HomeMy WebLinkAboutBID - 5982 SUBSTATION LIGHTNING TOWERAdministrative Services
Purchasing Divison
215 North Mason Street y 2nd Floor y P.O. Box 580 y Fort Collins, CO 80522-0580 y (970) 221-6775 y Fax (970) 221-6707 www.fcgov.com
ADDENDUM No. 1
5982 Substation Lightning Tower Installation
SPECIFICATIONS AND CONTRACT DOCUMENTS
Description of Bid: 5982 Substation Lightning Tower Installation
OPENING DATE: 2:00 (Our Clock) June 27, 2006
To all prospective bidders under the specifications and contract documents described above,
the following changes are hereby made.
CHANGE:
SECTION 00520
AGREEMENT
3.1 The Work shall be Substantially Complete within one
hundred forty (140) calendar days after the date when the
Contract Times commence to run as provided in the General
Conditions and completed and ready for Final Payment and
Acceptance in accordance with the General Conditions within one
hundred forty seven (147) calendar days after the date when the
Contract Times commence to run.
3.2. Liquidated Damages.
1) Substantial Completion:
Five Hundred Dollars ($500) for each calendar day
or fraction thereof that expires after the one
hundred forty (140) calendar day period for
Substantial Completion of the Work until the Work
is Substantially Complete.
2) Final Acceptance:
After Substantial Completion, Five Hundred
Dollars ($500) for each calendar day or fraction
thereof that expires after the seven (7) calendar
day period for Final Payment and Acceptance until
the Work is ready for Final Payment and
Acceptance.
Questions regarding this addendum should be directed to Opal F. Dick, CPPO, Senior Buyer
(970) 221-6778.
RECEIPT OF THIS ADDENDUM MUST BE ACKNOWLEDGED BY A WRITTEN STATEMENT
ENCLOSED WITH THE BID/QUOTE STATING THAT THIS ADDENDUM HAS BEEN
RECEIVED.
SPECIFICATIONS
AND
CONTRACT DOCUMENTS
FOR
Substation Lightning Tower Installation
BID NO. 5982
PURCHASING DIVISION
215 NORTH MASON STREET, 2ND FLOOR, FORT COLLINS
June 27, 2006 – 2:00 P.M. (OUR CLOCK)
CONTRACT DOCUMENTS TABLE OF CONTENTS
Section Pages
BID INFORMATION
00020 Notice Inviting Bids 00020-1 - 00020-2
00100 Instruction to Bidders 00100-1 - 00100-9
00300 Bid Form 00300-1 - 00300-3
00400 Supplements to Bid Forms 00400-1
00410 Bid Bond 00410-1 - 00410-2
00420 Statements of Bidders Qualifications 00420-1 - 00420-3
00430 Schedule of Major Subcontractors 00430-1
CONTRACT DOCUMENTS
00500 Agreement Forms 00500-1
00510 Notice of Award 00510-0
00520 Agreement 00520-1 - 00520-6
00530 Notice to Proceed 00530-1
00600 Bonds and Certificates 00600-1
00610 Performance Bond 00610-1 - 00610-2
00615 Payment Bond 00615-1 - 00615-2
00630 Certificate of Insurance 00630-1
00635 Certificate of Substantial Completion 00635-1
00640 Certificate of Final Acceptance 00640-1
00650 Lien Waiver Release(Contractor) 00650-1 - 00650-2
00660 Consent of Surety 00660-1
00670 Application for Exemption Certificate 00670-1 - 00670-2
CONDITIONS OF THE CONTRACT
00700 General Conditions 00700-1 - 00700-34
Exhibit GC-A GC-A1 - GC-A2
00800 Supplementary Conditions 00800-1 - 00800-2
00900 Addenda, Modifications, and Payment 00900-1
00950 Contract Change Order 00950-1 - 00950-2
00960 Application for Payment 00960-1 - 00960-4
SPECIFICATIONS
SOILS REPORT
07/2001 Section 00020 Page 2
SECTION 00020
INVITATION TO BID
07/2001 Section 00020 Page 1
SECTION 00020
INVITATION TO BID
Date: May 23, 2006
Sealed Bids will be received by the City of Fort Collins (hereinafter referred
to as OWNER), at the office of the Purchasing Division, 2:00 P.M., our clock,
on June 27, 2006, for the Substation Tower Installation; BID NO. 5982. If
delivered, they are to be delivered to 215 North Mason Street, 2nd Floor, Fort
Collins, Colorado, 80524. If mailed, the mailing address is P. O. Box 580,
Fort Collins, CO 80522-0580.
At said place and time, and promptly thereafter, all Bids that have been duly
received will be publicly opened and read aloud.
The Contract Documents provide for the construction of Bid 5982 Substation
Lightning Tower Installation.
All Bids must be in accordance with the Contract Documents on file with The
City of Fort Collins, 215 North Mason St., 2nd floor, Fort Collins, Colorado
80524.
Contract Documents will be available June 5, 2006.
1. Download the Bid from the Purchasing Webpage, Current Bids page,
at:
https://secure2.fcgov.com/bso/login.jsp.
2. Come by Purchasing at 215 North Mason St., 2nd floor, Fort Collins,
and request a copy of the Bid.
Bids will be received as set forth in the Bidding Documents.
The Work is expected to be commenced within the time as required by Section
2.3 of General Conditions. Substantial Completion of the Work is required as
specified in the Agreement.
The successful Bidder will be required to furnish a Performance Bond and a
Payment Bond guaranteeing faithful performance and the payment of all bills
and obligations arising from the performance of the Contract.
No Bid may be withdrawn within a period of forty-five (45) days after the date
fixed for opening Bids.
The OWNER reserves the right to reject any and all Bids, and to waive any
informalities and irregularities therein.
Bid security in the amount of not less than 5% of the total Bid must accompany
07/2001 Section 00020 Page 2
each Bid in the form specified in the Instructions to Bidders.
Sales Prohibited/Conflict of Interest: No officer, employee, or member of City
Council, shall have a financial interest in the sale to the City of any real
or personal property, equipment, material, supplies or services where such
officer or employee exercises directly or indirectly any decision-making
authority concerning such sale or any supervisory authority over the services
to be rendered. This rule also applies to subcontracts with the City.
Soliciting or accepting any gift, gratuity favor, entertainment, kickback or
any items of monetary value from any person who has or is seeking to do
business with the City of Fort Collins is prohibited
City of Fort Collins
By ______________________________________
James B. O'Neill, II, CPPO, FNIGP
Purchasing/Risk Management Director
SPECIFICATIONS
AND
CONTRACT DOCUMENTS
FOR
Substation Lightning Tower Installation
BID NO. 5982
PURCHASING DIVISION
215 NORTH MASON STREET, 2ND FLOOR, FORT COLLINS
June 27, 2006 – 2:00 P.M. (OUR CLOCK)
CONTRACT DOCUMENTS TABLE OF CONTENTS
Section Pages
BID INFORMATION
00020 Notice Inviting Bids 00020-1 - 00020-2
00100 Instruction to Bidders 00100-1 - 00100-9
00300 Bid Form 00300-1 - 00300-3
00400 Supplements to Bid Forms 00400-1
00410 Bid Bond 00410-1 - 00410-2
00420 Statements of Bidders Qualifications 00420-1 - 00420-3
00430 Schedule of Major Subcontractors 00430-1
CONTRACT DOCUMENTS
00500 Agreement Forms 00500-1
00510 Notice of Award 00510-0
00520 Agreement 00520-1 - 00520-6
00530 Notice to Proceed 00530-1
00600 Bonds and Certificates 00600-1
00610 Performance Bond 00610-1 - 00610-2
00615 Payment Bond 00615-1 - 00615-2
00630 Certificate of Insurance 00630-1
00635 Certificate of Substantial Completion 00635-1
00640 Certificate of Final Acceptance 00640-1
00650 Lien Waiver Release(Contractor) 00650-1 - 00650-2
00660 Consent of Surety 00660-1
00670 Application for Exemption Certificate 00670-1 - 00670-2
CONDITIONS OF THE CONTRACT
00700 General Conditions 00700-1 - 00700-34
Exhibit GC-A GC-A1 - GC-A2
00800 Supplementary Conditions 00800-1 - 00800-2
00900 Addenda, Modifications, and Payment 00900-1
00950 Contract Change Order 00950-1 - 00950-2
00960 Application for Payment 00960-1 - 00960-4
SPECIFICATIONS
SOILS REPORT
07/2001 Section 00020 Page 2
SECTION 00020
INVITATION TO BID
07/2001 Section 00020 Page 1
SECTION 00020
INVITATION TO BID
Date: May 23, 2006
Sealed Bids will be received by the City of Fort Collins (hereinafter referred
to as OWNER), at the office of the Purchasing Division, 2:00 P.M., our clock,
on June 27, 2006, for the Substation Tower Installation; BID NO. 5982. If
delivered, they are to be delivered to 215 North Mason Street, 2nd Floor, Fort
Collins, Colorado, 80524. If mailed, the mailing address is P. O. Box 580,
Fort Collins, CO 80522-0580.
At said place and time, and promptly thereafter, all Bids that have been duly
received will be publicly opened and read aloud.
The Contract Documents provide for the construction of Bid 5982 Substation
Lightning Tower Installation.
All Bids must be in accordance with the Contract Documents on file with The
City of Fort Collins, 215 North Mason St., 2nd floor, Fort Collins, Colorado
80524.
Contract Documents will be available June 5, 2006.
1. Download the Bid from the Purchasing Webpage, Current Bids page,
at:
https://secure2.fcgov.com/bso/login.jsp.
2. Come by Purchasing at 215 North Mason St., 2nd floor, Fort Collins,
and request a copy of the Bid.
Bids will be received as set forth in the Bidding Documents.
The Work is expected to be commenced within the time as required by Section
2.3 of General Conditions. Substantial Completion of the Work is required as
specified in the Agreement.
The successful Bidder will be required to furnish a Performance Bond and a
Payment Bond guaranteeing faithful performance and the payment of all bills
and obligations arising from the performance of the Contract.
No Bid may be withdrawn within a period of forty-five (45) days after the date
fixed for opening Bids.
The OWNER reserves the right to reject any and all Bids, and to waive any
informalities and irregularities therein.
Bid security in the amount of not less than 5% of the total Bid must accompany
07/2001 Section 00020 Page 2
each Bid in the form specified in the Instructions to Bidders.
Sales Prohibited/Conflict of Interest: No officer, employee, or member of City
Council, shall have a financial interest in the sale to the City of any real
or personal property, equipment, material, supplies or services where such
officer or employee exercises directly or indirectly any decision-making
authority concerning such sale or any supervisory authority over the services
to be rendered. This rule also applies to subcontracts with the City.
Soliciting or accepting any gift, gratuity favor, entertainment, kickback or
any items of monetary value from any person who has or is seeking to do
business with the City of Fort Collins is prohibited
City of Fort Collins
By ______________________________________
James B. O'Neill, II, CPPO, FNIGP
Purchasing/Risk Management Director
SECTION 00100
INSTRUCTIONS TO BIDDERS
12/03 Section 00100 Page 1
SECTION 00100
INSTRUCTIONS TO BIDDERS
1.0 DEFINED TERMS
Terms used in these Instructions to Bidders which are defined in the
Standard General Conditions of the Construction Contract (No. 1910-8,
1990 ed.) have the meanings assigned to them in the General Conditions.
The term "Bidder" means one who submits a Bid to OWNER, as distinct from
a sub-bidder, who submits a Bid to Bidder. The terms "Successful Bidder"
means the lowest, qualified, responsible and responsive Bidder to whom
OWNER (on basis of OWNER's evaluation as hereinafter provided) makes an
award. The term "Bidding Documents" includes the Advertisement or
Invitation to Bid, Instructions to Bidders, the Bid Form, and the
proposed Contract Documents (including all Addenda issued prior to
receipt of Bids).
2.0 COPIES OF BIDDING DOCUMENTS
2.1. Complete sets of Bidding Documents may be obtained as stated in the
Invitation to Bid. No partial sets will be issued. The Bidding
Documents may be examined at the locations identified in the Invitation
to Bid.
2.2. Complete sets of Bidding Documents shall be used in preparing Bids;
neither OWNER nor Engineer assumes any responsibility for errors or
misinterpretations resulting from the use of incomplete sets of Bidding
Documents.
2.3. The submitted Bid proposal shall include Sections 00300, 00410,
00420, and 00430 fully executed.
2.4. OWNER and Engineer, in making copies of Bidding Documents available
on the above terms, do so only for the purpose of obtaining Bids on the
Work and do not confer a license or grant for any other use.
3.0 QUALIFICATION OF BIDDERS
3.1 To demonstrate qualifications to perform the Work, each Bidder must
submit at the time of the Bid opening, a written statement of
qualifications including financial data, a summary of previous
experience, previous commitments and evidence of authority to conduct
business in the jurisdiction where the Project is located. Each Bid must
contain evidence of Bidder's qualification to do business in the state
where the Project is located or covenant to obtain such qualification
prior to award of the contract. The Statement of Qualifications shall be
prepared on the form provided in Section 00420.
12/03 Section 00100 Page 2
3.2. In accordance with Section 8-160 of the Code of the City of Fort
Collins in determining whether a bidder is responsible, the following
shall be considered: (1) The ability, capacity and skill of the bidder to
perform the contract or provide the services required, (2) whether the
bidder can perform the contract or provide the service promptly and
within the time specified without delay or interference, (3) the
character, integrity, reputation, judgment, experience and efficiency of
the bidder, (4) the quality of the bidder's performance of previous
contracts or services, (5) the previous and existing compliance by the
bidder with laws and ordinances relating to the contract or service, (6)
the sufficiency of the financial resources and ability of the bidder to
perform the contract or provide the service, (7) the quality,
availability and adaptability of the materials and services to the
particular use required, (8) the ability of the bidder to provide future
maintenance and service for the use of the subject of the contract, and
(9) any other circumstances which will affect the bidder's performance of
the contract.
3.3. Each Bidder may be required to show that he has handled former Work
so that no just claims are pending against such Work. No Bid will be
accepted from a Bidder who is engaged on any other Work which would
impair his ability to perform or finance this Work.
3.4 No Bidder shall be in default on the performance of any other
contract with the City or in the payment of any taxes, licenses or other
monies due to the City.
4.0 EXAMINATION OF CONTRACT DOCUMENTS AND SITE
4.1. It is the responsibility of each Bidder, before submitting a Bid,
to (a) examine the Contract Documents thoroughly, (b) visit the site to
familiarize himself with local conditions that may in any manner affect
cost, progress or performance of the Work, (c) familiarize himself with
federal, state and local laws, ordinances, rules and regulations that may
in any manner affect cost, progress or performance of the Work, (d) study
and carefully correlate Bidder's observations with the Contract
Documents, and (e) notify Engineer of all conflicts, errors or
discrepancies in the Contract Documents.
4.2. Reference is made to the Supplementary Conditions for
identification of: Subsurface and Physical Conditions SC-4.2.
4.3. The submission of a Bid will constitute an incontrovertible
representation by Bidder that Bidder has complied with every requirement
of this Article 4, that without exception the Bid is premised upon
performing and furnishing the Work required by the Contract Documents and
such means, methods, techniques, sequences or procedures of construction
as may be indicated in or required by the Contract Documents, and that
12/03 Section 00100 Page 3
the Contract Documents are sufficient in scope and detail to indicate and
convey understanding of all terms and conditions for performance and
furnishing of the Work.
5.0 INTERPRETATIONS AND ADDENDA.
5.1. All questions about the meaning or intent of the Bidding Documents are to
be submitted in writing to the Engineer and the OWNER. Interpretation or
clarifications considered necessary in response to such questions will be
issued only by Addenda. Questions received less than seven days prior to
the date for opening of the Bids may not be answered. Only questions
answered by formal written Addenda will be binding. Oral and other
interpretations or clarifications will be without legal effect.
5.2. All questions concerning the scope of this project should be
directed to the Engineer. Questions regarding submittal of bids should
be directed to the City of Fort Collins' Purchasing Division.
5.3. Addenda may also be issued to modify the Bidding Documents as
deemed advisable by OWNER or Engineer.
5.4. Addenda will be mailed or delivered to all parties recorded by the
OWNER as having received the Bidding documents.
6.0 BID SECURITY
6.1. Each Bid must be accompanied by Bid Security made payable to OWNER
in the amount stated in the Invitation to Bid. The required security
must be in the form of a certified or bank cashier's check payable to
OWNER or a Bid Bond on the form enclosed herewith. The Bid Bond must be
executed by a surety meeting the requirements of the General Conditions
for surety bonds.
6.2. The Bid Security of the successful Bidder will be retained until
such Bidder has executed the Agreement and furnished the required
contract security, whereupon Bid Security will be returned. If the
successful Bidder fails to execute and deliver the Agreement and furnish
the required contract security within 15 days of the Notice of Award,
OWNER may annul the Notice of Award and the Bid Security of that Bidder
will be forfeited. The Bid Security of other Bidders whom OWNER believes
to have reasonable chance receiving the award may be retained by OWNER
until the earlier of the seventh day after the effective date of the
Agreement or the thirty-first day after the Bid Opening, whereupon Bid
Security furnished by such Bidders will be returned. Bid Security with
Bids which are not competitive will be returned within seven days after
the Bid opening.
7.0 CONTRACT TIME.
12/03 Section 00100 Page 4
The number of days within which, or the date by which the Work is to be
substantially complete and also completed and ready for Final Payment
(the Contract Times) are set forth in the Agreement.
8.0 LIQUIDATED DAMAGES.
Provisions for liquidated damages are set forth in the Agreement.
9.0 SUBSTITUTE ("OR EQUAL") MATERIAL AND EQUIPMENT
The Contract, if awarded, will be on the basis of material and equipment
described on the Drawings or specified in the Specifications without
consideration of possible substitute or "or equal" items. Whenever it is
indicated on the Drawings or specified in the Specifications that a
substitute or "or equal" item of material or equipment may be furnished
or used by CONTRACTOR if acceptable to Engineer, application for such
acceptance will not be considered by Engineer until after the "effective
date of the Agreement". The procedure for submittal of any such
application by CONTRACTOR and consideration by Engineer is set forth in
the General Conditions which may be supplemented in the General
Requirements.
10.0 SUBCONTRACTORS, SUPPLIERS AND OTHERS
10.1. Each Bidder shall submit at the Bid opening to OWNER a list of
principal subcontractors he proposes to use in the Work. Refer to
Section 00430 contained within these Documents.
10.2. If OWNER or Engineer after due investigation has reasonable
objection to any proposed Subcontractor, either may, before the Notice of
Award is given, request the apparent successful Bidder to submit an
acceptable substitute without an increase in Bid price. If the apparent
successful Bidder declines to make any substitution, OWNER may award the
contract to the next lowest responsive and responsible Bidder that
proposes to use acceptable subcontractors. Subcontractors, suppliers,
other persons or organization listed and to whom OWNER or Engineer does
not make written objection prior to the giving of the Notice of Award
will be deemed acceptable to OWNER and ENGINEER subject to revocation of
such acceptance after the effective date of the Agreement as provided in
the General Conditions.
10.3. CONTRACTOR shall not be required to employ any subcontractor,
supplier or other persons or organizations against whom he has reasonable
objection. The use of subcontractors listed by the Bidder and accepted
by OWNER prior to the Notice of Award will be required in the performance
of the Work.
11.0 BID FORM.
12/03 Section 00100 Page 5
11.1. A copy of the Bid Form is bound in the Contract Documents which
may be retained by the Bidder. A separate unbound copy is enclosed for
submission with the Bid.
11.2. Bid Forms must be complete in ink or typed. All lump sum prices
on the form must be stated in words and numerals; in case of conflict,
words will take precedence. Unit prices shall govern over extensions of
sums.
11.3. Bids by corporations must be executed in the corporate name by the
president or a vice-president (or other appropriate officer accompanied
by evidence of authority to sign) and the corporate seal shall be affixed
and attested by the secretary or an assistant secretary. The corporate
address and state of incorporation shall be shown below the corporate
name.
11.4. Bids by partnerships must be executed in the partnership name and
signed by a partner, his title must appear under his signature and the
official address of the partnership must be shown below the signature.
11.5. Bids by joint venture shall be signed by each participant in the
joint venture or by an authorized agent of each participant. The full
name of each person or company interested in the Bid shall be listed on
the Bid Form.
11.6. The Bid shall contain an acknowledgement of receipt of all Addenda
(the numbers of which must be filled in on the Bid Form).
11.7. No alterations in Bids, or in the printed forms therefore, by
erasures, interpolations, or otherwise will be acceptable unless each
such alteration is signed or initialed by the Bidder; if initialed, OWNER
may require the Bidder to identify any alteration so initialed.
11.8. The address and telephone number for communications regarding the
Bid shall be shown.
12.0 BID PRICING.
Bids must be priced as set forth in the Bid Schedule or Schedules.
13.0 SUBMISSION OF BIDS.
13.1. Bids shall be submitted at the time and place indicated in the
Invitation to Bid and shall be enclosed in an opaque sealed envelope
marked with the Project title, Bid No., and name and address of the
Bidder and accompanied by the Bid Security, Bid Form, Bid Bond, Statement
of Bidders Qualifications, and Schedule of Subcontractors as required in
Section 00430. If the Bid is sent through the mail or other delivery
system, the sealed envelope shall be enclosed in a separate envelope with
12/03 Section 00100 Page 6
the notation "BID ENCLOSED" on the face of it.
13.2. Bids shall be deposited at the designated location prior to the
time and date for receipt of Bids indicated in the Invitation to Bid, or
any extension thereof made by addendum. Bids received after the time and
date for receipt of Bids will be returned unopened. Bidder shall assume
full responsibility for timely delivery at the location designated for
receipt of Bids.
13.3. Oral, telephonic, telegraphic, or facsimile Bids are invalid and
will not receive consideration.
13.4. No Bidder may submit more than one Bid. Multiple Bids under
different names will not be accepted from one firm or association.
14.0 MODIFICATION AND WITHDRAWAL OF BIDS.
14.1. Bids may be modified or withdrawn by an appropriate document duly
executed (in a manner that a Bid must be executed) and delivered to the
place where Bids are to be submitted at any time prior to the opening of
Bids.
14.2. Bids may also be modified or withdrawn in person by the Bidder or
an authorized representative provided he can prove his identity and
authority at any time prior to the opening of Bids.
14.3. Withdrawn Bids may be resubmitted up to the time designated for
the receipt of Bids provided that they are then fully in conformance with
these Instructions to Bidders.
15.0 OPENINGS OF BIDS.
Bids will be opened and (unless obviously non-responsive) read aloud
publicly as indicated in the Invitation to Bid. An abstract of the
amounts of the Base Bids and major alternates (if any) will be made
available after the opening of Bids.
16.0 BIDS TO REMAIN OPEN SUBJECT TO ACCEPTANCE.
All Bids shall remain open for forty-five (45) days after the day of the
Bid Opening, but OWNER may, in his sole discretion, release any Bid and
return the Bid Security prior to that date.
17.0 AWARD OF CONTRACT.
17.1. OWNER reserves the right to reject any and all Bids, to waive any
and all informalities not involving price, time or changes in the Work,
to negotiate contract terms with the Successful Bidder, and the right to
12/03 Section 00100 Page 7
disregard all nonconforming, nonresponsive, unbalanced or conditional
Bids. Also, OWNER reserves the right to reject the Bid of any Bidder if
OWNER believes that it would not be in the best interest of the Project
to make an award to that Bidder, whether because the Bid is not
responsive or the Bidder is unqualified or of doubtful financial ability
or fails to meet any other pertinent standard or criteria established by
OWNER. Discrepancies between the indicated sum of any column of figures
and the correct sum thereof will be resolved in favor of the correct sum.
17.2. In evaluating Bids, OWNER will consider the qualifications of the
Bidders, whether or not the Bids comply with the prescribed requirements,
and such alternates, unit prices and other data, as may be requested in
the Bid Form or prior to the Notice of Award.
17.3. OWNER may consider the qualification and experience of
Subcontractors, Suppliers, and other persons and organizations proposed
for those portions of the Work as to which the identity of
Subcontractors, Suppliers, and other persons and organizations is
submitted as requested by OWNER. OWNER also may consider the operating
costs, maintenance requirements, performance data and guarantees of major
items of materials and equipment proposed for incorporation in the Work
when such data is required to be submitted prior to the Notice of Award.
17.4. OWNER may conduct such investigations as OWNER deems necessary to
assist in the evaluation of any Bid and to establish the responsibility,
qualifications and financial ability of the Bidder's proposed
Subcontractors, Suppliers and other persons and organizations to do the
Work in accordance with the Contract Documents to OWNER's satisfaction
within the prescribed time.
17.5. If the Contract is to be awarded, it will be awarded to the lowest
responsive and responsible Bidder whose evaluation by OWNER indicates to
OWNER that the award will be in the best interest of the OWNER. Award
shall be made on the evaluated lowest base bid excluding alternates. The
basis for award shall be the lowest Bid total for the Schedule or, in the
case of more than one schedule, for sum of all schedules. Only one
contract will be awarded.
17.6. If the Contract is to be awarded, OWNER will give the Successful
Bidder a Notice of Award within forty-five (45) days after the date of
the Bid opening.
18.0 CONTRACT SECURITY.
The General Conditions and the Supplementary Conditions set forth OWNER's
requirements as to performance and other Bonds. When the Successful
Bidder delivers the executed Agreement to the OWNER, it shall be
accompanied by the required Contract Security.
12/03 Section 00100 Page 8
19.0 SIGNING OF AGREEMENT.
When OWNER gives a Notice of Award to the Successful Bidder, it will be
accompanied by the required number of unsigned counterparts of the
Agreement with all other written Contract Documents attached. Within
fifteen (15) days thereafter, CONTRACTOR shall sign and deliver the
required number of counterparts of the Agreement and attached documents
to OWNER with the required Bonds. Within ten (10) days thereafter, OWNER
shall deliver one fully signed counterpart to CONTRACTOR. Each
counterpart is to be accompanied by a complete set of the Drawings with
appropriate identification.
20.0 TAXES.
OWNER is exempt from Colorado State Sales and Use Taxes on materials and
equipment to be incorporated in the Work. Said taxes shall not be
included in the Contract Price. Reference is made to the General and
Supplementary Conditions.
21.0 RETAINAGE.
Provisions concerning retainage are set forth in the Agreement.
22.0 PURCHASING RESTRICTIONS.
Purchasing restrictions: The Bidder's authorized signature of this Bid
assures the Bidder's compliance with the City's purchasing restrictions.
A copy of the resolutions are available for review in the Purchasing and
Risk Management Division or the City Clerk's office.
A. Cement Restrictions: City of Fort Collins Resolution 91-121
requires that suppliers and producers of cement or products
containing cement to certify that the cement was not made in cement
kilns that burn hazardous waste as a fuel.
23.0 COLLUSIVE OR SHAM BIDS.
Any Bid deemed by the City in its sole discretion to be a collusive or
sham Bid will be rejected and reported to authorities as such. Your
authorized signature of this Bid assures that such Bid is genuine and is
not a collusive or sham Bid.
24.0 BID RESULTS.
For information regarding results for individual Bids send a self-
addressed, self-stamped envelope and a Bid tally will be mailed to you.
Bid results will be posted in the Purchasing office seven (7) days after
the Bid Opening.
12/03 Section 00100 Page 9
END OF SECTION
SECTION 00300
BID FORM
7/96 Section 00300 Page 1
SECTION 00300
BID FORM
PROJECT: 5982 Substation Tower Installation
City of Fort Collins
PURCHASING DIVISION
215 NORTH MASON STREET, 2ND FLOOR, FORT COLLINS
June 27, 2006 – 2:00 P.M. (OUR CLOCK)
1. In compliance with your Invitation to Bid dated
, and subject to all conditions thereof, the undersigned
a (Corporation, Limited Liability Company, Partnership, Joint Venture, or
Sole Proprietor) authorized to do business in the State of Colorado
hereby proposes to furnish and do everything required by the Contract
Documents to which this refers for the construction of all items listed
on the following Bid Schedule or Bid Schedules.
2. The undersigned Bidder does hereby declare and stipulate that this
proposal is made in good faith, without collusion or connection with any
other person or persons Bidding for the same Work, and that it is made in
pursuance of and subject to all the terms and conditions of the
Invitation to Bid and Instructions to Bidders, the Agreement, the
detailed Specifications, and the Drawings pertaining to the Work to be
done, all of which have been examined by the undersigned.
3. Accompanying this Bid is a certified or cashier's check or standard Bid
bond in the sum of ______________________________________________________
($ ) in accordance with the Invitation To Bid
and Instructions to Bidders.
4. The undersigned Bidder agrees to execute the Agreement and a Performance
Bond and a Payment Bond for the amount of the total of this Bid within
fifteen (15) calendar days from the date when the written notice of the
award of the contract is delivered to him at the address given on this
Bid. The name and address of the corporate surety with which the Bidder
proposes to furnish the specified performance and payment bonds is as
follows: _________________________________________________________.
5. All the various phases of Work enumerated in the Contract Documents with
their individual jobs and overhead, whether specifically mentioned,
included by implication or appurtenant thereto, are to be performed by
the CONTRACTOR under one of the items listed in the Bid Schedule,
irrespective of whether it is named in said list.
6. Payment for Work performed will be in accordance with the Bid Schedule or
Bid Schedules subject to changes as provided in the Contract Documents.
7/96 Section 00300 Page 2
7. The undersigned Bidder hereby acknowledges receipt of Addenda No.
_______through .
BID SCHEDULES
BID SCHEDULE A – HARMONY SUBSTATION LIGHTNING MAST
ITEM NO. DESCRIPTION EST.QTY UNIT UNIT PRICE TOTAL
1 Mobilization, Insurance,
Bonds
1 LS $
2 Drilled pier excavation 1 LS
3 Spoil 1 LS
4 Concrete pier foundation 1 LS
5 Lightning mast materials 1 LS
6 Lightning mast installation 1 LS
7 Site restoration, Aggregate
surface replacement, Final
grading.
1 LS
Subtotal Bid Schedule A
BID SCHEDULE B – OVERLAND TRAIL SUBSTATION LIGHTNING MAST
ITEM NO. DESCRIPTION EST.QTY UNIT UNIT PRICE TOTAL
1 Mobilization, Insurance,
Bonds
1 LS
2 Drilled pier excavation 1 LS
3 Spoil 1 LS
4 Concrete pier foundation 1 LS
5 Lightning mast materials 1 LS
6 Lightning mast installation 1 LS
7 Site restoration, Aggregate
surface replacement, Final
grading.
1 LS
Subtotal Bid Schedule B
BID SCHEDULE C – LINDEN SUBSTATION LIGHTNING MAST
ITEM NO. DESCRIPTION EST.QTY UNIT UNIT PRICE TOTAL
1 Mobilization, Insurance,
Bonds 1 LS $ $
2 Excavation 1 LS $ $
3 Spoil 1 LS $ $
4 Structural fill 1 LS $ $
5 Structure backfill 1 LS $ $
6 Concrete spread footing
foundation 1 LS $ $
7 Lightning mast materials 1 LS $ $
8 Lightning mast installation 1 LS $ $
9 Site restoration, Aggregate 1 LS $ $
7/96 Section 00300 Page
surface replacement, Final
grading.
Subtotal Bid Schedule C $
TOTAL PRICE (BID SCHEDULE A, B, AND C).
__________________________________________________________ ($ ______ ___).
(Use Words) (Use Figures)
9. PRICES
The foregoing prices shall include all labor, materials, transportation,
shoring, removal, dewatering, overhead, profit, insurance, etc., to cover
the complete Work in place of the several kinds called for.
Bidder acknowledges that the OWNER has the right to delete items in the
Bid or change quantities at his sole discretion without affecting the
Agreement or prices of any item so long as the deletion or change does
not exceed twenty-five percent (25%) of the total Agreement Price.
RESPECTFULLY SUBMITTED:
_______________________________
COMPANY
________________________________ __________________
Signature Date
________________________________
Title
________________________________
License Number (If Applicable)
(Seal - if Bid is by corporation)
Attest:___________________________
Address _____________________________________
_____________________________________
Telephone _____________________________________
7/96 Section 00410 Page 1
SECTION 00400
SUPPLEMENTS TO BID FORMS
00410 Bid Bond
00420 Statement of Bidder's Qualifications
00430 Schedule of Subcontractors
7/96 Section 00410 Page 2
SECTION 00410
BID BOND
KNOW ALL MEN BY THESE PRESENTS: that we, the undersigned
as Principal, and as Surety, are
hereby held and firmly bound unto the City of Fort Collins, Colorado, as
OWNER, in the sum of $ ______________________ for the
payment of which, well and truly to be made, we hereby jointly and severally
bind ourselves, successors, and assigns.
THE CONDITION of this obligation is such that whereas the Principal has
submitted to the City of Fort Collins, Colorado the accompanying Bid and
hereby made a part hereof to enter into a Construction Agreement for the
construction of Fort Collins Project, 5982 Substation Lightning Tower
Installation.
NOW THEREFORE,
(a) If said Bid shall be rejected, or
(b) If said Bid shall be accepted and the Principal shall execute and deliver
a Contract in the form of Contract attached hereto (properly completed in
accordance with said Bid) and shall furnish a BOND for his faithful
performance of said Contract, and for payment of all persons performing
labor or furnishing materials in connection therewith, and shall in all
other respects perform the Agreement created by the acceptance of said
Bid, then this obligation shall be void; otherwise the same shall remain
in force and effect, it being expressly understood and agreed that the
liability of the Surety for any and all claims hereunder shall, in no
event, exceed the penal amount of this obligation as herein stated.
The Surety, for value received, hereby stipulates and agrees that the
obligations of said Surety and its BOND shall be in no way impaired or
affected by any extension of the time within which the OWNER may accept such
Bid; and said Surety does hereby waive notice of any such extension.
Surety Companies executing bonds must be authorized to transact business in
the State of Colorado and be accepted by the OWNER.
7/96 Section 00410 Page 3
IN WITNESS WHEREOF, the Principal and the Surety have hereunto set their hands
and seals this day of , 20__, and such of them as are
corporations have caused their corporate seals to be hereto affixed and these
presents to be signed by their proper officers, the day and year first set
forth above.
PRINCIPAL SURETY
Name:_____________________________ __________________________________
Address:__________________________ __________________________________
__________________________________ __________________________________
By:_______________________________ By: ______________________________
Title: ___________________________ Title:____________________________
ATTEST:
By:_______________________________
(SEAL) (SEAL)
7/96 Section 00420 Page 1
SECTION 00420
STATEMENT OF BIDDER'S QUALIFICATIONS
All questions must be answered and the data given must be clear and
comprehensive. This statement must be notarized. If necessary, questions may
be answered on separate attached sheets. The Bidder may submit any additional
information he desires.
1. Name of Bidder: _________________________________________________
2. Permanent main office address: __________________________________
3. When organized: _________________________________________________
4. If a corporation, where incorporated: ___________________________
5. How many years have you been engaged in the contracting business
under your present firm or trade name?___________________________
6. Contracts on hand: (Schedule these, showing the amount of each
contract and the appropriate anticipated dates of completion.)
_________________________________________________________________
_________________________________________________________________
_________________________________________________________________
_________________________________________________________________
7. General character of Work performed by your company:
_________________________________________________________________
_________________________________________________________________
8. Have you ever failed to complete any Work awarded to you?________
If so, where and why?____________________________________________
_________________________________________________________________
9. Have your ever defaulted on a contract?__________________________
If so, where and why?____________________________________________
_________________________________________________________________
10. Are you debarred by any government agency? ______________________
If yes list agency name._________________________________________
7/96 Section 00420 Page 2
11. List the more important projects recently completed by your company,
stating the approximate cost of each, and the month and year completed,
location and type of construction.
_________________________________________________________________________
_________________________________________________________________________
_________________________________________________________________________
12. List your major equipment available for this contract.
_________________________________________________________________________
_________________________________________________________________________
_________________________________________________________________________
13. Experience in construction Work similar in importance to this
project:
_________________________________________________________________________
_________________________________________________________________________
_________________________________________________________________________
14. Background and experience of the principal members of your organization,
including officers:
_________________________________________________________________________
_________________________________________________________________________
_________________________________________________________________________
15. Credit available: $______________________________________________________
16. Bank reference:__________________________________________________________
17. Will you, upon request, fill out a detailed financial statement and
furnish any other information that may be required by the OWNER?
_________________________________________________________________________
18. Are you licensed as a General CONTRACTOR?________________________________
If yes, in what city, county and state? __________________________What
class, license and numbers?______________________________________________
19. Do you anticipate subcontracting Work under this
Contract?_________________
If yes, what percent of total contract?__________________________________
and to whom?_____________________________________________________________
20. Are any lawsuits pending against you or your firm at this time?__________
IF yes, DETAIL___________________________________________________________
_________________________________________________________________________
7/96 Section 00420 Page 3
21. What are the limits of your public liability? DETAIL
_________________________________________________________________________
What company?____________________________________________________________
22. What are your company's bonding limitations?_____________________________
_________________________________________________________________________
23. The undersigned hereby authorizes and requests any person, firm or
corporation to furnish any information requested by the OWNER in
verification of the recital comprising this Statement of Bidder's
Qualifications.
Dated at ________________ this ______ day of __________________, 20__.
_____________________________________________
Name of Bidder
By:__________________________________________
Title:_______________________________________
State of________________________
)
County of_______________________
___________________________________being duly sworn deposes and says that he
is ______________________of_____________________________ and that
(name of organization)
the answers to the foregoing questions and all statements therein contained
are true and correct.
Subscribed and sworn to before me this _______ day of
____________, 20__.
___________________________________
Notary Public
___________________________________
___________________________________
My commission expires _____________________________.
7/96 Section 00430 Page 1
SECTION 00430
SCHEDULE OF SUBCONTRACTORS
List all subcontractors for the work items listed below and all subcontractors
performing over 15% of the contract.
ITEM SUBCONTRACTOR
______________________________ _______________________________
______________________________ _______________________________
______________________________ _______________________________
______________________________ _______________________________
______________________________ _______________________________
______________________________ _______________________________
______________________________ _______________________________
______________________________ _______________________________
______________________________ _______________________________
______________________________ _______________________________
______________________________ _______________________________
______________________________ _______________________________
______________________________ _______________________________
______________________________ _______________________________
______________________________ _______________________________
______________________________ _______________________________
______________________________ _______________________________
______________________________ _______________________________
SECTION 00500
AGREEMENT FORMS
00510 Notice of Award
00520 Agreement
00530 Notice to Proceed
9/12/01 Section 00510 Page 1
SECTION 00510
NOTICE OF AWARD
Date:
TO:
PROJECT: Bid 5982 Substation Lightning Tower Installation
OWNER: CITY OF FORT COLLINS
(hereinafter referred to as "the OWNER")
You are hereby notified that your Bid dated ___________, 20__ for the above
project has been considered. You are the apparent successful Bidder and have
been awarded an Agreement for 5982 Substation Tower Installation:
The Price of your Agreement is ________________________________________________
_______________________________________________________________________________
Three (3) copies of each of the proposed Contract Documents (except Drawings)
accompany this Notice of Award. Three (3) sets of the Drawings will be
delivered separately or otherwise made available to you immediately.
You must comply with the following conditions precedent within fifteen (15)
days of the date of this Notice of Award, that is by _________, 20__.
1. You must deliver to the OWNER three (3) fully executed counterparts of
the Agreement including all the Contract Documents. Each of the Contract
Documents must bear your signature on the cover of the page.
2. You must deliver with the executed Agreement the Contract Security
(Bonds) as specified in the Instructions to Bidders, General Conditions
(Article 5.1) and Supplementary Conditions.
Failure to comply with these conditions within the time specified will entitle
OWNER to consider your Bid abandoned, to annul this Notice of Award and to
declare your Bid Security forfeited.
Within ten (10) days after you comply with those conditions, OWNER will return
to you one (1) fully-signed counterpart of the Agreement with the Contract
Documents attached.
City of Fort Collins
OWNER
By:________________________________________
James B. O’Neill, II, CPPO, FNIGP
Director of Purchasing & Risk Management
9/12/01 Section 00520 Page 1
SECTION 00520
AGREEMENT
THIS AGREEMENT is dated as of the day of in the
year of 20__ and shall be effective on the date this AGREEMENT is signed by
the City.
The City of Fort Collins (hereinafter called OWNER) and
(hereinafter called CONTRACTOR)
OWNER and CONTRACTOR, in consideration of the mutual covenants hereinafter set
forth, agree as follows:
ARTICLE 1. WORK
CONTRACTOR shall complete all Work as specified or indicated in the Contract
Documents. The Project for which the Work under the Contract Documents may be
the whole or only a part is defined as the construction of the Bid 5982
Substation Lightning Tower Installation; the scope of the project will involve
the purchase of three substation lightning towers and erecting them at three
different substations within the city of Fort Collins. The work will include
drilling, excavating, and construction of the pier foundation; construction
and erection of the steel tower, and site restoration and is generally
described in Section 01010.
ARTICLE 2. ENGINEER
The Project has been designed by Smith Geotechnical, who is hereinafter called
ENGINEER and who will assume all duties and responsibilities and will have the
rights and authority assigned to ENGINEER in the Contract Documents in
connection with completion of the Work in accordance with the Contract
Documents.
ARTICLE 3. CONTRACT TIMES
3.1 The Work shall be Substantially Complete within fifteen (15)
calendar days after the date when the Contract Times commence to run as
provided in the General Conditions and completed and ready for Final Payment
and Acceptance in accordance with the General Conditions within thirty (30)
calendar days after the date when the Contract Times commence to run.
3.2. Liquidated Damages. OWNER and CONTRACTOR recognize that time is of
the essence of this Agreement and that OWNER will suffer financial loss if the
Work is not completed within the times specified in paragraph 3.1. above, plus
any extensions thereof allowed in accordance with Article 12 of the General
Conditions.
They also recognize the delays, expenses and difficulties involved in proving
9/12/01 Section 00520 Page 2
in a legal proceeding the actual loss suffered by OWNER if the Work is not
completed on time. Accordingly, instead of requiring any such proof, OWNER
and CONTRACTOR agree that as liquidated damages for delay (but not as penalty)
CONTRACTOR shall pay OWNER the amounts set forth hereafter.
1) Substantial Completion:
Five Hundred Dollars ($500) for each calendar day or fraction
thereof that expires after the fifteen (15) calendar day period for
Substantial Completion of the Work until the Work is Substantially
Complete.
2) Final Acceptance:
After Substantial Completion, Five Hundred Dollars ($500) for each
calendar day or fraction thereof that expires after the fifteen
(15) calendar day period for Final Payment and Acceptance until the
Work is ready for Final Payment and Acceptance.
ARTICLE 4. CONTRACT PRICE
4.1. OWNER shall pay CONTRACTOR for performance of the Work in
accordance with the Contract Documents in current funds as follows: ($ ),
$ Dollars, in accordance with Section 00300, attached and incorporated
herein by this reference.
ARTICLE 5. PAYMENT PROCEDURES
CONTRACTOR shall submit Applications for Payment in accordance with
Article 14 of the General Conditions. Applications for Payment will be
processed by ENGINEER as provided in the General Conditions.
5.1. PROGRESS PAYMENTS. OWNER shall make progress payments on account
of the Contract Price on the basis of CONTRACTOR's Application for Payment as
recommended by ENGINEER, once each month during construction as provided
below. All progress payments will be on the basis of the progress of the Work
measured by the schedule of values established in paragraph 2.6 of the General
Conditions and in the case of Unit Price Work based on the number of units
completed, and in accordance with the General Requirements concerning Unit
Price Work.
5.1.1. Prior to Substantial Completion, progress payments will be in the
amount equal to the percentage indicated below, but, in each case, less the
aggregate of payments previously made and less such amounts as ENGINEER shall
determine, or OWNER may withhold, in accordance with paragraph 14.7 of the
General Conditions. 90% of the value of Work completed until the Work has
been 50% completed as determined by ENGINEER, when the retainage equals 5% of
the Contract Price, and if the character and progress of the Work have been
satisfactory to OWNER and ENGINEER, OWNER on recommendation of ENGINEER, may
determine that as long as the character and progress of the Work remain
satisfactory to them, there will be no additional retainage on account of Work
9/12/01 Section 00520 Page 3
completed in which case the remaining progress payments prior to Substantial
Completion will be in an amount equal to 100% of the Work completed. 90% of
materials and equipment not incorporated in the Work (but delivered, suitably
stored and accompanied by documentation satisfactory to OWNER as provided in
paragraph 14.2 of the General Conditions) may be included in the application
for payment.
5.1.2. Upon Substantial Completion payment will be made in an amount
sufficient to increase total payments to CONTRACTOR to 95% of the Contract
Price, less such amounts as ENGINEER shall determine or OWNER may withhold in
accordance with paragraph 14.7 of the General Conditions or as provided by
law.
5.2. FINAL PAYMENT. Upon Final Completion and Acceptance of the Work in
accordance with paragraph 14.13 of the General Conditions, OWNER shall pay the
remainder of the Contract Price as recommended by ENGINEER as provided in said
paragraph 14.13.
ARTICLE 6. CONTRACTOR'S REPRESENTATION
In order to induce OWNER to enter into this Agreement, CONTRACTOR makes
the following representations:
6.1. CONTRACTOR has familiarized himself with the nature and extent of
the Contract Documents, Work, site, locality, and with all local conditions
and Laws and Regulations that in any manner may affect cost, progress,
performance or furnishing of the Work.
6.2. CONTRACTOR has studied carefully all reports of explorations and
tests of subsurface conditions and drawings of physical conditions which are
identified in the Supplementary Conditions as provided in paragraph 4.2 of the
General Conditions.
6.3. CONTRACTOR has obtained and carefully studied (or assumes
responsibility for obtaining and carefully studying) all such examinations,
investigations, explorations, tests, reports, and studies (in addition to or
to supplement those referred to in paragraph 6.2 above) which pertain to the
subsurface or physical condition at or contiguous to the site or otherwise may
affect the cost, progress, performance or furnishing of the Work as CONTRACTOR
considers necessary for the performance or furnishing of the Work at the
Contract Price, within the Contract Times and in accordance with the other
terms and conditions of the Contract Documents, including specifically the
provisions of paragraph 4.2 of the General Conditions; and no additional
examinations, investigations, explorations, tests, reports, studies or similar
information or data are or will be required by CONTRACTOR for such purposes.
6.4. CONTRACTOR has reviewed and checked all information and data shown
or indicated on the Contract Documents with respect to existing Underground
Facilities at or contiguous to the site and assumes responsibility for the
9/12/01 Section 00520 Page 4
accurate location of said Underground Facilities. No additional examinations,
investigations, explorations, tests, reports, studies or similar information
or data in respect of said Underground Facilities are or will be required by
CONTRACTOR in order to perform and furnish the Work at the Contract Price,
within the Contract Times and in accordance with the other terms and
conditions of the Contract Documents, including specifically the provision of
paragraph 4.3. of the General Conditions.
6.5. CONTRACTOR has correlated the results of all such observations,
examinations, investigations, tests, reports and data with the terms and
conditions of the Contract Documents.
6.6. CONTRACTOR has given ENGINEER written notice of all conflicts,
errors or discrepancies that he has discovered in the Contract Documents and
the written resolution thereof by ENGINEER is acceptable to CONTRACTOR.
ARTICLE 7. CONTRACT DOCUMENTS
7.1 The Contract Documents which comprise the entire Agreement between
OWNER and CONTRACTOR concerning the Work consist of the General Conditions,
Supplementary Conditions, those items included in the definition of “Contract
Documents” in Article 1.10 of the General Conditions, and such other items as
are referenced in this Article 7, all of which are incorporated herein by this
reference.
7.2 Forms for use by CONTRACTOR in performing the Work and related
actions in carrying out the terms of this Agreement are deemed Contract
Documents and incorporated herein by this reference, and include, but are not
limited to, the following:
7.2.1 Certificate of Substantial Completion
7.2.2 Certificate of Final Acceptance
7.2.3 Lien Waiver Releases
7.2.4 Consent of Surety
7.2.5 Application for Exemption Certificate
7.2.6 Application for Payment
7.3 Drawings, consisting of sheet numbered as follows:
Sheet 1 Lighting Mast and Foundations
The Contract Drawings shall be stamped "Final for Construction" and dated.
Any revisions made shall be clearly identified and dated.
7.4. Addenda Numbers to , inclusive.
7.5. The Contract Documents also include all written amendments and
other documents amending, modifying, or supplementing the Contract Documents
pursuant to paragraphs 3.5 and 3.6 of the General Conditions.
9/12/01 Section 00520 Page 5
7.6. There are no Contract Documents other than those listed or
incorporated by reference in this Article 7. The Contract Documents may only
be amended, modified or supplemented as provided in paragraphs 3.5 and 3.6 of
the General Conditions.
ARTICLE 8. MISCELLANEOUS
8.1. Terms used in this Agreement which are defined in Article I of the
General Conditions shall have the meanings indicated in the General
Conditions.
8.2. No assignment by a party hereto of any rights under or interests in
the Contract Documents will be binding on another party hereto without the
written consent of the party sought to be bound; and specifically but not
without limitations, moneys that may become due and moneys that are due may
not be assigned without such consent (except to the extent that the effect of
this restriction may be limited by law), and unless specifically stated to the
contrary in any written consent to an assignment no assignment will release or
discharge that assignor from any duty or responsibility under the Contract
Document.
8.3. OWNER and CONTRACTOR each binds itself, its partners, successors,
assigns and legal representatives to the other party hereto, its partners,
successors, assigns and legal representatives in respect to all covenants,
Agreement and obligations contained in the Contract Document.
9/12/01 Section 00520 Page 6
OWNER: CITY OF FORT COLLINS CONTRACTOR:
By: ____________________________ By:_______________________________
JAMES B. O’NEILL II, CPPO, FNIGP
DIRECTOR OF PURCHASING __________________________________
AND RISK MANAGEMENT
Title:____________________________
Date:___________________________ Date:_____________________________
(CORPORATE SEAL)
Attest: ________________________ Attest:___________________________
City Clerk
Address for giving notices: Address for giving notices:
P. O. Box 580 __________________________________
Fort Collins, CO 80522 __________________________________
LICENSE NO.:______________________
Approved as to Form
_______________________________
Assistant City Attorney
7/96 Section 00530 Page 1
SECTION 00530
NOTICE TO PROCEED
Description of Work: Bid 5982 Substation Lightning Tower Installation
To:
This notice is to advise you:
That the contract covering the above described Work has been fully executed by
the CONTRACTOR and the OWNER.
That the required CONTRACTOR's Performance Bond and Payment Bond have been
received by the OWNER.
That the OWNER has approved the said Contract Documents.
Therefore, as the CONTRACTOR for the above described Work, you are hereby
authorized and directed to proceed within ( ) calendar days from
receipt of this notice as required by the Agreement.
Dated this day of , 20__.
The dates for Substantial Completion and Final Acceptance shall be ,
and , 20__, respectively.
City of Fort Collins
OWNER
By:
Title:
ACKNOWLEDGMENT OF NOTICE
Receipt of the above Notice to Proceed is hereby acknowledged this
day of , 20__.
CONTRACTOR:
By:
Title:
SECTION 00600
BONDS AND CERTIFICATES
00610 Performance Bond
00615 Payment Bond
00630 Certificate of Insurance
00635 Certificate of Substantial Completion
00640 Certificate of Final Acceptance
00650 Lien Waiver Release (CONTRACTOR)
00660 Consent of Surety
00670 Application for Exemption Certificate
7/96 Section 00610 Page 1
SECTION 00610
PERFORMANCE BOND
Bond No.
KNOW ALL MEN BY THESE PRESENTS: that
(Firm)
(Address)
(an Individual), (a Partnership), (a Corporation), hereinafter referred to as
the "Principal" and
(Firm)
(Address)
hereinafter referred to as "the Surety", are held and firmly bound unto City
of Fort Collins, 300 Laporte Ave, Fort Collins, Colorado 80522 a (Municipal
Corporation) hereinafter referred to as the "OWNER", in the penal sum of
in lawful money of the United States,
for the payment of which sum well and truly to be made, we bind ourselves,
successors and assigns, jointly and severally, firmly by these presents.
THE CONDITIONS OF THIS OBLIGATION are such that whereas the Principal entered
into a certain Agreement with the OWNER, dated the day of ,
20__, a copy of which is hereto attached and made a part hereof for the
performance of The City of Fort Collins project, Bid 5982 Substation Lightning
Tower Installation.
NOW, THEREFORE, if the Principal shall well, truly and faithfully perform its
duties, all the undertakings, covenants, terms, conditions and agreements of
said Agreement during the original term thereof, and any extensions thereof
which may be granted by the OWNER, with or without Notice to the Surety and
during the life of the guaranty period, and if the Principal shall satisfy all
claims and demands incurred under such Agreement, and shall fully indemnify
and save harmless the OWNER from all cost and damages which it may suffer by
reason of failure to do so, and shall reimburse and repay the OWNER all outlay
and expense which the OWNER may incur in making good any default then this
obligation shall be void; otherwise to remain in full force and effect.
7/96 Section 00610 Page 2
PROVIDED, FURTHER, that the said Surety, for value received, hereby stipulates
and agrees that no change, extension of time, alteration or addition to the
terms of the Agreement or to the Work to be performed thereunder or the
Specifications accompanying the same shall in any way affect its obligation on
this bond; and it does hereby waive notice of any such change, extension of
time, alteration or addition to the terms of the Agreement or to the Work or
to the Specifications.
PROVIDED, FURTHER, that no final settlement between the OWNER and the
CONTRACTOR shall abridge the right of any beneficiary hereunder, whose claim
may be unsatisfied.
PROVIDED, FURTHER, that the Surety Company must be authorized to transact
business in the State of Colorado and be acceptable to the OWNER.
IN WITNESS WHEREOF, this instrument is executed in three (3) counterparts,
each one of which shall be deemed an original, this day of ,
20__.
IN PRESENCE OF: Principal
______________________________ ________________________________________
______________________________ ________________________________________
(Title)
________________________________________
(Address)
(Corporate Seal)
IN PRESENCE OF: Other Partners
_____________________________ By:_____________________________________
_____________________________ By:_____________________________________
IN PRESENCE OF: Surety
_____________________________ By:_____________________________________
_____________________________ By:_____________________________________
(Address)
(Surety Seal)
NOTE: Date of Bond must not be prior to date of Agreement.
If CONTRACTOR is Partnership, all partners should execute Bond.
7/96 Section 00615 Page 1
SECTION 00615
PAYMENT BOND
Bond No.
KNOW ALL MEN BY THESE PRESENTS: that
(Firm)
(Address)
(an Individual), (a Partnership), (a Corporation), hereinafter referred to as
the "Principal" and
(Firm)
(Address)
hereinafter referred to as "the Surety", are held and firmly bound unto the
City of Fort Collins, 300 Laporte Ave., Fort Collins, Colorado 80522 a
(Municipal Corporation) hereinafter referred to as "the OWNER", in the penal
sum of in lawful money of the
United States, for the payment of which sum well and truly to be made, we bind
ourselves, successors and assigns, jointly and severally, firmly by these
presents.
THE CONDITIONS OF THIS OBLIGATION are such that whereas the Principal entered
into a certain Agreement with the OWNER, dated the day of ,
20__, a copy of which is hereto attached and made a part hereof for the
performance of The City of Fort Collins project, Bid 5982 Substation Lightning
Tower Installation.
NOW, THEREFORE, if the Principal shall make payment to all persons, firms,
subcontractors, and corporations furnishing materials for or performing labor
in the prosecution of the Work provided for in such Agreement and any
authorized extension or modification thereof, including all amounts due for
materials, lubricants, repairs on machinery, equipment and tools, consumed,
rented or used in connection with the construction of such Work, and all
insurance premiums on said Work, and for all labor, performed in such Work
whether by subcontractor or otherwise, then this obligation shall be void;
otherwise to remain in full force and effect.
7/96 Section 00615 Page 2
PROVIDED, FURTHER, that the said Surety, for value received, hereby stipulates
and agrees that no change, extension of time, alteration or addition to the
terms of the Agreement or to the Work to be performed thereunder or the
Specifications accompanying the same shall in any way affect its obligation on
this bond; and it does hereby waive notice of any such change, extension of
time, alteration or addition to the terms of the Agreement or to the Work or
to the Specifications.
PROVIDED, FURTHER, that no final settlement between the OWNER and the
CONTRACTOR shall abridge the right of any beneficiary hereunder, whose claim
may be unsatisfied.
PROVIDED, FURTHER, that the Surety Company must be authorized to transact
business in the State of Colorado and be acceptable to the OWNER.
IN WITNESS WHEREOF, this instrument is executed in three (3) counterparts,
each one of which shall be deemed an original, this day of ,
20__.
IN PRESENCE OF: Principal
______________________________ By:___________________________________
______________________________ ______________________________________
(Title)
______________________________________
(Address)
(Corporate Seal)
IN PRESENCE OF: Other Partners
______________________________ ______________________________________
______________________________ ______________________________________
IN PRESENCE OF: Surety
______________________________ By:___________________________________
______________________________ By:___________________________________
(Address)
(Surety Seal)
NOTE: Date of Bond must not be prior to date of Agreement.
If CONTRACTOR is Partnership, all partners should execute Bond.
7/96 Section 00630 Page 1
SECTION 00630
CERTIFICATE OF INSURANCE
CONTRACTOR shall insert his own standard form for Certificate of Insurance.
7/96 Section 00635 Page 1
SECTION 00635
CERTIFICATE OF SUBSTANTIAL COMPLETION
TO: CITY OF FORT COLLINS
(OWNER)
DATE OF SUBSTANTIAL COMPLETION: PROJECT TITLE: Bid 5982 Substation Lightning
Tower Installation
_____________________________
PROJECT OR SPECIFIED PART SHALL LOCATION: Fort Collins, Colorado
INCLUDE:
OWNER: City of Fort Collins
____________________________
____________________________ CONTRACTOR: ______________________________
____________________________
CONTRACT DATE:____________________________
The Work performed under this contract has been inspected by authorized
representatives of the OWNER, CONTRACTOR, and the ENGINEER and the project (or
specified part of the project, as indicated above) is hereby declared to be
substantially completed on the above date.
A tentative list of items to be completed or corrected is appended hereto.
This list may not be exhaustive, and the failure to include an item on it does
not alter the responsibility of the CONTRACTOR to complete all the Work in
accordance with the Contract Documents.
_________________________________ ________________________________________
ENGINEER AUTHORIZED REPRESENTATIVE DATE
The CONTRACTOR accepts the above Certificate of Substantial Completion and
agrees to complete and correct the items on the tentative list within the time
indicated.
________________________________ By: ________________________________________
CONTRACTOR AUTHORIZED REPRESENTATIVE DATE
The OWNER accepts the project or specified area of the project as
substantially complete and will assume full possession of the project or
specified area of the project at 12:01 a.m., on . The
responsibility for heat, utilities, security, and insurance under the Contract
Documents shall be as set forth under "Remarks" below.
CITY OF FORT COLLINS, COLORADO By: ________________________________________
OWNER AUTHORIZED REPRESENTATIVE DATE
REMARKS:
7/96 Section 00640 Page 1
SECTION 00640
CERTIFICATE OF FINAL ACCEPTANCE
, 20__
TO:
Gentlemen:
You are hereby notified that on the day of , 20__, the City of
Fort Collins, Colorado, has accepted the Work completed by
for the City of Fort Collins project, Bid 5982 Substation Lightning Tower
Installation.
A check is attached hereto in the amount of $________________________ as Final
Payment for all Work done, subject to the terms of the Contract Documents
which are dated ________________.
In conformance with the Contract Documents for this project, your obligations
and guarantees will continue for the specified time from the following
date:___________________________.
Sincerely,
OWNER: City of Fort Collins
By:
Title:
ATTEST:
Title:
7/96 Section 00650 Page 1
SECTION 00650
LIEN WAIVER RELEASE
(CONTRACTOR)
TO: City of Fort Collins, Colorado (OWNER)
FROM: (CONTRACTOR)
PROJECT: Bid 5982 Substation Lightning Tower Installation
1. The CONTRACTOR acknowledges having received payment, except retainage
from the OWNER for all work, labor, skill and material furnished,
delivered and performed by the CONTRACTOR for the OWNER or for anyone in
the construction, design, improvement, alteration, addition or repair of
the above described project.
2. In consideration of such payment and other good and valuable
consideration, the receipt and adequacy of which are hereby acknowledged,
the CONTRACTOR voluntarily waives all rights, claims and liens, including
but not limited to, mechanic's liens, Miller Act claims (40 U.S.C.A. 270
a and b), stop notices, equitable liens and labor and material bond
rights which the CONTRACTOR may now or may afterward have, claim or
assert for all and any work, labor, skill or materials furnished,
delivered or performed for the construction, design, improvement,
alteration, addition or repair of the above described project, against
the OWNER or its officers, agents, employees or assigns, against any fund
of or in the possession or control of the OWNER, against the project or
against all land and the buildings on and appurtenances to the land
improved by the project.
3. The CONTRACTOR affirms that all work, labor and materials, furnished,
delivered or performed to or for the construction, design, improvement,
alteration, addition or repair of the project were furnished, delivered
or performed by the CONTRACTOR or its agents, employees, and servants, or
by and through the CONTRACTOR by various Subcontractors or materialmen or
their agents, employees and servants and further affirms the same have
been paid in full and have released in full any and all existing or
possible future mechanic's liens or rights or claims against the project
or any funds in the OWNER'S possession or control concerning the project
or against the OWNER or its officers, agents, employees or assigns
arising out of the project.
4. The CONTRACTOR agrees to defend and hold harmless the OWNER, the lender,
if any, and the Surety on the project against and from any claim
hereinafter made by the CONTRACTOR'S Subcontractors, materialmen,
employees, servants, agents or assigns against the project or against the
OWNER or its officers, employees, agents or assigns arising out of the
project for all loss, damage and costs, including reasonable attorneys
7/96 Section 00650 Page 2
fees, incurred as a result of such claims.
5. The parties acknowledge that the description of the project set forth
above constitutes and adequate description of the property and
improvements to which this Lien Waiver Release pertains. It is further
acknowledged that this Lien Waiver Release is for the benefit of and may
be relied upon by the OWNER, the lender, if any, and Surety on any labor
and material bonds for the project.
Signed this day of , 20__.
CONTRACTOR
By:
Title:
ATTEST:
Secretary
STATE OF COLORADO )
)ss.
COUNTY OF LARIMER )
Subscribed and sworn to before me this day of
20__, by
Witness my hand and official seal.
My Commission Expires: .
Notary Public
7/96 Section 00660 Page 1
SECTION 00660
CONSENT OF SURETY
TO: City of Fort Collins, Colorado
(hereinafter referred to as the "OWNER")
CONTRACTOR:
PROJECT: Bid 5982 Substation Lightning Tower Installation
CONTRACT DATE:
In accordance with the provisions of the Contract between the OWNER and the
CONTRACTOR as indicated above, for
(Surety)
on bond of
hereby approves of the Final Payment to the CONTRACTOR, and agrees that Final
Payment to the CONTRACTOR shall not relieve the Surety Company of any of its
obligations to the OWNER, as set forth in the said Surety Company's Bond.
IN WITNESS WHEREOF, the Surety Company has hereunto set its hand this
day of , ____ .
(Surety Company)
By
ATTACH: Power of Attorney and Certificate of Authority of Attorney(s)-in-
Fact.
Section 00670 Page 1
SECTION 00670
APPLICATION FOR EXEMPTION CERTIFICATE
Section 00670 Page 2
SECTION 00700
GENERAL CONDITIONS
SE
SECTION 00800
SUPPLEMENTARY CONDITIONS
7/96 Section 00800 Page 1
SECTION 00800
SUPPLEMENTARY CONDITIONS
Conditions of the Contract
These Supplementary Conditions amend or supplement the General Conditions of
the Construction Contract (EJCDC General Conditions 1910-8, 1990 edition with
City of Fort Collins modifications) and other provisions of the Contract
Documents as indicated below.
SC-4.2 Subsurface and Physical Conditions:
A. Add the following language to paragraph 4.2.1 of the General
Conditions.
4.2.1.1.1 The following report(s) of exploration and tests of
subsurface conditions at the site of the Work:
Geotechnical Investigation for Substation Lightning Towers’
Smith Geotechnical
Project NO 06.007
May 2006
Contractor may rely upon the accuracy of the technical data
contained in the geotechnical documents, but not upon nontechnical
data, interpretations or opinions contained therein or upon the
completeness of any information in the report.
B. 4.2.1.2.1 No drawing of physical conditions in or relating to
existing surface or subsurface structures (except Underground
Facilities referred to in Paragraph 4.3) which are at or contiguous
to the site have been utilized by the Engineer in preparation of
the Contract Documents, except the following:
SC-5.4.8 Limits of Liability
A. Add the following language at the end of paragraph 5.4.8.
The limits of liability for the insurance required by the paragraph
numbers of the General Conditions listed below are as follows:
7/96 Section 00800 Page 2
5.4.1 and 5.4.2
Coverage A - Statutory Limits
Coverage B - $100,000/$100,000/$500,000
5.4.3 and 5.4.5 Commercial General Liability policy will have limits of
$1,000,000 combined single limits (CSL). This policy will include
coverage for Explosion, Collapse, and Underground coverage unless waived
by the Owner.
5.4.6 The Comprehensive Automobile Liability Insurance policy will have
limits of $1,000,000 combined single limits (CSL).
5.4.9 This policy will include completed operations coverage/product
liability coverage with limits of $1,000,000 combined single limits
(CSL).
SC-12.3 Add the following language to the end of paragraph 12.3.
Contractor will include in the project schedule five (5) days lost due to
abnormal weather conditions.
9/99
SECTION 00900
ADDENDA, MODIFICATIONS AND PAYMENT
00950 Contract Change Order
00960 Application for Payment
9/99 Section 00950 Page 1
SECTION 00950
CHANGE ORDER NO.
PROJECT TITLE: Bid 5982 Substation Lightning Tower Installation
CONTRACTOR:
PROJECT NUMBER:
DESCRIPTION:
1. Reason for change:
2. Description of Change:
3. Change in Contract Cost
4. Change in Contract Time:
__
ORIGINAL CONTRACT COST $ .00
TOTAL APPROVED CHANGE ORDER 0.00
TOTAL PENDING CHANGE ORDER 0.00
TOTAL THIS CHANGE ORDER 0.00
TOTAL % OF THIS CHANGE ORDER
TOTAL C.O.% OF ORIGNINAL CONTRACT
ADJUSTED CONTRACT COST $ 0.00
(Assuming all change orders approved) _
ACCEPTED BY: DATE:
Contractor's Representative
ACCEPTED BY: DATE: __
Project Manager
REVIEWED BY: DATE:
Title:
APPROVED BY: DATE:
Title:
APPROVED BY: DATE:
Purchasing Agent over $30,000
cc: City Clerk Contractor
Project File Architect
Engineer Purchasing
9/997/96 Section 00960 Page 1
Section 00960
APPLICATION FOR PAYMENT PAGE 1 OF 4
OWNER: City of Fort Collins PROJECT: APPLICATION NUMBER:
APPLICATION DATE:
PERIOD BEGINNING:
ENGINEER: CONTRACTOR: PERIOD ENDING:
PROJECT NUMBER:
CHANGE ORDERS Application is made for Payment as shown below in connection with Contract
NUMBER DATE AMOUNT
The present status of the account for this Contract is as
follows:
1
2 Original Contract Amount:
3 Net Change by Change Order:
Current contract Amount: $0.00
Total Completed and Stored to Date:
Less Previous Applications:
Amount Due this Application - Before Retainage: $0.00
Less Retainage:
Net Change by Change Order $0.00 AMOUNT DUE THIS APPLICATION: $0.00
CERTIFICATION:
The undersigned CONTRACTOR certifies that all obligations of CONTRACTOR incurred in connection with
the Work have been satisfied as required in Paragraph 14.3. of the General Conditions of the Contract.
The above Amount Due This Application is requested by the
CONTRACTOR.
Date: By:
Payment of the above Amount Due This Application is recommended by the ENGINEER.
Date: By:
Payment of the above Amount Due This Application has been reviewed by the OWNER'S Project Manager.
Date: By:
Payment of the above Amount Due This Application is approved by the OWNER.
Date: By:
7/96 Section 00960 Page 2
CONTRACT AMOUNTS
APPLICATION FOR
PAYMENT PAGE 2 OF 4
Work
Completed
Work
Completed
Work
Completed Stored
Bid
This
Month
Previous
Periods
To
Date Materials Total
Item This Earned Percent
Number Description Quantity Units
Unit
Price Amount Qty. Amount Qty. Amount Qty. Amount Period To Date Billed
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
TOTALS $0.00 $0.00 $0.00 $0.00 $0.00
7/96 Section 00960 Page 3
CHANGE ORDERS APPLICATION FOR PAYMENT PAGE 3 OF 4
Work Completed
Work
Completed
Work
Completed Stored
Bid
This
Month
Previous
Periods
To
Date Materials Total
Item This Earned Percent
Number Description Quantity Units
Unit
Price Amount Qty. Amount Qty. Amount Qty. Amount Period
To
Date Billed
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
TOTALS CHANGE ORDERS $0.00 $0.00 $0.00 $0.00 $0.00
PROJECT TOTALS $0.00 $0.00 $0.00 $0.00 $0.00
7/96 Section 00960 Page 4
STORED MATERIALS
SUMMARY PAGE 4 OF 4
On Hand Received Installed On Hand
Item Invoice Previous This This This
Number Number Description Application Period Period Application
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
TOTALS $0.00 $0.00 $0.00 $0.00
City of Fort Collins Power & Light-06.007 1A-1
PART 1 - GENERAL REQUIREMENTS
Section 1A - GENERAL REQUIREMENTS
1A.1 GENERAL
This section covers the general requirements for the equipment, materials and services included
under these specifications.
1A.2 CORRESPONDENCE
All correspondence shall be addressed to the Owner as follows:
City of Fort Collins Utilities
700 Wood Street
P.O. Box 580
FORT COLLINS, COLORADO 80522-0580
ATTENTION: Matt Haag
Letters of transmittal shall accompany all submittals of engineering data. All correspondence
and drawings shall be identified with the project name, Owner's contract number, and
Contractor's job number.
1A.3 PRE-CONSTRUCTION CONFERENCE
Prior to the start of construction, the Owner will hold a pre-construction conference at the office
of the Owner to review matters relative to the performance of this contract. The Contractor, the
Contractor's superintendent for this project, and the Contractor's personnel responsible for
ordering Contractor furnished materials for this project shall attend this conference.
1A.4 DRAWING AND ENGINEERING DATA REQUIREMENTS
1A.4.1 Submittal of Drawings and Engineering Data
Drawings and other engineering data for the specified equipment and materials are essential to
the design and subsequent construction of the project. The Contractor will be required to submit
drawings and engineering data in accordance with the requirements specified in Article 1A.4 and
the schedule specified in Article 1A.11 to assure compliance with the overall construction and
operating schedule.
1A.4.2 Review of Drawings and Engineering Data
The Owner's review of drawings and engineering data will cover only general conformity of the
drawings and data to the specifications and documents, external connections, interfaces with
City of Fort Collins Power & Light-06.007 1A-2
equipment and materials furnished under separate specifications, and dimensions which affect
plant arrangements. The Owner's review does not indicate a thorough review of all dimensions,
quantities, and details of the equipment, material, device, or item indicated or the accuracy of the
information submitted; nor shall review by the Owner be construed as relieving the Contractor
from any responsibility for errors, omissions, or deviations from the requirements of the contract
documents.
All engineering data submitted, after final processing and acceptance by the Owner, shall
become a part of the contract documents and the work indicated or described thereby shall be
performed in conformity therewith, unless otherwise required by the Owner.
1A.4.3 [This Section Not Used]
1A.4.4 Drawing Requirements
All drawings shall be in accordance with the following requirements.
1A.4.4.1 General
Final drawings are to be submitted on paper copies and electronically to the Owner in Portable
Document Format (PDF) or in AutoCAD (DWG) format.
Drawings shall be in sufficient detail to indicate the kind, size, arrangement, weights of each
component, electrical characteristics, and operation of component materials and devices; the
external connections, anchorages, and supports required; the dimensions needed for installation
and correlation with other materials and equipment.
Certified drawings only shall be submitted unless a requirement for preliminary drawings is
specifically stated in the drawing submittal schedule. Such requirement shall not preclude the
Contractor from submitting certified drawings in lieu of preliminary drawings.
"Preliminary" drawings shall mean drawings not fully completed or approved by the Contractor;
however, they shall be reasonably complete and suitable for the Owner's use in establishing basic
plant arrangements and design requirements. Preliminary drawings shall be clearly stamped
"Preliminary." Preliminary drawings will not be reviewed by the Owner; however, the Owner
will advise the Contractor of any discrepancies or conflicts which he may discover in the
reference to the drawings.
"Certified" drawings shall mean drawings fully completed and certified by the Contractor as to
the compliance of the information contained thereon with the requirements of these
specifications. Certified drawings shall be clearly stamped "Certified" or shall have title block
entries clearly indicating the drawing is certified. Certified drawings will be reviewed by the
Owner and processed as specified in this Section 1A.4.4.3.
Each drawing submitted shall be clearly marked with the name of the project, the unit
designation, the contract title and number, and the Contractor's name. If standard drawings or
City of Fort Collins Power & Light-06.007 1A-3
catalog cuts are submitted, the applicable equipment and devices furnished shall be clearly
marked on the front of each drawing.
When the specification requires furnishing equipment and materials for more than one project,
the Contractor shall furnish separate and complete drawings for each project site in accordance
with these specifications. No common drawings are allowed.
Prints shall be black line on white background or blue line on white background. Print size shall
not exceed 24 inches by 36 inches unless, due to the size of the equipment, larger drawings are
necessary. Larger drawing sizes shall not be used without the approval of the Owner.
All drawings shall be suitable for microfilming. Drawing and lettering practices shall be in
general accordance with the requirements of Military Standard Engineering Drawing Practices,
MIL-STD-100B. Drawings submitted which are not suitable for microfilming will not be
accepted.
1A.4.4.2 Drawing Types Required
The drawings and information required to be furnished by the Contractor is listed in each section
of Technical Requirements.
1A.4.4.3 Drawing Processing
A copy of each drawing reviewed will be returned to the Contractor as stipulated herein. Copies
of drawings returned to the Contractor will be in the form of a print with the Owner's marking.
No work shall be performed in connection with the purchase or installation of equipment and
materials until the drawings and data, therefore, have been reviewed by the Owner except at the
Contractor's own risk and responsibility.
Drawings reviewed by the Owner will be returned to the Contractor marked RETURNED FOR
CORRECTION, EXCEPTIONS NOTED, NO EXCEPTIONS NOTED, or RECEIVED FOR
DISTRIBUTION. The Contractor shall make all required corrections to the drawings and
resubmit the required number of prints to the Owner no later than the date indicated in the
Owner's drawing transmittal letter. Each time a drawing is revised an appropriate revision
number and note shall be added to that drawing.
RETURNED FOR CORRECTION (RFC) means that the drawing must be revised in accordance
with the Owner's notations and all work represented by the drawing must cease until the revised
drawing has been resubmitted, reviewed by the Owner, and returned to the Contractor marked
EXCEPTIONS NOTED, NO EXCEPTIONS NOTED, or RECEIVED FOR DISTRIBUTION.
EXCEPTIONS NOTED (EN) means that the drawing must be revised in accordance with the
Owner's notations and resubmitted. Work represented by the drawing may proceed but it must
be in accordance with the Owner's notations.
City of Fort Collins Power & Light-06.007 1A-4
NO EXCEPTIONS NOTED (NEN) means that the Owner has no specific objections to the
drawing at this time. Work may proceed with the understanding that the design process may
require drawing revision at a later time.
RECEIVED FOR DISTRIBUTION (RFD) means that the Owner has not reviewed the drawing
but that the drawing is required for the design process and has been included in the drawing file.
If drawing revisions occur during the course of the contract, the Contractor is obligated to submit
revised copies to the Owner in order to keep the drawing file current.
Initial drawing and data submittals by the Contractor shall be three (3) copies of each. When the
drawings and data are returned by the Owner marked RETURNED FOR CORRECTION or
EXCEPTIONS NOTED, the corrections shall be made by the Contractor as noted thereon and
three (3) copies of the corrected drawing shall be resubmitted to the Owner.
When the drawings are returned marked NO EXCEPTIONS NOTED or RECEIVED FOR
DISTRIBUTION, such drawings shall be considered final and the work shall proceed in
accordance therewith. The Owner will retain 2 copies of the drawing, one for themselves and
one for the Engineer.
If changes are made at the project site to the equipment to correct for manufacturing errors, due
to design changes or wiring revisions; revised drawings indicating the changes made shall be
sent to the Contractor by the Owner. Contractor shall revise the drawings with changes and
submit five (5) of each drawing furnished by the Contractor for this contract.
1A.6 RECEIVING AND HANDLING
1A.6.1 Contractor-Furnished Equipment and Materials
The Contractor shall be responsible for the prompt unloading of all equipment or materials to be
furnished under this contract and shall pay all demurrage incurred. The Contractor shall handle
all equipment and materials carefully to prevent damage or loss. The use of bare wire rope
slings for unloading and handling materials and equipment is prohibited except with the specific
permission of the Owner.
1A.6.2 [This Section Not Used]
1A.7 STORAGE
Contractor shall assume responsibility for and protect all equipment and materials during the
storage period in accordance with the manufacturer or supplier's recommendations.
Stored equipment and materials shall be adequately supported and protected to prevent damage.
Equipment shall be moved to its permanent location as soon as construction will permit.
Stored equipment and materials shall not be allowed to contact the ground.
City of Fort Collins Power & Light-06.007 1A-5
All openings in equipment and piping not stored under weatherproof covers shall be closed to
prevent entrance of dirt or moisture during storage.
All platforms, enclosures, shoring and weatherproof coverings for storage use shall remain the
property of the Contractor and shall be removed upon completion of the work.
All storage methods and schedules shall be acceptable to the Owner.
1A.8 [This Section Not Used]
1A.9 CONSTRUCTION SAFETY
The Contractor shall furnish all necessary safety equipment required for performance of the work
and shall be responsible for persons on the work site. The Contractor shall contact the Owner
before starting work inside an energized substation or near buried power cables or equipment.
The Contractor shall be responsible for maintaining proper electrical clearances from energized
lines and equipment and shall request clearances from the Owner for work that impedes safe
working distances.
1A.10 CONSTRUCTION SERVICES
This section covers the requirements for construction services to be provided by the Contractor
in the performance of the Work.
1A.10.1 Construction Plant and Temporary Facilities
The Contractor shall furnish all construction plant and temporary facilities which are required for
performance of the Work but which will not be incorporated in the completed Work.
All temporary structures and facilities furnished by the Contractor shall remain the property of
the Contractor. When the work is completed, all such temporary structures and facilities shall be
removed from the site and the area restored to a satisfactory condition.
All construction plant and facilities shall be in sound condition, of the proper type and size to
adequately perform the Work, and shall be regularly and systematically maintained throughout
the Work to ensure proper, efficient operation. Plant and facilities that are inadequate or
improperly maintained shall be promptly modified, repaired, or removed from the site and
replaced.
1A.10.2 Temporary Structures
Temporary structures for offices, change houses, warehouses, and other uses for the Contractor
or the Contractor’s subcontractors, shall be provided by the Contractor using materials, design,
and construction acceptable to the Owner. Suitable construction trailers may be used in lieu of
temporary structures.
City of Fort Collins Power & Light-06.007 1A-6
Temporary structures or trailers shall be placed only in locations assigned by the Owner.
1A.10.3 Construction Utilities
Construction utilities shall be provided by the Contractor as specified herein.
1A.10.3.1 Telephone
The Contractor shall arrange and provide for the Contractor’s own telephone service.
1A.10.3.2 Compressed Air
The Contractor shall provide all air compressors, fuels, lubricants, hoses, piping, and other
apparatus required for supplying compressed air for prosecution of the Work.
1A.10.3.3 Construction Power
The Contractor shall be responsible for obtaining temporary construction power to be metered at
the Contractor's expense.
Temporary power facilities shall conform with applicable safety and code requirements, shall be
constructed and located to provide proper clearances and minimum interference with
construction activities, and shall be acceptable to the Owner.
All temporary wiring in the yard area shall be placed underground at a minimum depth of 2'-0"
below grade with at least 4 inches of sand cover on all sides of grouped conductors.
Underground cable shall be NEC Type USE.
1A.10.3.4 Temporary Lighting
The Contractor shall furnish and install all temporary lighting required in the prosecution of
work. Conductors shall be not less than 12 AWG copper and insulated for 600 volts. A fuse
shall be provided for the protection of each circuit.
1A.10.3.5 Welding Facilities
The Contractor shall furnish all welding machines and welding equipment required for the
Contractor’s work. Electric power may be obtained from the construction power source or from
engine-driven welding machines. The Contractor shall furnish all fuel required for engine-
driven machines.
City of Fort Collins Power & Light-06.007 1A-7
1A.10.3.6 Water
The Contractor shall provide the Contractor’s own water for construction and drinking. Piping,
valves, and hoses shall be provided as required for construction distribution. Drinking water
facilities shall include coolers, cups, cup dispensers, and disposal receptacle.
1A.10.3.7 Heat
The Contractor shall provide all heating facilities required for the efficient performance of the
Contractor’s work, and as required to prevent freeze damage to equipment under the
Contractor’s custody. The method of heating shall be acceptable to the Owner.
Open fires, or other methods that constitute a hazard to personnel or property shall not be used.
All heating equipment shall be provided with adequate safeguards.
1A.10.3.8 Sanitary Facilities
The Contractor shall arrange and provide for the Contractor’s own sanitary facilities.
1A.11 CONSTRUCTION SCHEDULE.
1A.11.1 General
This section covers the schedule and scheduling requirements for performance and completion of
the Work under these specifications and documents.
1A.11.2 [This Section Not Used]
1A.11.3 Contractor's Detailed Schedule
Within 15 days after receiving the Owner's Notice to Proceed, the Contractor shall submit a
detailed construction schedule. The detailed schedule shall be based upon the dates specified in
the construction schedule included herein.
The detailed construction schedule shall be in bar graph form acceptable to the Owner.
The detailed construction schedule shall contain all activities of the construction plan, including
acquisition and installation of special materials. For all materials fabricated or supplied by the
Contractor especially for this project, the schedule shall include the sequence of activities
including issuance of purchase orders, preparation of shop drawings, fabrication, and delivery.
Each activity shall be identified on the schedule by a descriptive title and shall be assigned an
estimated number of working days required and an expected completion date.
The Contractor is responsible to determine the sequence and time estimates of the detailed daily
construction activities; however, the Owner reserves the right to require the Contractor to modify
any portion of the schedule the Owner determines to be impractical, infeasible, or unreasonable,
City of Fort Collins Power & Light-06.007 1A-8
and as required to coordinate the Contractor's activities with those of other contractors, and to
assure the completion of the Work by the stipulated date.
Schedules returned to the Contractor for revision or correction shall be resubmitted for review
within 15 calendar days. Upon acceptance by the Owner of the detailed schedule of activities,
the Contractor will be responsible for maintaining such schedule.
Each month the Contractor shall submit a complete list of all deviations from the detailed
construction schedule to reflect the actual progress of the Work, together with the Contractor’s
proposed actions to alleviate any delays caused by the deviations.
City of Fort Collins Power & Light – 06.007 2A-1
Section 2A - EARTHWORK
2A.1. GENERAL
This section covers excavating, hauling, stockpiling, spoiling, mixing, blending, placing, wetting,
compacting, and other earthwork procedures required for installation of the structures.
All structures shall be constructed to the lines, grades, and details indicated on the Drawings or as
otherwise directed by the Engineer.
2A.2. FREEZING WEATHER RESTRICTIONS
Backfill of new structures shall not be performed during freezing weather except by written
permission of the Engineer. No fill materials shall be placed on frozen surfaces. Frozen materials,
snow, or ice shall not be placed in the fill. Structures shall not be placed on frozen subgrades except
by written permission of the Engineer.
2A.3. SHEETING AND SHORING
Except where banks are cut back on a stable slope, excavations shall be properly and substantially
sheeted, braced, and shored, as necessary, to prevent caving or sliding and to provide protection for
workmen and the work. Sheeting, bracing, shoring, or trench boxes shall be designed and built to
withstand all loads that might be caused by earth movement or pressure, and shall be rigid,
maintaining shape and position under all circumstances. Hazardous and dangerous conditions shall
be prevented and the safety of personnel shall be maintained.
2A.4. REMOVAL OF WATER
The Contractor shall provide for and maintain adequate dewatering to remove and dispose of all
water entering excavations or other parts of the work. Each construction area and excavation shall
be kept dry during subgrade preparation and continually thereafter until the construction required
therein is completed to the extent that no damage from hydrostatic pressure, flotation, or other cause
will result.
All construction areas and excavations which extend down to or below static ground water
elevations shall be dewatered by lowering and maintaining the ground water surface beneath such
excavations.
Surface water shall be diverted or otherwise prevented from entering construction areas and
excavations to the greatest extent practicable.
2A.5. SITE PREPARATION
Ground surfaces within the construction areas shall be cleared of all trees, brush, debris, and surface
City of Fort Collins Power & Light – 06.007 2A-2
vegetation. Stumps and roots larger than 2" in diameter shall be completely grubbed and removed.
Matted roots shall be removed regardless of size. Surface vegetation shall be removed complete
with roots to a depth of not less than 4" below the ground surface.
All combustible and other waste materials shall be removed from the construction areas and
disposed of by and at the expense of the Contractor. Open burning is not permitted at the site.
Aggregate surfacing within the construction areas shall be removed and stored on site for later
replacement.
2A.6. MAINTENANCE OF TRAFFIC
The Contractor shall conduct the Contractor’s work so as to interfere as little as possible with the
Owner's operations and the work of other contractors. Whenever it is necessary to cross, obstruct, or
close roads, driveways, parking areas and walks, the Contractor shall provide and maintain suitable
and safe bridges, detours, or other temporary expedience at the Contractor’s own expense. In
making open cut road crossing, the Contractor shall not block more than one half of the road at any
time.
2A.7. BLASTING
No blasting or other use of explosive for excavation will be permitted for any of the onsite
excavations or construction.
2A.8. CLASSIFICATION OF MATERIALS
Soil identification shall be in accordance with ASTM D2487. Identification and classification of
materials will be based upon visual examination and simple manual tests performed under the
direction of the Engineer by an independent testing laboratory. If visual examination and manual
tests are inadequate for the required identification and classification, the Engineer will require the
testing laboratory to determine definite index properties of the questionable material.
2A.9. UNAUTHORIZED EXCAVATION
Any material excavated below the elevation or otherwise beyond the limits indicated on the draw-
ings, unless otherwise authorized by the Engineer, shall be replaced and compacted to the density
indicated in 2A.25. The unauthorized excavation of material and subsequent replacement and
compaction shall be by and at the expense of the Contractor.
2A.10. STABILIZATION
Subgrades for structures, fills, and backfills shall be firm, dense, and thoroughly compacted and
consolidated; shall be free from mud and muck; and shall be sufficiently stable to remain firm and
intact under the feet of the workmen or equipment in use.
City of Fort Collins Power & Light – 06.007 2A-3
Subgrades for structures which are otherwise solid but which become mucky on top due to
construction operation shall be covered with two to four inches (2”-4”) of gravel by and at the
expense of the Contractor.
The finished elevation of stabilized structure subgrades shall not be above the subgrade elevations
indicated on the drawings.
Stabilization material shall be utilized where necessary and shall be approved by the Engineer. This
material shall generally be minus 4-inch granular material except in areas where the migrations of
fines into the stabilization material would be unacceptable. In these areas, a layer of filter sand or
gravel or geotextile filter fabric may be required.
2A.11. PROTECTION OF UNDERGROUND CONSTRUCTION
The Contractor shall locate, protect, shore, brace, support, and maintain all existing underground
pipes, conduits, drains, and other underground construction which may be uncovered, damaged or
otherwise be affected by the work.
2A.12. TEMPORARY TOPSOIL STOCKPILE – This Section Not Used
2A.13. BORROW AREAS
No borrow material is available.
2A.14. SPOIL MATERIAL
Material that is unsuitable for use in the required fills shall be removed from the site and disposed of
by the Contractor.
2A.15. STRUCTURE FOUNDATIONS AND BACKFILL
This section covers earthwork required for construction of all structures including excavation,
subgrade preparation, structural fill, and backfill.
2A.15.1. Excavation
This article covers the excavation required for all new structures.
The existing subgrade fill material shall be completely removed to the sandy gravel layer below. The
approximate excavation is 9 feet below grade.
A Geotechnical Engineer will inspect the natural soils at the bottom of the excavation prior to
subgrade preparation. Provide Engineer with 72 hours notice when the area is expected to be ready
City of Fort Collins Power & Light – 06.007 2A-4
for such inspection.
Excavation for structures shall be done to the lines and grades indicated on the Drawings and to the
limits required to perform the construction work. Machine excavation shall be controlled to prevent
undercutting the proper subgrade elevation. In order to ensure a controlled operation, only small
excavating equipment and hand tools approved by the Engineer shall be used for excavation within
two feet (2’) of existing structures and facilities. Damage to structures incurred during excavation
shall be repaired to the satisfaction of the Engineer at the Contractor’s expense.
All excavated materials must be spoiled off site.
Vertical faces of excavations shall not be undercut to provide for extended footings.
Except as otherwise authorized, indicated or specified, all material excavated below the bottom of
concrete walls, footings, slabs on grade, and foundations shall be replaced and recompacted in
accordance with these specifications at the expense of the Contractor.
2A.15.2. Subgrade Preparation
This article pertains to subgrade preparation for all structures indicated on the Drawings.
2A.15.2.1. Stripping
Shall be as required in Section 2A.5.
2A.15.2.2. Compaction
Prior to placement of fill or concrete, the top twelve inches (12”) of subgrade shall be thoroughly
compacted to a minimum of eighty-five percent (85%) relative density, or 98% of maximum
Standard Proctor Density, as determined by ASTM D4253 and D4254, or ASTM D698, using
vibratory rollers, plate compactors, or other suitable methods approved by the Engineer. Soft or
otherwise unsuitable material shall be removed from the subgrade and replaced with material
specified in Section 2A.15.3.
No fill material or foundations shall be placed until the subgrade has been properly prepared and
accepted by the Engineer.
2A.15.3. Structural Fill
This article pertains to fill required to bring foundation subgrade elevations to the lines and grades
shown on the Drawings.
City of Fort Collins Power & Light – 06.007 2A-5
2A.15.3.1. Structural Fill Materials
Structural fill material, used as fill beneath slabs or foundations, shall consist of pit run type granular
materials consisting of sands, gravels, and small cobbles. Structural fill material is to be approved
by the Engineer.
Material for structure backfill shall be composed of earth only and shall contain no wood, grass,
roots, broken concrete, stones, trash, or debris of any kind.
2A.15.3.3. Placement and Compaction
The designated structural fill material shall be placed in layers not to exceed eight-inches (8") in
uncompacted thickness. Material deposited in windrows or piles by excavating or hauling
equipment shall be spread and leveled before compaction.
Each layer of material being compacted shall be uniformly compacted using equipment and
materials that shall achieve the specified density and moisture content. The Contractor shall add
water and harrow, disc, blade, or otherwise work the material in each layer as required to insure
uniform moisture content and specified compaction. If the moisture and density requirements are
not met, the lift shall be broken up and recompacted until the specified requirements are met.
Structural fill shall be compacted to 98% of the maximum dry density as determined by a Standard
Proctor test (ASTM D698), at ±2% of the optimum moisture content, unless noted otherwise. If the
material has less than twelve percent (12%) fines, the fill shall be compacted to seventy-five percent
(75%) relative density in accordance with ASTM D4253 and D4254 using vibratory rollers, plate
compactors, or other methods approved by the Engineer.
2A.15.4. Backfill
This article pertains to backfill for all structures shown on the Drawings.
2A.15.4.1. Backfill Materials
The materials from the required excavations at Harmony and Overland trail Substations are suitable
for use as backfill materials. The materials from the required excavation at Linden Substation are
not suitable for use as backfill and must be spoiled offsite.
All material placed as backfill shall be free from rocks or stones in excess of 2-inches in size, and
from brush, stumps, logs, roots, organics and other objectionable materials.
All backfill materials shall be sands and gravels or mixtures, thereof. Materials classified in USCS
Groups ML, MH, CH, OL, and OH are not suitable backfill materials and shall not be used. Backfill
materials shall be approved by the Engineer prior to placement.
City of Fort Collins Power & Light – 06.007 2A-6
2A.15.4.2. Placement and Compaction
The designated backfill material shall be placed in layers not to exceed six inches (6") in
uncompacted thickness. Do not backfill against structure until concrete has obtained 28 day
compressive strength. Place backfill simultaneously on both sides of structure, where required, to
prevent differential pressures. Material deposited in windrows or piles by excavating or hauling
equipment shall be spread and leveled before compaction.
Each layer of material being compacted shall be uniformly compacted using equipment and
materials that shall achieve the specified density and moisture content. The Contractor shall add
water and harrow, disc, blade, or otherwise work the material in each layer as required to insure
uniform moisture content and specified compaction. If the moisture and density requirements are
not met, the lift shall be broken up and recompacted until the specified requirements are met.
Cohesive materials with greater than 12 percent (12%) fines (passing the Number 200 sieve) shall be
compacted to a minimum density of 95% of maximum density at ±2% of optimum moisture content
as determined by a Standard Proctor Test, ASTM D698.
Sands and gravels with less than twelve percent (12%) fines shall be thoroughly compacted to a
minimum density of seventy percent (70%) relative density as determined by ASTM D4253 and
D4254 using vibratory rollers, plate compactors, or other methods approved by the Engineer.
Self-propelled rollers and compactors may be utilized for compaction of backfill adjacent but not
immediately adjacent to the structures. Within five feet of the structures, backfill shall be compacted
using vibratory plate compactors or other small equipment approved by the Engineer. Any
structures damaged during backfill compaction shall be replaced or repaired in accordance with
Engineer requirements at the Contractor’s expense.
2A.16. EQUIPMENT
The Contractor shall be responsible to provide the size and type of equipment best suited to perform
the various tasks required for the project. Insufficient size and weight of compacting equipment will
not be an excuse for not obtaining compaction.
For compaction of granular materials, vibratory steel drum or plate type vibratory compactors will
be allowed. No segmented pad, sheep’s foot rollers, or other rollers that would create high contact
stresses on the granular particles will be allowed. The use of rubber-tired vehicles to provide
compaction will not be allowed except at the direction of the Engineer.
Discs used on the project shall be of sufficient size and weight to fully penetrate the lift.
2A.19. GENERAL FILLS
Earth fill for general purposes shall follow the requirements for placement and compaction as set
City of Fort Collins Power & Light – 06.007 2A-7
forth throughout this section. Compaction of general fills shall be to a minimum of 95% of
maximum density by ASTM D698 at a moisture content ±3% of optimum moisture. For granular
materials with less than 12% fines, compaction shall be to 70% relative density as defined in ASTM
D4253 and D4254.
2A.20. MAINTENANCE AND RESTORATION OF FILLS, BACKFILLS, ROADWAYS
Fills and backfills that settle or erode before final acceptance of the work under these specifications,
and pavement, structures, and other facilities damaged by such settlement or erosion, shall be
repaired at the Contractor's expense. The settled or eroded areas shall be refilled, compacted, and
graded to conform to the elevations indicated on the Drawings or to the elevation of the adjacent
ground surface. Damaged facilities shall be repaired in a manner acceptable to the Engineer.
Existing roadways used during construction shall be regraded and gravel shall be applied as
necessary to return the roadways to their original condition prior to construction. Roadways
constructed under these specifications and used in the process of the construction, shall be regraded
and re-graveled as necessary to return them to their original condition.
2A.21. TOPSOIL – none required.
2A.22. FINAL GRADING
After all construction work under these specifications has been completed, the aggregate surface is
to be replaced to its original condition and all ground surface areas disturbed by the construction
operations shall be graded. The grading shall be finished to the contours and elevations indicated on
the drawings or, if not indicated, to the matching contours and elevations of the original, undisturbed
ground surface. In any event, the final grading shall provide smooth uniform surfacing and effective
drainage of the ground areas.
2A.23. DISPOSITION OF MATERIALS – This Section Not Used
2A.24. CONTROL TESTING
All field and laboratory testing required to determine compliance with the requirements of this
section will be provided by the Owner. The Contractor shall provide the services of one or more
employees as necessary to assist the Owner’s field testing representative. The Contractor will be
furnished one copy of the test results.
Maximum density for cohesive compacted materials placed under this section shall be determined in
accordance with ASTM D698, Method A or C, unless otherwise specified. The terms "maximum
density" and "optimum moisture content" shall be as defined in ASTM D698 unless otherwise
specified.
The relative density for compacted granular materials containing less than 12 percent fines (-No. 200
City of Fort Collins Power & Light – 06.007 2A-8
sieve) placed under this section shall be determined in accordance with ASTM D4253 and D4254.
Density testing will be according to ASTM D2922 and D3017.
At least one field moisture and density test will be performed for every 500 cubic yards of the
compacted fill materials. Each lift placed will be tested independent of the number of cubic yards
placed. If determined to be necessary by the Engineer to ensure the quality of the fill and backfill,
additional field control tests will be conducted at a frequency determined by the Engineer to fit the
conditions.
Testing being conducted by the Owner will not relieve the Contractor of his responsibility to ensure
all materials being placed are at the proper moisture content before compaction begins. The testing
by the Owner is to determine that the requirements of the Specifications are being met and are not
intended to provide the Quality Control for the Contractor's operation.
2A.25. CLEANUP
Upon completion of the work associated with this Contract, the Contractor shall perform a cleanup
of the temporary facilities. The cleanup should return the disturbed areas as much as practicable to
the original ground surface contours.
**** END OF SECTION ***
City of Fort Collins Power & Light – 06.007 2B-1
Section 2B – STEEL STRUCTURES
2B.1.1 General
The structures shall be complete with all field connection bolts required for erecting the
structures and required for mounting the equipment furnished under other sections of these
specifications. In addition; mounting bolts, lock washers, etc., shall be furnished for mounting
other equipment furnished by Owner as indicated on the drawings.
No field welding of structural steel shall be required.
Certain dimensions indicated on the Owner’s drawings shall be adjusted as required to suit the
equipment furnished by the Contractor under other sections of these specifications. The
dimensions required for the equipment furnished shall be shown on the Contractor’s detail shop
drawings and the materials and fabrication required shall be provided as part of the contract
work. There will be no adjustment in price because of these requirements.
All shielding masts shall be tapered tubular steel.
2B.1.2. Manufacturers
The following is a list of approved manufacturers:
1. Dis-Tran Steel Pole, LLC., Pineville, LA; Phone#: (318) 767-5587.
2. JEM Manufacturing, Tulsa, OK; Phone#: (918) 446-4517.
3. Valmont, Valley, Nebraska; Phone#: (402) 359-2201.
2B.1.2 Materials
All materials shall be new and undamaged and shall conform to pertinent AISC and ASTM
standard specifications and the following requirements:
Steel shapes and plates ASTM A36 steel. Minimum yield point of
for structures 36,000 psi including appurtenant materials.
Structural Tubing ASTM A500 Grade A or B, ASTM A501,
ASTM A513, ASTM A573, ASTM A588,
0.250 inch minimum wall thickness. Square
tube rolled from round pipe will not be
acceptable.
Tubular structures ASTM A572 weldable quality or ASTM A36;
and attachments 3/16 inch minimum thickness
Baseplates for tapered ASTM A588, cast or fabricated steel; 1 ½
tubular structures inch minimum thickness
City of Fort Collins Power & Light – 06.007 2B-2
Welding electrodes:
For steel shapes, plates, AWS specifications. Low hydrogen types.
and structural tubing Tensile strength to be compatible with parent
material.
Connecting bolts and
bolts for equipment mounting:
For steel shapes, plates, ASTM A394; hexagon bolts and nuts, flat or
and structural tubing beveled washers, and MacLean-Fogg “M-F
Lock Nut #1” locking devices.
For tapered tubular ASTM A325 Type 1, ASTM A354 Grade BC,
structures ASTM A354 Grade BD, or ASTM A687;
heavy hexagon bolts and nuts, flat or beveled
washers, and MacLean-Fogg "M-F Lock Nut
No. 1" locking devices.
Galvanizing:
Shapes, plates, and ASTM A123
structural tubing
Bolts, nuts, and washers Galvanized as specified in ASTM A394 and
for shapes, plates, and ASTM A153
structural tubing
Tapered tubular structures ASTM A123
Bolts and studs for tapered Galvanized as specified in ASTM A325 and
tubular structure ASTM A1533
Anchor bolts for tapered ASTM A153
tubular structures
2B.1.3 Design
Provide interphase spacing and clearances conforming to the recommended spacing and
clearances listed in IEEE and N.E.M.A. standards, unless larger dimensions are shown on the
drawings. Conform as nearly as possible to the data and dimensions shown on the drawings,
with variations permissible to make the structures fit the manufacturer’s standard material or
equipment or to give an improved installation provided the following requirements are
maintained:
(1) Overall space limitations are as shown on the drawings.
(2) Maintain ample aisle space for operation and maintenance of the equipment.
(3) Clearance from fences, structures, and other equipment for both the present and future
City of Fort Collins Power & Light – 06.007 2B-3
development as indicated on the drawings is maintained.
(4) All baseplates shall be designed for installation with leveling nuts and grout.
All bus and equipment stands shall be designed according to NEMA SG-6 and the AISC Manual
for Steel Construction.
All shielding masts shall be designed according to the NESC and Design of Steel Transmission
Pole Structures, ASCE guide and recommendations report of the task committee on Steel
Transmission Poles of the Committee in Analysis and Design of Structures of the Structural
Division, 1978.
2B.1.3.1 Tapered Tubular Design
For a tapered tubular structure the following requirements shall also be met:
Width to thickness ratios or diameter to thickness ratios for the tubular steel members shall be in
accordance with the requirements of the ASCE guide for the "Design of Steel Transmission Pole
Structures" 1978. Unless local buckling resistance is demonstrated by test for polygonal
members, polygonal members shall be proportioned without stress reduction so that:
w/t less than or equal to 240
(Fy)1/2
where: w = The flat width of a side in inches. In determining w, the actual inside bend
radius shall be used unless it exceeds 4t. Bend radii greater than 4t shall be taken as 4t in
determining w.
t = The thickness of the plate in inches.
Fy = The yield stress in ksi
The value of w÷t may exceed 240/(Fy)1/2 the allowable stresses are reduced in accordance with
the applicable formulae in the ASCE guide referenced herein before.
Unless local buckling resistance is demonstrated by test for circular or smooth elliptical cross
sections, the members shall be proportioned using the applicable formulae for bending, axial
load or a combination of the two in the ASCE guide referenced herein before.
Nondestructive testing shall be provided in accordance with the requirements of Article 6.7 of
the referenced AWS code. Magnetic particle inspection or ultrasonic inspection shall be
provided on tubular steel structures at all circumferential welds and all other critical welds.
Inspection and evaluation of the test data shall be performed by persons fully qualified by
training and experience to inspect, evaluate, and accept or reject these welds. Any defective
weld shall be removed, rewelded, and reinspected at the Contractor's expense. All
nondestructive weld inspection and testing shall be performed by the Contractor's quality control
City of Fort Collins Power & Light – 06.007 2B-4
inspectors.
Material for tapered tubular sections, excluding ASTM A36, baseplates, anchor bolts, and
welding materials, shall resist a minimum of 15 foot-pounds of energy on a Type A specimen at
a temperature of -20°F in accordance with the standard Charpy "V" notch impact test. The
Charpy test shall be in accordance with ASTM A370. The Charpy test shall be made on a heat
lot basis.
In addition to the foregoing requirements, the material for the tapered tubular sections shall be
capable of welding without reduction in yield strength or corrosion resistance.
This material shall have a uniform color and appearance after galvanizing.
2B.1.3.2 Structural Tubing Design
This section covers design, materials, and fabrication for substation structural tubing members.
Certain dimensions indicated on the Engineer’s drawings shall be adjusted as required to suit the
equipment furnished by the Contractor under other sections of these specifications. The
dimensions required for the equipment furnished shall be indicated on the Contractor’s detail
shop drawings and materials and fabrication required shall be provided as part of the contract
work. There will be no adjustment in price because of these requirements.
Drawings and Calculations. Drawings for shop fabrication and field erection of all materials
shall be prepared, checked, and submitted to the Contractor as specified. Field erection data
shall include written instructions for proper structure assembly, erection, and inspection,
including explicit step by step instructions for the proper installation, tightening and inspection
of the connection bolts being furnished. Drawings shall indicate details and dimensions as
required to enable the Contractor to coordinate hardware attachment and electrical clearances.
Supplier shall be responsible for all, equipment and equipment operator assembly interfacing
with structures.
Design data shall be submitted with the proposal including calculations indicating the adequacy
of each structure, steel beams, attachments, and appurtenances regarding strength and deflection.
The calculations shall include baseplate sizes, anchor bolt patterns, anchor bolt lengths, anchor
bolt stress; groundline shears, moments, and axial loads; and all other structure design data
required for the Contractor’s foundation design. The accuracy and correctness of the design of
the structures and their components, based on the loads indicated on the Contractor’s drawings,
are the sole responsibility of the Supplier. The proposal shall also include the approximate total
weight of each structure.
Design. The yield strength of the material used in the design of the structural shapes shall, not
exceed the yield stress tabulated in the ASTM specification or modified subject to the
Contractor’s acceptance.
City of Fort Collins Power & Light – 06.007 2B-5
Calculated stresses shall not exceed the yield stress of material for the maximum combination
loadings indicated on the drawings. The loads indicated on the drawings include overload
capacity factors.
Substation structures shall be designed to meet the deflection requirements of NEMA SG6, part
36. Switch and interrupting device structures shall be designed to meet the following deflection
requirements. The horizontal deflection of vertical members shall be limited to 1/100 of the
span. The vertical deflection of horizontal members shall be limited to 1/200 of the span. The
horizontal deflection of horizontal members shall be limited to 1/200 of the span.
All other structures unless noted otherwise shall be designed to meet the following requirements.
The horizontal deflection of vertical members shall be limited to 1/50 of the span. The vertical
deflection of horizontal members shall be limited to 1/200 of the span. The horizontal deflection
of horizontal members shall be limited to 1/100 of the span.
Deflection criteria indicated shall apply for all load cases using an overload factor of 1.0.
The span shall be defined as the distance between supporting members or the length of the
cantilever.
Anchor bolts shall be designed for a stress not to exceed the yield stress of the anchor bolt
material on the net cross section using the maximum combination loadings indicated on the
drawings. Anchor bolts length shall not be less than the required projection above the
foundation including leveling nuts plus an embedment of the development length required in
accordance with ACI 318-02 based on f’c 4,000 psi. Anchor bolts shall include leveling nuts.
Wide flange structures shall be shipped assembled where shipping conditions permit. Each
bidder shall furnish, in the BID DATA section, a list of the structure items that will require field
assembly and shall describe the shipping sections. When proposals are submitted without
statements describing sectional shipments, it will be understood that no field assembly of the
structures will be required.
Anchor Bolts. Anchor bolts, nuts, and washers furnished under this section shall be as scheduled
and detailed on the drawings. Anchor bolts, nuts, and washers shall be hot-dip galvanized after
fabrication, threads being undercut to provide a tolerance equal to ANSI Class 2A. Each bolt
shall be furnished with two nuts and washers and sufficient threads to permit a nut to be installed
on each side of the concrete form or template.
2B.1.4 Loading Criteria
All equipment structures, as indicated on the drawings shall be designed in accordance with the
following loading criteria. All calculations shall be mutually exclusive with the final design
being the worst case condition of the cases.
All equipment stands:
(a) 120 MPH wind on bare equipment and connected bus.
City of Fort Collins Power & Light – 06.007 2B-6
(b) 40 MPH wind on ½ inch of ice on equipment and connected bus.
All shielding masts:
(a) N.E.S.C. Heavy Loading Case:
Design all structures for 1/2" radial ice on conductors and a simultaneous 4 lbs.
per square foot of horizontal wind pressure on iced conductor and bare structures.
The overload factors shall be as per 1990 N.E.S.C. Section 261A1.
(b) High Wind Case:
Design all structures for 120 mph wind, 37 lbs. per square foot of horizontal wind
pressure, on bare conductor and structures, using an effective net area based on
one of the following multiples of the area of one face:
Round Tubular Shapes - 1.00
Octagonal Tubular Shapes - 1.20
Rectangular Tubular Shapes - 1.70
Rolled Sections, Members of
Lattice, or Truss Structures - 2.00
The overload Factor shall be 1.0 as per 1990 N.E.S.C. Section 260C.
(c) Extreme Ice Load:
Design all structures for 1" radial ice on conductors and a simultaneous 0 lbs. per
square foot of horizontal wind pressure on iced conductor and bare structures with
an overload factor of 1.00 for resultant loading.
2B.1.5 Field Connection and Equipment Mounting Bolts
Field connection and equipment mounting bolts, nuts, washers, and lock washers shall be
furnished for all structure field connections and equipment mounting with an overage of 5
percent, plus five bolts, of each type, size, and length. The length of connection bolts shall
provide sufficient projection for washer, nut, and locknut. With locknuts in place, bolt
projection beyond the locknut shall be from ¼ inch to ½ inch inclusive.
Smooth beveled washers shall be furnished for use when the bearing faces of the bolted parts
will have a slope of 1:20 or greater with respect to a plane normal to the bolt axis.
All field connection bolts for the substation bus and equipment structures shall be of the same
length.
2B.1.6 Fabrication
The structures shall be fabricated in conformity with the dimensions, arrangements, sizes and
City of Fort Collins Power & Light – 06.007 2B-7
weights or thicknesses indicated on the drawings or stipulated in the specifications. All
members shall be detailed and fabricated in accordance with AISC standards, specifications, and
details unless otherwise indicated on the drawings or specified herein.
When delivered, members shall be straight, free from warp, unauthorized splices and bends, or
local deformations. Holes and other provisions for field connections shall be accurate and shop
checked so that when the structure is field assembled proper fit will be provided. All punching,
drilling, and reaming of the holes shall be done in the shop before galvanizing.
All fabricated materials shall conform to the tolerances specified in the AISC Manual and ASTM
A6. In addition, the allowable tolerance for sweep shall be no more than 1/8 inch in 10 feet of
length regardless of the type of steel section. If necessary, the Contractor shall cull out or
straighten materials which do not comply with the specified tolerances. Materials which do not
comply with the specified sweep and camber requirements may be rejected.
Baseplates shall also be checked after fabrication and will be rejected if anchor bolt holes are not
within 1/32 inch of their theoretical location with respect to the center of the anchor bolt group
or cluster. Holes in one inch plate or greater will be within 1/16 inch of their theoretical
location.
Contact surfaces at all column splices and at all other compression joints depending upon contact
bearing shall have the bearing surfaces prepared to a common plane by milling, sawing, or other
acceptable means. Only milling will be acceptable where milling is specifically indicated on the
drawings.
Before being laid out or worked in any manner, structural material shall be straight and shall be
cleaned of all rust and dirt. If straightening is necessary, it shall be done by methods that will
not injure or fatigue the metal.
Shearing and cutting shall be performed carefully and all portions of the work which will be
exposed to view after completion shall be finished neatly. Blades shall be sharp and clearances
adjusted to give smooth cuts. Manually guided cutting torches shall not be used.
All holes in structural steel less than 13/16 of an inch thick may be punched to full size unless
otherwise noted on the drawings. Holes shown on the drawings as drilled holes and all holes in
structural 13/16 of an inch or more in thickness shall be drilled or subpunched and reamed. All
holes shall be clean cut and without torn or ragged edges. All burrs resulting from reaming or
drilling shall be removed with a tool making 1/16-inch bevel. All holes shall be cylindrical and
perpendicular to the member. Where necessary to avoid distortion of the holes, holes close to
the points of bends shall be made after bending.
For punching to full size, the diameter of the punch shall be 1/16 of an inch smaller than the
nominal diameter of the die, but shall be not more than 1/16 of an inch larger than the diameter
of the bolt. For subpunching, the diameter of the punch shall be 3/16 of an inch smaller than the
nominal diameter of the bolt and shall not be more than 3/32 of an inch larger than the diameter
of the punch.
City of Fort Collins Power & Light – 06.007 2B-8
Where holes are reamed or drilled, the diameter of the finished hole after galvanizing shall be
not greater than the nominal diameter of the bolt after galvanizing plus 1/16 of an inch, unless
construction tolerances require greater clearance.
All holes shall be spaced accurately in accordance with the drawings and shall be located on the
gagelines. The maximum allowable variation in hole spacing from that indicated on the
drawings for all bolt holes shall be 1/32 of an inch.
Except as otherwise indicated on the drawings or specified herein, shop connections shall be all
welded and field connections shall be all bolted. Bolted connections shall be bearing type with
all threads excluded from the shear planes of the connected parts.
2B.1.7 Welding
Except as otherwise specified, all welds, welding, and related operations for steel structures shall
be in conformity with the applicable provisions of the AWS Structural Welding Code, AWS
D1.1, as issued by the American Welding Society.
Welding shall be performed using only those joint details which have a prequalified status when
performed in accordance with the referenced AWS code. Accurate records of operator and
procedure qualifications shall be maintained by the Contractor and shall be available to the
Owner. All welds shall be continuous and shall develop the full strength of the least strength
component unless otherwise indicated on the drawings. Components shall be thoroughly
cleaned before welding and shall be accurately fitted and rigidly secured in position during
welding to provide a sound, full strength weld without distortion. Weld surfaces shall be smooth
and uniform and shall be thoroughly cleaned of all slag and flux before galvanizing. Low
hydrogen electrodes shall be used.
All testing and welding qualifications required by these specifications shall be performed by an
independent testing laboratory retained by the Contractor and accepted by the Owner. All
testing and welding qualification expenses shall be paid by the Contractor.
2B.1.8 Identification
All separate structural members and parts shall be plainly marked, as an aid in assembly, with
the identifying mark on the member corresponding to the identical mark on the erection
drawings. Marks shall be metal stamped into each member in painted on the members with
nonpermanent paint in characters not less than one inch high.
2B.1.9 Galvanizing
Where indicated steel materials furnished under this section shall be hot-dip galvanized after
fabrication.
After the shop work has been completed and accepted, all material shall be cleaned of rust, loose
scale, dirt, oil, grease, and other foreign substances. Particular care shall be taken to clean slag
City of Fort Collins Power & Light – 06.007 2B-9
from welded areas.
All plates and shapes shall be galvanized after fabrication, except that members of assemblies
built up by welding may be galvanized before they are welded. All welds shall be coated and all
galvanizing damaged by the welding operations shall be repaired as provided herein. Where
members are of such lengths that they cannot be dipped in one operation, great care shall be
exercised to prevent warping. Finished compression members shall not have lateral variations
greater than 1/1000 of the axial length between the points which are to be supported laterally.
All holes in material shall be free of excess spelter after galvanizing.
All plates and shapes which have been warped by the galvanizing process shall be straightened
by being rerolled or pressed. The material shall not be hammered or otherwise straightened in a
manner that will injure the protective coating. If, in the opinion of the Owner, the material has
been harmfully bent or warped in the process of fabrication or galvanizing, such defects shall be
cause for rejection.
The galvanizing coating shall cover all interior surfaces of hollow members as well as exterior
surfaces. Channels, angles, and all other unsymmetrical sections shall be straightened after
galvanizing as required to meet the specified tolerance requirements.
A durable, high quality, relatively smooth coating is required. The Contractor’s attention is
directed to the requirements of ASTM A384, ASTM A385, and ASTM A386 in this regard. The
Owner may at his option inspect the galvanizing in process. Grounds for rejection of members
because of galvanizing defects shall be as listed in Table II of the “Inspection Manual for Hot-
dip Galvanized Products” published by the American Zinc Institute except that excessive general
roughness, pimples, lumpiness, excessive discoloration, and runs shall be cause for rejection.
The Owner will determine whether defects are excessive or not.
Precautions shall be taken against embrittlement in accordance with the latest revision of ASTM
specification A143, “Recommended Practice for Safeguarding Against Embrittlement of Hot-
Galvanized Structural Steel Products and Procedure for Detecting Embrittlement.”
2B.1.10 [This Section Not Used.]
2B.1.11 Bolting
Bolted connections shall be securely wrench tightened. Wrench tightened is defined as 50 to 75
foot-pounds of torque on 5/8 inch bolts and 75 to 100 foot-pounds of torque on 3/4 inch bolts.
Wherever clearances allow, bolts shall be inserted from the outside to place the nuts on the least
visible side of each connection. Locknuts shall be finger tightened to contact the nut, then
wrench tightened an additional one-half to one full turn. Nuts and bolts shall be handled and
installed in a manner that will not damage the finish. The Contractor shall furnish bolt torques in
the event high strength bolts are used.
2B.1.12 [This Section Not Used.]
City of Fort Collins Power & Light – 06.007 2B-10
2B.1.13 Structure Grounding
Furnish ground tab with 9/16” hole, mounted one (1) foot above base. Ground clamp mounting
holes shall be provided near the bottom of each structure leg and at approximately three (3) to
five (5) foot intervals on the structure legs selected to support ground conductors leading to
equipment ground connections.
Provide means for grounding equipment, CCVTs, switches, bus supports, switch operator
handles and operator platforms.
2B.1.14 [This Section Not Used.]
City of Fort Collins Power & Light-06.007 2C-1
Section 2C – CONCRETE
2C.1 DESCRIPTION
This Section covers all concrete, cast-in-place and drilled pier, and includes reinforcing steel
forms, finishing, curing and other appurtenant work.
2C.2 WORK TO BE PERFORMED
The following list is intended to give a general definition of the concrete work to be done and
shall not be construed as a complete listing.
One spread footing and two drilled piers to support lightning masts.
2C.3 CODES AND STANDARDS
Equipment furnished and work performed under these specifications shall be in accordance with
the latest requirements of applicable ASTM, ACI, CASI, PCA, and ANSI standards.
2C.4 DRAWING AND INFORMATION REQUIRED
The Contractor shall submit the drawings and information required in accordance with the
requirements of ARTICLE 1A.4.
2C.4.1 Concrete Materials and Proportions
The source and quality of concrete materials and the concrete proportions for the Work shall be
submitted to the Owner for review before the concrete work is started. This review will be for
general acceptability only and continued compliance with all contract provisions will be
required.
2C.4.2 Shop Drawings and Bar Lists
Bar lists and drawings for the fabrication and placing of reinforcement shall be prepared,
checked and submitted. Each bar list and placement drawing shall have noted thereon "ASTM
A615 Grade 60 only" or a similar statement which identifies the grade of reinforcing indicated
on that drawing.
2C.5 CONCRETE MATERIALS AND PLACEMENT
2C.5.1 General
This Section covers the requirements for all concrete (drilled piers and cast-in-place), reinforcing
steel, forms, finishing, curing, and other appurtenant work.
City of Fort Collins Power & Light-06.007 2C-2
The disposal of all unused excavated material shall be as required in Section 2A.
2C.5.2 Materials
Where the use of the following materials is specified herein, such materials shall be in
accordance with these requirements.
Concrete
Cement ASTM C150, Type II, or I/II
Fine aggregate Clean natural sand, ASTM C33
Coarse aggregate Crushed stone, washed gravel, or other acceptable
inert granular material conforming to ASTM C33
Water Clean and free from deleterious substances
Water stop 12 gauge ungalvanized steel not less than 8 inches wide or
PUC ribbed or serrated 9 inches wide, with "0" bulb center
Admixtures
Plasticizer Grace "WRDA," Master Builders "Possolith Normal,"
Protex "PDA 25 XL Normal Set," Sika Chemical
"Plastocrete 161," or acceptable equal
Air entraining agent ASTM C260; Grace "Darex AEA," Master Builders "MB-
VR," Protex "Air Entraining Solution," Sika Chemical
"AER," or acceptable equal
Plasticizing retarder Grace “Daratard,” Master Builders
“Pozzolith Retarder,” Protex “PDA
25R Retarder,” Sika Chemical
“Plastocrete 161R,” or acceptable
Reinforcing steel
Bars not otherwise noted ASTM A615 Grade 60 including Supplement
S-1. Yield strength shall be determined by full size
bar.
Ties and stirrups ASTM A615, Grade 60
Anchor bolts 3/4 inch ASTM [A36] threaded bars, with
and larger nuts conforming to ASTM [A563 Grade A] heavy
hexagon; all galvanized after fabrication.
City of Fort Collins Power & Light-06.007 2C-3
Anchor bolts smaller
than 3/4 inch ASTM [A307 Grade A] with hexagon heads and
ASTM [A563 Grade A] hexagon nuts; all
galvanized after fabrication.
Forms
Prefabricated Simplex "Industrial Steel Frame Forms," Symons
"Steel Ply," or Universal "Uniform"
Plywood Product Standard PSI, waterproof, resin-bonded,
exterior type Douglas fir; face adjacent to concrete
Grade B or better
Lumber Straight, uniform width and thickness, and free
from knots, offsets, holes, dents, and other surface
defects
Chamfer strips Clear pine, surface against concrete planed
Form coating Nox-Crete "Nox-Crete Form Coating," L & M
"Debond," Protex "Pro-Cote," or Richmond "Rich
Cote"
Polyethylene film Fed Spec L-P-378, Type I; 6 mil
Insulation Styrofoam SM, Fed Spec HH-I-524B, Type II,
Class B, extruded polystyrene
Expansion joint materials
Filler Performed, ASTM D1752, Type I (sponge rubber)
or closed cell plastic foam (PVC or polyethylene)
Sealer Polysulfide rubber, two component, ANSI A116.1
and Fed Spec TT-S-227 gray color
Primer As recommended by sealant manufacturer
Epoxy bonding compound Sika Chemical "Sikadur Hi-Mod" or acceptable
equal
Membrane curing compound Fed Spec TT-C-800A, Type II, Class 1; chlorinated
rubber, min 18 percent solids; Grace "Dekote,"
ProSoCo "Kure & Seal," Protex "Triple Seal Series
CCL-18," or T. K. Products "Tri-Kote TK-18"
City of Fort Collins Power & Light-06.007 2C-4
2C.5.3 Limiting Requirements for Concrete Mix
Each concrete mix shall be designed and concrete shall be controlled within the following
limiting requirements.
2C.5.3.1 Strength
The concrete mix classes to be supplied for the project are listed in Table 2C.5.3-1. The location
of use for the various classes is as indicated on the Drawings and as indicated as follows.
Class 1 Concrete - structural concrete for reinforced concrete structures.
Class 2 Concrete - structural concrete for drilled piers.
The minimum acceptable compressive strengths as determined by ASTM C39 shall be as shown
in Table 2C.5.3-1.
TABLE 2C.5.3-1
CONCRETE MIX REQUIREMENTS
Class
Minimum
28-Day
Strength
(PSI)
Minimum
Cement
Content
(LBS)
Entrained
Air Content
(Percent)
Maximum
Slump
(In)
Maximum
W/C
Ratio
1
4000
564
6% ± 1-1/2%
4.0
0.48
2
4000
564
6% ± 1-1/2%
6” to 8”
0.48
All concrete shall exceed the minimum strength and meet all requirements of ACI-318. The
Engineer shall be the sole judge of the quality of the concrete and tests.
2C.5.3.2 Minimum Cement Factors
The quantity of portland cement, expressed in pounds per cubic yard, shall be not less than that
indicated in Table 2C.5.3-1.
Flyash may be substituted for cement but shall not exceed twenty percent (20%) of the total
pozzolanic material.
2C.5.3.3 Water-Cement Ratio
The water to cement ratio shall not exceed the values shown in Table 2C.5.3-1.
City of Fort Collins Power & Light-06.007 2C-5
2C.5.3.4 Slump
Concrete slump shall be kept as low as possible consistent with proper handling and thorough
compaction. Unless otherwise authorized by the Owner, slump shall not exceed that indicated in
Table 2C.5.3-1.
2C.5.3.5 Ratio of Fine to Total Aggregates
The ratio of fine to total aggregates based on solid volumes (not weights) shall be:
Concrete Coarse Aggregate Size Maximum Ratio Minimum Ratio
Class
1 & 2 3/4 inch to No. 4 0.50 0.40
2C.5.3.6 Initial Set
The initial set as determined by ASTM C403 shall not be attained until at least 5 hours after the
water and cement are added to the aggregates. The quantity of retarding admixture shall be
adjusted as necessary to compensate for variations in temperature and job conditions.
2C.5.3.7 Total Air Content
The total volumetric air content of concrete after placement shall be 6% ± 1-1/2% or as shown in
Table 2C.5.3-1.
2C.5.3.8 Admixtures
The admixture content, batching method, and time of introduction to the mix shall be in
accordance with the manufacturer's recommendations for the compliance with these
specifications.
2C.5.4 Batching and Mixing
Batching and mixing shall be performed by an acceptable ready-mix concrete supplier.
Personnel at the batching and mixing plant shall be qualified and experienced.
2C.5.4.1 Ready-Mixed Concrete
Ready-mixed concrete shall conform to ASTM C94, except as otherwise specified herein.
Truck mixers shall be revolving drum type and shall be equipped with a mixing water tank.
Only the prescribed amount of mixing water shall be placed in the tank for any one batch, unless
the tank is equipped with a device by which the amount of water added to each batch can be
readily verified.
City of Fort Collins Power & Light-06.007 2C-6
A delivery ticket shall be prepared for each load of ready-mixed concrete delivered. A copy of
each ticket shall be handed to the Owner by the truck operator at the time of delivery. Tickets
shall show the time the mix was batched, the mix identification, the number of yards delivered,
the quantities of each material in the batch, the outdoor temperature in the shade, the time at
which the cement was added, the amount of water that may be added at the placement site, and
the numerical sequence of the delivery.
When a truck mixer or agitator is used for transporting concrete, the concrete shall be delivered
to the site of the work and discharge shall be completed within 1-1/2 hours, after the introduction
of the mixing water to the cement and aggregates, or the introduction of the cement to the
aggregates, when the air temperature is 90° F or less. Exceeding this time limit shall be cause
for rejection. When the air temperature exceeds 90° F, concrete shall be placed in accordance
with the requirements of Section 2C.5.5.4, within a time depending on air temperature and
humidity as set forth by the guidelines of ACI 305 to prevent the temperature of the concrete
from reaching 90° F. On very hot days, the time for placement may be reduced to 30 minutes.
The Contractor shall schedule concrete pours for early morning or evening hours when hot days
are anticipated. Concrete temperatures exceeding 90° F may be cause for rejection.
2C.5.5 Placement
The handling, depositing, and compacting of concrete shall conform to these specifications
subject to adjustment by the Owner for weather or placement conditions.
Concrete shall not be pumped through aluminum pipe or aluminum alloy pipe.
Prepare slab subgrades in accordance with ACI 301. Moisten subgrade before placement. Do
not cause water to pond, become muddy, or cause soft spots to appear.
Cover with polyethylene film all gravel or crushed stone subgrades that do not contain at least
twenty-five percent (25%) material passing a No. 4 sieve to protect concrete from loss of water.
2C.5.5.1 Bonding to Hardened Concrete
The surface of hardened concrete upon which fresh concrete is to be placed shall be rough, clean
and damp. Surface mortar shall be removed to expose the aggregate to a full amplitude of 1/4 in.
The hardened surface shall be cleaned of all foreign substances (including curing compound),
washed with clean water, and kept saturated during the 24 hour period preceding placement of
fresh concrete or handled per the instructions as indicated by the bonding agent manufacturer.
2C.5.5.2 Conveyance and Distribution
Concrete shall be conveyed to the point of final deposit by methods which will prevent the
separation or loss of the ingredients. Concrete shall be deposited in its final position without
moving it laterally in the forms for a distance in excess of 5 feet.
City of Fort Collins Power & Light-06.007 2C-7
2C.5.5.3 Depositing Concrete
Concrete shall be deposited in approximately horizontal layers of proper depth for effective
compaction; however, the depth of a layer shall not exceed twenty inches (20”). Each layer of
concrete shall be plastic when covered with the following layer, and the forms shall be filled at a
rate of vertical rise of not less then two feet (2’) per hour. Horizontal and vertical construction
joints shall be provided as necessary and as accepted by the Engineer to comply with these
requirements.
Maximum height of concrete fall shall not exceed four feet (4’). Use a tremie for placing
concrete in columns and walls to prevent free fall of more than four feet (4’).
2C.5.5.4 Compaction
During and immediately after depositing, all concrete shall be thoroughly compacted, worked
around reinforcements and embedments, and worked into the corners of the forms.
All concrete shall be compacted by means of mechanical vibrating equipment; except concrete
slabs six inches (6”) or less in thickness may be either vibrated or tamped. Unless otherwise
accepted by the Engineer, mechanical vibrators shall be spud-type immersion vibrators. The
number and type of vibrators shall be subject to the acceptance of the Engineer. Provide at least
one stand-by vibrator in operable condition at placement site prior to placing concrete.
2C.5.5.5 Hot Weather Concreting
Except as modified herein, hot weather concreting shall comply with ACI 305. At air
temperatures of 90° F or above, special procedures shall be adopted to keep the concrete as cool
as possible during placement and curing. The temperature of the concrete when it is placed in
the work shall not exceed 90° F.
Whenever the air temperature exceeds 95° F, membrane cured slabs shall be kept wet to promote
cooling of the concrete during the curing period.
2C.5.5.6 Cold Weather Concreting
Except as modified herein, cold weather concreting shall comply with ACI 306. The
temperature of concrete at the time of mixing shall not be less than that indicated in the
following table for corresponding outdoor temperature (in shade) existing at the time of
placement.
Outdoor Temperature Concrete Temperature
Below 30° F 70° F
Between 30° F and 45° F 60° F
Above 45° F 45° F
City of Fort Collins Power & Light-06.007 2C-8
When deposited, the temperature of heated concrete shall not be over more than 10° F higher
than the above minimums.
When freezing temperatures may be expected during the curing periods, suitable means shall be
provided for maintaining the concrete at temperatures of not less than 50° F for 5 days or 70° F
for 3 days after the concrete is placed. Concrete and adjacent form surfaces shall be kept moist
at all times. Sudden cooling of concrete shall not be permitted.
The use of calcium chloride will not be permitted.
2C.5.6 Reinforcement
Reinforcements shall be accurately formed and placed in accordance with ACI 117, “Standard
Tolerances for Concrete Construction and Materials.”. Unless otherwise indicated on the
drawings or specified herein, the details of fabrication shall conform to the latest version of ACI
318 and ACI 117.
2C.5.6.1 Accessories
The Contractor shall provide all bar supports, ties, spacers, bolsters, inserts, screeds, and other
concrete accessories required to maintain reinforcing in its proper position and permit proper
placement of concrete.
2C.5.6.2 Concrete Cover
Except as otherwise indicated on the drawings, metal reinforcement for concrete shall have the
concrete protective cover specified in Chapter 7 of ACI 318.
2C.5.6.3 Welding
Welding of reinforcement for any purpose, and tack welding in particular, is expressly
prohibited. Reinforcements upon which unauthorized welding has been done shall be presumed
to be damaged and such reinforcing shall be removed and replaced at the Contractor's expense.
Replacement materials shall conform to all applicable requirements of these specifications.
Welded chairs and supports may be used provided they are clamped or wired to the
reinforcement.
2C.5.6.4 Placement
Reinforcements shall be accurately positioned on supports, spacers, hangers, or other
reinforcements, and shall be secured in place with wire ties or suitable clips. Bare metal
supports shall not be used in contact with forms for exposed surfaces. Pre-formed standees are
City of Fort Collins Power & Light-06.007 2C-9
required for all slabs to support and properly space the top layer of steel and fabricated side form
spacers are required for all walls.
2C.5.6.5 Splices
Unless otherwise required by the specifications or drawings, splices shall conform to ACI 318
and shall be tension-lapped splices. Splices shall be Class B tension-lapped splices unless a
different class is indicated on the drawings. Both compression and tension-lapped splices shall
be designed for a steel yield stress and a concrete compressive strength as specified in Section
2C.
2C.5.7 Anchor Bolts
Anchor bolts furnished under these specifications shall be as listed and detailed on the drawings.
Sleeves and anchor plates shall also be provided where they are indicated on the drawings.
Unless otherwise indicated on the drawings, fabrication details for all anchor bolts shall comply
with ASTM A307. Anchor bolts, nuts, and washers shall be hot-dip galvanized after fabrication,
threads being undercut to provide a tolerance equal to ANSI Class 2A. Anchor bolts longer than
3 feet shall have the top 18 inches hot-dip galvanized after fabrication, threads being undercut to
provide a tolerance equal to ANSI Class 2A. Each bolt without a sleeve shall be furnished with
two nuts and sufficient threads to permit a nut to be installed on each side of the concrete form or
template.
2C.5.8 Forms
Forms shall be designed to produce hardened concrete having the shape, lines, and dimensions
indicated on the drawings. Forms shall be substantial and sufficiently tight to prevent leakage of
mortar and shall be maintained in proper position and accurate alignment. Forms shall be
thoroughly cleaned and oiled before concrete is placed and shall not be removed until the
concrete has hardened sufficiently to support all loads without damage.
Form dimensions and placement shall be within 1/2 inch of the plan dimensions and locations
indicated on the drawings.
Where concrete is placed against dry or porous surfaces, such surfaces shall be covered with
polyethylene film to protect the concrete from loss of water. Joints in the film shall be sealed
with waterproof sealing tape. Unless otherwise accepted by the Owner, all concrete in contact
with dry earth or granular fill shall be placed against polyethylene film.
Vertical concrete surfaces above extended footings shall be formed.
Form ties shall be of the permanently-embedded body type with removable ends that can be
broken off at least ¾-inch inside the form face, and shall have sufficient strength, siffness, and
rigidity to support and maintain the form in proper position and alignment without the use of
auxiliary spreaders. The type of form ties used shall be acceptable to the Engineer.
City of Fort Collins Power & Light-06.007 2C-10
Chamfer strips shall be placed in forms to bevel all salient edges and corners except where
otherwise noted. Bevel dimensions shall be 3/4 inch by 3/4 inch unless otherwise indicated on
the drawings.
2C.5.9 Embedments
Materials that are to be embedded in the concrete shall be accurately positioned and securely
anchored. Embedments shall be clean when they are installed. After installation, surfaces not in
contact with concrete shall be cleaned of all concrete spatter and other foreign substances.
2C.5.10 Finishing Formed Surfaces
All fins and other surface projections shall be removed from all formed surfaces when the forms
are stripped except exterior surfaces that will be in contact with earth backfill. In addition,
exterior surfaces which will be exposed above grade shall be cleaned and rubbed to produce a
smooth, uniform surface free of marks, voids, surface glaze and discolorations.
The removable ends of all form ties shall be removed and the recesses resulting from such
removal shall be filled with mortar and rubbed smooth.
2C.5.11 Finishing Unformed Surfaces
The unformed surfaces of concrete shall be screeded and given an initial float finish followed by
additional floating and troweling where required.
Unformed surfaces which are specified on the drawings to be steel trowel finished shall be
finished to provide a flat profile within 1/8 inch deviation as measured from a 10 foot long
straight edge. The deviation for other surfaces shall not exceed 1/4 inch in 10 feet.
Surfaces designated on the drawings and the exposed top surfaces of equipment bases shall be
steel trowel finished. Troweling shall be performed after the second floating when the surface
has hardened sufficiently to prevent an excess of cement being drawn to the surface. Troweling
shall produce a dense, smooth, uniform surface free from blemishes and trowel marks.
2C.5.12 Curing
Concrete shall be protected from loss of moisture for at least 7 days by membrane curing
compound. Membrane curing compound shall be applied at twice the rate recommended by the
manufacturer. Concrete shall not be permitted to freeze for at least 7 days following placement.
2C.5.13 Repairing Defective Concrete
Defects in formed concrete surfaces shall be repaired to the satisfaction of the Owner within 24
hours, and defective concrete shall be replaced within 48 hours after the adjacent forms have
City of Fort Collins Power & Light-06.007 2C-11
been removed. All concrete which is porous, honeycombed, or otherwise defective to a depth in
excess of one inch shall be cut out and removed. Cut surfaces shall be coated with epoxy
bonding compound before the repair concrete is placed.
Concrete repair work shall be performed in a manner that will not interfere with thorough curing
of surrounding concrete. Mortar and concrete used in repair work shall be adequately cured.
2C.5.14 Construction Joints
Construction joints shall be provided where indicated and detailed on the drawings.
Construction joints designated on the drawings shall be provided with a metal water stop.
Junctions between adjacent sections of water stop shall be lapped 5 inches and securely welded
or bolted together.
2C.5.15 Expansion Joints
Expansion joints shall be located and constructed as indicated on the drawings. Accessible
edges of each expansion joint shall be sealed. Polysulfide rubber (Thiokol type) sealants shall
not be used in contact with bituminous or asphaltic materials.
Expansion joints designated on the drawings shall be provided with a flexible water stop.
Flexible water stops shall be spliced in strict conformity with the manufacturer's
recommendations. A sample 90 degree corner splice mitered at 45 degrees shall be prepared and
submitted to the Owner for acceptance before any permanent splices are made.
2C.5.16 Tolerances for Substation Bases
The concrete bases and their embedments for substation yard structures and equipment shall
meet the following tolerance requirements in addition to those specified herein before.
Concrete form dimensions and placement shall be within 1/2 inch of the plan dimensions and
locations indicated on the drawings. The top of the forms shall be accurately set to the elevation
required to produce finished surfaces within the specified tolerances.
The elevation of all points on all float finished surfaces shall be within 1/4 inch of the elevation
indicated on the drawings. The elevation of all points on all trowel finished surfaces shall be
within 1/8 inch of the elevation indicated on the drawings.
Anchor bolts and all other materials that are to be embedded in the concrete shall be accurately
positioned and securely anchored. The center of each anchor bolt group or cluster shall be
within 1/8 inch of the location indicated on the drawings. The center-to-center dimensions
between the anchor bolts in a group or cluster shall be within 1/16 inch of the dimensions
indicated on the drawings.
City of Fort Collins Power & Light-06.007 2C-12
2C.6 DRILLED PIERS
2C.6.1 General
This section covers the requirements for drilling of earth and placing of concrete for foundation
piers. Pier installation shall follow the requirements of ACI 336.1, Reference Specifications for
the Construction of Drilled Piers.
2C.6.2 Drilling
Foundation piers shall be drilled with an auger in earth and with an auger with hardened teeth
suitable for drilling rock or a core drill as required depending on hardness. Casings shall be used
where the sides of the excavation are unstable and may be used at all locations. A pier
excavation will be considered dry if the infiltration of ground water from a source at or near the
bottom is at a rate of less than 1/2 inch rise per minute at the bottom of the pier. The total
theoretical height of water in the bottom of the pier may not exceed 6 inches at the time
sufficient concrete has been placed to balance the water head.
Drilling equipment shall be designed to drill straight and clean holes. Casings, if used, shall be
installed as the drilling proceeds or immediately after the auger is withdrawn as required to
prevent sloughing and caving of the excavation walls. The Contractor may elect to advance the
excavation and facilitate the removal of cuttings by utilizing a densified fluid. All loose material
shall be removed from the bottom of the pier excavations.
Casings shall be of steel construction and shall be of ample strength to withstand handling and
installation stresses. Casings may be removed as the concrete is placed or left in place at the
Contractor's option. During removal the casing shall be continually plumb and the concrete
surface within the casing shall be continually observed for maintenance of concrete "head"
sufficient to offset the casing's external water head. A minimum head of 4 to 5 feet of concrete
shall be maintained above the bottom of the casing during casing extraction. Casings left in
place shall not be exposed above grade.
Each pier shall be accurately located, sized, and plumbed. The maximum variation of any pier
from its designated location shall not be more than 2 inches at its top elevation. No pier shall be
out of plumb more than one inch in 5 feet of height. Variation of pier location within specified
limits shall not be cause for variation in anchor bolt or concrete cap location.
Each pier excavation shall be made to the depth indicated on the drawings.
2C.6.3 Placing of Concrete
Concrete work for foundation piers shall conform to the requirements of Section 2C.5 and to
these additional requirements. Unless otherwise permitted by the Owner, concrete shall be
placed in the pier holes the same day the holes are drilled.
City of Fort Collins Power & Light-06.007 2C-13
All water and loose materials shall be removed from the holes and pier reinforcing shall be
thoroughly cleaned before any concrete is placed. Pier holes shall be dry when concrete is
placed unless otherwise acceptable to the Owner.
Concrete shall be placed with a tremie or funnel, or pumped to prevent segregation and the top 6
feet shall be rodded or vibrated to provide a dense mass free of voids. During the filling of the
holes, if water begins to accumulate on the top of the concrete, the placement shall be suspended
and the water removed before placement resumes. If water continues to accumulate during the
suspension of placement, the concrete placed shall be removed and the pier shall be installed by
underwater methods. Should there be an accumulation of scum or laitance on the top of the
concrete, it shall be removed and additional concrete shall be placed to bring the pier back to the
proper elevation.
Pumping methods shall conform to ACI 304, Chapter 9. The maximum loss of slump due to
pumping shall be 2 inches. Aluminum or aluminum alloy pipes shall not be used to convey
pumped concrete.
After the concreting is started for each pier, it shall be completed in a continuous process. A
sufficient quantity of concrete to fill the pier shall be in delivery trucks at the pier site when the
first concrete is placed in each pier. If the concreting of any pier is suspended for more than 30
minutes before the pier is completed, laitance and water shall be removed from the joint surface
and the joint surface shall be coated with epoxy bonding compound before concreting is
resumed. In order to provide for an emergency stoppage, bonding compound shall be at the site
before the concreting of piers is started.
Piers shall be reinforced as indicated on the drawings and all reinforcements shall be installed
and secured to prevent shifting during the placement of concrete. The upper portion of the piers
shall be formed where indicated on the drawings. Each pier shall be cured for at least 7 days by
continuous saturation with water or the use of membrane curing compound as specified in
Section 2C.5.12.
If casings are to be left in place, the void areas between the form and the excavation walls shall
be filled with grout. The grout shall be placed and compacted in such a manner that the annular
space is completely filled.
Records shall be kept by the Contractor indicating the exact volume of each pier excavated and
this volume shall then be compared to the volume of concrete actually placed in each pier. A
lesser amount of concrete placed than calculated may indicate fault pier construction. In the
event of such an occurrence, the Owner shall be notified, and immediate remedial action shall
then be taken by the Contractor.
City of Fort Collins Power & Light-06.007 2C-14
2C.6.4 Underwater Concrete
Concrete shall not be deposited under water except with specific permission of the Owner. For
concrete deposited under water the limiting requirements shall be adjusted to provide not more
than 6 inches of slump and to increase the cement content by one sack per cubic yard. Any extra
charges for these changes by the concrete supplier shall be borne by the Contractor.
Underwater concrete shall be placed through 12 inch or larger tremies having a tremie seal at the
lower end and a hopper at the upper end. Before the flow of concrete is started, water shall be
kept out of the tremie by means of a suitable bottom closure. After the flow of concrete is
started, the lower end of the tremie shall be kept below the surface of the deposited concrete.
Agitation of the deposited concrete shall be avoided. When necessary to move laterally, the
tremie shall be lifted free of the concrete and lowered vertically at the new location. The entire
mass of concrete shall be placed as quickly as possible so that it will flow into place without the
necessity of horizontal shifting below water.
The water shall be quiescent when concrete is deposited therein. After placing, the ground water
level in the area adjacent to the pier shall be kept static until the concrete has taken its initial set.
2C.7 GROUTING
2C.7.1 General
This section covers materials and procedures for grouting equipment and structural base plates as
required on the drawings.
Grouting under these specifications shall include only the grouting of equipment and structural
base plates installed under these specifications. Grouting of all other equipment and structural
base plates will be done under separate specifications covering the equipment or base plate
installation.
All grouting shall be done with non-shrinking grout.
Cold weather grouting shall be as specified for cold weather concreting in Section 2C.5.5.5.
2C.7.2 Materials
Where the use of the following materials is specified herein, such materials shall be in
accordance with these requirements:
Water Clean and free from mud, oil, organic
matter, and other deleterious substances
City of Fort Collins Power & Light-06.007 2C-15
Plasticizer Grace "WRDA," Master Builders "Pozzolith
Normal," Protex "PDA 25XL Normal Set,"
or Sika Chemical "Plastocrete 161"
Nonshrinking grout Tested in accordance with CRD-C621 and
ASTM C1107, Grade B. Metallic and
nongas-liberating flowable fluid. Minimum
strength of grout, 4,000 psi at 1 day, and
9,000 psi at 28 days.
2C.7.3 Grouting of Bases for Structures and Equipment
Where noted on the drawings, equipment and structural base plates shall be firmly and solidly
grouted in place by methods that will insure complete, uniform, and permanent filling of all
space beneath the base without disturbing or displacing the alignment or level of the base in its
correct position. Should the installation of any equipment be done under the supervision and
direction of a manufacturer's erection superintendent, or other accredited supervisor provided by
the manufacturer of the equipment, then the grouting procedure shall follow his direction.
Otherwise, these specifications shall govern.
2C.7.3.1 Surface Preparation
The surfaces of hardened concrete upon which grout will be placed shall be chipped to remove
laitance and surface mortar and to expose the aggregate. The surface of the hardened concrete
shall be cleaned of all loose materials and shall be saturated with water for not less than 2 hours
immediately before the grout is placed. All excess water shall be removed.
2C.7.3.2 Alignment and Leveling
Each base shall be set in place over its anchor bolts and shall be carefully aligned in proper
position and then brought to accurate level. If permission is given by the Owner in the case of
small bases or equipment bases, steel wedges may be used for leveling, but such wedges shall
be of a type that cannot be easily or accidentally dislodged. Unless otherwise accepted, leveling
shall have three-point control. The use of wood blocking or wood wedges to hold the base in
position will not be permitted.
2C.7.3.3 This Section Not Used
2C.7.3.4 Placing of Grout
After the base has been set, its alignment and level shall be checked and accepted before placing
any grout. Grout may be placed by the "dry pack" method when the least dimension of the base
being grouted is 2'-0" or less, the grout space is more than one inch, and the grout space is
readily accessible, unless noted otherwise. Dry pack grout shall contain only enough water to
produce a grout which can be tamped in place. Grout shall be tamped in place from one of the
City of Fort Collins Power & Light-06.007 2C-16
longer sides of the base, working against a backing board rigidly wedged against the opposite
side of the base. Tamping shall be done with the end of a board at least 1 by 4 inches in
nominal size. The board shall be struck with a hammer or mallet as required to compact the
grout into a dense mass, free from voids. After the initial set of the grout, all grout which
extends beyond the edge of the base shall be cut off flush and removed.
2C.7.3.5 Finishing of Edges
When the placing of the grout has been completed, it shall be allowed to stand undisturbed until
set stiff. Then immediately the form or dam, if any, shall be taken off, and the portions of the
grout which extend beyond the edges of the base shall be cut off flush and removed. The edges
of the grout shall then be pointed with fresh one-to-two cement mortar pressed firmly to bond
with the body of the grout, and smoothed with a tool to present a smooth vertical surface.
All grouting shall be completed in a proper and workmanlike manner with the exposed edges of
the foundation and the surfaces adjacent thereto left clean and free from cement and grout.
2C.7.4 Nonshrinking Grout
Nonshrinking grout shall be furnished factory premixed so that only water is added at the
jobsite. The grout shall be mixed in a mechanical mixer and no more water shall be used than
recommended by the manufacturer to produce a flowable grout.
Surface preparation and alignment and leveling shall be as specified herein before for portland
cement grout. Nonshrinking grout shall be placed in strict accordance with the grout
manufacturer's directions so that all grout space is completely filled without voids. Edges shall
be finished as specified for portland cement grout.
2C.7.5 Curing
All grout shall be protected against rapid loss of water by covering with wet rags and
polyethylene. After edge finishing is completed, the grout shall be wet cured for at least 7 days
when temperatures of 90° F or above may be expected during curing, special procedures shall
be adopted by the Contractor to keep the grout as cool as possible. In cold weather, the
requirements of Section 2C.5.5.5 shall be followed.
2C.8 TESTING
An air content test shall be made from one of the first three batches mixed each day and from
each batch of concrete from which concrete compression test cylinders are made. Air content
shall be made in accordance with ASTM C231. Slump shall be determined in accordance with
ASTM C143.
Concrete compression test cylinders shall be taken as determined by the Owner. Each set of
compression test cylinders shall be marked or tagged with the date and time of day the cylinders
City of Fort Collins Power & Light-06.007 2C-17
were made, the location, the work where the concrete represented by the cylinders was placed,
the delivery truck or batch number, the air content, and the slump. The cylinders shall be tested
at 7 days and 28 days.
The concrete test cylinders and all field control field testing shall be made by an independent
testing laboratory retained and paid by the Owner. The Contractor shall cooperate with the
testing laboratory representative.