HomeMy WebLinkAboutCHANGE ORDER - BID - 7125 WATERS WAY NEIGHBORHOOD PARK (8)CHANGE ORDER NO. 11
PROJECT TITLE:
Water's Way Neighborhood Park
CONTRACTOR:
Walsh Construction Incorporated
PROJECT NUMBER:
# 7125
PURCHASE ORDER NO.:
9111356
DESCRIPTION: Change in work request
1. Reason for change: Developer finished Bellwood Court and Storrs Water Improvements
days cost
2. Description of Change: Field Order 21 15 $ 40,388.00
Field Order 25 5 $ 8,498.00
total: 20 $ 48,886.00
3. Change in Contract Cost: $ 48,886.00
4. Change in Contract Time: 20
TOTAL APPROVED CHANGE ORDER
$ 90,015.79
TOTAL PENDING CHANGE ORDER
$ 40,276.00
TOTAL THIS CHANGE ORDER
$ 48,886.00
TOTAL % OF ORIGINAL CONTRACT, THIS C.O.
4.02%
TOTAL % OF ORIGINAL CONTRACT, ALL C.O.'S
14.73%
ADJUSTED CONTRACT COST
,395,4 .79
(Assuming all change orders approved)
ACCEPTED BY: DATE:
Contractor's Representative
ACCEPTED BY: `�j�� �� DATE: ell ZO /v
Project Manager
REVIEWED BY
Title:
APPROVED BY:
Title:
APPROVED BY:
DATE:
DATE:
DATE:
Purchasing Agent over $30,000
cc: City Clerk Architect
Contractor Engineer
Project File Purchasing
Field Order 25
Initiation Date:
81+1;zt i>
Project
\5'ater's way iNeiehborhood Park
Owner:
CitN ui F:,r Collin
To:
Walsh Construction inc.
Requested by:
\':att DIN
Authorized by:
%watt Pi,_ Pniieet Flan;__r
Please famish change in contract sum for the change in work described below. Do not order material or start any work until approval is
received. Evely effort will be made to incorporate this change into the work without affecting the contract date.
Description of Proposed Changes- Proposal Request and/or Supplemental Information
Turf Grass
NE existing turf: spray for weeds utilizing " Q4 plus", fertilize, top dress and overseed with attached bluegrass turf mix. SW
turf grass area: fine grade, fill low spots and provide soil prep per specifications, seed with amended mix and add hydro -
mulch to the seeding operation. Hillside grass seeding: utilize seed mix per specifications and add hydro -mulch.
20% sr 2284
20% orfeo
20% spitfire
20% sr 2100
10% argos
10% champion blend perennial rye
Walsh Cnnstrnciian me. , agrees to change the work described above for the change in price shown below. I have attached
a breakdown which lists all costs of labor. materials, taxes, overhead, profit, and all other changes and/or charges involved. Signature of
the Contractor indicates his agreement herewith, including any adjustment in the Contract Sum or Contract Time.
The Contract Time will be (increased) t''^" "'- ) by 5 Days.
No change in Contract Sum (Initial if no change)
fl�
ADD to the Contract Sum S co;,
1 � d
DEDUCT from the Contract Sum S
This information shall be valid for thirty (30) calendar days from the date of signature below.
CONTRACTOR'S SIGNATURE.
Coniracinr.shall retain one (1) raln, and return ORIGINAL to Owner
APPROVED BY OWNER:
DATE:
DATE:
Accepted change in work request will be included in a future formal change order. DO NOT bill far this change until a formal change
order has been execuled by all parties. Acceptance is direction to proceed with the work described herein. Not ralid unless signed br
the owner and the contractor.
Field Order 21 - revised
Initiation Date: 5/3i2012 - revised 861/i2
Project:
N. titer's %> av ei-7dntrhond Park
Owner:
i h% 0i Port Ct�llin�.
To:
Walsh Construction Inc.
Requested by:
\oat€ i)m
Authorized by:
n I'at Day. Pru e t Man __er
Please famish change in contract sum for the change in work described below. Do not order material or start any work until approval is
received. Every effort will be made to incorporate this change into the work without affecting the contract date.
Description of Proposed Changes- Proposal Request and/or Supplemental Information
Exisitng ROW Strip
Re -work the existing ROW strip. Work includes demolition of the existing dead trees marked by Forestry, grass, and
irrigation. Please protect existing connections to the valves along the main line. Work includes grading, irrigation (strip and
drip per attached Hines plan), soil preparations, and turf grass sod (salt tolerant bluegrass sod). Trees in the ROW strip:
(10) bur oaks and (14) kentucky coffee trees, 3" cal (typ).
w:d h consaucfion inc. , agrees to change the work described above for the change in price shown below. I have attached
a breakdown which lists all costs of labor, materials, taxes, overhead, profit, and all other changes and/or charges involved. Signature of
the Contractor indicates his agreement herewith, including any adjustment in the Contract Sum or Contract Time.
The Contract Time will be (increased) (", ^ 11 % .... I ...... Lj:) by IIS'- Days.
No change in Contract Sum (Initial if no change) ADD to the Contract Sum $ �[ !J o l 3 s J !�!—
DEDl1CT from the Contact Sum $
This information shall be valid for thirty (30) calendar days from the date of signature below.
CONTRACTOR'S SIGNATURE DATE:
Contractor shall retain one (1) copy and recant ORICIAAL to Owner
APPROVED BY OWNER: DATE:
Accepted change in work request will be included in o ftture formal charge order. DO NOT hill for this change until a formal change
order has been executed by all parties. acceptatce is direction to proceed ii,ith tite work described herein. No! valid unless signed by
the owner and the contractor.