October 30, 2012
Brian Ainsley
CRISP Project Manager
2221 S Timberline Road
Fort Collins, CO 80525
Subject: Change Order-007 to EP-1272: Add Freeze and Transfer button to the Maintenance Tab
Reference: EP-1272: Unix to Windows Migration by and between Tiburon, Inc. and the City of Fort
Collins and Latimer County
Dear Mr. Ainsley:
Tiburon, Inc. is pleased to present the City of Fort Collins (hereinafter, "Client") with this Change Order
for Tiburon to add a freeze and transfer button to the Maintenance Tab (hereinafter, referred to as the
"Change Order").
Scope Description and Responsibilities
The attached Exhibit 1, Statement of Work ("SOW") describes the project tasks, responsibilities of each
party and defined completion criteria.
Price Description
1) Additional firm fixed price: $ 2,508
2) The Tiburon Annual Maintenance Fee will not increase as a result of this Change Order.
3) This Change Order does not include:
• Warranty
• Documentation
• Hardware or third party products or services
• Travel and on -site time
4) Any taxes levied by a government agency. Taxes, if applicable are the sole responsibility of the
Client.
Effective Date and Pavment Schedule
1) The work described herein will be scheduled to commence at a mutually agreeable date after Client's
acceptance of this Change Order.
Tiburon, Inc. 3000 Executive Parkway, Suite 500, San Ramon, CA 94583 t: 925-621-2700 f: 925-621-2799
Fort Collins
CP-011: Add Freeze and Transfer Button to the Maintenance Tab in
Page 2 of 3
2) Payment Schedule:
• 50% Upon Tiburon receipt of the signed acceptance of this Change Order.
• 50% Upon achievement of the completion criteria set forth in the SOW.
Note: No scheduling of resources will occur until after the first payment milestone is paid. This
Change Order may be cancelled at Tiburon's discretion upon written notice to Client if the first
payment milestone is not paid when due.
3) Client's acceptance of this Change Order in the signature block provided below, authorizes Tiburon
to proceed with the work described herein and confirms funding will be obligated. Any requisite
contractual documents required by Client's purchasing procedures are the responsibility of the Client.
4) The terms and conditions of the above referenced Agreement, and this Change Order prevail
regardless of any conflicting or additional terms and conditions on any Purchase Order or other
correspondence. Any contingencies or additional terms obtained on any Purchase Order are not
binding upon Tiburon. All Purchase Orders are subject to approval and acceptance by Tiburon.
5) This fixed price Change Order is valid through December 31, 2012.
Upon review and acceptance of this Proposal, please have a duly authorized person sign below and return
the signed copy of the Proposal to Vinnie Richardson via e-mail at Vinnie.Richardson@tiburoninc.com or
fax 510-217-6466. 1f you have any questions or require further information, please contact Vinnie at 925-
621-2386, at your convenience.
Sincerely, A
Donald Doepke
Executive Director of Operations
Attachment:
Exhibit 1 - Statement of Work
By this signature, Client accepts this Change Order:
Printed Name / Title ®�
I
Date
oe=���GX1-b�CJ�
Tiburon, Inc. 3000 Executive Parkway, Suite 500, San Ramon, CA 94583 t: 925-621-2700 f: 925-621-2799
Fort Collins
CP-011: Add Freeze and Transfer Button to the Maintenance Tab in
Page 3 of 3
Tiburon, Inc. 3000 Executive Parkway, Suite 500, San Ramon, CA 94583 t: 925-621-2700 f: 925-621-2799
Fort Collins
CP-011: Add Freeze and Transfer Button to the Maintenance Tab in
Page 4 of 3
Exhibit 1.
Statement of Work
Scope Description
Remotely, Tiburon will modify Client's existing Field Interview application so that on the Freeze tab,
there is an additional button labeled "Freeze and Transfer" that will do both steps of Freezing the Field
Interview and sending it to Crime Analysis. This button will require the security that both Freeze and
Transfer buttons require.
Tiburon Responsibilities
1) Modify the application per the Scope Description.
2) Install the modified code in Client's test environment.
3) Upon Client's testing, correct any discrepancies in operation based on the Scope Description.
4) Install the modified code in Client's production environment.
Client Responsibilities
1) Designate a person to be the principal point of contact for all technical questions and administrative
arrangements relating to this Proposal.
2) Provide VPN access to Tiburon.
3) As required, coordinate the participation of non -Tiburon provided third parties and outside agencies.
4) Complete testing of the modified code within ten (10) business days from receipt of Tiburon's
notification the code is ready for testing to ensure conformance with the Scope Description.
Completion Criteria
This work will be considered complete ten (10) business days after Tiburon has provided the Client with
written notification that the modified code is ready for testing in the test system, or has been placed into
production, whichever comes first. If Client does not confirm completion with a sign off letter presented
by the Tiburon project manager within ten (10) business days of submittal of such letter, or otherwise
notifies Tiburon in writing why completion sign -off has not been provided any final invoice(s) will be
issued and will be payable in accordance with the payment terms of this Change Order.
Tiburon, Inc. 3000 Executive Parkway, Suite 500, San Ramon, CA 94583 t: 925-621-2700 f: 925-621-2799
City of Fort Collins
CP— 009: Allow CMS Initialize to ARS Multiple Times
Page 2 of 3
2) Payment Schedule:
• 50% Upon Tiburon receipt of the signed acceptance of this Change Order.
• 50% Upon achievement of the completion criteria set forth in the SOW.
Note: No scheduling of resources will occur until after the first payment milestone is paid. This
Change Order may be cancelled at Tiburon's discretion upon written notice to Client if the first
payment milestone is not paid when due.
3) Client's acceptance of this Change Order in the signature block provided below, authorizes Tiburon
to proceed with the work described herein and confu-ms funding will be obligated. Any requisite
contractual documents required by Client's purchasing procedures are the responsibility of the Client.
4) The terms and conditions of the above referenced Agreement, and this Change Order prevail
regardless of any conflicting or additional terms and conditions on any Purchase Order or other
correspondence. Any contingencies or additional terms obtained on any Purchase Order are not
binding upon Tiburon. All Purchase Orders are subject to approval and acceptance by Tiburon.
5) This fixed price Change Order is valid through December 31, 2012.
Upon review and acceptance of this Change Order, please have a duly authorized person sign below and
return the signed copy of the Change Order to Vinnie Richardson via e-mail
at Vinnie.Richardson@tiburoninc.com or fax 510-217-6466. If you have any questions or require further
information, please contact Vinnie at 925- 621-2386, at your convenience.
Sincerely, `,
/
Donald Doepke
Executive Director, Operations
By this signature, Client accepts this Change Order:
a"--? �s'` V�tv
Si a re Date
Jto'lu►e-5 Rt011j4g L
Printed Name / Title
L P��J
Tiburon, Inc. 3000 Executive Parkway, Suite 500, San Ramon, CA 94583 t: 925-621-2700 f: 925-621-2799
TIBURIIN0
November 9, 2012
Mr. Brian Ainsley
Fort Collins Police Services
2221 Timberline Road
Fort Collins, CO 80525
Subject: Change Order (CP) — CP-009: Allow CMS initialize to ARS multiple times
Reference: EP-1272: Unix to Windows Migration by and between Tiburon, Inc. and the City of Fort
Collins and Larimer County
Dear Mr. Ainsley:
Tiburon, Inc. is pleased to present the City of Fort Collins (hereinafter, "Client") with this Change Order
for Tiburon to allow CMS initialize to ARS multiple times (hereinafter, referred to as the "Change
Order").
Scope Description and Responsibilities
The attached Exhibit 1, Statement of Work ("SOW") describes the project tasks, responsibilities of each
party and defined completion criteria.
Price Description
1) Firm fixed price: $3,648
2) Upon achievement of the completion criteria set forth in the SOW the Tiburon Annual Maintenance
Fee will increase by $410. This additional maintenance fee will be prorated and added to the
following year's annual maintenance renewal.
3) This Change Order does not include:
• Warranty
• Documentation
• Hardware or third party products or services
• Travel and on -site time
4) Any taxes levied by a government agency. Taxes, if applicable are the sole responsibility of the
Client.
Effective Date and Payment Schedule
1) The work described herein will be scheduled to commence at a mutually agreeable date after Client's
acceptance of this Change Order.
Tiburon, Inc. 3000 Executive Parkway, Suite 500, San Ramon, CA 94583 t: 925-621-2700 f: 925-621-2799
City of Fort Collins
CP— 009: Allow CMS Initialize to ARS Multiple Times
Page 3 of 3
Exhibit 1
Statement of Work
Scope Description
Remotely, Tiburon will modify Client's MobileREPORTS (ARS) application to change the processing
behind the CMS Initialize button so the user is allowed to pull the same Booking Number details from
JailRECORDS into more than I MobileREPORTS (ARS) report. Once the user performs the action to
pull the number, a message will display for notification that the Booking Number is now on more than 1
ARS report.
Tiburon Responsibilities
1) Modify the application per the Scope Description.
2) Install the modified code in Client's test environment.
3) Upon Client's testing, correct any discrepancies in operation based on the Scope Description.
4) Install the modified code in Client's production environment.
Client Responsibilities
1) Designate a person to be the principal point of contact for all technical questions and administrative
arrangements relating to this Change Order.
2) Provide VPN access to Tiburon.
3) As required, coordinate the participation of non -Tiburon provided third parties and outside agencies.
4) Complete testing of the modified code within ten (10) business days from receipt of Tiburon's
notification the code is ready for testing to ensure conformance with the Scope Description.
Completion Criteria
This work will be considered complete ten (10) business days after Tiburon has provided the Client with
written notification that the modified code is ready for testing in the test system, or has been placed into
production, whichever comes first. If Client does not confirm completion with a sign off letter presented
by the Tiburon project manager within ten (10) business days of submittal of such letter, or otherwise
notifies Tiburon in writing why completion sign -off has not been provided any final invoice(s) will be
issued and will be payable in accordance with the payment terms of this Change Order.