HomeMy WebLinkAboutCHANGE ORDER - BID - 7362 RADIANT NEIGHBORHOOD PARK (2)CHANGE ORDER NO. #4
PROJECT TITLE: Radiant Park
CONTRACTOR: Designscapes
PROJECT NUMBER: 7362
PURCHASE ORDER NO.: g j Z 3 6 74
DESCRIPTION: Construction changes
1. Reason for change: irrigation credit se corner, steel beams in restroom, concrete footing added under elliptical
pipe, steel beams added to water deck, remove sandstone boulders and replace with
boulders provided on site. Add additional concrete se corner of site and for benches in
playground. Substantial completion date set to June 1st) v., 13
}
2. Description of Change: irrigation credit se corner, steel beams in restroom, concrete
footing added under elliptical pipe, steel beams added to water
deck, remove sandstone boulders and replace with boulders
provided on site. Add additional concrete se corner of site and for
benches in playground. Substantial completion date set to June
1st.
3. Change in Contract Cost: ($6,350.70)
4. Change in Contract Time: Substantial Completion Date set to June 1st r 2_0 j
ORIGINAL CONTRACT COST $1,345,034.40
TOTAL APPROVED CHANGE ORDER ($11,725.75)
TOTAL PENDING CHANGE ORDER $3,670.00
TOTAL THIS CHANGE ORDER ($6,350.70)
TOTAL % OF ORIGINAL CONTRACT, THIS C.O. -0.47%
TOTAL % OF ORIGINAL CONTRACT, ALL C.O.'S -1.34%
ADJUSTED CONTRACT COST //%% $1,330,623.95
(Assuminq all chanqe orders a6 bved)
ACCEPTED BY:
Contractor's Rep
ACCEPTED BY:
Project Manager
REVIEWED BY:
Title:
APPROVED BY:
Title:
APPROVED BY:
Purchasing Agent over $30,000
cc: City Clerk Architect
Contractor Engineer
Project Fite Purchasing
DATE: 11/29/12
DATE:
DATE:
DATE:
DATE: