Change Order Form
PROJECTTITLE: Tumbe" Rd. Improvements
PROJECT NUMBER: 400901718 (Bid #7405)
CONTRACTOR: Connell Resouces, Inc. (PO #9124395)
CHANGE ORDER NUMBER: 3
n preparing -change rderssslow in order as separate numnerea paragrapns me touowmg:
1. Reason for change. 2. Description of change.
3. Change in contract cost. 4. Change in contract time.
1 &2. See attached sheet for detail.
3. The contract cost will increase by $51,459.40
4. There will be no change in contract time.
ORIGINAL CONTRACT COST
TOTAL APPROVED CHANGE ORDERS
TOTAL PENDING CHANGE ORDERS
TOTAL THIS CHANGE ORDER
TOTAL % OF THIS CHANGE ORDER
TOTAL C.O. % OF ORIGINAL CONTRACT
ADJUSTED CONTRACT COST
(Assuming all change orders approved)
ACCEPTED BY: c.
-REVIEWED BY:
'SUBMITTED BY:
2.21 %
1.54%
$2,329,248.20
($15,687.00)
$0.00
$51,459.40
$2,365,020.60
DATE: it / 4 f ( Z
DATE: ' I Tt 1 1
APPROVED BY: O" DATE:
*(Department Head)
APPROVED BY: DATE:
(Purchasing Agent over $80,000)
cc: Contractor
Purchasing
Project He
CHANGE ORDER 3
Turnberry Road Improvement Project
SUMMARY OF WORK
Itnm If eem nuantity Unit . 3/Unit Total
7
Subgrade Prep
1560
SY
1.5
$ 2,340.00
2
Fly -ash Mobilization
1
EA
$ 2,800.00
$ 2,800.00
3
Fly -ash Treated Subgrade 12%
4430
SY
$ 8.60
$ 38,098.00
4
Unclassified Excavation
407
CY
$ 5.30
$ 2,157.10
5
Embankment
407
CY
1 $ 2.20
$ 895.40
6
1 Haul off material and haul in material
814
CY
1 $ 6.35
$ 5.168.90
TOTAL
REASON FOR CHANGE
Soft Subgrade repairs between Mainsail and Brightwater Drive
WHEN POSTED
Posted to Pay App #3
$51,459.40