; or fill
within concrete at the time of the appurtenant structure concrete pour.
2. For over-excavations greater than 2 inches, backfill and compact with an
approved granular material.
All granular footings, structural floor slabs, or other structure areas shall be
compacted with a vibratory plate compactor prior to placement of concrete,
reinforcing, or bedding materials.
B. Backfill, and fill within 2 feet of and adjacent to all structures and for full height of
the walls, shall be selected non-swelling material. It shall be granular, well graded,
and free from stones larger than 3 inches. Material may be job excavated, but
selectivity will be required as determined by the ENGINEER. Refer to the Drawings
for job specific requirements. Stockpiled material, other than topsoil from the
excavation shall be used for backfilling unless an impervious structural backfill is
specified. The backfill material shall consist of either clean on-site granular materials
free of stones larger than 3 inches in diameter with no more than 20% passing the No.
200 sieve, or equivalent imported materials. All backfill around the structures shall
be consolidated by mechanical tamping. The material shall be placed in 8-inch loose
lifts within a range of 2% above to 2% below the optimum moisture content and
compacted to 95% of Maximum Standard Proctor Density (ASTM D698) for
cohesive soils, or to 70% relative density for pervious material as determined by the
relative density of cohesionless soils test, ASTM D4253.
When specified on the Drawings or as required by the ENGINEER, Class I structural
backfill shall meet the following gradation requirements:
% by Weight Passing
Sieve Size Square Mesh Sieves
2-Inch 100
No. 4 30 - 100
No. 50 10 – 60
No. 200 5 – 20
In addition, this material shall have a liquid limit not exceeding 35 and a plasticity
index of not over 6.
END OF SECTION
LPATH Berm Erosion 02370-1 Erosion and Sediment Control
Protection Measures
SECTION 02370
EROSION AND SEDIMENT CONTROL
PART 1 GENERAL
1.01 SECTION INCLUDES
A. This work shall consist of temporary measures needed to control erosion and water
pollution. These temporary measures shall include, but not be limited to, berms,
dikes, dams, sediment basins, fiber mats, netting, gravel, mulches, grasses, slope
drains and other erosion control devices or methods. These temporary measures shall
be installed at the locations where needed to control erosion and water pollution
during the construction of the project, and as directed by the ENGINEER, and as
shown on the Drawings.
B. The erosion control measures presented in the Drawings serves as a minimum for the
requirements of erosion control during construction. The CONTRACTOR has the
ultimate responsibility for providing adequate erosion control and water quality
throughout the duration of the project. Therefore, if the provided plan is not working
sufficiently to protect the project areas, then the CONTRACTOR shall provide
additional measures as required to obtain the required protection. The
CONTRACTOR shall include in his bid price for erosion control a minimum of all
items shown on the Erosion Control Plan and any additional items that may be
needed to control erosion and water pollution.
1.02 RELATED SECTIONS
A. Section 02240 – Water Control and Dewatering
1.03 SUBMITTALS
A. Construction schedule for Erosion Control per subsection 3.01
B. Sequencing Plan per subsection 3.12
PART 2 PRODUCTS
2.01 MATERIALS
A. Materials may include hay bales, straw, fiber mats, fiber netting, wood cellulose,
fiber fabric, gravel and other suitable materials, and shall be reasonably clean, free of
deleterious materials, and certified weed free. All materials shall be submitted for
approval prior to installation.
B. Temporary grass cover (if required) shall be a quick growing species suitable to the
area, which will provide temporary cover and will not later compete with the grasses
sown for permanent cover. All grass seed shall be approved by the ENGINEER prior
to installation.
C. Fertilizer and soil conditioners shall be approved by the ENGINEER prior to
installation.
LPATH Berm Erosion 02370-2 Erosion and Sediment Control
Protection Measures
PART 3 EXECUTION
3.01 CONSTRUCTION REQUIREMENTS
A. When so indicated in the Contract Documents, or when directed by the ENGINEER,
the CONTRACTOR shall prepare construction schedules for accomplishing
temporary erosion control work. These schedules shall be applicable to clearing and
grubbing, grading, structural work, construction, etc. He shall also submit for
acceptance his proposed method of erosion control on haul roads and borrow pits and
his plan for disposal of waste material. Work shall not be started until the erosion
control schedules and methods of operations have been accepted.
B. The CONTRACTOR will be required to incorporate all permanent erosion control
features into the project at the earliest practicable time as outlined in his accepted
schedule. Temporary erosion control measures will then be used to correct
conditions that develop during construction.
C. The erosion control features installed by the CONTRACTOR shall be adequately
maintained by him until the project is accepted.
D. In the event of conflict between these requirements and erosion and pollution control
laws, rules, or regulations of other Federal, State or local agencies, the more
restrictive laws, rules, or regulations shall apply.
3.02 PERMITS AND COMPLIANCE
A. The CONTRACTOR must apply for and obtain a Construction Dewatering Permit
402 from the Colorado Department of Public Health and Environment. All costs for
this permit shall be the responsibility of the CONTRACTOR. This permit requires
that specific actions be performed at designated times. The CONTRACTOR is
legally obligated to comply with all terms and conditions of the permit including
testing for effluent limitations.
The CONTRACTOR shall allow the Colorado Department of Public Health and
Environment or other representatives to enter the site to test for compliance with the
permit. Non compliance with the permit can result in stoppage of all work.
The CONTRACTOR must apply for and obtain a State of Colorado Stormwater
Discharge Permit. All costs for this permit shall be the responsibility of the
CONTRACTOR. This permit requires that specific actions be performed at
designated times. The CONTRACTOR is legally obligated to comply with all terms
and conditions of the permit. Non compliance with the permit can result in stoppage
of all work.
In addition to permit requirements, the OWNER shall also monitor the
CONTRACTOR’s erosion control and work methods. If the overall function and
intent of erosion control is not being met, then the OWNER shall require the
CONTRACTOR to provide additional measures as required to obtain the desired
results. Costs for any additional erosion control measures shall be the responsibility
of the CONTRACTOR, since he has the ultimate responsibility for providing
adequate erosion control and water quality for the duration of the project.
LPATH Berm Erosion 02370-3 Erosion and Sediment Control
Protection Measures
3.03 STABILIZATION OF DISTURBED AREAS
A. Temporary sediment control measures shall be established within 5 days from time of
exposure/disturbance. Permanent erosion protection measures shall be established
within 5 days after final grading of areas.
3.04 PROTECTION OF ADJACENT PROPERTIES
A. Properties adjacent to the site of a land disturbance shall be protected from sediment
deposition. In addition to the erosion control measures required on the Drawings,
perimeter controls may be required if damage to adjacent properties is likely.
Perimeter controls include, but are not limited to, a vegetated buffer strip around the
lower perimeter of the land disturbance, sediment barriers such as straw bales and silt
fences; sediment basins; or a combination of such measures. Vegetated buffer strips
may be used only where runoff in sheet flow is expected and should be at least 20
feet in width.
3.05 TIMING AND STABILIZATION OF SEDMENT AND EROSION CONTROL
MEASURES
A. Sediment barriers, perimeter dikes, and other measures intended to either trap
sediment or prevent runoff from flowing over disturbed areas must be constructed as
a first step in grading and be made functional before land disturbance takes place.
Earthen structures such as dams, dikes, and diversions must be stabilized within 5
days of installation. Stormwater outlets must also be stabilized prior to any upstream
land disturbing activities.
3.06 STABILIZATION OF WATERWAYS AND OUTLETS
A. All on-site stormwater conveyance channels used by the CONTRACTOR for
temporary erosion control purposes shall be designed and constructed with adequate
capacity and protection to prevent erosion during storm and runoff events.
Stabilization adequate to prevent erosion shall also be provided at the outlets of all
pipes and channels.
3.07 STORM SEWER INLET PROTECTION
A. All storm sewer inlets which are made operable during construction or which drain
stormwater runoff from a construction site shall be protected from sediment
deposition by the use of filters.
3.08 WORKING IN OR CROSSING WATERCOURSES AND WETLANDS
A. Construction vehicles should be kept out of watercourses to the extent possible.
Where in-channel work is necessary, precautions must be taken to stabilize the work
area during construction to minimize erosion. The channel (including bed and banks)
must always be restabilized immediately after in-channel work is completed.
B. Where a live (wet) watercourse must be crossed by construction vehicles during
construction, a temporary crossing must be provided for this purpose. If the crossing
involves a pipe or other type of conduit placed in the watercourse, the pipe shall be
sized to allow unrestricted passage of all flows anticipated to be carried by the
LPATH Berm Erosion 02370-4 Erosion and Sediment Control
Protection Measures
watercourse. Likewise, installation of a span-type crossing across the watercourse
shall be placed so no restriction of anticipated flows occur.
3.09 CONSTRUCTION ACCESS ROUTES
A. Wherever construction vehicles enter or leave a construction site, a stabilized
construction entrance and Tracking Pad are required. Where sediment is transported
onto a public road surface, the roads shall be cleaned thoroughly at the end of each
day. Sediment shall be removed from roads by shoveling or sweeping and be
transported to a sediment controlled disposal area. Street washing shall be allowed
only after sediment is removed in this manner.
3.10 DISPOSITION OF TEMPORARY MEASURES
A. All temporary erosion and sediment control measures shall be disposed of within 30
days after final site stabilization is achieved or after the temporary measures are no
longer needed as determined by the OWNER. Trapped sediment and other disturbed
soil areas resulting from the disposition of temporary measures shall be permanently
stabilized to prevent further erosion.
3.11 MAINTENANCE
A. All temporary and permanent erosion and sediment control practices must be
maintained and repaired as needed to assure continued performance of their intended
function.
3.12 SEQUENCING
A. The CONTRACTOR shall submit a sequencing plan for approval for erosion control
in conformance with his overall Construction Plan for approval by the OWNER.
Changes to the Erosion Control Sequencing Plan may be considered by the OWNER
only if presented in writing by the CONTRACTOR.
3.13 SUBSTANTIAL COMPLETION OF EROSION CONTROL MEASURES
A. At the time specified in the Contract Documents, and subject to compliance with
specified materials and installation requirements, the CONTRACTOR will receive a
Substantial Completion Certificate for temporary erosion control measures.
3.14 MAINTENANCE OF EROSION CONTROL MEASURES AFTER SUBSTANTIAL
COMPLETION
A. The CONTRACTOR will be responsible for maintaining temporary erosion control
measures as specified in the Drawings and Contract Documents until such time as the
disturbed drainage area has stabilized as determined by the ENGINEER and the
OWNER.
3.15 FINAL COMPLETION AND ACCEPTANCE OF EROSION CONTROL MEASURES
A. After the ENGINEER and OWNER have determined that the drainage area has
stabilized, the CONTRACTOR shall remove all remaining temporary erosion control
LPATH Berm Erosion 02370-5 Erosion and Sediment Control
Protection Measures
measures. Any damage to the site shall be repaired to the satisfaction of the
ENGINEER and at no cost to the OWNER.
END OF SECTION
LPATH Berm Erosion 02370-6 Erosion and Sediment Control
Protection Measures
THIS PAGE INTENTIONALLY LEFT BLANK.
LPATH Berm Erosion 02371-1 Geotextile Fabric for Concrete
Protection Measures Block Revetment
SECTION 02371
GEOTEXTILE FABRIC FOR CONCRETE BLOCK REVETMENT
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Geotextile to prevent soil loss resulting in excessive scour and to prevent hydraulic
uplift pressures causing instability of energy absorbing armor permanent erosion
control system. This specification does not apply to other types of geosynthetic soil
erosion control materials such as turf reinforcement mats.
1.02 RELATED SECTIONS
A. Section 02700 – Concrete Block Revetment
1.03 REFERENCES
A. AASHTO Standards:
1. T88 - Particle Size Analysis of Soils
2. T90 - Determining the Plastic Limit and Plasticity Index of Soils
3. T99 - The Moisture-Density Relations of Soils Using a 5.5lb (2.5 kg)
Rammer and a 12in (305 mm) Drop.
4. M288-96 - Geotextile Specification for Highway Applications
B. American Society for Testing and Materials (ASTM):
1. D 123 - Standard Terminology Relating to Textiles
2. D 276 - Test Method for Identification of Fibers in Textiles
3. D 3786 - Standard Test Method for Hydraulic Bursting Strength of Knitted
Goods and Nonwoven Fabrics
4. D 4354 - Practice for Sampling of Geosynthetics for Testing
5. D 4355 - Test Method for Deterioration of Geotextiles from Exposure to
Ultraviolet Light and Water (Xenon-Arc Type Apparatus)
6. D 4439 - Terminology for Geotextiles
7. D 4491 - Test Methods for Water Permeability of Geotextiles by Permittivity
8. D 4533 - Test Method for Index Trapezoid Tearing Strength of Geotextiles
9. D 4595 - Test Method for Tensile Properties of Geotextiles by the Wide-
Width Strip Method
LPATH Berm Erosion 02371-2 Geotextile Fabric for Concrete
Protection Measures Block Revetment
10. D 4632 - Test Method for Grab Breaking Load and Elongation of Geotextiles
11. D 4751 - Test Method for Determining Apparent Opening Size of a
Geotextile
12. D 4759 - Practice for Determining the Specification Conformance of
Geosynthetics
13. D 4833 - Test Method for Index Puncture Resistance of Geotextiles,
Geomembranes, and Related Products
14. D 4873 - Guide for Identification, Storage, and Handling of Geotextiles
15. D 5141 - Test Method to Determine Filtering Efficiency and Flow Rate for
Silt Fence Applications Using Site Specific Soils
C. Texas Department of Transportation, Manual of Testing Procedures:
1. TEX 616-J - Asphalt Retention and Potential Change of Area
D. Federal Highway Administration (FHWA) - Geosynthetic Design and Construction
Guidelines, Publication No. FHWA HI-95-038, May 1995.
E. American Association for Laboratory Accreditation (A2LA).
F. Geosynthetic Accreditation Institute (GAl) - Laboratory Accreditation Program
(LAP).
G. National Transportation Product Evaluation Program (NTPEP).
1.04 DEFINITIONS
A. Minimum Average Roll Value (MARV): Property value calculated as typical minus
two standard deviations. Statistically, it yields a 97.7 percent degree of confidence
that any sample taken during quality assurance testing will exceed value reported.
1.05 SUBMITTALS
A. Submit the following:
1. Certification: The contractor shall provide to the Engineer a certificate
stating the name of the manufacturer, product name, style number, chemical
composition of the filaments or yarns and other pertinent information to fully
describe the geotextile. The Certification shall state that the furnished
geotextile meets MARV requirements of the specification as evaluated under
the Manufacturer's quality control program. The Certification shall be
attested to by a person having legal authority to bind the Manufacturer.
LPATH Berm Erosion 02371-3 Geotextile Fabric for Concrete
Protection Measures Block Revetment
1.06 QUALITY ASSURANCE
A. Manufacturer Qualifications:
1. Geosynthetic Accreditation Institute (GAI)- Laboratory Accreditation
Program (LAP)
2. American Association for Laboratory Accreditation (A2LA)
1.07 DELIVERY, STORAGE, AND HANDLING
A. Geotextiles labeling, shipment, and storage shall follow ASTM D 4873. Product
labels shall clearly show the manufacturer or supplier name, style name, and roll
number.
B. Each geotextile roll shall be wrapped with a material that will protect the geotextile
from damage due to shipment, water, sunlight, and contaminants.
C. During storage, geotextile rolls shall be elevated off the ground and adequately
covered to protect them from the following: site construction damage, precipitation,
extended ultraviolet radiation including sunlight, chemicals that are strong acids or
strong bases, flames including welding sparks, excess temperatures, and any other
environmental conditions that may damage the physical property values of the
geotextile.
PART 2 PRODUCTS
2.01 MANUFACTURERS
A. Mirafi Construction Products or approved equal
365 South Holland Drive
Pendergrass, GA, USA 30567
1-888-795-0808
1-706-693-2226
1-706-693-2083, fax
www.mirafi.com
or approved equal
2.02 MATERIALS
A. Geotextile:
1. The geotextile shall be manufactured with fibers consisting of long-chain
synthetic polymers composed of at least 95 percent by weight of polyolefins
or polyesters. They shall form a stable network such that the filaments or
yarns retain their dimensional stability relative to each other, including
selvages.
2. Woven slit film geotextiles (i.e., geotextiles made from yarns of a flat, tape-
like character) shall not be allowed.
LPATH Berm Erosion 02371-4 Geotextile Fabric for Concrete
Protection Measures Block Revetment
3. The geotextile shall meet the requirements of Table 1. All numeric values in
Table 1 except AOS represent MARV in the weakest principal direction.
Values for AOS represent maximum average roll values.
Table 1 - Permanent Erosion Control Geotextile
Property Test Method Units Elongation < 50%1
Grab Tensile Strength ASTM D 4632 N (lbs) 1100 (247)
Sewn Seam Strength2 ASTM D 4632 N (lbs) 990 (222)
Tear Strength3 ASTM D 4533 N (lbs) 400 (90)
Puncture Strength ASTM D 4833 N (lbs) 400 (90)
Burst Strength ASTM D 3786 kPa (psi) 2700 (391)
Permittivity ASTM D 4991 sec-1 0.7
Apparent Opening
Size
ASTM D 4751 mm (U.S.
Sieve)
0.43 max (40)
Ultraviolet Stability4 ASTM D 4355 % 50
1 A measured in accordance with ASTM D 4632
2 When sewn seams are required.
3 The required MARV Tear Strength for woven monofilament geotextiles is 250 N (56 lbs)
4
After 500 hrs
4. Approved geotextiles are as follows:
Elongation < 50%: Mirafi Filterweave 400
2.03 QUALITY CONTROL
A. Manufacturing Quality Control: Testing shall be performed at a laboratory accredited
by GAI-LAP and A2LA for tests required for the geotextile, at frequency meeting or
exceeding ASTM D 4354.
B. Geotextile properties, other than Sewn Seam Strength, Burst Strength, and Ultraviolet
Stability shall be tested by NTPEP to verify conformance with this specification.
C. Sewn Seam Strength shall be verified based on testing of either conformance samples
obtained using Procedure A of ASTM D 4354, or based on manufacturer's
certifications and testing of quality assurance samples obtained using Procedure B of
ASTM D 4354. A lot size for conformance or quality assurance sampling shall be
considered to be the shipment quantity of the given product or a truckload of the
given product, whichever is smaller.
D. Ultraviolet Stability shall be verified by an independent laboratory on the geotextile
or a geotextile of similar construction and yarn type.
PART 3 EXECUTION
3.01 PREPARATION
A. The installation site shall be prepared by clearing, grubbing, and excavation or filling
the area to the design grade. This includes removal of topsoil and vegetation.
LPATH Berm Erosion 02371-5 Geotextile Fabric for Concrete
Protection Measures Block Revetment
3.02 INSTALLATION
A. The geotextile shall be placed in intimate contact with the soils without wrinkles or
folds and anchored on a smooth graded surface approved by the Engineer. The
geotextile shall be placed in such a manner that placement of the overlying materials
will not excessively stretch so as to tear the geotextile. Anchoring of the terminal
ends of the geotextile shall be accomplished through the use of key trenches or
aprons at the crest and toe of the slope.
B. The geotextile shall be placed with the machine direction parallel to the direction of
water flow which is normally parallel to the slope for erosion control runoff and
wave action, and parallel to the stream or channel in the case of streambank and
channel protection. Adjacent geotextile sheets shall be joined by either sewing or
overlapping. Overlapped seams of roll ends shall be a minimum of 300 mm (12 in)
except where placed under water. In such instances the overlap shall be a minimum
of 1 m (3.28 ft). Overlaps of adjacent rolls shall be a minimum of 300 mm (12 in) in
all instances.
C. When overlapping, successive sheets of the geotextile shall be overlapped upstream
over downstream, and/or upslope over downslope. In cases where wave action or
multidirectional flow is anticipated, all seams perpendicular to the direction of flow
shall be sewn.
D. Care shall be taken during installation so as to avoid damage occurring to the
geotextile as a result of the installation process. Should the geotextile be damaged
during installation, a geotextile patch shall be placed over the damaged area
extending 1 m (3.28 ft) beyond the perimeter of the damage.
E. The armor system placement shall begin at the toe and proceed up the slope.
Placement shall take place so as to avoid stretching and subsequent tearing of the
geotextile. Riprap and heavy stone filling shall not be dropped from a height of more
than 300 mm (12 in). Stone with a mass of more than 100 kg (220 lbm) shall not be
allowed to roll down the slope.
F. Slope protection and smaller sizes of stone filling shall not be dropped from a height
exceeding 1 m (3.28 ft), or a demonstration provided showing that the placement
procedures will not damage the geotextile. In underwater applications, the geotextile
and backfill material shall be placed the same day. All void spaces in the armor stone
shall be backfilled with small stone to ensure full coverage.
G. Following placement of the armor stone, grading of the slope shall not be permitted if
the grading results in movement of the stone directly above the geotextile.
H. Field monitoring shall be performed to verify that the armor system placement does
not damage the geotextile.
I. Any geotextile damaged during backfill placement shall be replaced as directed by
the Engineer, at the contractor's expense.
END OF SECTION
LPATH Berm Erosion 02371-6 Geotextile Fabric for Concrete
Protection Measures Block Revetment
THIS PAGE INTENTIONALLY LEFT BLANK.
LPATH Berm Erosion 02375-1 Riprap
Protection Measures
SECTION 02375
RIPRAP
PART 1 GENERAL
1.01 SECTION INCLUDES
A. The work of this section shall include excavation, grading and installation of all
riprap, and bedding placed at the locations shown on the Drawings. The materials to
be used for the construction of such structures shall be as specified herein.
1.02 RELATED SECTIONS
A. Section 02240 – Water Control and Dewatering
B. Section 02315 – Excavation and Embankment
1.03 SUBMITTALS
A. The CONTRACTOR shall cooperate with the ENGINEER in obtaining and
providing samples of all specified materials. The CONTRACTOR shall submit
certified laboratory test certificates for all items required in this section.
PART 2 PRODUCTS
2.01 MATERIALS
A. Riprap:
Riprap used shall be the type designated on the Drawings and shall conform to the
following:
Riprap Designation
% Smaller Than Given
Size By Weight
Intermediate Rock
Dimension (Inches)
d50
*
(Inches)
Type VL (Class 6)
70 - 100
50 - 70
35 - 50
2 - 10
12
9
6
2
6
Type L (Class 9)
70 - 100
50 - 70
35 - 50
2 - 10
15
12
9
3
9
Type M (Class 12)
70 - 100
50 - 70
35 - 50
2 - 10
21
18
12
4
12
LPATH Berm Erosion 02375-2 Riprap
Protection Measures
Type H (Class 18)
70 - 100
50 - 70
35 - 50
2 - 10
30
24
18
6
18
Type VH (Class 24) 70 - 100
50 - 70
35 - 50
2 - 10
42
33
24
9
24
* d50
= Mean Particle Size
1. The riprap designation and total thickness of riprap shall be as shown on the
Drawings. The maximum stone size shall not be larger than the thickness of
the riprap.
2. The specific gravity of the riprap shall be 2.65 or greater.
3. Neither width nor thickness of a single stone of riprap shall be less than 1/3
of its length.
4. Broken concrete or asphalt pavement shall not be acceptable for use in the
work. Rounded riprap (river rock) is not acceptable unless specifically
designated on the Drawings.
5. The color of the riprap shall be as approved by the OWNER prior to delivery
to the project site. Color shall be consistent on the entire project and shall
match the color of rock to be used for all other portions of the work. Color
required for this project shall be green-gray rock.
6. Minimum density for acceptable riprap shall be 165 pounds per cubic foot.
The specific gravity shall be according to the bulk-saturated, surface-dry
basis, AASHTO T85.
7. The riprap shall have a percentage loss of not more than 40 percent after 500
revolutions when tested in the Los Angeles machine in accordance with
AASHTO Test T96.
8. The riprap shall have a percentage loss of not more than 10 percent after 5
cycles when tested in accordance with AASHTO Test T104 for ledge rock
using sodium sulfate.
9. The riprap shall have a percentage loss of not more than 10 percent after 12
cycles of freezing and thawing when tested in accordance with AASHTO
Test T103 for ledge rock, procedure A.
10. Rock shall be free of calcite intrusions.
11. Each load of riprap shall be reasonably well graded from the smallest to the
largest size specified. Stones smaller than the 2-10 percent size will not be
permitted in an amount exceeding 10 percent by weight of each load.
LPATH Berm Erosion 02375-3 Riprap
Protection Measures
Control of gradation will be by visual inspection. However in the event the
ENGINEER determines the riprap to be unacceptable, the ENGINEER will
pick 2 random truck loads to be dumped and checked for gradation.
Mechanical equipment and labor needed to assist in checking gradation shall
be provided by the CONTRACTOR at no additional cost.
B. Bedding:
1. Gradation for Granular Bedding
U.S. Standard Percent by Weight Passing Square Mesh Sieves
Sieve Size Type I Type II
3 Inch 90 - 100
1-½ Inch
¾ Inch 20 - 90
3/8 Inch 100
No. 4 95 – 100 0 - 20
No. 16 45 - 80
No. 50 10 - 30
No. 100 2 - 10
No. 200 0 - 2 0 - 3
Granular bedding designation and total thickness of bedding shall be as shown on the
Drawings. Granular bedding shall meet the same requirements for specific gravity,
absorption, abrasion, sodium sulfate soundness, and freeze-thaw durability as
required for riprap and specified above.
C. Geotextile Fabric:
Where soil conditions dictate, geotextile fabric shall be placed directly on excavated
slopes, channel beds, etc. prior to the placement of any riprap bedding or riprap. The
extent and location of geotextile placement will be shown on the Drawings.
Geotextile fabric shall be Trevira S1120 or approved equal under all riprap.
PART 3 EXECUTION
3.01 CONSTRUCTION REQUIREMENTS
A. Channel slopes, bottoms, or other areas that are to be protected with riprap shall be
free of brush, trees, stumps, and other objectionable material and be graded to a
smooth compacted surface. The CONTRACTOR shall excavate areas to receive
riprap to the subgrade for granular bedding. The subgrade for bedding materials shall
be stable. If unsuitable materials are encountered, they shall be removed and
replaced as Muck Excavation in accordance with Section 02315 of the Specifications.
Unsuitable materials shall be disposed of from the site by the CONTRACTOR at his
expense. After an acceptable subgrade for granular bedding material is established,
the bedding shall be immediately placed and leveled to the subgrade elevation.
Immediately following this, the riprap shall be placed. If bedding material is
disturbed for any reason, it shall be replaced and graded at the CONTRACTOR’s
expense. In-place bedding materials shall not be contaminated with soils, debris or
LPATH Berm Erosion 02375-4 Riprap
Protection Measures
vegetation before the riprap is placed. If contaminated, the bedding material shall be
removed and replaced at the CONTRACTOR’s expense.
3.02 PLACEMENT
A. Following acceptable placement of geotextile fabric, granular bedding, riprap
placement shall commence as follows:
1. Machine Placed Riprap: Riprap shall be placed on the prepared slope or
channel bottom areas in a manner which will produce a reasonably well-
graded mass of stone with the minimum practicable percentage of voids.
Riprap shall be machine placed, unless otherwise stipulated in the Drawings
or Specifications.
When riprap is placed on slopes, placement shall commence at the bottom of
the slopes working up the slope. Place the riprap in a stepped fashion with
the bottom of the uphill riprap below the top of the downhill riprap by half of
the height of the riprap minimum.
The entire mass of riprap shall be placed on either channel slopes or bottoms
so as to be in conformance with the required gradation mixtures and to lines,
grades, and thickness shown on the Drawings. Riprap shall be placed to its
full course thickness at one operation and in such a manner as to avoid
displacing the underlying bedding material. Placing of riprap in layers, or by
dumping into chutes, or by similar methods shall not be permitted.
All material going into riprap protection for channel slopes or bottoms shall
be so placed and distributed that there will be no large accumulations of
either the larger or smaller sizes of stone. Some hand placement may be
required to achieve this distribution.
It is the intent of these Specifications to produce a fairly compact riprap
protection in which all sizes of material are placed in their proper
proportions. Unless otherwise authorized by the ENGINEER, the riprap
protection shall be placed in conjunction with the construction of
embankments or channel bottoms with only sufficient delay in construction
of the riprap protection, as may be necessary, to allow for proper
construction of the portion of the embankment and channel bottom which is
to be protected. The CONTRACTOR shall maintain the riprap protection
until accepted. Any material displaced for any reason shall be replaced to the
lines and grades shown on the Drawings at no additional cost to the
OWNER. If the bedding materials are removed or disturbed, such material
shall be replaced prior to replacing the displaced riprap.
2. Hand Placed Riprap: Hand placed riprap shall be performed during machine
placement of riprap and shall conform to all the requirements of Section
02375 PART 1 above. Hand placed riprap shall also be required when the
depth of riprap is less than 2 times the nominal stone size, or when required
by the Drawings or Specifications.
After the riprap has been placed, hand placing or rearranging of individual
stones by mechanical equipment shall be required to the extent necessary to
LPATH Berm Erosion 02375-5 Riprap
Protection Measures
secure a flat uniform surface and the specified depth of riprap, to the lines
and grades as shown on the Drawings.
3. Soil Replacement In and Over Riprap: Where riprap is designated to be
buried, place onsite excavated material that is free from trash and organic
matter in riprap voids by washing and rodding. Prevent excessive washing of
material into stream. When voids are filled and the surface accepted by the
ENGINEER, place a nominal 6 inches of soil over the area, or as designated
on the Drawings. Fine grade, seed, and mulch per the Specifications.
4. Rejection of Work and Materials: The ENGINEER shall reject placed riprap
which does not conform to this Section and the CONTRACTOR shall
immediately remove and relay the riprap to conform with said sections.
Riprap shall be rejected, which is either delivered to the job site or placed,
that does not conform to this Section. Rejected riprap shall be removed from
the project site by the CONTRACTOR and at his expense.
5. Geotextile fabric shall be installed according to the manufacturer’s
specifications. Material proposed for use shall be submitted and approved by
the ENGINEER prior to installation.
END OF SECTION
LPATH Berm Erosion 02375-6 Riprap
Protection Measures
THIS PAGE INTENTIONALLY BLANK.
LPATH Berm Erosion 02376-1 Concrete Rubble
Protection Measures
SECTION 02376
CONCRETE RUBBLE
PART 1 GENERAL
1.01 SECTION INCLUDES
A. The work of this section shall include excavation, grading and installation of all
concrete rubble placed at the locations shown on the Drawings. The materials to be
used for the construction of such structures shall be as specified herein.
1.02 RELATED SECTIONS
A. Section 02315 – Excavation and Embankment
B. Section 02371 – Geotextile fabric for Concrete Block revetment
C. Section 02700 – Concrete Block Revetment System Specifications for Overtopping
Applications
1.03 SUBMITTALS
A. The CONTRACTOR shall cooperate with the ENGINEER in obtaining and
providing samples of all specified materials.
PART 2 PRODUCTS
2.01 MATERIALS
A. Concrete Rubble:
Concrete Rubble used shall be the type designated on the Drawings and shall
conform to the following:
% Smaller Than Given
Size By Weight
Intermediate Dimension
(Inches)
d50
*
(Inches)
Concrete Rubble (4” to
8”)
50 - 100
50 - 0
8
4
6
* d50
= Mean Particle Size
1. The concrete rubble designation and total thickness of concrete rubble shall
be as shown on the Drawings. The maximum individual rubble size shall not
be larger than the thickness of the concrete rubble layer.
2. Broken asphalt pavement shall not be acceptable for use in the work.
Rounded river rock is not acceptable unless specifically designated on the
Drawings. Concrete rubble shall be free from reinforcing steel bars or mats
and debris
LPATH Berm Erosion 02376-2 Concrete Rubble
Protection Measures
3. Control of gradation will be by visual inspection. However in the event the
ENGINEER determines the concrete rubble to be unacceptable, the
ENGINEER will pick 2 random truck loads to be dumped and checked for
gradation. Mechanical equipment and labor needed to assist in checking
gradation shall be provided by the CONTRACTOR at no additional cost.
PART 3 EXECUTION
3.01 CONSTRUCTION REQUIREMENTS
A. Channel slopes, bottoms, or other areas that are to be filled with concrete rubble shall
be free of brush, trees, stumps, and other objectionable material and be graded to a
smooth compacted surface. The CONTRACTOR shall excavate areas to receive
concrete rubble to the subgrade. The subgrade shall be stable. If unsuitable materials
are encountered, they shall be removed and replaced as Muck Excavation in
accordance with Section 02315 of the Specifications. Unsuitable materials shall be
disposed of from the site by the CONTRACTOR at his expense. After an acceptable
subgrade is established, the concrete rubble shall be placed.
3.02 PLACEMENT
A. Following acceptable subgrade preparation, concrete rubble placement shall
commence as follows:
1. Machine Placed Concrete rubble: Concrete rubble shall be placed on the
prepared slope or channel bottom areas in a manner which will produce a
reasonably well-graded mass of rubble with the minimum practicable
percentage of voids. Concrete rubble shall be machine placed, unless
otherwise stipulated in the Drawings or Specifications.
When concrete rubble is placed on slopes, placement shall commence at the
bottom of the slopes working up the slope. Place the concrete rubble in a
stepped fashion with the bottom of the uphill concrete rubble below the top
of the downhill concrete rubble by half of the height of the concrete rubble
minimum.
The entire mass of concrete rubble shall be placed on either channel slopes or
bottoms so as to be in conformance with the required gradation mixtures and
to lines, grades, and thickness shown on the Drawings. Concrete rubble shall
be placed to its full course thickness at one operation and in such a manner as
to avoid displacing the underlying subgrade. Placing of concrete rubble in
layers, or by dumping into chutes, or by similar methods shall not be
permitted.
All material going into concrete rubble protection for channel slopes or
bottoms shall be so placed and distributed that there will be no large
accumulations of either the larger or smaller sizes of rubble. Some hand
placement may be required to achieve this distribution.
It is the intent of these Specifications to produce a fairly compact concrete
rubble protection in which all sizes of material are placed in their proper
proportions. Unless otherwise authorized by the ENGINEER, the concrete
LPATH Berm Erosion 02376-3 Concrete Rubble
Protection Measures
rubble protection shall be placed in conjunction with the construction of
embankments or channel bottoms with only sufficient delay in construction
of the concrete rubble protection, as may be necessary, to allow for proper
construction of the portion of the embankment and channel bottom which is
to be protected. The CONTRACTOR shall maintain the concrete rubble
protection until accepted. Any material displaced for any reason shall be
replaced to the lines and grades shown on the Drawings at no additional cost
to the OWNER.
2. Hand Placed Concrete Rubble: Hand placed concrete rubble shall be
performed during machine placement of concrete rubble and shall conform to
all the requirements of Section 02376 Part 1 above. Hand placed concrete
rubble shall also be required when the depth of concrete rubble is less than 2
times the nominal rubble size, or when required by the Drawings or
Specifications.
After the concrete rubble has been placed, hand placing or rearranging of
individual stones by mechanical equipment shall be required to the extent
necessary to secure a flat uniform surface and the specified depth of concrete
rubble, to the lines and grades as shown on the Drawings.
3. Rejection of Work and Materials: The ENGINEER shall reject placed
concrete rubble which does not conform to this Section and the
CONTRACTOR shall immediately remove and relay the concrete rubble to
conform with said sections.
Concrete rubble shall be rejected, which is either delivered to the job site or
placed, that does not conform to this Section. Rejected concrete rubble shall
be removed from the project site by the CONTRACTOR and at his expense.
END OF SECTION
LPATH Berm Erosion 02376-4 Concrete Rubble
Protection Measures
THIS PAGE INTENTIONALLY BLANK.
������������������� �������� ���������������������������������
���������������������������������������������������������������������� �������������������������������������������
SECTION 02700
CONCRETE BLOCK REVETMENT SYSTEM
SPECIFICATION FOR OVERTOPPING APPLICATIONS
PART 1 GENERAL
����� �����������������
�
����� �����������������������������������������������������������������������������������
��������� ���� �������� ���� ����������� ��� ����������� ����� ���� ������������� ��� ���������
��������� �������� �������� ����� ��� ����������� ����� ���� ������� �������� ������� ����
�������������������������������������������������������������������
�
����� �����������������
���� ������������������������������������������������������������
�
����� ����������
��� �������������������������������������������������������������������������������������
���������������������������������������������������������������������������������������
�
����������������������������������������������������������������������������������������
��������� ������������� ���������� ������� ���� ���� ���������� ������ ��������� ����
������������ � ���� ����������� ������ ����� �������� ���� ��������������� ����������������
������������ ����� ��������� ���� ���� ������� ��� ���� ������ ���� ���� ����������������� ���
������������������������������������������������������������
�
���������������������������������������������������������������������������������
�������� ��� ���� ��������� ������ ��� ���� ������ � ������������ ��������� ��������� ����� ���
���������� ��� ���� ��������� �� �������� ��� �������� ����� ����� ������ ��� ���� �������
��������������������������������������������������������������
�
��� ����������� ����������� �������� ���� ����������� ����������� �������������
������������ ���� ���������� ��������� ��� ���� ��������� ��������� ��������� ����
������������������������������������������������������
�
����� �����������������������������������������������������������������������������������
��������������������������������������������������������������������������������
���������������������������������������������������������
PART 2 PRODUCTS
����� ��������
�
���� ��������� ��������� ����� ������ ��� �������������� ��� ��� ��������� ��� ��������� �������� �����
��������� ���������� ������������ ������������������������������������������������������������
���������� �������� ��� ������������� ���� ����������� ������ ������� ����� ��� �������� �����������
���������������������
������������������� �������� ���������������������������������
���������������������������������������������������������������������� �������������������������������������������
����������� ������ ��� ���� ������� ������ ��� ���������� ���� ������������ ���� ���������
���������������������������������������������������������������������������������������
���� ��������� ���������� � ���� ����� ����� ������ ����� ���� ���� ��������� ��������� ���
������������ ������ �������� ����� ����������� ����� ���������� ��� ������� ��������� �������
�����������������������������������������������������������������������������������������
���������������������������������������������������������������������������������������
��������������������������������������������������������������������������������������
�������������������������������������������������������������������������������������
�����������������������
�
��������������������������������������������������������������������������������������
��� ���� ������� ������� ���� ����� ����� ����� ���� ������� ��� ���� ������������� ����������
�������� � ���� ������������� ��������� ����� ���� ��������� ������� ���� ���������� ��� ����
����������������������������������������������������������������������������������������
���� ��������� ����� ��� ������� �������� ��� ������� ����� ���� ����� ���� ������� �������
������������������������������������������������������������������������������������
��������� ���� �������� ������������� ��� ���� ������� ����� ��� ���� ������� ������� �������
�������������������������������������������������������������������������������
���������������������������������������������������������������������������������
��������������������
�
� ��������������������������������������������������������������������������������������
��������������������������������������������������������������������������������������
���������������������������������������������������������������������������������������
���������������������������������������������������������������������������������������
���������������������������������������������������
�
� ���� ��������� ��������� ����� ������ ��� ������� ��� �� ������� ������� ��� ���������� ���������
�������������������������������������������������������������������������������������
���������������������������������������������������������������������������������������
���� ������� �������� � �������������� ���� ������� ������� ������ ��� ������������ ��� ���� ������
����������
�
� Certification (Overtopping Flow):� � ��������� ��������� ����� ����� ����� ��� ���������
����� ������������ ��� ����������� ���������� ������������ ���������������� ����� ����
�������� ����� ������ ������ ����������� ����� ������������ � �������� ����������� �������
�������� ����������������������������������������������������������������������
�������� ��������� ��� ����������� ��� ������������ ����������� ������� �������
������������ ������� ������� ���� ��������������� ���� ���� ���������� ������������
�����������������������������������������������
�
Performance (Overtopping Flow): �����������������������������������������������
��� ��� ����������� ����� ���� ����������������� ������� ������������ ��� ���������� ���
��������� ���� ��������������� ��� ������� �������� ���������� ����������� ������� �������
���������������������������������������������������������������������������������������
�
������������������������������
����������������������������������
���������������
�����������
�
�����������������������������������������������������������������������������������
��������������������������������������������������������������������������������������
������������������� �������� ���������������������������������
���������������������������������������������������������������������� �������������������������������������������
�������� ����� ��������� �������� ��� ������ ����������� ���� ������������� ��� �������� ������
�������� ���������������������������������������������������������������������������
���������������������������������
�
����� ������������������������
� ��� ������
�
��� ����� �������������� ������� �������� �������� ����� ����� ��� ����������� ���� �����
���������������
�
Note 1 �� ��������� ������ �������� ��� ����� �������������� ���� ����� �����
��������������������������������������������������
�
Note 2 ����������������������������������������������������������������������
����������
� ��� ����������
�
��� �����������������������������������������������������������������������������
���������������������
�
��� �������������������������������������������������������������
�
��� ����������������������������������������������������������������������
�
��� ��������������������������������������������������������������������
�
��� �������������������������������������������������������������������������
�����������������������������������������������
�
���� ���������������������������������������������������������������������������
��������������������������������������������������
�
� ����� �������������������������������������������������������������
�
��� ��������
��� ���� ��������� ������ ������ ��� ��������� ��� �� ���� ���������������������������
������ ������� ��������� ��� �� �������� ��������� ��� ����� ��� ��� ��������� ��� ����
���������������������������������������������
���� ����������������������
�
��� ��� ���� ����� ��� ��������� ��� ���� ����� ������ ���� ������ ������ �������� ���������������������������
��������������������������������������������������������������
�
�
�
�
������������������� �������� ���������������������������������
���������������������������������������������������������������������� �������������������������������������������
Table 1. Physical Requirements
�
������������������������������
���������������
�����������������
����������
�
������
�
��
���������������� ���������������� ���������������� ����������������
������������� ������������� ��������� ���������
�
��� ����������������������������������������������������������������������������
����������������������������������������������������������������������
�
��� ������ ������ ��� �������� ���� ������� ��� ����������� ����� ����� �� ���������
��������� �������������� ���� ���������� ���� ������������ ��� �������������
������������������������������������������
� �
� ��� ������������������
�
��� ������������������������������������������������������������������������������
���� ������� ���������� ��� ���� ����� ��� ������� ���� ������������ ��� ���� ���������
�������� ������� ����������� ��� ���� ������ �������� ��� ������������� ��� ��������
��������� ���������� ����� ���������� �������� ��� ��������� ��� ��������� ����
�����������������������������������������������������
�
��� �����������������������������������������������������������������������������
���������������������������������������������
�
��� �����������������������������������������������������������������������������
�����������������������������������������������������
�
��� ������� ��������� ������ ��� ��������� ����� ���� ������ ��� ������������ ������ ���
�������������������������������������������������������������������������������
��������������������������������������������������������������������������������
�
� ��� ���������������������
��� ���� ���������� ��� ������ ����������� ��������������� ������ ��� ��������� �������
���������������������������������������������������������������������������������
������������������������������
�
��� �������������������������������������������������������������������������������
���� ���������� �������� ����������� ��� ���� ������������ �������� ���� �������
����������� ���� ���������� ����������� ������ ��� ���������� ��������� ���������
������������������������������������������������������������������������������
�������� �������������� �������� �� ��������� ������ ����� ���� ������ ������������� �����
�������������������������������������������������������������������������������
����������������
�
��� ���� ������������ �������������� ��������� ����� ���� ������������ ��������������
�����������������������������������������������������������������������������
������� ���������� �������� ��� �������� ������� � ����� ������������� ������������
�����������������������������������������������������������������������������������
������������������� �������� ���������������������������������
���������������������������������������������������������������������� �������������������������������������������
������������������������������������������������������������������������������
������� � ����������� ���� ������������ �������������� ����� ��� ������ ��� �������
����������������������������������������������������������������������������������
���������������������������������
�
��� ����������� ��������� ������ ����� ����� ��������� ��� ���� �������������� ������ ���
������������������������
� �
��� �������������
��������������������������������������������������������������������������������������
�������������������������������������������������
�
Table 2. Standard Sizes of Concrete Blocks
�
Class Type
Lbs
(kg)
Lbs./Sq.f
t.
(kg/m2)
Length
Inches
(cm)
Width
Inches
(cm)
Height
Inches
(cm)�
Open
Area %
����� �����
������
��������
������
����������
�����
�������
�����
�������
�����
�����
���
����� �����
������
��������
������
����������
�����
�������
�����
�������
����
�������
���
����� �����
�������
��������
������������������� �������� ���������������������������������
���������������������������������������������������������������������� �������������������������������������������
Option 1. Polyester Revetment Cable ���� ���������� � � ���������� ������ ������ ���
������������ ��� ����� ���������� ���� ������������ ���� ����������� ��������� ����������
�������� � ������ ������ �������� ��� �� ����� ������������� ���������� ��� ��������� �������
�������������������������������������������������������������������������������������
�������������������������������������������������������������������������������������
����������������������������������������
� � � � � � � ��
����� ���������������������������������������������� � �����������������������������������������
� �������������������������������������������������������������������������������������������������
� � ��������������������������������������������� � ����� ������ � �������������
� � ������������ ����������������������� � ����� ����������������� ������������������
� � ���������������������������������� � ����� ������ ����������� �������������
� �������������������������������� ���������������������� � ����� ������ ����������� �������������
�
����������� ������������� ���������� ������ ���� ���������������������������������������
������������������������������������������������������������������������������������������
����� �������������� ��� ����
�
� ���� �� ����� ������ ��� ����� ���� ��� ���� ��� ���� ��������
�������������������������������������������������������������������������������������
���������������������������������������������������������
�
� ����������������������������������������������� � ����������������������������
� ��������������������������������������������������������������������������������������������������
� ���� ����������������������������������������������� � ����������������� ��������������������������
� ����� ������������� ������������������������� ����� ����������������� ��������������������������
� ����� ������������� ������������������������� � ����������������� �������������������������
� ��� �������������� ������������������������ ��������������������������� �������������������������
� � � � � ���������� �
�������������������������������������������������������������������������������������
������������������������������������������������������������������������������������
������������������������������������������������������������������������������������
���������������������������������������������������������
�
�������������������������������������������������������������������������������������
������� ���� ����� ������ ������� ����� ����� ������ �������� �������� �� �����������
�������������� ������ ��� ������ ���� ���� �������� ��� ���� ������� ������� ������ ��� �����
�������������������������������������������������������������������������������������������
�������������������������������������������������������������������������������������
����� ��� ��������������������������������������������������������������������������
�������������������������������������������������
Option 2. Galvanized Steel Revetment Cable �������������������������������������
��������������������������������������������������������������������������������������
�����������������������������������������������������������������������������������
������������������������������������
�
� � ������ ������ �������� ��� �� ����� ������������� ���������� ��� ���� ���� ��� ������ ���� ������
�����������������������������������������������������������������������������������
����������������������������������������
� �����������
�
�
�
������������������� �������� ���������������������������������
���������������������������������������������������������������������� �������������������������������������������
������������������������������������������������ � �����������������������������
������������������������� ����������������������������������������������������������������������
����������������������� ���������������������������� ������������������������������������������������������������
�������������������������������������������������� ��� �������������������������������������������������
��������������������������������������������������� � �����������������������������������������������
�������������������������������������������������� � �����������������������������������������������
�
� � ���������������������������������������������������������������������������������������
�������������������������������������������������������������������������������������
���������������������������
�
� � �������������������������������������������������������������������������������������
������� ���� ����� ������ ������� ����� ����� ������ �������� �������� �� �����������
�������������� ������ ��� ������ ���� ���� �������� ��� ���� ������� ������� ������ ��� �����
�������������������������������������������������������������������������������������������
���������������������������������������������������������������������������
�
� ��� ��������
�
� � ������������������������������������������������������������������������������
� ��� ��������������
�
���� ����������� ������� �������������������������������������������������������������
�������������������������������������������������������������������������������������
�
���� ����������� ����� ��� ���������� ��� ��������� ��������� ��� ��������� ������� ���
�����������������������������������������������������������������������������������������
�
� � ������������������������������������������������������������������������������������
��������������������������������������������������������������������������������������
������������ ������� ����������� ������ ��� ���� ����� ��������� ��� ����������� ��� ����� ����
�����������������������������������������������������������������������������������������
����������������������������������������������������������������������������������������
�������������
�
� � ���������������������������������������������������������������������������������������
����������������������������������������������������������������������������������������
������������������������������������
�
� � ��������������������������������������������������������������������������������������
������������������������������������������������������������������������������������������
�
��� ���� ������� ���������� ���� ������� ������ ��� ����������� �������� ��� ���� �����������
���������� �����������������������������������������������������������������������������
�����������������������������
�
������������������� �������� ���������������������������������
���������������������������������������������������������������������� �������������������������������������������
Table 3. Physical Requirements
�
������������������ ��������������� ��������������
����������������������
��������������������
�����������
���������
�����������������������������
��������������������
��������������������
�����������
���������
�����������������������������
��������������� ����������� ��������
������������������ ����������� ���������
������������������������ ����������� ������������������
������������ ������������� ���
������������� ����������� ����������
� �
��������������������������������������������������������������������������������������
�������������������������������������������������������������������������������
����� ������� ���� ���������� ���� ���������������� ������� ��������� ��� ���� ���������
�����������������������������������������������������������������������������������������
����� ���������� ���� ����������� ������ ��� ����������� ���� ������ �������� ������� ����� ���
���������������������������������������������������������������������������������������
������������������������������������������������������������������������������������������
�����������������������������������������������������������������������������������������
������������������������������������������������������������������������������������������
��������� ��� ���� ���������� � ���� ����������� ������ �������� ���� �������������� ����� ����
��������� �������� ������� ���� ���� ����������� ��� ���� ���� ��������� ��� ���� ���������������
�������������������������������������������������������������������������������������
������������ ����������� ������������ ��� ����������� ����� ������ � ���� ����� ������ ���
���������� ������ ���� ������� ������ ����� ����������� ��� ��� ���������� ��������� ��� ����
����������
�
� � ��� ���� ���������������������������������������������������������������������������������
����� ���� ����������� ������ ���� ����� ��� ������ ��� ���� ��������� ������� ����������� �����
���������������������������������������������������������������������������������������
����������������������������������������������������������������������������������������
���������������������������������������������������������������������������������������
��������������������������������������������������������������������������������������
�
� � ��������������������������������������������������������������������������������������
�������������������������������������������������������������������������
�
��� �������������������������������
�
� � General.�������������������������������������������������������������������������������
������������������������������������������������������������������������������������
������������������������������������������������������������������������������
�
� � Mat Length:� � ���� ��������� ��������� ����� ������ ����� ���� �������� ���� ������������ ���
������������������������������������������������������������������������
������������������� �������� ���������������������������������
���������������������������������������������������������������������� �������������������������������������������
�
PART 3 EXECUTION
����� �����������������������
General.��������������������������������������������������������������������������������������
�����������������������������������������������������������������������������������������
�������������������������������������������������������������������
�
Grading.� � ���� ������ ������ ��� ������� ��� �� ������� ������ �������� ��� ������� ����� ���������
�����������������������������������������������������������������������������������������������
����������� ���� ���� ������� ������� �������� ��� ���� ��������� ��������� �������� � ���� ������
�����������������������������������������������������������������������������������������������
�����������������������������������������������������������������������������������������
�����������������������������������������������������������������������������������������������
����������������������������������������������������������������������������������������������
������ ������ �������������������������������������������������������������������������������
������ ����� ������ ���� ��������� ����� ������ ��� �������� ��� ������ ��� �������� ����������
������������ ���������� ��� ����������� ���� ����������� ��� ������� � ���� ������ ���� ������ �����
������������������������������������������������������������������������������������������
�������������������������������������������������
�
� ����������� �������������������������������������������������������������������������������
������ ��� ����� ��� ����������� ��� ���� ������� ������� ���� ����������� ������ ��� ���� ���������
�������������������������������������������������������������������������������������������
�������������������������������������������������������������������������������������������
������ ��� ���� ������� ������� ������������ ������ ����� ��� ������� ���������� ��� ������� ���������
������������������������������������������������������������������������������������������
�
� Inspection.�����������������������������������������������������������������������������������
���������������������������������������������������������������������������������������������
��� ��������������������������������������������������������������������������������������
���������������
����� ��������������������������������������
General.������������������������������������������������������������������������������������������
�������������������������������������������
� ��
Placement.� � ���� ����������� ����������� ������ ��� ������� ��������� ��� ���� ��������� ������ ���
������������������������������������������������������������������������������������������������
������� ��� ��� �����������������������������������������������������������������������������
����������������������������������������������������������������������������������������������
���������������������������������������������������������������������������������������������������
���� ������������� ���� ����������� ������� ������ ��� ����������� ��� ������ ���� ���� ������ � ����
�������������������������������������������������������������������������������������������
�����������������������������������������������������������������������������������������������
����� ��� ���� ����������� ������� ���� ������ ��� ���� ����� ��������� ��� �� ������ �������� ���������
���������������������������������������������������
�
�
�
������������������� ��������� ���������������������������������
���������������������������������������������������������������������� �������������������������������������������
����� �������������������������������������������
General.����������������������������������������������������������������������������������������
�������������������������������������������������������������������������������������
�
� �Placement.� � ���� ��������� ��������� ������� ������ ��� ������� ��� ���� ������� ������� ��� ����� ��
��������������������������������������������������������������������������������������������
����������������������������������������������������������������������������������������������
�����������������������������������������������������������������������������������������������
����������������������������������������������������������������������������������������������
����������������������������������������������������������
�
� ��������������������������������������������������������������������������������������������������
�������������������������������������������������������������������������������������������������
�����������������������������������������������������������������������������������������
��������� ������ ��� ������ ������ ��� ���� ��������� ����������� ��� ��������������� �������
����������������������������������������������������������������������������������������������
��������������������������������������������������������������������������������������������
�����������������������������������������������������������������������������������������������
���������������������������������������������������������������������������������������
�������������������������������
�
� ������������������������������������������������������������������������������������������������
���������������������������������������������������������������������������������������������
���������������������������������������������������������������������������������������
������� ����� ��������� ��������� ��� ������ ���� ����� �������� ��������� ���������� �������� ���
���������� ��������� ���� ����������� �������� � ���� ����� ������ ��� ������� ��������������������
������������������������������������������������������������������������������������������
���������������������������������������������������������������������������������������������
�����������������������������������������������������������������������������������������������
���������������������������������������������������������������������������������������������
��������������������
�
� �������������������������������������������������������������������������������������������
���� �������� � ���� ���������� ��� �� ����� ������� ��������� ����� ��� ����������� ��� ��� ��� ������� ��
��������������������������������������������������������������������������������������������������
��������������������������������������������������������������������������������������������
���������������������������������������������������������������������������������������������
������������������������������������������������������������������������������������������
�����������������������
�
� Finishing.� � ���� ������ ��� ��������� ��� ���� ��������� ��������� ������� ������ ��� ����������� ����
���������� ������������ ����� ��������� ��������� ��� ������� ������ ���� ��� ������ ���� ��� �����
���������� ��������� �������� ����� ���� ������� ������� ��� ��������� ������ ���� �������� ��� ����
�������������������������������������������������������������������������������������������
�����������������������������������������������������������������
Consultation.�����������������������������������������������������������������������������
����������������������������������������������������������������������������������������������
����������
�
END OF SECTION.
LPATH Berm Erosion 02921-1 Ground Preparation
Protection Measures for Seeding
SECTION 02921
GROUND PREPARATION FOR SEEDING
PART 1 GENERAL
1.01 SECTION INCLUDES
A. This section covers soil preparation for areas to be reseeded.
B. This section addresses work within the limits of disturbance as shown on the
Drawings. However, if disturbance does occur outside of this designated area, this
section will also pertain to those areas, which have been disturbed.
1.02 INITIAL INSPECTION
The CONTRACTOR will inspect existing site conditions and note irregularities affecting
work of this section. Verify that grading operations have been satisfactorily completed and
that topsoil of adequate quantity and quality has been replaced in all areas as specified.
Verify that the area to be revegetated is protected from concentrated runoff and sediment
from adjacent areas. Note any previous treatments to the area such as temporary seeding or
mulching and discuss how these treatments will effect permanent revegetation with the
ENGINEER. Report all irregularities affecting work of this section to the ENGINEER
before beginning work. Beginning work of this section implies acceptance of existing
conditions.
1.03 CLEANING
Perform cleaning daily during installation of the work, and upon completion the work.
Remove and haul from the site all excess materials, debris, and equipment. Repair damage
resulting from ground preparation operations.
PART 2 EXECUTION
2.01 GENERAL SOIL PREPARATION
A. Inspection: Examine the substrate in which the work is to be performed. Do not
proceed until unsatisfactory conditions have been corrected.
B. Grades: Grades have been established under work of another Section to within 1
inch, plus or minus, of required finished grades. Verify that grades are within 1 inch,
plus or minus, of required finished grades. Notify the ENGINEER prior to
commencing soil preparation work if existing grades are not satisfactory, or assume
responsibility for conditions as they exist.
C. Weed and Debris Removal: All ground areas to be planted shall be cleaned of all
weeds and debris prior to any soil preparation or grading work. Weeds and debris
shall be disposed of off the site.
LPATH Berm Erosion 02921-2 Ground Preparation
Protection Measures for Seeding
D. Contaminated Soil: Do not perform any soil preparation work in areas where soil is
contaminated with cement, plaster, paint or other construction debris. Bring such
areas to the attention of the ENGINEER and do not proceed until the contaminated
soil is removed and replaced.
E. Moisture Content: Soil shall not be worked when moisture content is so great that
excessive compaction will occur, nor when it is so dry that dust will form in the air
or that clods will not break readily. Water shall be applied, if necessary, to bring soil
to an optimum moisture content for tilling and planting.
F. Ripping & Scarification: Rip, scarify, or otherwise loosen all areas to a depth of 6
inches, removing all obstructions encountered in excavating, such as loose rock, con-
struction debris, etc. Thoroughly till all areas which are to be seeded that previously
supported vehicular traffic to a depth of 12". Till all remaining areas to a depth of
6". Channel bottom areas are to be ripped to a depth of at least 2 feet on
approximately 2- to 4-foot centers. Work the soil only when moisture conditions are
suitable. Remove rocks and other objects 3" or greater in any dimension.
END OF SECTION
LPATH Berm Erosion
Protection Measures
DIVISION 3 - CONCRETE
SECTION 03110 STRUCTURAL CAST-IN-PLACE CONCRETE
FORMS
SECTION 03210 REINFORCING STEEL
SECTION 03310 STRUCTURAL CONCRETE
SECTION 03320 CONSTRUCTION JOINTS
SECTION 03350 CONCRETE FINISHING
SECTION 03390 CONCRETE CURING
SECTION 03615 GROUT
LPATH Berm Erosion 03110-1 Structural Cast-In-Place
Protection Measures Concrete Forms
SECTION 03110
STRUCTURAL CAST-IN-PLACE CONCRETE FORMS
PART 1 GENERAL
1.01 SECTION INCLUDES
The CONTRACTOR shall supply all labor, tools, equipment and materials to set forms for
the proper placement of concrete for structures. It is the CONTRACTOR’s responsibility to
design and build adequate forms and to leave them in-place until the forms can be safely re-
moved. The CONTRACTOR is responsible for damage and injury caused by removing
forms carelessly or before the concrete has gained sufficient strength. Means and methods of
repair shall be reviewed by the ENGINEER prior to performing the work.
1.02 RELATED SECTIONS
A. Section 03310 – Structural Concrete
B. Section 03320 – Construction Joints
C. Section 03350 - Concrete Finishing
D. Section 03615 - Grout
1.03 QUALITY STANDARDS
A. American Concrete Institute
1. ACI 318 - Building Code Requirements for Structural Concrete
2. ACI SP-4 - Formwork for Concrete
B. American Plywood Association
1. PS 1 - US Product Standard for Construction and Industrial Plywood
2. J20 - Grades and Specifications
3. V345 - Concrete Forming
1.04 SUBMITTALS
A. General
Design, placement and maintenance of formwork and form systems is the responsi-
bility of the CONTRACTOR. Submittals other than listed herein are not required
nor will they be reviewed.
B. Product Technical Data
1. Manufacturer and type of form materials
LPATH Berm Erosion 03110-2 Structural Cast-In-Place
Protection Measures Concrete Forms
2. Manufacturer and type of form ties
3. Manufacturer and type of void form including compressive strength
4. Manufacturer of form release agent
C. Formwork Design
A copy of a transmittal letter from the designing engineer to the CONTRACTOR in-
dicating that the design of the formwork for the project was prepared by or under his
supervision. The letter shall be stamped with the seal of the designing engineer and
signed in accordance with the professional engineering registration laws where the
project is located. The designing engineer’s qualifications shall be attached to the
transmittal letter.
1.05 QUALITY ASSURANCE
Formwork, and if required shoring and reshoring, shall be designed by a Professional Engi-
neer licensed to practice in the state where the project is located and having a minimum of
five years’ experience in the design of concrete formwork or form systems.
PART 2 PRODUCTS
2.01 GENERAL
For the purposes of this specification exposure shall be defined as a surface, interior or exte-
rior, of a structure that will be exposed to view during its use. For example, the interior wall
of a buried water retaining structure is a surface exposed to view.
2.02 FORMS FOR SURFACES EXPOSED TO VIEW
A. Walls
1. APA B-B Plyform Class I, Exterior, PS-1-83. The plywood shall be mill
oiled and edge sealed.
2. Symons hand set steel-ply forms, or equal.
B. Beams
1. APA B-B Plyform Class I, Exterior, PS-1-83. The plywood shall be mill
oiled and edge sealed.
2. Symons hand set steel-ply forms, or equal.
C. Sides of Column Footings
1. APA B-B Plyform Class I, Exterior, PS-1-83. The plywood shall be mill
oiled and edge sealed.
LPATH Berm Erosion 03110-3 Structural Cast-In-Place
Protection Measures Concrete Forms
2. Symons hand set steel-ply forms, or equal.
3. Steel of sufficient thickness that the form will remain true to shape after nu-
merous repetitive uses.
D. Sides of Curved or Straight Continuous Wall Footings
1. APA High Density Overlay Plyform Class I Exterior.
2. APA B-B Plyform Class I, Exterior, PS-1-83.
For curved surfaces, plywood of sufficient thickness, free from knots and other im-
perfections, which can be cut and bent and held in place accurately to the required
curvature without splintering or splitting shall be used.
E. Floor and Roof Slabs
1. APA B-B Plyform Class I, Exterior, PS-1-83. The plywood shall be mill
oiled and edge sealed.
F. Columns
Regardless of materials of construction the forms shall be such to permit bracing in
two directions at half-height and full height at a minimum. Two braces at 90° are re-
quired at half and full height.
1. Steel of sufficient thickness that the form will remain true to shape after nu-
merous repetitive uses.
2. Fiberglass of sufficient thickness that the form will remain true to shape.
G. Column Capitals
1. Steel, 16 gage or thicker, so that the form will remain true to shape after nu-
merous repetitive uses.
2.03 FORMS FOR SURFACES NOT EXPOSED TO VIEW
Wood or steel sufficiently tight to prevent mortar leakage.
2.04 ANCHORAGE IN SLABS FOR BRACES FOR WALL AND COLUMN FORMS
Braces shall be anchored to deadmen of sufficient size and weight to maintain the proper
wall/column alignment under all load conditions including wind.
Wedge anchors of any type, inserts or concrete nails are specifically not permitted for an-
chorage of wall or column braces in water retaining structures. Wedge anchors or nails may
be used in other structures when in the opinion of the ENGINEER the resulting concrete fin-
ish patch will be acceptable. The CONTRACTOR shall make a submittal including informa-
LPATH Berm Erosion 03110-4 Structural Cast-In-Place
Protection Measures Concrete Forms
tion about the type of wedge anchor or nail and the means of patching the surface for review
and acceptance by the ENGINEER.
2.05 ANCHORAGE IN SLABS FOR UPTURNED COLUMN FOOTING FORMS
Braces shall be anchored to deadmen of sufficient size and weight to maintain the proper
wall/column configuration and diameter. Wedge anchors of any type, inserts or concrete
nails are specifically not permitted for anchorage of column footing forms.
2.06 FORM TIES
A. Water Retaining Structures and Below Grade Structures:
Symons, S-Panel Ties, or equal, with water seal and one-inch break back cones on
both tie ends, shall be used on all wall forms.
B. Other Structures:
Symons, S-Panel Ties, or equal, with one-inch break back cones on both tie ends
unless otherwise called out or shown in the Drawings or approved by the ENGI-
NEER, shall be used on all wall forms.
C. Twisted Wire Ties:
Twisted wire ties with loops to hold forms in position are not permitted.
2.07 CHAMFER STRIP
Chamfer strips (3/4 inch) shall be placed in the corners of forms and at the tops of walls or
up-turned footings, to produce beveled edges on permanently exposed concrete surfaces. In-
terior angles of intersecting concrete surfaces and edges of construction joints shall not be
beveled unless otherwise indicated in the Drawings. The chamfer strip may be made of
wood or polyvinyl chloride (PVC).
2.08 STIFFBACKS
Stiffbacks for wall forms shall be constructed of lumber or Glulams, uniform in width and
thickness, free from knots and other surface defects. Only one joint is permitted in the board
of a stiffback and joints shall be offset so as to not occur at the same point. Stiffbacks shall
extend to a point not less than six inches above the top of forms.
2.09 GANG WHALER PLATES FOR THE TOP OF CURVED WALLS
Gang whaler plates shall be constructed of plywood as described below cut to the radius of
the wall curve. The gang whaler plate shall be of sufficient depth to permit notching for
stiffbacks.
A. APA High Density Overlay Plyform Class I Exterior.
B. APA B-B Plyform Class I, Exterior, PS-1-83.
LPATH Berm Erosion 03110-5 Structural Cast-In-Place
Protection Measures Concrete Forms
2.10 WEDGE INSERTS
When permitted by the ENGINEER at the tops of walls or columns, wedge inserts may be
used to support future formwork or catwalks. The inserts shall be Richmond Screw Anchor,
or equal.
2.11 FORM RELEASE AGENT
Magic Kote by Symons Corp. or equal.
PART 3 EXECUTION
3.01 GENERAL
Forms shall be used, wherever necessary, to confine the concrete and shape it to the specified
lines and grades as shown on the Drawings. The CONTRACTOR shall set and maintain
concrete forms so as to ensure completed work is within all applicable tolerance limits. If a
type of form does not, in the opinion of the ENGINEER, consistently perform in an accept-
able manner, the type of form shall be changed and the method of erection shall be modified
by the CONTRACTOR, subject to the review of the ENGINEER.
Forms shall have sufficient strength to withstand the pressure resulting from placement and
vibration of concrete, and shall be maintained rigidly in position. The design of formwork
and placing rate of concrete with medium and high-range water reducing agents shall be ad-
justed to compensate for the greater hydraulic pressures exerted on the forms by concrete of
high fluidity.
Forms shall be clean and free from mortar and other foreign material from previous use prior
to being placed.
The CONTRACTOR shall demonstrate that forms are vertical, proper alignment, grade or
radius when requested by the ENGINEER.
3.02 FORM SURFACE TREATMENT
A. General
Prior to placing reinforcing steel coat the forms with a non-staining release agent that
will effectively prevent the absorption of moisture and prevent bond of the concrete
to the form. Contact with hardened concrete against which fresh concrete is to be
placed is prohibited. All bond breaking materials or processes shall be used only af-
ter acceptance by the ENGINEER. Care shall be taken in applying form oil to avoid
contact with reinforcement steel. Embedded material which becomes coated with
form oil shall be thoroughly cleaned or replaced at the expense of the CONTRAC-
TOR.
B. For Potable Water Facilities
Form release agents for potable water facilities, such as treated water storage reser-
voirs or water treatment plants, shall be non-toxic 30 days after application.
LPATH Berm Erosion 03110-6 Structural Cast-In-Place
Protection Measures Concrete Forms
3.03 TOLERANCES
Tolerances are defined as allowable variations from specified alignments, grades and dimen-
sions. Allowable variations from specified alignments, grades and dimensions are prescribed
in the following sub-section. Descriptions of these criteria can be found in Part 2 of the ACI
Manual of Concrete Practice 1995, Commentary of Standard Specifications for Tolerances
for Concrete Construction and Materials (ACI 117-90).
A. Footings and Foundations
1. Drilled Piers
Vertical alignment ≤ 2 % of the shaft length
Lateral alignment ≤ 1/24 of shaft diameter, 3 inch maximum
Level alignment to cut-off elevation: +1 inch, -3 inch
2. Continuous Wall Footings (Circular and Non-circular)
Lateral alignment: ≤ 2% of the footing width, 2 inches maximum
Relative alignment: Variation ≤ 1 inch in 10 feet (variation between speci-
fied plane and as built surface)
Cross-sectional dimension:
Horizontal dimension: Variation +2 inch, -1/2 inch
Vertical dimension (thickness): Variation ± 1/2 inch
Circular Wall Footing Only
Variation in Radius in any 20 feet of wall length: ≤ 1/2 inch
Variation in Radius in entire wall length: ≤ 1 inch
3. Column footings
Lateral alignment: Variation ≤ 2 inch
Level alignment: Variation from specified elevation +1/2 inch, - 2 inch
Relative alignment: Variation ≤ 1 inch in 10 feet (variation between speci-
fied plane and as built surface)
Cross-sectional dimension:
Horizontal dimension: Variation +2 inch, -1/2 inch
Vertical dimension (thickness): Variation ± 1/2 inch
LPATH Berm Erosion 03110-7 Structural Cast-In-Place
Protection Measures Concrete Forms
B. Cast-in-Place Concrete for Buildings and other Structures
1. Member (such as a beam, column, wall, slab, or pier)
Vertical alignment:
Variation from specified plumb ≤ 3/8 inch (full height)
1/4 inch (one form section)
Lateral alignment:
Maximum in any bay: Variation ≤ 1/2 inch
Maximum in any 20 feet of length: Variation ≤ 1/2 inch
Maximum for entire wall length: Variation ≤ 1 inch
Floor and wall opening locations: Variation ≤ 1/2 inch
Sawcuts and joints: Variation ≤ 3/4 inch
Level alignment:
Top elevation of slabs: Variation ≤ 3/4 inch
Lintels, other lines exposed to view: Variation ≤ 3/4 inch
Cross sectional dimensions:
Walls and slabs (thickness): Variation ±1/4 inch
Columns and Beams: Variation +1/2 inch, -1/4 inch
Size of wall and floor openings: Variation ± 1/4 inch
Relative alignment:
Offset between adjacent formwork: Variation ±1/4 inch
Variation in Specified Grade:
For any distance less than 10 feet: Variation ≤ 1/4 inch
For entire structure: Variation ± 1/2 inch
For manholes and outlet structures: Variation ≤ 1 inch
2. Stairways
Relative alignment:
LPATH Berm Erosion 03110-8 Structural Cast-In-Place
Protection Measures Concrete Forms
Difference in height between adjacent risers: 1/8 inch
Difference in width between adjacent treads: 1/4 inch
3.04 PLUMB AND STRING LINES
Plumb and string lines shall be installed on wall and column forms before, and maintained,
during concrete placement. There shall be sufficient number of plumb or string lines in walls,
for example at every other stiffback, properly installed to permit continuous monitoring. Dur-
ing concrete placement, the CONTRACTOR shall continually monitor plumb and string line
positions and immediately correct deficiencies. The plumb and string lines shall extend to a
point at least six inches above the top of wall or column.
3.05 FORMWORK CAMBER
In order to maintain specified tolerances of joists, beams or slabs subject to dead load deflec-
tion, the CONTRACTOR shall camber formwork to compensate for dead load deflection
prior to hardening of the concrete.
3.06 GANG WHALER PLATES FOR CIRCULAR WALLS
The CONTRACTOR shall place a gang whaler plate cut to the curvature of the wall, such as
a circular reservoir wall, at the top of the wall forms. The gang whaler plate shall be at-
tached to the forms with a gang whaler rod at appropriately designed intervals. The gang
whaler plate may be notched to permit the stiffback to extend above the top of the wall
forms. The gang whaler plate shall be sufficiently stiff to maintain the required curvature.
3.07 HAND SET MODULAR FORMS
Hand set modular forms, such as Symons hand set steel-ply forms, shall be placed with no
more than two intersecting joints occur at one level in the formwork above the bottom modu-
lar form level. The following figure illustrates the required form pattern.
Figure 1
LPATH Berm Erosion 03110-9 Structural Cast-In-Place
Protection Measures Concrete Forms
The above form configuration is one way recommended by Simons Corp. to eliminate verti-
cal, in plane, bending of the forming system. The CONTRACTOR may develop alternate
means of maintaining vertical alignment. Alternate form system configurations require
preparation by a licensed Professional Engineer in Colorado and submittal to the ENGI-
NEER for review and approval.
3.08 FORMWORK CLOSURE
Forms which will prohibit visual review of items such as reinforcing steel, waterstops and
bearing pads by the ENGINEER, shall not be placed until the ENGINEER has performed a
final review of the reinforcing steel.
The CONTRACTOR shall use compressed air from an air-compressor to blow-out construc-
tion debris and dirt at the bottom of sections or members to be placed such as walls, slabs,
beams and columns, prior to placing forms or concrete. The CONTRACTOR shall demon-
strate to the ENGINEER that all debris, such as loose concrete particles, saw dust, loose tie
wire, bar tags, tape, trash and dirt, have been thoroughly removed.
3.09 HOT OR COLD WEATHER PLACEMENT AND STEEL FORMS
Prior to placing concrete when steel forms are used, the forms shall be heated when the sur-
face temperature of the form is below 40° F or cooled when the surface temperature of the
form is above 90° F. If water is used to cool forms where ponding of water may occur, i.e.,
at the bottom of a column, the water shall be permitted to drain prior to placing concrete.
3.10 REMOVAL OF FORMS
The forms for any portion of a structure shall not be removed until the concrete has reach
sufficient strength with a factor of safety of 2.0, to withstand applied loads such as self
weight and wind loads or withstand damage when the forms are removed.
For post-tensioned concrete slabs and beams, formwork shall not be removed until the entire
slab or member has been stressed and stressing records accepted.
3.11 RESHORES
When a reshore plan is to be performed, it shall comply with Section 1.04 of this Specifica-
tion.
END OF SECTION
LPATH Berm Erosion 03110-10 Structural Cast-In-Place
Protection Measures Concrete Forms
THIS PAGE INTENTIONALLY LEFT BLANK.
LPATH Berm Erosion 03210-1 Reinforcing Steel
Protection Measures
SECTION 03210
REINFORCING STEEL
PART 1 GENERAL
1.01 SECTION INCLUDES
This work shall consist of furnishing and placing reinforcing steel in accordance with these
Specifications and in conformity with the Drawings.
1.02 RELATED SECTIONS
A. Section 03310 – Structural Concrete
1.03 QUALITY STANDARDS
A. American Concrete Institute
1. ACI 318 - Building Code Requirements for Reinforced Concrete
2. ACI Detailing Manual - (SP-66)
3. ACI 117 - Standard Tolerance for Concrete Construction and Materials
B. American Society for Testing and Materials
1. ASTM A 615, A 616 including supplementary requirement S1, A 617, A 706
2. ASTM A 767, Zinc-coated (galvanized) reinforcing bars
3. ASTM A 775 Epoxy-coated reinforcing bars
C. Concrete Reinforcing Steel Institute (CRSI)
1. Manual of Standard Practice
2. Placing Reinforcing Bars
D. American Welding Society (AWS)
1. AWS D1.4 - Structural Welding Code - Reinforcing Steel
PART 2 PRODUCTS
2.01 REINFORCING STEEL
A. Deformed Bars:
All bar steel reinforcement shall be of the deformed type, ASTM A 615, (AASHTO
M31) and grade (40 or 60) as specified in the Drawings.
LPATH Berm Erosion 03210-2 Reinforcing Steel
Protection Measures
B. Spirals:
Spirals, hot-rolled plain or deformed bars per ASTM A 615, Grade 60 or cold drawn
wire per ASTM A 82 as specified in the Drawings.
Spirals for columns shall have two “spacers” with a section modulus > 0.008in3 in
order to maintain the proper pitch and spacing.
C. Epoxy-Coated Reinforcing Bars:
Epoxy-coated reinforcing bars shall conform to ASTM A 775. When required, dam-
aged epoxy coating shall be repaired with patching material conforming to ASTM A
775 in accordance with the material manufacturer's recommendations.
D. Zinc-coated (Galvanized Reinforcing Bars):
Zinc-coated reinforcing bars shall conform to ASTM A 767. When required, dam-
aged zinc coating shall be repaired with a zinc-rich formulation conforming to
ASTM A 767.
2.02 TIE WIRE
16 gauge wire ties, manufactured by American Wire Tie, Inc., or equal. When epoxy coated
reinforcing steel is shown in the Drawings, PVC coated wire ties shall be used. The mini-
mum PVC coating is 0.7 mils.
2.03 IDENTIFICATION
Bundles of reinforcing bars and wire spirals shall be tagged, with a metal tag, showing speci-
fication, grade, size, quantity and suitable identification to permit checking, sorting and plac-
ing. When bar marks are used to identify reinforcing bars in the Drawings, the bar mark
shall be shown on the tag. Tags shall be removed prior to concrete placement.
Bundles of flat sheets and rolls of welded wire fabric shall be tagged similar to reinforcing
bars.
2.04 STORAGE AND PROTECTION
Reinforcing steel shall be stored off of the ground and protected from oil or other materials
detrimental to the steel or bonding capability of the reinforcing bar. Epoxy-coated reinforc-
ing bars shall be stored on protective cribbing.
Rust, seams, surface irregularities, or mill scale, shall not be cause for rejection provided that
the weight and height of deformations of a hand-wire-brushed test specimen are not less than
the applicable ASTM Specification.
When placed in the work, the reinforcing bars shall be free from dirt, loose mill scale, paint,
oil, loose rust or other foreign substance.
LPATH Berm Erosion 03210-3 Reinforcing Steel
Protection Measures
2.05 BAR SUPPORTS
A. General:
Bar supports and spacing shall be in accordance with the CRSI Manual of Standard
Practice, Chapter 3, a maximum of four feet or as required by the Drawings.
B. Floor Slabs:
Uncoated steel or non-metallic composite chairs shall be used unless otherwise
shown in the Drawings. If required by the ENGINEER, the chair shall be stapled on
a bearing pad to prevent chair displacement. The bearing pad shall be made of exte-
rior grade plywood and be approximately five inches square.
C. Soffits:
Steel wire bar supports in concrete areas where soffits are exposed to view or are
painted shall be Class 1 or Class 2, Types A or B: Class 3 is acceptable in other ar-
eas.
D. Water and Wastewater Vaults, Tank and Basin Walls, and Roof Slabs:
Only plastic clip, non-metallic composite or 100% epoxy coated steel chair bar and
bolster supports are acceptable for use in walls and roof slabs. Supports shall be se-
curely stapled to formwork.
E. Columns:
Plastic "space wheels" manufactured by Aztec (Model DO 12/40), or equal, are re-
quired.
F. Epoxy-Coated and Zinc-Coated Bar Supports:
Epoxy-coated reinforcing bars supported from formwork shall rest on coated wire
bar supports made of dielectric or other acceptable materials. Wire supports shall be
fully coated with dielectric material, compatible with concrete. Reinforcing bars
used as support bars shall be epoxy-coated. In walls reinforced with epoxy-coated
bars, spreader bars shall be epoxy coated. Proprietary combination bar clips and
spreaders used in walls with epoxy-coated reinforcing shall be made of corrosion-
resistant material or coated with dielectric material.
PART 3 EXECUTION
3.01 BAR LIST
Eight copies of a list of all reinforcing steel and bending diagrams shall be furnished to the
ENGINEER at the site of the work at least two weeks before the placing of reinforcing steel
is begun. The CONTRACTOR shall be responsible for the accuracy of the lists and for fur-
nishing and placing all reinforcing steel in accordance with the details shown on the Draw-
ings.
LPATH Berm Erosion 03210-4 Reinforcing Steel
Protection Measures
Bar lists and bending diagrams for structures, which are included in the Drawings, do not
have to be furnished by the CONTRACTOR. When bar lists and bending diagrams are in-
cluded in the Drawings, they are intended for estimating approximate quantities. The
CONTRACTOR shall verify the quantity, size and shape of the bar reinforcement against
those shown on the Drawings and make any necessary corrections before ordering.
3.02 FABRICATION
Fabrication tolerances for straight and bent bars shall be in accordance with the requirements
of Subsection 4.3, Tolerance, of the American Concrete Institute Standard 315 and the CRSI
Manual of Standard Practice.
3.03 BENDING
All reinforcing bars shall be bent cold. Bars partially embedded in concrete shall not be field
bent except as shown on the Drawings or as permitted by the ENGINEER. Bars shall not be
bent or straightened in a manner that will injure the material.
3.04 SPIRALS
One and one-half finishing bends are required at the top and bottom of the spiral. Spacers
shall be provided in accordance with Chapter 5, Section 9 of the CRSI Manual of Standard
Practice. Welding as an aid to fabrication and/or installation is not permitted.
3.05 PLACING AND FASTENING
The placing, fastening, splicing and supporting of reinforcing steel and wire mesh or bar mat
reinforcement shall be in accordance with the Drawings and the latest edition of "CRSI Rec-
ommended Practice for Placing Reinforcing Bars". In case of discrepancy between the
Drawings and the CRSI publication stated above, the Drawings shall govern. Reinforcement
shall be placed within the tolerances provided in ACI 117.
Steel reinforcement shall be accurately placed in the positions shown on the Drawings and
firmly held during the placing and setting of concrete by means of spacer strips, stays, metal
chairs or other approved devices or supports. Chair and bolster supports for slabs and walls
shall be spaced at a maximum of four foot centers unless otherwise shown in the Drawings.
Staples used to attach bar supports to wall and roof forms shall have the staple "tails" clipped
after form removal. For Columns, three wheels, spaced 120 degree apart, shall be placed
every four feet of column height. The CONTRACTOR may increase the column spiral pitch
if a conflict occurs with the wheel. Pre-tied column reinforcing steel lowered into column
forms shall be lowered vertically to prevent damage to the space wheels.
Bars shall be securely tied at 50% of all intersections except where spacing is less than one
foot in each direction, when alternate intersections shall be tied unless otherwise called out
in the Drawings or in applicable specifications. Tying of steel by spot welding will not be
permitted unless specifically authorized by the ENGINEER. The placing and securing of the
reinforcement in any unit or section shall be accepted by the ENGINEER before any con-
crete is placed in any such unit or section.
Bundle bars shall be tied together at not more than 6-foot centers.
LPATH Berm Erosion 03210-5 Reinforcing Steel
Protection Measures
3.06 SPLICING
Bar steel reinforcement shall be furnished in the full lengths indicated on the Drawings.
Splicing of bars, except where shown on the Drawings, will not be permitted without the
written acceptance of the ENGINEER. Splices shall be staggered. In cases where permis-
sion is granted to splice bars, other than those shown on the Drawings, the additional mate-
rial required for the lap shall be furnished by the CONTRACTOR at his own expense. The
minimum distance between staggered splices for reinforcing bars shall be the length required
for a lapped splice in the bar. All splices shall be full contact splices.
Splices will not be permitted at points where the section is not sufficient to provide a mini-
mum distance of two inches between the splice and the nearest adjacent bar or the surface of
the concrete.
Welding of reinforcement shall be done only if detailed on the Drawings or if authorized by
the ENGINEER in writing. Welding shall be done by a certified welder. The welding shall
conform to AWS D 12.1, Recommended Practices for Welding Reinforcing Steel, Metal In-
serts and Connections in Reinforced Concrete Construction, with the modifications and addi-
tions specified hereinafter. Where AWS D 2.0 Specifications for Welded Highway and
Railway Bridges is referenced, the reference shall be construed to be for AWS D 1.1. Where
the term AWS D1.1 is used it shall mean the American Welding Society Structural Welding
Code, D 1.1 as modified and amended by the AASHTO Standard Specifications for Welding
of Structural Steel Highway Bridges. After completion of welding, coating damage to coated
reinforcing steel bars shall be repaired.
When required or permitted, a mechanical connection may be used to splice reinforcing steel
bars or as substitution for dowel bars. The mechanical connection shall be capable of devel-
oping a minimum of 125% of the yield strength of the reinforcing bar in both tension and
compression. All parts of mechanical connections used on coated bars, including steel splice
sleeves, bolts, and nuts shall be coated with the same material used for repair of coating
damage.
3.07 CUTTING
When coated reinforcing bars are cut in the field, the ends of the bars shall be coated with the
same material used for repair of coating damage. All rebar cut in the field shall be cut with a
cut-off saw, any other method must be approved by the ENGINEER.
END OF SECTION
LPATH Berm Erosion 03210-6 Reinforcing Steel
Protection Measures
THIS PAGE INTENTIONALLY LEFT BLANK.
LPATH Berm Erosion 03310-1 Structural Concrete
Protection Measures
SECTION 03310
STRUCTURAL CONCRETE
PART 1 GENERAL
1.01 SECTION INCLUDES
The CONTRACTOR shall furnish all labor, tools and equipment for the construction of
reinforced cast-in-place concrete for sills as shown on the Drawings and herein specified.
This section includes basic finishing and curing methods, accessory control, and expansion
and contraction joint devices.
1.02 CONCRETE PRODUCER QUALIFICATIONS
The ready-mixed concrete supplier to the CONTRACTOR shall have the capability to
produce and deliver concrete, meeting the requirements of the Drawings and Specifications.
The supplier shall have a contingency plan for a back-up plant in the event of a mechanical
malfunction of one of the primary plant(s). This plan shall be submitted in accordance with
Section 01330.
1.03 RELATED SECTION
A. Section 03110 - Structural Cast-In-Place Concrete Forms
B. Section 03210 – Reinforcing Steel
C. Section 03320 - Construction Joints
D. Section 03350 - Concrete Finishing
E. Section 03900 - Concrete Curing
1.04 QUALITY STANDARDS
A. American Society for Testing Materials (ASTM)
1. ASTM C 33 - Concrete Aggregates
2. ASTM C 94 - Ready Mixed Concrete
3. ASTM C 150 - Portland Cement
4. ASTM C 260 - Air-entraining Admixtures for Concrete
5. ASTM C 494 - Chemical Admixtures for Concrete
6. ASTM C 618 - Fly Ash in Portland Cement Concrete
7. ASTM C 979 - Pigments for Colored Concrete
LPATH Berm Erosion 03310-2 Structural Concrete
Protection Measures
8. ANSI/ASTM D 994 - Preformed Expansion Joint Fillers
9. ASTM D 1751 - Preformed Non-Extruding and Resilient Expansion Joint
Fillers
10. ASTM D 3575 - Test Methods for Flexible Cellular Materials made from
Olefin Polymers
B. American Concrete Institute (ACI)
1. ACI 211 - Standard Practice for Selecting Proportions for Concrete
2. ACI 212 - Guide for Use of Concrete Admixtures
3. ACI 221 - Guide for Use of Normal Weight Aggregates
4. ACI 301 - Structural Concrete for Buildings
5. ACI 304 - Guide for Measuring, Mixing, Transporting and Placing Concrete
6. ACI 305 - Hot Weather Concreting
7. ACI 306 - Cold Weather Concreting
8. ACI 309 - Standard Practice for Consolidating Concrete
9. ACI 318 - Building Code Requirements for Structural Concrete
10. ACI 503 - Use of Epoxy Compounds
11. ACI 504 - Guide to Joint Sealants
1.05 SUBMITTALS
A. Product Data:
1. Admixtures (such as air-entraining and water-reducing admixtures)
2. Fly Ash
3. Form Release Agents
4. Ready Mixed Concrete Mix Designs
5. Form Ties
6. Bonding Agents
7. Grouts
8. Vibrator Specifications
LPATH Berm Erosion 03310-3 Structural Concrete
Protection Measures
9. Ready-Mixed Concrete Plant Production Contingency Plan
1.06 QUALITY ASSURANCE
A. Acquire cement and aggregate from the same source for all work.
B. Conform to ACI 305 for hot weather concrete placement
C. Conform to ACI 306 for cold weather concrete placement
D. Conform to ACI 309 for concrete consolidation
1.07 CONTRACTOR ASSISTANCE
The CONTRACTOR shall assist the OWNER or his concrete testing consultant as requested
during the performance of quality control testing. When concrete is placed using a concrete
pumper, concrete for testing will be taken from the pumper discharge hose.
1.08 DELIVERY, STORAGE, AND HANDLING
A. Ready-Mixed Concrete Delivery Ticket:
The ready-mixed concrete truck driver shall provide the batch ticket to the
ENGINEER at the time of concrete delivery. The ticket shall summarize the
following information legibly in an easily discernible table:
1. Weight in pounds of all materials, excepting the water reducing and air-
entraining agents which shall be in ounces.
2. Cubic yards batched
3. The ratio of water to cementitious (W / C) materials ratio
4. Temperature of the concrete at the time it was batched
5. Time of batching.
6. Free moisture in the fine and coarse aggregates in percent of weight of
aggregate.
7. Gallons of water that may be added at the site without exceeding the
permissible W / C ratio.
B. Delivery:
Delivery shall conform to the recommendations of ACI 304 as determined by the
ENGINEER.
LPATH Berm Erosion 03310-4 Structural Concrete
Protection Measures
PART 2 PRODUCTS
2.01 CEMENT
Cement shall be Portland Cement Type II, unless otherwise indicated on the Drawings.
2.02 AGGREGATE
A. Fine Aggregate:
Fine aggregate shall consist of hard, strong, durable particles to the provisions of
ASTM C 33.
B. Coarse Aggregate:
Coarse aggregate shall conform to the provisions of ASTM C 33 except that all
aggregate shall be crushed aggregate. Screened aggregate is unacceptable.
2.03 WATER
Water shall be clean and free from injurious amounts of oils, acids, alkalis, salts, organic
materials, or other substances that may be deleterious to concrete or steel. Mixing water for
prestressed pretensioned and prestressed post-tensioned concrete or for concrete which will
contain aluminum embedments, shall not contain deleterious amounts of chloride ion.
Unless otherwise permitted or specified in the Drawings, the concrete shall be proportioned
and produced to have a slump not to exceed four inches or less than two and one-half inches.
Concrete not consolidated by internal vibration shall be proportioned to have a slump not to
exceed five and one-half inches or less than four inches. The slump shall be determined by
the "Test for Slump of Portland Cement" ASTM C 143.
2.04 ADMIXTURES
Admixtures to be used in concrete shall be subject to prior acceptance by the ENGINEER.
The admixture shall maintain the same composition and performance throughout the work as
the product used in the concrete proportions established in accordance with ACI 211.
Admixtures containing chloride ions shall not be used.
A. Air Entrainment:
An air-entraining agent shall be used in all concrete. The agent used shall conform
to ASTM C 260.
Unless otherwise shown in the Drawings, the amount of air entraining agent used in
each concrete mix shall be such as will effect the entrainment of the percentage of air
shown in the following tabulation in the concrete as discharged from the mixer. This
table is applicable for concrete strengths less than 5000 psi.
LPATH Berm Erosion 03310-5 Structural Concrete
Protection Measures
Table 1
Nominal
max.
aggregate
size, in.
Average air content, percent
Severe exposure Moderate
exposure
3/8 7 1/2 ± 1 1/2 6 ± 1 1/2
¾ 6 ± 1 1/2 5 ± 1 1/2
1 1/2 5 1/2 ± 1 1/2 4 1/2 ± 1 1/2
The level of exposure will be determined by the ENGINEER.
B. Water Reducing, Set-Controlling Admixture:
The CONTRACTOR shall use a “mid-range” water reducing, set controlling
admixture, Polyheed 997, or equal. The water-reducing admixture shall be used in
all concrete and shall conform to ASTM C 494, specifically Types A, B, C, D and E.
C. Finely Divided Mineral Admixtures:
Mineral admixtures shall be limited to fly ash conforming to ASTM C 618, Class C.
2.05 BATCHING
Measuring and batching of materials shall be done at a batching plant.
A. Portland Cement:
Either sacked or bulk cement may be used. No fraction of a sack of cement shall be
used in a batch of concrete unless the cement is weighed. Bulk cement shall be
weighed on scales separate and distinct from the aggregate hopper or hoppers.
Batching shall be such that the accuracy of batching shall be plus or minus one
percent of the required weight.
B. Water:
Unless water is to be weighed, the water-measuring equipment shall include an
auxiliary tank from which the measuring tank shall be filled. In lieu of the volume
method, the CONTRACTOR will be permitted to use a water-metering device.
C. Aggregates:
Aggregates shall be handled from stockpiles or other sources to the batching plant in
such a manner as to secure a uniform grading of the material. Aggregates that have
become segregated, or mixed with earth or foreign material, shall not be used.
Batching shall be so conducted as to result in the weights of material required for
each type aggregate within a tolerance of two percent.
Free water contents of the coarse and fine aggregates shall be continuously tested
LPATH Berm Erosion 03310-6 Structural Concrete
Protection Measures
and concrete mixture adjusted for moisture conditions of the aggregate in order to
meet the designated water/cement ratio.
D. Fine Aggregate:
The proportion of fine aggregate shall be between 36 and 44 percent by volume of
the total aggregates in the concrete.
2.06 MIXING
Ready-mixed concrete shall be either “central mixed” or “shrink mixed” concrete as defined
in ASTM C 94. “Truck mixed” concrete as defined in ASTM C 94 shall not be permitted.
Mixing time shall be measured from the time water is added to the mix, or cement contracts
the aggregate. All concrete shall be homogeneous and thoroughly mixed, and there shall be
no lumps or evidence of undispersed cement. Mixers and agitators, which have an
accumulation of hard concrete or mortar, shall not be used. Ready-mixed concrete shall be
mixed and transported in accordance with ASTM C 94.
The temperature of mixed concrete, immediately before placing shall not be less than 50°F or
more than 80°F for slabs larger than 10,000 square feet and not be less than 50°F or more
than 85°F for walls. Aggregates and water shall be heated or cooled as necessary to produce
concrete within these temperature limits. Neither aggregates nor mixing water shall be
heated to exceed 150°F.
The time elapsing from the time water is added to the mix (or the cement comes in contact
with aggregate) until the concrete is deposited in place at the site of the work shall not
exceed 45 minutes when the concrete is hauled in non-agitating trucks, nor more than 90
minutes when hauled in truck mixers or truck agitators.
The batch shall be so charged into the drum that a portion of the mixing water shall enter in
advance of the cement and aggregates. The flow of water shall be uniform and all water shall
be in the drum by the end of the first 1/4 of the specified mixing time.
Cement shall be charged into the mixer by means that will not result in loss of cement due to
the effect of wind, or in accumulation of cement on surfaces of hoppers or in other
conditions which reduce or vary the required quantity of cement in the concrete mixture.
2.07 TRANSPORTING MIXED CONCRETE - MIXED CONCRETE OR TRUCK MIXERS
Transporting of mixed concrete shall conform to ASTM C 94.
Truck agitators shall be loaded not to exceed the manufacturer's guaranteed capacity. They
shall maintain the mixed concrete in a thoroughly mixed and uniform mass during hauling.
No additional mixing water shall be incorporated into the concrete during hauling or after
arrival at the delivery point, unless approved. If additional water is to be incorporated into
the concrete at the site, the drum shall be revolved not less than 30 revolutions at mixing
speed after the water is added and before discharge is commenced. One addition of water at
the site to adjust mix workability is permitted but the maximum water cement ratio shall not
be exceeded.
LPATH Berm Erosion 03310-7 Structural Concrete
Protection Measures
The CONTRACTOR shall furnish a water-measuring device in good working condition,
mounted on each transit mix truck, for measuring the water added to the mix on the site. All
water tanks on transit mix trucks shall be filled prior to being batched and arrive at the
construction site 100% full.
Each load of ready mixed concrete delivered at the job shall be accompanied by the ticket
referencing design mix and showing volume of concrete, the weight of cement in pounds,
percent of free water in coarse and dry aggregates, and the total weight of all ingredients in
pounds. The ticket shall also show the time of day at which the materials were batched and
the reading of the revolution counter at the time the truck mixer is charged. See Paragraph
1.08.
2.08 COMPRESSIVE STRENGTH
Concrete compressive strength requirements consist of a minimum strength that must be
obtained before various loads of stresses are applied to the concrete and, for concrete
designated by strength, a minimum strength at the age of 28 days. Unless otherwise shown
on the Drawings, the 28-day compressive strength of structural concrete shall be a minimum
of 4,000 psi.
The mix shall be designed for required strengths in accordance with ACI 301. The ratio of
water to the sum of concrete + pozzolan shall not exceed 0.41 by weight for durable,
watertight, concrete. The amount of fly ash in the mix shall be between 15 and 20 percent by
weight of the total cementitious materials.
2.09 CONCRETE VIBRATORS
Concrete vibrators for consolidating concrete shall be 2 1/2 inch diameter "high cycle"
vibrators with a frequency under load of 8,000 - 10,400 vibrations per minute (vpm).
Concrete vibrators of lesser capacity are unacceptable for use in any part of the construction.
The CONTRACTOR shall have at least one standby concrete vibrator ready for use for every
two concrete vibrators in use during a concrete placement.
PART 3 EXECUTION
3.01 PRIOR TO PLACEMENT
Prior to placing concrete the CONTRACTOR shall remove all debris and thoroughly dampen
the surfaces that will be in contact with the concrete to be placed.
The CONTRACTOR shall use compressed air from an air-compressor to blow-out
construction debris and dirt at the bottom of members to be placed such as walls, beams and
columns, prior to final placement of forms that will obscure any joint. The CONTRACTOR
shall demonstrate to the ENGINEER that all debris, such as concrete particles, saw dust,
loose tie wire, bar tags, tape, trash and dirt, have been thoroughly removed.
No concrete shall be placed when form surfaces that will be in contact with the concrete,
LPATH Berm Erosion 03310-8 Structural Concrete
Protection Measures
reinforcement, embedded items or sub-base is less than 32°F. When the mean daily outdoor
temperature is less than 40°F, the temperature of the concrete shall be maintained between
50°F and 70°F for the required curing period. When necessary, arrangements for heating,
covering, insulating, or housing the concrete work shall be made in advance of placement
and shall be adequate to maintain the required temperature without injury due to
concentration of heat. Combustion heaters shall not be used during the first 24 hours unless
precautions are taken to prevent exposure of the concrete to exhaust gases which contain
carbon dioxide.
Concrete shall not be placed against forms exposed to heating by the unless the temperature
of the forms is first cooled to ≤ 90°F.
3.02 PLACEMENT
Placement shall conform to ACI 301, Chapter 8 "Placing", ACI 304R, "Guide of Measuring,
Mixing, Transporting and Placing Concrete," ACI 306 "Recommended Practice for Cold
Weather Concreting", ACI 305 "Recommended Practice for Hot Weather Concreting" and
ACI 309, "Standard Practice for Consolidation of Concrete". No concrete shall be placed
until all formwork, reinforcement, installation of parts to be embedded, bracing of forms, and
preparation of surfaces involved in the placing have been reviewed by the ENGINEER. No
concrete shall be placed in water except with the written permission of the ENGINEER. All
surfaces of forms and embedded materials that have become encrusted with dried mortar or
grout from concrete previously placed shall be cleaned of all such mortar or grout before the
surrounding or adjacent concrete is placed. Immediately before placing concrete, all surfaces
upon or against which the concrete is to be placed shall be free from standing water, mud,
debris or loose materials. The surfaces of absorptive materials against or upon which
concrete is to be placed shall be moistened thoroughly so that moisture will not be drawn
from the freshly placed concrete. The concrete shall be placed by equipment that will
prevent segregation or loss of ingredients. The stream of concrete shall not be allowed to
separate by permitting it to fall freely over rods, spacers or other embedded materials.
No wetting of concrete surfaces during slab finishing operations shall be permitted. Further,
no concrete finishing operation shall be permitted while there is water on the surface of slabs
and other flatwork.
Unless otherwise called out in these Specifications or shown in the Drawings, the placement
lift depth of concrete in walls shall be limited to two feet or less to minimize surface defects
such as air voids that can form on concrete surfaces. Lift depths will be limited to one foot
if, in the opinion of the ENGINEER, the quality of the finish is unacceptable at the 2-foot lift
depth.
3.03 CONSOLIDATION
All concrete shall be thoroughly consolidated with internal vibrators as recommended in ACI
309 immediately after deposition. The concrete shall be thoroughly worked around the
reinforcing steel, around embedded items and into corners of forms. Vibration shall be
supplemented by spading, rodding or forking to eliminate all honeycomb and voids around
embedded items.
The vibrator shall be inserted vertically, allowing it to penetrate rapidly to the bottom of the
lift and at least six inches into the previous lift. The vibrator shall be held at the bottom of
LPATH Berm Erosion 03310-9 Structural Concrete
Protection Measures
lift for 5 to 15 seconds. The vibrator shall be pulled up at a rate of about three inches per
second.
The vibrator shall be inserted so that the fields of action overlap. The field of action is
approximately eight times the vibrator’s head diameter. Thus for a 2 1/2 inch diameter
vibrator, the spacing of each insertion will be approximately 20 inches.
Vibration shall be stopped when the concrete surface takes a sheen and large air bubbles no
longer escape.
Do not use a vibrator to move concrete horizontally.
3.04 OPENINGS AND INSERTS
Pipe sleeves, inserts for pipe connections, anchors and forms for pipe holes must be
accurately placed and securely fastened to the forms in such a manner that the placing of
concrete will not alter their alignment or location. In the event that openings are
inadvertently omitted or improperly placed, the ENGINEER may require the concrete to be
cored at the proper location. Filling of improperly placed openings shall be done with
expansive grout or dry pack or mortar applied with an accepted epoxy adhesive. The
surfaces of the opening shall be roughened prior to filling.
3.05 EMBEDDED ITEMS
At the time of concrete placement, embedded items should be clean and free from mud, oil
and other coatings that may adversely affect bonding capacity. Aluminum embedments shall
be coated with a bituminous material to prevent electrolytic action between the embedded
item and reinforcing steel that results in concrete deterioration. Embedment items shall be
accurately placed and securely fastened to the forms in such a manner that the placing of
concrete will not alter their alignment or location. Contact between embedded items and
reinforcing steel or tendon ducts is unacceptable and is not permitted.
3.06 CONSTRUCTION JOINTS
The location of all construction joints will be subject to the acceptance of the ENGINEER.
The surface of all construction joints shall be thoroughly cleaned and all laitance and
standing water removed. Clean aggregate shall be exposed by abrasive blast cleaning. Wire
brushing and air water jets may be used while concrete is fresh provided results are equal to
abrasive blast cleaning. Construction joints shall be keyed at right angle to the direction of
shear. Except where otherwise shown on the Drawings, keyways shall be at least 1-1/2" in
depth over at least 25% of the area of the section.
3.07 EVAPORATIVE RETARDANT
The use of an evaporative retardant is required to assist in proper placement of concrete. See
Section 03390. When an evaporative retardant is used, it shall be applied two times: after
screeding and after the first floating operation. The retardant should be applied at a rate of
one gallon of sprayable solution per 200 - 400 square feet by spraying with an industrial type
sprayer. If the nozzle of the sprayer becomes plugged, the CONTRACTOR shall clean, or
replace, the nozzle. Under no circumstances shall the retardant be used except by spraying a
LPATH Berm Erosion 03310-10 Structural Concrete
Protection Measures
mist with a nozzle. The retardant shall be applied in strict conformance with the
manufacturer’s recommendations and precautions. In no case shall the retardant be used as a
finishing agent. The use of an evaporative retardant requires review and approval by the
ENGINEER.
END OF SECTION
LPATH Berm Erosion 03320-1 Construction Joints
Protection Measures
SECTION 03320
CONSTRUCTION JOINTS
PART 1 GENERAL
1.01 SECTION INCLUDES
The CONTRACTOR shall supply all labor, tools, equipment and material for the preparation
of construction joints in concrete in accordance with these specifications and as shown in the
Drawings. This includes joints such as column-footing joints, wall construction joints, col-
umn capital-slab joints, grout closures around pipe-slab penetrations and footing-slab joints.
1.02 RELATED SECTIONS
A. Section 03110 - Structural Cast-In-Place Concrete Forms
B. Section 03210 - Reinforcing Steel
C. Section 03310 - Structural Concrete
D. Section 03615 - Grout
1.03 QUALITY STANDARDS
A. American Concrete Institute (ACI)
1. ACI 117 - Standard Tolerance for Concrete Construction and Materials
2. ACI 301 - Specifications for Structural Concrete for Buildings
3. ACI 302 - Guide for Concrete Floor and Slab Construction
4. ACI 318 - Building Code Requirements for Structural Concrete
1.04 CONSTRUCTION REVIEW
The ENGINEER shall review the preparation of all construction joints prior to concrete and
grout closure placements. It is the responsibility of the CONTRACTOR to notify and pro-
vide a minimum of 24 hours notice to the ENGINEER of these activities. If joint placement
is performed without the ENGINEER’s presence, the work will be deemed unacceptable and
non-conforming to these specifications. If the ENGINEER determines that construction re-
view of a particular activity is unnecessary, he will provide written direction to the
CONTRACTOR to proceed with that particular activity without his construction review.
PART 2 PRODUCTS (Not Applicable)
LPATH Berm Erosion 03320-2 Construction Joints
Protection Measures
PART 3 EXECUTION
3.01 SURFACE PREPARATION
The surface of concrete construction joints shall be clean and all materials that inhibit bond,
such as curing compounds, laitance, saw dust, wood, dirt, polyethylene, pipe tape coating
and paper shall be removed. Concrete shall be roughened to produce a rough, plus or minus
1/16 inch, surface texture. Concrete surfaces shall be wetted with clean potable water and
standing water removed immediately before new concrete or closure grout is placed. Unless
otherwise called out in the Drawings, a bonding agent shall be used prior to placing the con-
crete or grout.
3.02 PIPE GROUT CLOSURE SECTIONS
A. Pipe Surface Preparation
Unless otherwise detailed in Drawings, all pipes penetrating concrete sections such
as wall and floor slabs shall have all coatings and other materials that can inhibit
bond completely removed from the portion of the pipe to be in contact with the con-
crete or slab closure grout.
B. Ground Surface Preparation
The ground surface at joints such as pipe / slab closures shall be smooth and properly
graded and compacted. All debris such as Styrofoam, paper, polyethylene and
wood shall be removed. The ground surface shall be dampened and prepared to pre-
vent the inclusion of dirt, pieces of aggregate or balls of soil in the concrete or grout.
3.03 CONCRETE AND CLOSURE GROUT PLACEMENT
Mixing, surface preparation in addition to that prescribed above, placement, and curing of
grout at pipe closure joints shall be performed in strict accordance with Specification Section
03615 and when a proprietary grout is specified, with the grout manufacturer’s directions.
Special care shall be taken to insure that the grout is thoroughly and properly consolidated at
waterstops, pipe weep rings, and existing concrete surfaces. An appropriate capacity vibrator
shall be used when necessary or required by the manufacturer to properly consolidate the
grout.
END OF SECTION
LPATH Berm Erosion 03350-1 Concrete Finishing
Protection Measures
SECTION 03350
CONCRETE FINISHING
PART 1 GENERAL
1.01 SECTION INCLUDES
The CONTRACTOR shall supply all labor, tools, equipment and materials to finish properly
placed concrete for structures such as box culverts, vaults, foundations, hydraulic and water
retaining structures.
The means and methods of repair of improperly placed or finished concrete shall be reviewed
by the ENGINEER prior to performing the work. Regardless of prior approval of the means
and methods of concrete finish repair, no concrete finish shall be repaired until the
ENGINEER has reviewed the existing finish. This includes defects caused by ineffective
and improper vibration such as honeycomb, excessive air voids on formed surfaces,
placement “pour” lines (cold joints) and sand streaking. It also includes defects caused by
excessive form deflections, form damage or form failure.
Unless otherwise called out in the Drawings tie holes shall be finished as specified herein.
1.02 RELATED SECTIONS
A. Section 03110 - Structural Cast-In-Place Concrete Forms
B. Section 03310 - Structural Concrete
C. Section 03615 - Grout
1.03 QUALITY STANDARDS
A. American Concrete Institute
1. ACI 116 - Cement and Concrete Terminology
2. ACI 121 - Quality Assurance Systems for Concrete Construction
3. ACI 301 - Specifications for Structural Concrete for Buildings
4. ACI SP-15 - ACI 301 Field Reference Manual
5. ACI 304 - Placing Concrete by Pumping Methods
6. ACI 309 - Identification and Control of Consolidation-Related Surface
Defects in Formed Concrete
7. ACI 311 - Guide for Inspection of Concrete
LPATH Berm Erosion 03350-2 Concrete Finishing
Protection Measures
B. American Society for Testing and Materials
1. ASTM STP 169C - Significance of Tests and Properties of Concrete and
Concrete-Making Materials
2. ASTM C 150 - Standard Specification for Portland Cement
3. ASTM C 33 - Concrete Aggregates
C. US Department of Interior - Bureau of Reclamation
1. M-47 Standard Specifications for Repair of Concrete
1.04 SUBMITTALS
A. General
Submittals shall be made in accordance with Section 01330.
B. Product Data
1. Grouts
2. Bonding agents
3. Means and methods of repairing defects unless otherwise called out herein.
C. Manufacturer’s safety data sheets
1.05 DELIVERY, STORAGE AND HANDLING
Deliver the materials to the project site in the manufacturer’s containers with all labels intact
and legible at the time of use. Materials shall be stored in a secure, indoor, dry area.
Maintain grouts and aggregates in a dry condition during delivery, storage, and handling.
PART 2 PRODUCTS
2.01 PREMIXED PRE-PACKAGED GROUTS
A. Master Builders EMACO R320
B. Master Builders EMACO S66-CR
2.02 EPOXY BONDING AGENTS
A. Master Builders Concresive Liquid (LPL)
B. Master Builders Concresive Standard Liquid
LPATH Berm Erosion 03350-3 Concrete Finishing
Protection Measures
2.03 CEMENT
ASTM C 150, Type 1
2.04 AGGREGATE
ASTM C 33, 100% passing the No. 30 mesh sieve
2.05 BOND COAT MORTAR
Mortar used to bond patching mortar shall be made of the same materials and of
approximately the same proportions as used for the concrete, except that the coarse aggregate
shall be omitted and the mortar shall consist of 1 part cement to not more than 1 part sand by
damp loose volume.
2.06 PATCHING MORTAR
Patching mixture shall be made of the same materials and of approximately the same
proportions as used for the concrete, except that the coarse aggregate shall be omitted and the
mortar shall consist of 1 part cement to not more than 2-1/2 parts sand by damp loose
volume. White Portland Cement shall be substituted for a part of the gray Portland Cement
on exposed concrete in order to produce a color matching the color of the surrounding
concrete, as determined by a trial patch. The quantity of mixing water shall be no more than
necessary for handling and placing. The patching mortar shall be mixed in advance and
allowed to stand with frequent manipulation with a trowel, without addition of water, until it
has reached the stiffest consistency that will permit placing.
2.07 WATER
Only clean potable water shall be used. A calibrated measuring device is required for
measuring the proper amount of water to be added to pre-packaged grouts and mortars.
PART 3 EXECUTION
3.01 REPAIR OF SURFACE DEFECTS
Surface defects, unless otherwise specified by the Contract Documents, shall be repaired
immediately after form removal but not before review by the ENGINEER. The surface
temperature of the concrete shall be 50° F and rising. The CONTRACTOR shall measure
surface temperatures when requested by the ENGINEER. If necessary the CONTRACTOR
shall enclose and heat the area to be repaired to bring the surface temperature of the concrete
and air temperature to acceptable levels and to permit proper curing.
All honeycombed and other defective concrete shall be removed down to sound concrete. If
chipping is necessary, the edges shall be perpendicular to the surface or slightly undercut.
Feathered edges will not be permitted. The area to be patched and an area at least six inches
wide surrounding it shall be dampened to prevent absorption of water from the patching
mortar. A bonding grout shall be prepared, mixed to the consistency of thick cream, and
after surface water has evaporated from the area to be patched, well brushed into the surface.
LPATH Berm Erosion 03350-4 Concrete Finishing
Protection Measures
When the bond coat begins to lose the water sheen, the premixed patching mortar shall be
applied. The mortar shall be thoroughly consolidated into place and struck off so as to leave
the patch slightly higher than the surrounding surface. To permit initial shrinkage, it shall be
left undisturbed for at least one hour before being finally finished. The patched area shall be
kept damp for seven days. Metal tools shall not be used in finishing a patch in a formed wall
that will be exposed.
3.02 TIE HOLES
A. Water Retaining Structures and Below Grade Vaults with Breakback Cone Ties
Fill tie holes solid as specified in Section 03615.
B. Other Structures
After being cleaned and thoroughly dampened, fill tie holes solid as specified in
Section 03615.
3.03 PROPRIETARY MATERIALS
Certain types of defects may require the use proprietary compounds for adhesion or as
patching ingredients. The ENGINEER will review these defects and request means and
methods for these repairs from the CONTRACTOR.
In lieu of, or in addition to, the foregoing patching procedures using bond coat and patching
mortars, epoxy bonding agents and premixed pre-packaged grouts may be used for repair of
defective areas. Such compounds shall be used in accordance with the manufacturer's
written recommendations and directions. The ENGINEER shall review and provide written
acceptance of these procedures.
3.04 FINISHING OF FORMED AND UNFORMED SURFACES
Finishes shall be performed as called out in the Drawings and in referenced Specifications.
A. Formed Surfaces
1. Smooth Form Finish
The form facing material shall produce a smooth, hard, uniform texture on
the concrete. The arrangement of the facing material shall be orderly and
symmetrical, with the number of seams kept to the practical minimum.
Surface textures that result from forms with raised grain, torn surfaces, worn
edges, patches, dents, or other defects shall be ground smooth or otherwise
repaired.
a. Air Voids on Formed Surfaces
Air voids on formed surfaces deeper than 1/4 inch shall be filled
with patching mortar. The frequency and size of air voids shall be
equal to or better than shown in Figure 1. The total void area is 1%
of the surface area, or 0.36 sq. in. This 6-inch x 6-inch figure is the
LPATH Berm Erosion 03350-5 Concrete Finishing
Protection Measures
visual standard for acceptance of the finish that does not require
filling of air voids.
b. Tie Holes
Tie holes shall be filled as specified in section 03615.
c. Form Fins
Chip or rub-off form fins exceeding 1/16 inch in height.
Figure 1
LPATH Berm Erosion 03350-6 Concrete Finishing
Protection Measures
d. Rock Pockets
Poorly consolidated concrete shall be removed to sound concrete
and the defect repaired. The ENGINEER shall outline the area to be
repaired.
2. As-Cast Finish
For as-cast concrete finish form materials shall produced a sound surface.
a. Air Voids
Fill air voids deeper than 1/4 inch. and larger than 0.50 sq. in. The
total area of acceptable air voids is 0.72 sq. in. in a 6 inch by 6-inch
square.
b. Tie Holes
Tie holes shall be filled as specified in section 03615.
c. Form Fins
Chip or rub-off form fins exceeding 1/8 inch in height.
3. Rubbed Finish
Immediately after removing the forms, form ties shall be broken back a
minimum of 3/4 inch from the surface, honeycomb, voids and other surface
defects grouted. The surfaces shall then be thoroughly dampened and
rubbed with a No. 16 carborundum stone or equal abrasive to create a
uniform surface paste. The rubbing shall be continued to remove all form
marks and surface irregularities producing a smooth, dense surface. After
setting, the surface shall then be rubbed with a No. 30 carborundum stone
until the surface is smooth in texture and uniform in color. Unless otherwise
shown in the Drawings only exposed surfaces shall have a rubbed finish.
4. Grout Finish
Prepare surface as described in Rubbed Finishes above. Mix one part
Portland cement and one-half parts fine sand with sufficient water to
produce a grout with the consistency of thick paint. Wet surface of concrete
to prevent absorption of water from grout and apply grout uniformly with
brushes. Immediately after applying grout mix, scrub the surface with a cork
float or stone to coat surface and fill remaining air voids and other remaining
surface defects. Remove excess grout by working the surface with rubber
float. After the surface whitens from drying, rub with clean burlap. Cure
surface for a period of 72 hours
LPATH Berm Erosion 03350-7 Concrete Finishing
Protection Measures
B. Unformed Surface
Unless otherwise shown in the Drawings unformed surfaces shall be finished as
follows.
1. Slabs
Screed with straightedge to remove low and high spots bringing the surface
to the required finish elevation of slope and float with a steel float at least 3
feet in width. When the concrete has reached its initial set, finish with a
steel (power) trowel. Leave finish essentially free of trowel marks, uniform
in texture and appearance and plane to the correct tolerance. Dusting the
surface with dry cement, sand or sprinkling with water is prohibited.
Finishes that are exposed and subject to foot traffic shall receive a broom
finish with a texture of ± 1/16 inch.
2. Tops of Walls with Bearings
Strike smooth tops of walls and similar unformed surfaces that will have
bearings or bearing pads, and finish with a steel trowel.
3. Tops of Exposed Footings in Reservoirs
Strike smooth tops of footings and finish with a light broom providing a
texture of ± 1/16 inch.
4. Stairways and Sidewalks
Strike smooth tops of stairs and sidewalks and finish with a light broom
providing a texture of ± 1/16 inch.
5. Slabs with Waterproofing Membranes
Strike smooth and float finish.
6. Construction Joint Surfaces
Surface shall be broom or raked finished. Surface shall be water or grit
blasted prior to placing additional concrete, such as columns on column
footings and column footings on reservoir slabs.
END OF SECTION
LPATH Berm Erosion 03350-8 Concrete Finishing
Protection Measures
THIS PAGE INTENTIONALLY LEFT BLANK.
LPATH Berm Erosion 03390-1 Concrete Curing
Protection Measures
SECTION 03390
CONCRETE CURING
PART 1 GENERAL
1.01 WORK INCLUDED
The CONTRACTOR shall furnish all labor, tools and equipment for curing plain and
reinforced cast-in-place concrete.
1.02 RELATED WORK
A. Section 03310 – Structural Concrete
B. Section 03320 – Construction Joints
C. Section 03350 – Concrete Finishing
1.03 QUALITY STANDARDS
A. American Concrete Institute (ACI)
1. ACI 305 - Hot Weather Concreting
2. ACI 306 - Cold Weather Concreting
3. ACI 308 - Standard Practice for Curing Concrete
B. American Society for Testing Materials (ASTM)
1. ASTM C 171 – Sheet Materials for Curing Concrete
2. ASTM C 309 – Liquid Membrane-Forming Compounds for Curing Concrete
3. ASTM D 2103 – Polyethylene Film and Sheeting
1.04 SUBMITTALS
Provide data on curing compounds sheet materials and methods of securing sheet materials in
place.
1.05 QUALITY CONTROL
Perform the work in accordance with this Specification and in accordance with applicable
ACI standards. When a conflict occurs between this Specification and ACI occurs, the ACI
standard shall control. The CONTRACTOR shall have a copy of the current applicable ACI
standards on site. All materials shall be used in accordance with the manufacturer’s printed
instructions, a copy of which shall be on site.
1.06 DELIVERY, STORAGE AND HANDLING
Deliver, store and handle products under the provisions of Section 01650.
LPATH Berm Erosion 03390-2 Concrete Curing
Protection Measures
Deliver curing materials in manufacturer’s original packaging including applicable
instructions and manufacturer’s safety data sheets (MSDS).
PART 2 PRODUCTS
2.01 SHEET MATERIALS FOR CURING CONCRETE
White burlap-polyethylene sheeting weighing not less than 10 oz/linear yard, 40 inches wide,
impregnated on one side with white opaque polyethylene 0.004 inches thick as specified in
ASTM C 171 shall be used when called out in the Drawings or in other applicable
specifications. The polyethylene shall be securely bonded to the burlap so that there will be
no separation.
2.02 LIQUID MEMBRANE-FORMING COMPOUNDS FOR CURING CONCRETE
Liquid membrane-forming compounds for curing concrete shall and conform to ASTM C
309, Type 1-D with a red or white fugitive dye. Use a white dye unless otherwise directed by
the ENGINEER.
2.03 POLYETHYLENE FILM
Polyethylene film shall conform to ASTM D 2103. The film shall have a thickness of 6 mils
and be a white opaque color.
2.04 LIQUID MEMBRANE FORMING COMPOUND AND EVAPORATIVE RETARDANT
APPLICATORS/ SPRAYERS
Membrane curing and evaporative retardant compounds shall be applied with a sprayer
manufactured by Allen Engineering, Inc., or equal, capable of maintaining a constant
pressure. (Allen Engineering, Inc., P.O. Box 819, Paragould, Arizona 74450, telephone (800)
643-0095.) Unless otherwise accepted in writing by the ENGINEER, spraying membrane
curing compounds or evaporative retardants by other methods, such as hand pressurized
sprayers, is unacceptable.
2.05 EVAPORATIVE RETARDANT
Confilm manufactured by Master Builders, Inc. or approved equal.
2.06 WATER
Water shall only be used when prior approval is granted by the ENGINEER. Only water that
has been determined to be non-detrimental to concrete shall be used.
PART 3 EXECUTION
3.01 GENERAL
Beginning immediately after placement, concrete shall be protected from premature drying,
excessively hot or cold temperatures, and mechanical injury, and shall be maintained with
minimal moisture loss at a relatively constant temperature for the period necessary for
hydration of the cement and hardening of the concrete in accordance with ACI 308,
"Standard Practice for Curing Concrete". The materials and method of curing shall be subject
LPATH Berm Erosion 03390-3 Concrete Curing
Protection Measures
to review and acceptance by the ENGINEER. Specific curing requirements may be called
out on the Drawings or other Technical Specifications.
Curing shall be continued for at least seven days. Alternatively, if tests are made of cylinders
kept adjacent to the structure and cured by the same methods, moisture retention measures
may be terminated when the average compressive strength has reached 70% of the specified
concrete strength.
When a spray applied membrane-curing compound is used, it shall be applied in two coats
with the second coat applied at right angles to the first coat.
3.02 EVAPORATIVE RETARDANT
An evaporative retardant shall be used during concrete placement for water retaining
structure floor and roof slabs and other slabs larger than 2,500 square feet in size. The
retardant shall be sprayed using a power sprayer at a rate of 10 gallons per 2,000 square feet
after screeding and repeated after the first floating operation. The evaporative retardant shall
not be applied during the final steel troweling operations or after the water sheen has
disappeared from the concrete surface.
3.03 SLABS
For concrete surfaces not in contact with forms, a procedure determined by the ENGINEER
shall be applied immediately after completion of placement and finishing.
3.04 WALLS AND COLUMNS
Moisture loss from surfaces placed against wooden or metal forms exposed to heating by the
sun shall be minimized by keeping the forms wet until they can be safely removed. After
form removal, the concrete shall be cured until the end of the curing time by one of the
previously described curing methods. Concrete shall not be placed against forms that have
been exposed to air below freezing temperatures until the forms have been heated so that the
surface temperature of the form is ≥ 40° F.
The top of walls and columns not covered by forms shall be cured using a membrane-curing
compound conforming to ASTM C 309 immediately after placement
3.05 OTHER SURFACES
Unless otherwise shown in the Drawings all other surfaces shall be cured using two
applications of a membrane-curing compound conforming to ASTM C 309. The second
application shall be applied at 90° to the first application.
3.06 COLD WEATHER
Curing during cold weather conditions shall include the above methods except for water cure
unless measures are taken to prevent freezing of the water.
3.07 HOT WEATHER
If the rate of evaporation approaches 0.2 lb/ft2
/hr, as estimated by ACI 305, precautions
against plastic shrinkage cracking are required. The CONTRACTOR shall have a recording
LPATH Berm Erosion 03390-4 Concrete Curing
Protection Measures
thermometer, hygrometer and wind gage on site seven days prior to first concrete placement.
When necessary, provision for windbreaks, shading, fog spraying, sprinkling, ponding, or wet
covering with a light colored material shall be made in advance of placement, and such
protective measures shall be taken as quickly as concrete hardening and finishing operations
will allow. Precautions against plastic shrinkage cracks may be required in conditions other
than what is normally considered hot weather conditions.
3.08 RATE OF TEMPERATURE CHANGE
Changes in temperature of the air immediately adjacent to the concrete during and
immediately following the curing period shall be kept as uniform as possible and shall not
exceed 5° F in any one hour or 50° F in any 24-hour period.
3.09 PROTECTION FROM MECHANICAL INJURY
During the curing period, the concrete shall be protected from damaging mechanical
disturbances, such as load stresses, heavy shock, and excessive vibration. All finished
concrete surfaces shall be protected from damage by construction equipment, materials, or
methods, by application of curing procedures, and by rain or running water. Self-supporting
structures shall not be loaded in such a way as to overstress the concrete.
END OF SECTION
LPATH Berm Erosion 03615-1 Grout
Protection Measures
SECTION 03615
GROUT
PART 1 GENERAL
1.01 SECTION INCLUDES
The Contractor shall furnish all labor, tools and equipment for the placement of grout in tie
holes and other locations as shown on the Drawings and specified herein.
This section includes basic mixing, application, and curing methods for grout.
Contractor shall have a printed set of manufacturer’s recommendations for product use on
site for review during preparation, mixing and application of grouts.
1.02 RELATED SECTIONS
A. Section 03110 - Structural Cast-In-Place Concrete Forms
B. Section 03310 - Structural Concrete
C. Section 03320 - Construction Joints
D. Section 03350 - Concrete Finishing
E. Section 03900 - Concrete Curing
1.03 QUALITY STANDARDS
A. ASTM C 78 - Test Method for Flexural Strength of Concrete (Using Simple Beam
with Third-Point Loading
B. ASTM C 109 - Test Method for Compressive Strength of Hydraulic Cement Mortars
- Modified
C. ASTM C 469 - Test Method for Static Modulus of Elasticity and Poisson’s Ratio of
Concrete in Compression
D. ASTM C 666 - Test Method for Resistance of Concrete to Rapid Freezing and
Thawing
E. ASTM C 882 - Test Method for Bond Strength of Epoxy Resin Systems used with
Concrete - Modified
F. ASTM C 1012 - Test Method for Length Change of Hydraulic Cement Mortars Ex-
posed to Sulfate Solution - Modified
G. ASTM C 1202 - Electrical Indication of Resistance to Chloride Ion Penetration
LPATH Berm Erosion 03615-2 Grout
Protection Measures
1.04 SUBMITTALS
A. Grout
B. Bonding Agent
C. Curing Compound
1.05 QUALITY ASSURANCE
A. Field Tests
1. When the Owner is to perform grout testing, the Contractor shall assist the
Owner or his concrete testing consultant as requested during the perform-
ance of quality control testing.
2. When prescribed in the Drawings or by these Specifications, length change
test specimens will be taken during construction from the first placement of
each type of mortar, and at intervals thereafter as selected by the Engineer to
insure continued compliance with these specifications. Unless otherwise
specified on the Drawings or Specifications the testing will be performed by
the Owner or testing representative.
3. When required length change tests and fabrication of specimens for cement
based mortar will be performed as specified in ASTM C 1012 at intervals
during construction as selected by the Engineer. A set of three specimens
will be made for testing at 7 and 28 days.
4. All mortar, already placed, that fails to meet the requirements of this Speci-
fication, is subject to removal and replacement at the cost of the Contractor.
5. Unless otherwise specified in the Drawings or Specifications, the cost of all
laboratory tests on grout will be borne by the Owner, but the Contractor shall
assist the Engineer in obtaining specimens for testing. However, the Con-
tractor shall be charged for the cost of any additional tests and investigation
on work performed which does not meet the Specifications.
B. Construction Tolerances
Construction tolerances shall be as specified in the Section 03110 except as modified
herein and elsewhere in the Contract Documents.
1.06 ACCEPTABLE MANUFACTURERS/PRODUCTS
Master Builders Technologies
EMACO R320 - Polymer-Modified Vertical/Overhead Patching Mortar
MB 429, Masterkure CR, Masterkure 200W or Masterkure 100W - curing com-
pounds
LPATH Berm Erosion 03615-3 Grout
Protection Measures
1.07 DELIVERY, STORAGE AND HANDLING
Cement based mortar shall be delivered and stored in manufacturer’s packaging until it is
ready to be mixed and placed. Mortar bags shall be stored off the ground and protected from
water and all other substances that will penetrate packaging.
PART 2 PRODUCTS
2.01 MORTAR FOR TIE HOLES
EMACO R320 or approved equal.
2.02 BONDING ADHESIVES
Concresive Liquid LPL, Concresive Standard Liquid or approved equal.
2.03 WATER
Only clean potable water shall be used. A calibrated measuring device is required for meas-
uring the proper amount of water to be added to grouts and mortars.
2.04 CURING COMPOUND
MB 429, Masterkure 100W, Masterkure 200Wor approved equal.
2.05 (EXPOSED) REINFORCING STEEL COATING
EMACO P22 or approved equal.
PART 3 EXECUTION
3.01 GENERAL
These grouts contain admixtures that increase grout strength and workability. The strength
and performance of the grout is dependent on proper surface preparation, grout mixing and
curing. The Contractor shall be required to use a calibrated measuring device to add clean
potable water to the grout mix. Water added to a grout mix without a calibrated device is
cause for grout rejection, removal and re-placement.
Curing is critical to prevent shrinkage cracks that can develop with grouts containing some
admixtures. Curing shall begin immediately after placement.
All mixing, surface preparation, handling, placing, consolidation, and other means of execu-
tion for pre-packaged mortars shall be done according to the instructions and recommenda-
tions of the manufacturer and this Specification. In the event that a conflict occurs between
this Specification and manufacturer’s instructions, the manufacturer’s instructions shall pre-
vail in all cases.
LPATH Berm Erosion 03615-4 Grout
Protection Measures
3.02 GROUT FOR TIE HOLES
A. Preparation:
Thoroughly clean the roughened surface and any exposed reinforcement of rust, dirt,
loose chips, and dust. Maintain substrate in a saturated, surface-dry condition.
Where applicable, exposed reinforcing steel shall be coated with EMACO P22 rein-
forcing steel bar protection coating prior to patching.
B. Mixing:
Comply with mortar manufacturer’s recommendations for water quantity. Mechani-
cally mix with a slow speed drill (400 to 600 RPM) and Jiffler-type paddle. Pour
approximately 90% of the mix water into the mixing container; then add the bagged
material while continuing to mix. Add remaining water as needed. Mix time shall
not exceed 5 minutes.
C. Application:
Apply bonding adhesive such as Concresive Liquid LPL or Concresive Standard
Liquid.
Place and finish with trowel or screed. In hot, windy, or dry conditions, where rapid
surface evaporation may occur, use Confilm Evaporation Reducer.
D. Curing:
Apply Masterkure 200 W curing compound in accordance with label instructions.
END OF SECTION
APPENDIX A
GEOTECHNICAL INVESTIGATION
CACHE LA POUDRE RIVER
CONTROLLED SPILL STRUCTURES
FORT COLLINS, COLORADO
Administrative Services
Purchasing Divison
215 North Mason Street y 2nd Floor y P.O. Box 580 y Fort Collins, CO 80522-0580 y (970) 221-6775 y Fax (970) 221-6707 www.fcgov.com
ADDENDUM No. 1
5998 LPATH Berm Erosion Protection Measures
SPECIFICATIONS AND CONTRACT DOCUMENTS
Description of Bid: 5998 LPATH Berm Erosion Protection Measures
OPENING DATE: 3:00 P.M. (Our Clock) October 19, 2006
To all prospective bidders under the specifications and contract documents described above,
the following changes are hereby made.
Bid Opening: 3:00 P.M. (Our Clock) October 19, 2006
PREBID Conference: 2:00 P.M. October 4, 2006
A prebid conference and job walk with representatives of prospective Bidders will be
held at 2:00 P.M., on October 4, 2006, at 215 N. Mason St. Conference Room 2E in
Fort Collins.
Please contact John D. Stephen, CPPO, CPPB, Senior Buyer at (970) 221-6777 with any
questions regarding this addendum.
RECEIPT OF THIS ADDENDUM MUST BE ACKNOWLEDGED BY A WRITTEN STATEMENT
ENCLOSED WITH THE BID/QUOTE STATING THAT THIS ADDENDUM HAS BEEN
RECEIVED.
Administrative Services
Purchasing Divison
215 North Mason Street y 2nd Floor y P.O. Box 580 y Fort Collins, CO 80522-0580 y (970) 221-6775 y Fax (970) 221-6707 www.fcgov.com
ADDENDUM No. 2
5998 LPATH Berm Erosion Protection Measures
SPECIFICATIONS AND CONTRACT DOCUMENTS
Description of Bid: 5998 LPATH Berm Erosion Protection Measures
OPENING DATE: 3:00 P.M. (Our Clock) October 19, 2006
To all prospective bidders under the specifications and contract documents described above,
the following changes are hereby made.
Revision: Section 01270 Measurement and Payment
SECTION 01270
MEASUREMENT AND PAYMENT
1.02 PAY ITEMS
5. Remove Concrete Rubble
The measurement for removal of this item will be made on a unit basis. The unit
price bid for this item shall be full compensation for removing, hauling and
disposal of such items including existing concrete rubble, and all other work
necessary to remove these items in accordance with the Drawings and
Specifications. Replacement of riprap, trees, or vegetation outside of the pay
lines due to the CONTRACTOR’s failure to protect existing, undisturbed
materials shall not be paid for and shall be replaced at the CONTRACTOR’s
expense.
Pay Item Pay Unit
Remove Concrete Rubble (Assume 3 feet thick) CY
9. Unclassified Excavation at Borrow Site
12. Excavation and Embankment of on-site material at South Spill (Complete In
Place) - No Haul
13. Embankment of Borrow Material at both spills (Complete In Place) including
Haul from Borrow Site
The measurement for payment of unclassified excavation will be the total
number of cubic yards of material excavated according to the final Drawings.
Unclassified excavation shall consist of excavation of all materials on the site to
final grades, excluding the bid items listed in Section 02220. Excavation of
unsuitable material will only be paid for if it is found to be unsuitable in its
original state. Unclassified excavation shall be measured from the drawings and
cross sections, and the plan quantity will be paid for by the cubic yard.
Muck excavation shall include excavation of unsuitable material and haul and
disposal of unsuitable material. Muck excavation shall also include the cost of
materials used to replace muck excavation. Muck excavation of material from
rain or weather damage will not be paid for and is entirely the CONTRACTOR’S
responsibility. This item will be measured in the field and will be paid for by the
cubic yard.
If unsuitable subgrade is encountered and the ENGINEER directs the
CONTRACTOR to overexcavate the material, the CONTRACTOR shall use
uniformly graded 1 1/2” rock. This item will be measured in the field and will be
paid by the cubic yard per ticket of material used.
Native Soil shall include stripping existing vegetation, temporarily stockpiling,
load, haul and placement of topsoil within all designated areas of the construction
site. This item shall be measured in the field and the volume calculated by the
area multiplied by the depth, as determined by the ENGINEER with no
allowance for shrinkage or swell, and shall be paid for by the cubic yard.
Embankment (Complete In Place) without Haul shall include all excavated
material, which is placed as embankment and compacted to final grades as
specified in Section 02315. This item shall include placement and compaction of
excavated material that has been determined as suitable from the on-site
excavations. This item will be measured from the drawings and cross sections
and the plan quantity will be paid for by the cubic yard.
Embankment (Complete In Place) with Haul shall include all excavated material,
which is placed as embankment and compacted to final grades as specified in
Section 02315. This item shall include haul, placement and compaction of
excavated material that has been determined as suitable from the on-site
excavations. This item will be measured from the drawings and cross sections
and the plan quantity will be paid for by the cubic yard.
Pay Item Pay Unit
Unclassified Excavation at Borrow Site CY
Muck Excavation CY
Native Soil (Over Revetment Mat Only) CY
Excavation and Embankment of on-site material at
South Spill (Complete In Place) without Haul CY
Embankment of Borrow Material at both spills
(Complete In Place) including Haul from Borrow Site CY
Addendum 2
5998 LPATH Berm Erosion Protection Measures
Revised Bid Schedule
Unit Item
Cost ($) Cost ($)
1 Mobilization LS 1
2 Traffic / Access Control LS 1
3 Clearing and Grubbing LS 1
Construction Dewatering
(North Spill and River Riprap Location)
5 Remove Concrete Rubble (Assume 3 feet thick) CY 1150
6 Fence Removal/Resetting (Wood Fence) LF 100
7 Silt Fence LF 3845
8 Straw Bale – Sediment and Erosion Control Structure EA 8
9 Unclassified Excavation at Borrow Site CY 10430
10 Muck Excavation CY 200
11 Native Soil (Over Revetment Mat Only) CY 1040
Excavation and Embankment of On-Site Material
at South Spill Only (Complete In Place) – No Haul
Embankment of Borrow Material at both spills
(Complete In Place) Including Haul from Borrow Site
North Spill = 6400 CY, South Spill = 2670 CY
(Assumed 15% shrinkage in Borrow Site material)
14 Concrete Sill (Complete In Place) CY 170
15 Concrete Block Revetment Mat - North Spill SF 27453
Concrete Block Revetment Mat (Including drainage layer)
- South Spill
17 Riprap (Class 12) TON 1560
4" to 8" Crushed Concrete Rubble
(Quantity Assumed 20% extra for voids)
19 1-1/2" Washed Rock (Quantity Assumed 35% extra for voids) TON 818
20 Landscape - Tree Removal (> 12" Diameter) EA 15
21 Ground Preparation for Seeding AC 9
22 Topsoil (Delivery and Stockpile only - No Installation) CY 200
TOTAL COST
8. BID SCHEDULE (Base Bid)Lump Sum
Total Cost in Words:___________________________________________________________________Dollars
28640
13
18 TON 1968
16 SF
4
12 CY 1652
LS 1
CY 9070
Item
Number Description Unit
Estimated
Quantity
Please contact John D. Stephen, CPPO, CPPB, Senior Buyer at (970) 221-6777 with any
questions regarding this addendum.
RECEIPT OF THIS ADDENDUM MUST BE ACKNOWLEDGED BY A WRITTEN STATEMENT
ENCLOSED WITH THE BID/QUOTE STATING THAT THIS ADDENDUM HAS BEEN
RECEIVED.
������
����������
�����
�������
�����
�������
����
�������
���
����� �����
��������
��������
������
����������
�����
�������
�����
�������
����
�������
���
�����
��
�����
�������
��������
������
����������
�����
�������
�����
�������
�����
�����
���
�����
��
�����
��������
��������
������
����������
�����
�������
�����
�������
����
�������
���
�����
��
�����
��������
��������
������
����������
�����
�������
�����
�������
����
�������
���
�����
��
�����
��������
��������
������
����������
�����
�������
�����
�������
����
�������
���
�������������������������������������������������������������������������������
����
�
� � ��������� � � � � � ������������������������
� � ���������������� � � � � �����������������������
� � ������������������������ � � � �
� � �
��������� ��������� ������� ������ ��� ����������� ��� ��������� ������ ��� ����� ����
����������������
�
� � ����������������������������������� � � ������������������������
� � ������������������ � � � � �����������������������
� � ���������������������������
�
� ��� �����������������������������
� � �
� � ����������������������������������������������������������������������