HomeMy WebLinkAboutCHANGE ORDER - BID - 7125 WATERS WAY NEIGHBORHOOD PARK (6)CHANGE ORDER Na 10
PROJECT TITLE: Water's Way Neighborhood Park
CONTRACTOR: Walsh Construction Incorporated
PROJECT NUMBER: # 7126
PURCHASE ORDER NO.: 9111356
DESCRIPTION: Change in work request
1. Reason for change: Landscape Skate Park and Bellwood Court Entrance
days cost
2. Description of Change: Field Order 26 20 $ ._. 40,276.00
total: 20 $ 40,276.00
3. Change in Contract Cost: $ 40,276.00
4. Change in Contract Time: 20
TOTAL APPROVED CHANGE ORDER
$ 90,015.00
TOTAL PENDING CHANGE ORDER
$ -
TOTAL THIS CHANGE ORDER
$ 40,276.00
TOTAL °% OF ORIGINAL CONTRACT, THIS C.O.
3.31 %
TOTAL °% OF ORIGINAL CONTRACT, ALL C.O.'S
10.71%
ADJUSTED CONTRACT COST
346,541.00
(Assuming all change orders approved)
ACCEPTED BY: G/''= DATE:
Contractors Representative
ACCEPTED BY: v DATE: 0
Project Manager
REVIEWED BY:
Title:
APPROVED BY:
Title:
DATE:
DATE:
APPROVED BY: DATE:
Purchasing Agent over $30,000
cc: City Clerk Architect
Contractor Engineer
Project File Purchasing
Field Order 26
Initiation Date: 9/1212012
Project: Water's Way Neighborhood Park
Owner:
Cite oll-or Collins
To:
Waleh Cousrruction Inc.
Requested by:
Man O n
Authorized by:
tfut 11... 1'r,11 i:Mann=err
Please furnish change in contract sum for the change in work described below. Do not order material or start any work until approval is
received. Every effort will be made to incorporate this change into the work without affecling the contract date.
Description of Proposed Changes- Proposal Request and/or Supplemental Information
Skate Park Entrance -Landscape stairs and skatepark.
Provide river rock mulch (74" & 6"+), backfill and grade around walls, provide drains behind the walls, raise (2) irrigation
valves, provide landscape (see plant schedule and layout plan) and irrigation. Work to include clean up/removal of debris
and reshaping of BMX area and installation of 5' wide breeze pathway(bmx track).
w akh construction tnc. , agrees to change the work described, above for the change in price shown below. I have attached
a breakdown which lists all costs of labor, materials, taxes, overhead, profit, and all other changes and/or charges involved. Signature of
the Contractor indicates his agreement herewith, including any adjustment in the Contract Sum or Contract Time.
The Contract Time will be (increased) (decreased) iurehan ed) by Rio Days.
No change in Contract Sum (initial if no change)
ADD to the Contract Sum S 40
DEDUCT from the Contract Sum S
This information shall be valid for thirty (30) calendar days from the date of signature below.
CONTRACTOR'S SIGNATURE DATE:
Contractor shall retain one (1) ropv and return ORIGINAL to Owner
APPROVED BY OWNER: DATE:
Accepted change in work request will be included in a future fortis/ change order. DO NOT bill for this change until a formal change
order has been eseculed by all parties. Acceptance is direction to proceed with the work described herein. Not valid unless signed by
the owner and the contractor.