HomeMy WebLinkAbout222075 BURLINGTON NORTHERN & SANTA FE RAILWAY COMP - CONTRACT - PURCHASE ORDER - 9124737ti
City of
F6rt Collins
Memorandum
Planning, Development & Transportation
Engineering Department
281 North College Avenue
P.O. Box 580
Fort Collins, CO 80522.0580 7 —
970.221.6605 / ,L 3�
970.221,6378 -fax 111
fcgov. com/engineering
To: Jun O'Neil, Director of Purchasing and Risk Management
From: Terry Tyrrell, Consultant Project Manger & Erika Keeton, Special Projects Engineer
U
Date: August 24, 2012
Re: MAX BRT — Requisition Request
BNSF Railroad Mason Street Track Rehabilitation
Justification and Independent Cost Estimate
In March of 2011, the City of Fort Collins entered into an Agreement, Mason Corridor Bus Rapid Transit
Construction and Maintenance Agreement (C&M Agreement), in which the BNSF and the City is bound
to adhere to. BNSF is required as part of the Project and the Agreement to improve their railroad
signalization and track systems along the Downtown Corridor of Fort Collins (Old Main to Maple Street
along Mason Street), In a joint effort to construct the necessary Project infrastructure, the City, FTA and
BNSF agreed to improve the safety of the traveling public by providing a curbed median section to house
the BNSF tracks. This effort coincides with the ongoing conversion of Mason Street to two-way traffic
that is necessary for the MAX BRT operations along existing Mason Street.
As railroad work must be performed by the railroad due to the Agreements and union regulations, the
costs were developed by BNSF and are proprietary. We have included the cost estimates for these BNSF
improvements as an attachment (BNSF Railway Company FHPM Estimate For City of Fort Collins
MP72.8 to FT COLLINS) in support of our Independent Cost Estimate (ICE). The original estimate,
which was developed by BNSF as part of the C&M agreement March 22, 2011, is in the amount of
$862,796.00.
BNSF went through the "Request for Proposals" procurement process to select a contractor for the
necessary civil construction work associated with the Project in support of track rehabilitation effort (see
attached BNSF Railway Company Request for Proposal Bid ID# GE02720). The low responsive bidder
was Oftedal Construction Incorporated. In the RFP, a scope of work and related bid tab was provided for
completion by the Contractor. BNSF supplied the City with bid tabs submitted by Oftedal on April 11,
2012 that includes the scope of work to remove the existing asphalt roadway, utility location, excavation
and sub -drain installations. The track, ballast and cross ties and portions of the excavation and backfill are
allocated to BNSF pursuant to the C&M Agreement. The City's responsible portion of this bid is
indicated in the spreadsheet in the RFP Attachment and totals 872,563.90. BNSF is solely responsible for
the cost of the track rehabilitation as indicated in the Bid tab spreadsheet. The City of Fort Collins
negotiated a weighted percentage of the total cost of the Oftedal proposal as it relates to the portion of
IlJ,5OI1 STREET OPTION 2
TRkCtl< REHABILITATION
IAP 7,3.46 - 74.,`.0 - LS 476
6
Bid Tab
=7
=
Description
I Estimated
QUdag
Unit
Unit Cost
TOWI
CityCosts
BNSF
Costs
Percentage
Cost
Percentage
Cost
n'mk �..CCF
I
OFTEDAL
I
:dobilivion
1
LS
5150,000.00
Si50.OD9.1i
9i:i
Sf36.5W.05
9%
S13.SO0.'1
'
AsphJt Removel
II.M
SY
$2,00
,S22.E66.05
100%
523.666M
D-A
50.00
3
Utility Lneetien
1
LS
SA,490.00
SA.490.00
i0085
E4.490.00
0%
S0.130
4
Tract: Remo,J
1
LS
M.200.00
°-3E.200.01i
Oa
So.05
100°A
SM200.00
5
E:caali0n
12,1C0
CY
15.70
572.9W.7,
845$
1.51.22 AD
16%
SiL67 M
6
Sub Errca0on
5.000
CY
£5.70
528.500.oc
100t1
S28.500.00
036
$0.00
7
C=e rl Tr.m,cnt
ITEM REMOVED
FROIA BID
$0.00
05;,
50.00
0%
S0.00
8
Gco Grid (dalerial)
5.090
SY
$2.70
513.500.00
Ia0::
513.500.00
0ed
50.00
9
Des Grid(Pla:cmc00
5.000
SY
Mae
54.000.OG
100•4
54.000.0(r
0°o
50.00
to
Drain Acerccam
448
CY
546.00
$20.608.00
loo.".1
E20,608.00
0tt
50.00
II
13'Pcrfmatcd Drain Rpe(EPW lnadinD Capabic)
3.759
LF
S18.00
567.602.00
10015
S57662.00
0%
50,00
12
Inlet Spccid(]rJi.c Dcin)
10
EA
53,010.00
530,10D.00
100-1.
530.100.00
oti,
SOLD
13
Inlet Spacial (Drein Buin HS foot)
6
EA
53,010.00
£18,060,00
100%
S18,050.00
0'14
$0.00
14 11.1.t
Spccinl(DrJn Bavigflortc.o
3
EA
$3,010.00
59,030.00
100%
59,039.00
0%
S0,01)
15 lInIcE
Tape C(10 Fool)
2
EA
53,700.00
57.400.00
t00%
57.400.00
0%
$0.00
16
Cleanout
23
EA
$310.00
$8.930.00
100%
58.990.00
05$
SO.OD
V
15 Inch reinforced Concmm Pipe (RCP)
12
LF
$100.00
$1.200.00
100!:
51,200.00
0%
Moo
)6
Geolexlile Filmr Fckic(Draimgc - Class A)
3.342
SY
$2.25
$7.519.61
10015
$7.519.50
0%
50.00
IC
Sub-Ballut
9.530
CY
1 $42-501
$405,025.DD
toot.
$405,025.00
0%
Som
20
IneidentiA hems
1
LS
550.000.00
$50.000.00
50til
525.000.00
5061
525.00DOD
SUBTOTAL (Oftedal Estimate):
5960.910.50
SUBTOTAL (CfT1'/BNSF COSTS WITHOUT N1013IL17ATI0NI:
ST36.036.90
574.873.60
PERCENTAGE OF TOTAL TO BE USED FOR MOBILIZATION SPLIT:
91 •-A
9%
SUBTOTAL ICR)'IBNSF
COSTS WITH MOBILIZ4Tf0N)
5872.536.90
S88,373.6D
!i urP fir Ur rrr of Fr, rnlrrvc
2I
0a11mt(13NSF Specification)
ITEM REMOVED FROM BID
7_3
Sim:mrai Bacull(Class 1)
ITEM REMOVED FROM BID
23
Curb S GuuerTSpe 2(Scdim B)
ITEM REMOVED FPOIA BID
24
Hot MixA.phaB(NIChing-Avemeel0"D:plh)
ITEM REMOVED FROM BID
�1
Tragic Central
REM REMOVED
FROM BID
NOTES:
1. Excavation vras divided assuming the top 8 inches of emava6on is ballast material removed v4th the track as part of the track removal. The underlying 3 feet 4 inches is assumed to be subballast or
embankment material that is typically under a madrrey. Therefore evcasalon costs were divided as 160,: Railroad cost and 640,: Roaduayc0s1 as fdlunvs:
BNSF Cost: (16%' 572,960)= $11.674 City Cast: (64%' 572,960)= $61,286
2. Item 6 Subexcava:ion is not anticipated to occur, as excavation below the albvable 4 feel rill have substantial cost implications due to the presence of uVRies. Cement Treated stebiL-ation was
agreed by both the City and BNSF to be removed.
3. Geogrid placement is at the discietion of the 614SF.
4. Idobilialio., was divided according lolhe percentage of sutxolal cost for the Railroad and City based on the assumptions above,
5. Item 21 6211asl has been removed fran the bid and will be included in the 614SF's import of material for (he rest of the Iack area as required and paid for by 614SF.
6. Items 2"-25 (Structural eadf!I. Cub & Ginter, HAM Patching and Traffic Control) have been removed from the bid and will be completed by the City's 6RT Contractor.
REVISION OF SECTION 604
A4AiNIIOLES, INLETS, Ai\� WATER VAULTS
INLINE DRAIN AND INLINE BASIN
Section 604 of the Standard Specifications is hereby revised for this project as follows:
The following sub -section shall be included:
DESCRIPTION
Subsection 604.01 shall include the following:
This work consists of the labor, equipment and materials necessary to install the inline drain, basin devices,
cleanout and appurtenances specified in the drawings and these specifications.
MATERIALS
Subsection 604.02 shall include the following:
Materials shall meet the requirements and specifications of the ADS manufacturer (or approved equal).
Subsection 604.04 shall include the following:
(a) ADS Inline Drain (or approved equal) shall be constructed to manufacturer's specifications and details.
(b) ADS Drain Basin (or. approved Equal) shall be constructed to manufacturer's specifications and details.
(c) ADS Cleanout (or approved Equal) shall be constructed to manufacturer's specifications and details.
The contractor shall submit detail drawings of hnline Drain and Drain Basin for approval prior to installation.
METHOD OF MEASUREMENT
Subsection 604.06 shall include the followinu:
Inline Drain shall be measured and paid for as Inlet Special (Inline Drain)
Drain Basin shall be measured and paid for as Inlet Special (Drain Basin) .
BASIS OF PA17AIENT
Subsection 604.07 shall include the following:
The accepted quantities of Inline Drain, Drain Basin and cleanout will be paid for at the contract unit price each.
PaY Item Pay, Unit
604-19001 Inlet Special (Inline Drain) Each
hilet Special (Drain Basin) O Each
604-90000 Cleanout Each
79
/�A/L I�YAY
ADDENDUM #2
To: Prospective Bidders
From: BNSF Railway Company
Gene Eliassen
3700 Globeville Road
Denver, CO 80216
Date: May 10, 2012
Office Phone: (303) 480-6586
Cell Phone: (720) 530-9956
Fax: (303) 480-5836
aene.eliassenr;bnsf con)
Subject: Addendum #2
BNSF Railway Company
Asphalt and Drainage Installation
Colorado Division — Fort Collins, CO Bid ID#'GE02720
BNSF Railway Company is issuing Addendum 92 for the above referenced project Bid
Documents:
Item 1: Underdrain pipe is to be E80 Loadin.g capable.
Item 2: Underdrain material to be determined by the Contractor and must be E80
Loading capable.
Item 3: Drainage plans are attached to this Addendum 2.
NOTE TO CONTRACTORS: No finther questions can be taken as of the distribution
of this Addendum 2.
Attacluneirt Follows:
Mason Drauna,e Site Plans
Page 1 of 1
703.09
703.07 Bed Course Material.
(a) Bed course material for sidewalks, curbing, and bikeways shall consist of
cinders, sand, slag, gravel, crushed stone, or other approved material of such
gradation that all particles shall pass through a sieve having 19.0 mm (3/
inch) square openings.
(b) Bed course material for slope protection, or riprap filter blanket shall be
a porous, free draining material consisting of sand, gravel, cinders, slag,
crushed stone, or other approved free draining material. This material shall
meet the following gradation requirements:
Sieve Size
75 min (3 inch)
4.75 mm (No. 4)
75 µm (No. 200)
703.08 Structure Backfill Alaterial.
Mass Percent Passing
Square Mesh Sieves
100
20-65
0-10
(a) Class I structure backfill shall meet the following gradation requirements:
Mass Percent Passing
Sieve Size Square Mesh Sieves
50 nun (2 inch) 100
4.75 min (No. 4) 30-100
300 µm (No. 50) 10-60
75 µm (Ito. 200) 5-20
In addition this material shall have a liquid limit not exceeding 35 and a plasticity
index of not over six when determined in conformity with AASI-ITO T S9 and T
90 respectively.
(b) Class 2 structure backfill shall be composed of suitable Materials developed
on the project. To be suitable for use under this classification, backfill shall
be free of frozen lumps, wood, or other organic material. If the material
contains rock fragments that, in the opinion of the Engineer, will be injurious
to the structure, the native material shall not be used for backfillinQ and the
Contractor shall furnish Class 1 structure backfill material at the contract
unit price. If contract unit price does not exist for Class I structure backfill, it
will be paid for in accordance with subsection 104.03.
703.09 Filter -Material. Filter material shall consist of free draining sand. ,ravel.
sag. or crushed :tone. The gradim, requirements are set Iorth in Table 703-7.
693
703.09
Table 703-7
GRADATION SPECIFICATIONS FOR FILTER MATERIAL
Siese Size
Mass Percent Passing
Square Mesh Sieves
Class A
Class B
Class C
75 mill (3")
100
37.5 min (I%")
100
19.0 n11n (3/")
20-90
100
4.75 nun (No. 4)
0-20
20-60
60-100
1.18 µm (No. 16)
10 30
300 µm (No. 50)
0-10
10-30
150 µm (No. 100)
0-10
75 lun (No. 200)
0-3
0-3
0-3
703.10 Aggregate for Median Cover. Aggregate for median cover shall consist
of clean crushed stone, crushed gravel, or natural gravel. The percentage of wear,
when tested in accordance with AASHTO T 96, shall not be more than 70. The
grading requirements shall be as follows:
Allass Percent Passing
Sieve Size Square Afesh Sieves
63 nim (2 V2 mcll) 100
50 min (2 inch) 95-100
19.0 nun (Ainch) 0-15
694
712.13
(4) Used rails, pipe or angles may be used provided the material is not rusted
or damaged to such an extent that the strength of the stakes is affected.
Soil anchor stakes shall be of the lengths called for on the plans.
712.10 Epoxy. Epoxy used for bonding new, or a -et concrete, to old concrete
shall be an approved product and shall be of the type specifically intended for
bonding -,vet concrete to existing concrete. Each container of epoxy shall conform
to ASTM C 881.
712.11 Plastic Pipe for Underdraius. Polyethylene perforated or nonperforated
corrugated pipe shall conform to AASHTO 1\4 252.
Perforated or nonperforated Polyvinyl Chloride Pipe -Smooth Interior. Smooth or
Ribbed Exterior, shall conform to AASHTO M 304.
712.12 Geocomposite Drains. Geocomposite drains, underdrains, and edge drains
for subsurface drainage shall be constructed of a drainage geotextile and a semi -rigid
drainage core. A drainage pipe collector may also be included in the drain system.
Drainage geotextile shall be a minimum Class 3, conforming to AASHTO M
288. The drainage pipe collector, when used, shall conform to the requirements
designated in subsection 605.02 for the type of pipe used.
The semi -rigid drainage core shall be constructed of material that will
i not deteriorate in subsurface conditions, and shall conform to the physical
requirements of Table 712
Table 712-'•
PHYSICAL REQUIREMENTS FOR DRAINAGE CORE
Property
Value
Test Method
Compressive Strengtli, kPa (lbs./sq. in.)
140 (20)
ASTM D 1621
In -Plane Flow Capacity L/s/m
(gallmindf -), minimum
2.12 (10)
ASTM D 4716
Minimum Core Thickness, mm (inch)
6(0.25)
712.13 Plastic Pipe. Plastic pipe shall confornn to the following requirements for
the type of pipe used:
(a) Polret/n•lene (PE) Pipe. Polyethylene (PE) pipe shall conform to the
following requirements for the type of culvert pipe used:
(1) AASHTO NJ 252 (Corrugated Pipe) tier nominal pipe sizes of 3 ro 10
inches (75 to 250 min) \Pith the following additions or exceptions:
(i) Type S, and Type SP are acceptable. (Type C. Type C P and Type D
Avill not be accepted.)
(ii) Rotational Molded Pipe Nvill not be accepted.
725
REVISION OF SECTION 630
CONSTRUCTION ZONE TRAFFIC CONTROL
Section 630 of the Standard Specifications is hereby revised as follows:
DESCRIPTION
Subsection 630.01 shall be revised as follows:
This work shall consist of furnishing, installing, moving maintaining and removing temporary traffic
signs, advance warning arrows panels, barricades, channelizing devices, and delineators as required by
the latest revision of the "Manual on Uniform Traffic Control Devices for Streets and Highways"
(MUTCD), the City of Fort Collins "Work Area Traffic Control Handbook", and the Larimer County
Urban Area Street Standards.
In the event of a conflict between the MUTCD criteria and the City's criteria, the City's criteria shall
govern.
When a device is not in use, the Contractor shall remove it from the project for the period it is not needed.
Devices temporarily not in use shall, as a minimum, be removed from the area. Moving will include
devices removed from the project and later returned to use. Payment shall be made for the maximum
number of each type of traffic control device being used at one given time per day.
Traffic control devices shall be placed and/or stored in the City right-of-way in such a manner that
minimizes the hazards to pedestrians, bicyclists and vehicles.
Traffic control devices shall be removed from the site immediately upon completion of the work for
any street(s).
MATERIALS
Subsection 630.02 shall include the following:
All traffic control devices placed for this project must meet or exceed the minimum standards set forth in
the MUTCD. All traffic control devices shall be clean and in good operating condition when delivered
and shall be maintained in that manner on a daily basis. All traffic control devices shall be clearly marked
and free of crossed out information or any other form of defacement that detracts from the purpose for
which they are intended (i.e. crossed out information, information written in long -hand style, etc.)
Additionally- any sign blank with sigon faces on both sides must have the back sign face covered when in
use to avoid confusion to motorists traveling in the opposite direction and other potentially affected
parties, such as residents affected.by any information the sign may present.
CONSTRUCTION REQUIRDIENTS
Subsection 630.09 shall be revised as follows:
-2-
REVISION OF SECTION 630
TRAFFIC CONTROL PLAN
Traffic control throush the construction areas is the responsibility of the Contractor.
For all locations, a Traffic Control Plan shall be prepared. The Traffic Control Plans shall be on City
supplied forms. The Traffic Control Plans shall be submitted for approval to the Traffic Engineer by 8:00
a.m, two working days prior to (lie commencement of work. (Note: Traffic Control Plans for work done
on Monday and Tuesday shall be submitted the previous Friday by 8:00 a.m.) Full road closure plans
shall be submitted no later than Friday mornings by 8:00 a.m. for projects starting the following week.
All plans shall be delivered to Traffic. Facsimiles of plans shall not be allowed. No phase of the
construction shall start until the Traffic Control Plan has been approved. Failure to have an approved
Traffic Control Plan shall constitute cause for the City to stop work, as well as the Contractor's forfeiture
of payment for all work and materials at that location, with no adjustment in the contract time.
All costs associated with Traffic Control Plan review will not be measured or paid for separately, but shall
be considered incidental to the Work.
The Traffic Control Plan shall include, as a minimum, the following:
(1) A detailed diagram which shows the location of all sign placements, including advance
construction signs (if not previously approved) and speed limit signs; method, length and time
duration for lane closures, and location of flag persons.
(2) A tabulation of all traffic control devices (with their associated unit costs) shown on the detailed
diagram including, but not linlited to: construction signs; vertical panel; vertical panel with light;
Type 1, Type lI, and Type III barricades; cones; drum channelizing devices; advance warning
flashing or sequencing arrow panel. Certain traffic control devices may be used for more than
one operation or phase. However, all devices required for any particular phase must be detailed
and tabulated for each phase.
(3) Number of flag°ers to be used.
(4) Parking Restrictions to be in affect.
Approval of the proposed method of handling traffic is intended to indicate those devices for which
payment is to be made. Such approval does not relieve the Contractor of liability specifically assigned to
hiul under this contract.
The owwner will review the unit costs supplied to ensure they are reasonable compared to other projects
and historic values. If the unit prices are deemed not reasonable, the owner will reject the traffic control
plan.
Parkin, Restriction Plans shall be submitted and approved which show the location and quantity of "NO
PARKING" sins. the date to be placed, and the date to be removed. The plans shall be prepared on City supplied(
forms. The Parking Restriction Plans shall be submitted to Parkin, tut o tworking days prior to the commencenlc'nt
of work. (Vote: Parking Restriction Plans for work done on Monday and Tuesday shall be submitted the
previous Friday by S:00 a.m.) All plans shall be delivered to Parkinn.
t: '
-3-
REVISION OF SECTION 630
TRAFFIC CONTROL PLAN
Facsimiles of plans shall not be allowed. No phase of the construction shall start until the Parking
Restriction Plan has been approved. Failure to have an approved Parking Restriction Plan shall constitute
cause for the City to stop work, as well as the Contractor's forfeiture of payment for all pork and
materials at that location, with no adjustment in the contract time. The cost for preparing and submitting
the traffic control plan shall be included in the contract unit price for Traffic Control Supervisor.
Subsection 630.10 shall be revised as follows:
TRAFFIC CONTROL AUNAGEAIENT
Traffic Control A4anageutent shall be performed by a Traffic Control Supervisor (TCS). The TCS(s)
shall possess a current American Traffic Safety Services Association (ATSSA) certification as a Worksite
Traffic Control Supervisor or Colorado Contractor's Association (CCA) certification as a Traffic Control
Supervisor. (Proof of certification shall be presented to the City Traffic Control Manager, and when
requested by a City representative, for each TCS utilized on this project.)
One TCS shall be desi.-hated as the Head TCS. The Head TCS shall have a minimum of one year
experience as a certified TCS. Qualifications shall be submitted to the Engineer for approval a
minimum of one week prior to commencement of the work. The Head TCS shall be on site at all
times during the construction when payment is made under the contract unit price for Traffic Control
Supervisor per day. When the TCS is being paid under the TCS per hour item, time spent on site may be
modified by the City Representative, as needed, based on the size and complexity of the project, location
of work.. duration of the project, traffic factors, weather, and roadway characteristics.
The TCS shall be equipped with a cellular phone. The cost of this phone shall be incidental to the day or
hour pay unit for TCS.
It is the intent of the specifications that the Head TCS be the Sallie throu0iout the project. if the Head
TCS is to be replaced during the project, the Engineer shall be given a minimum of one (1) weeks notice
and qualifications shall be submitted for approval for the replacement.
The Head TCS will be paid for under the TCS item.
The TCS's duties shall include, but not be limited to:
(1) Preparing, revising and submitting Traffic Control Plans as required. (Review fees will not be
measured or paid for separately, but shall be considered incidental to the Work.)
(3) Direct supervision of project flsggers.
(3) Coordinating all traffic control related operations, including those of the
Subcontractors and Suppliers.
-4-
RE• VISIOI' OF SECTION 630
TRAFFIC CONTROL PLAN
(4) Coordinating project activities with appropriate police and fire control agencies, Transfort, school
districts and other affected agencies and parties prior to construction. Typed hand delivered
notification to all businesses and residents at least 24 hours prior to construction. (The
notification of residents and businesses may be accomplished by a representative of the TCS.)
(5) Maintaining a project traffic control diary which shall become part of the City's project records.
(6) Inspecting traffic control devices on every calendar day for the duration of the project.
(7) Insuring that traffic control devices are functioning as required.
(3) Overseeing all requirements covered by the plans and specifications which contribute to the
convenience, safety and orderly movement of traffic.
(9) Flagging.
(10) Setting up traffic control devices.
Notification of residents and businesses shall be the responsibility of the TCS and shall consist of
distributing letters indicating the nature of the work to be completed, any special instructions to the
residents ti.e. limits on lawn watering during concrete pouring, etc.), the dates and limes of the work, and
the parking and access restrictions that will apply, as well as thorough information placed on "NO
PARKING" signs. Sample letters will be provided' by the Engineer and shall be distributed prior to the
commencement of each phase of the work. Letters shall be submitted with the Traffic Control Plans for
approval. Approved letters shall be distributed a minimum of 24 hours prior to the commencement of
work. (Note: The time frame criteria for distributing letters are the same as for posting "NO PARKING"
signs.) The cost for preparing. and distributing the letters shall be included in tlue cost for TCS.
Traffic control management shall be maintained on a 24 hour per day basis. The Contractor shall make
arrangements so that the Traffic Control Supervisor or their approved representative will be available on
every working day, "on call" at all times and available upon theEngineer's request at other than normal
working hours. All costs associated with "on call" service, excluding actual hours worked. shall be
included in the contract unit price for Traffic Control Supervisor.
The TLS's will be paid only for days the Contractor works, and as directed by the Engineer. On
weekends and other days the Contractor is not working, the TCS will not be paid. Time spent
nnaitteinins signs on the weekends, holidays, bad ttenther clays, and other days the Contractor does
not mrork shall be included in the unit prices for the equipment. Time spent setting up equipment,
modifying equipment, maintaining equipment, and picking up equipment shall be included in (lie
unit prices for the equipment.
13 4
City of
Fort Collins
work necessary for the MAX BRT project in accordance with the C&M Agreement and is better
described in the notes at the bottom of the bid tab spreadsheet located in the BNSF RFP.
The cost difference between the ICE developed by BNSF and the Request for Proposal provided by
Oftedal is $9769.90, or approximately 1% difference between the ICE and the Oftedal proposal. After
reviewing BNSF's original estimate for this effort we reviewed previous cost estimates from BNSF and
compared them to the estimates attached herein and found them to be comparable.
BNSF must be utilized for this work, as it is a requirement of the C&M Agreement. Based on our
understanding of the C&M Agreement and the requested scope and budget provided by BNSF/Oftedal of
$872,536.90 for the Mason Street MAX BRT Project required BNSF efforts to convert Mason Street to
two-way traffic in order to safely operate the BRT Buses, we believe the requested budget is reasonable
and adequate. As such, I recommend approval of this contract budget for BNSF for the Downtown Mason
Street two-way conversion.
2
_5-
REVISION OF SECTION 630
TRAFFIC CONTROL PLAN
All traffic control devices shall be placed under the supervision of a Traffic Control Supervisor.
The Traffic Control Supervisor shall have up to date copies of the City of Fort Collins' "Work Area
Traffic Control Handbook", and Part VI of the MUTCD. pertaining to traffic controls for street and
highway construction, available at all times.
METHOD OF MEASUREMENT
Subsection 630.15 shall be revised as follows:
Quantities to be measured for construction traffic control devices shall be the number of units of the
various sizes and descriptions listed below:
Construction Traffic Signs: Size A Signs - 0.01 to 9.00 Square Feet
Size B Signs - 9.01 to 16.00 Square Feet
"NO PARKING" Sign with Stand will be measured and paid for separately and not included in the item
for Size A Signs. "NO PARKING" Sign with Stand shall consist of a metal sign attached to a device
(stand) such as a Vertical Panel or Type I Barricade. The sign material and stand shall be approved by the
Engineer. The sign material and stand will not lie measured and paid for separately but shall be included
in the Contract Unit Price for "NO PARKING" Sign with Stand. The cost for "NO PARING" Sign
«Atli Stand shall include delivery, rental, setup, modification, maintenance, and pickup.
"NO PARKING" signs must remain in place until the street is open to traffic.
Traffic channelizing devices consisting of vertical panel, cones, or drum channelizing devices will be
measured by the unit. Barricade warning lights shall be measured and paid for separately if approved by
the Engineer. Advance Warning Flashing or Sequencing Arrow Panels will be measured by the unit.
The number of Traffic Control Supervisors shall be approved by the Engineer prior to each days work.
The quantity to be measured for Traffic Control Supervisor will be the number of authorized days
performed by the Traffic Control Supervisor or his approved representative. An authorized day shall be
any day, or portion of a day, authorized by the Engineer, that construction operation would require a
Traffic Control Supervisor. "On Call" and project inspections on all other days will not be measured and
paid for separately but shall be included in the work.
The cost for settina up equipment, modifying equipment, maintainina equipment, and picking up
equipment (not including "NO PARKING" Sign with Stand) during authorized days shall be included in
the Contract Unit Price for Traffic Control Supervisor.
135
-6-
REVISION OF SECTION 630
TRAFFIC CONTROL PLAN
If a TCS(s) is used for an authorized day, but not for the entire day, the TCS shall be paid at the Contract
Unit Price for "Traffic Control Supervisor" at the per hour rate.
The quantity to be measured for flagging will be the total number of hours that Flagging is actually used
as authorized. Horns of flagging in excess of those authorized shall be at the Contractor's expense.
Flagger breaks shall be included in the Contract Unit Price for Flagging. The method for covering flagger
breaks shall be approved by the Engineer.
Flagging outside of the construction work hours will not be paid for under the terms of this contract
unless authorized in writing by the Engineer.
Flagger stand-by time will not be paid for under the terms of this contract.
In locations where traffic control is set up and the work is not performed due to Contractor caused delays,
the traffic control shall not be paid for under the terms of this contract. The costs for advance warning
"NO PARKING" signs for periods in excess of 24 hours prior to the advancement of work, including
those instances when said sighs have been changed or otherwise updated to reflect current schedules, will
not be paid for under the terms of this contract unless authorized by the Engineer in writing.
In addition, the Owner shall deduct from compensation due the Contractor $10.00 for each traffic co» trot
device per day for said conditions, including "NO PARKING signs and any signs which are not removed
from the site immediately upon completion of the work.
BASIS OF PAYMENT
Subsection 630.16 shall be revised as follows:
The unit prices indicated in the traffic control plan shall be used to determine total costs for each item
The cost for Traffic Control Devices, not including "NO PARKING" Sign with Stand, shall include
delivery, rental. and pickup. The cost for setting up equipment, modifying equipment, and maintaining
equipment will be paid for under the Contract Unit Price for TCS as described above.
The cost for "NO PARKING" Si.au with Stand shall include delivety, rental. setup, modification,
maintenance, and pickup.
Payment shall be full compensation for furnishing. erecting, maintaining. moving, removing and
disposing of construction traffic control devices necessary to complete the work. All construction traffic
control devices which are not permanently incorporated into the project tt ill remain the property of the
Contractor.
The initial manufacturing will be paid for Specialty Signs per unit and the actual use paid for under the
appropriate unit cost for Size A or Size B sign. This item shall apply to new sins only.
W
7
RE• VISION OF SECTION 630
TRAFFIC CONTROL PLAN
Once manufactured,
they may be used throughout the
project. Upon completion of the work, the
Specialty Signs shall be returned to the Contractor.
The accepted
quantities will be paid for at the contract unit
price for each of the pay items listed below:
Pav Item
Unit
630.01
"NO PARKING" Sign with Stand
Per Day Per Each
630.02
Vertical Panel Without Light
Per Day Per Each
630.03
Channelizing Drum Without Light
Per Day Per Each
630.04
Type Ull Barricade Without Light
Per Day Per Each
630.05
Type IiI Barricade Without Light
Per Day Per Each
630.06
Size A Sign With Stand
Per Day Per Each
630.07
Size B Sign With Stand
Per Day Per Each
630.05
Size A Specialty Sign - Cost of
Manufacturing
Each
630.09
Size B Specialty Sign - Cost of
Manufacturing
Each
630.10
Cote With Reflective Strip
Per Day Per Each
630 1 1
Safety Pence
Per Day Per Roll
630.12
Light
Per Day Per Each
630.13
Advance Warnina Flashing or
Sequencing Arrow Panel
Per Unit Per Day
630.14
Variable Message Board
Per Day Per Each
630.15
Traffic Control Supervisor
Per Day
630.16 Traffic Control Supervisor Per Hour
630.17 Flaaaina Per Each Per Hour
Fingm (land si,m will not be measured and paid for separately. but shall be Included in the 11ork.
The flaaaers shall be provided with electronic communication devices tyhen required. These devices trill
not be pleasured and paid for separately. but shall be included in the work.
1?7
-8-
REVISION OF SECTION 630
TRAFFIC CONTROL PLAN
The cost of batteries, electricity and/or fuel for all lighting or waming devices will not be paid for
separately but will be considered subsidiary to the item.
Sand bags will not be measured and paid for separately. but shall be included in the work.
The Contractor may provide larger construction traffic signs than those typically used in accordance with
the MUTCD, if approved; hoxvever, payment will be made for the typical panel size.
The City shall not be responsible for any losses or damage due to theft or vandalism.
SPECIAL CONDITIONS FOR WORK ON ARTERIALS AND COLLECTORS
NOTE: CROSS STREET TRAFFIC SHALL BE MAINTAINED AT ALL TIMES UNLESS
AUTHORIZED BY THE ENGINEER IN WRITING.
NOTE: FULL CLOSURES ON ARTERIALS AND COLLECTORS, INCLUDING THOSE LISTED
ABOVE, WILL BE ALLOWED UNDER EXTREME CIRCUMSTANCES AND ONLY UPON
APPROVAL OF THE ENGINEER. PLANS SHALL BE APPROVED A MINIMUM OF ONE WEEK
PRIOR TO THE COMMENCEMENT OF WORK AND/OR THE TIME REQUIRED TO
ADEQUATELY NOTIFY THE PUBLIC THROUGH THE MEDIA.
SPECIAL CONDITIONS FOR WORK ON RESIDENTIAL STREETS
NOTE: FULL CLOSURES ON ALL RESIDENTIAL STREETS SHALL BE ALLOWED AS
SHOWN ON THE TRAFFIC CONTROL PLANS.
l:S
cf
Fort CoWns Independent Cost Estimate
Date of Estimate: 22-Mar-11
Contract Type: T&M
Existing Contract or PO (YIN): Y
Description of Goods (A) or Services (B):
In March 22, 2011, the City of Fort Collins entered into an Agreement (Mason Corridor Bus Rapid Transit Construction and
Maintenance Agreement) with BNSF in a joint effort to construct the necessary infrastructure to support the MAX GIRT
Project. As a function of that agreement, the City is required to improve safety for the traveling public by adding sub -
drainage system and a curbed median on the outer limits of the existing track system through downtown Fort Collins. As
railroad costs are proprietary, we have included the cost estimate provided by BNSF for the downtown track rehabilitation
improvements as part of this ICE (see attachment - BNSF Railway Company FHPM Estimate for City of Fort Collins). This
estimate only includes cost incurred by the City of Fort Collins civil portion of the work, and does not include rail, ballast or
cross ties which is the responsibility of BNSF.
I have obtained the following estimate from;
Published Price List / Past Pricing (date)
Engineering or Technical Estimate (performed by)
Independent Third Party Estimate (performed by) BNSF
Other (specify)
Cost Estimate Details:
(Estimate calculated in US Dollars)
Cost of Standard Items
Product
Cost ($/ea)
Cost ($/ea)
Notes/Data Source
Delivered
No Freight
ola
Cost of Services, Repairs, or Non -Standard Items
Item/Task:
Materials or Work Description
Other Direct
Costs
Labor
Rate ($)
Labor
Hours
Labor
Class
Allocated
Overhead
SGW
Profit
TOTAL
City of Fort Collins
$ 872,536.90
$ 872.536.90
Total
$ 872,536.90
'Self g. General and kl.mmtr.w. Expenses
Signature of Preparers
K9fi Craven, City of Fort Collins
/ 021
0
""• MAINTAIN PROPRIETARY CONFIDENTIALITY "•••
BNSF RAILWAY COMPANY
FHPM ESTIMATE FOP.
CITY OF FORT COLLINS
LOCATION TIP72.9TOFTCOLLTNS DETAILS OF ESTIMATE PLANJTEM: 00017829E VERSION: 2
PURPOSE, JUSTIFICATIONAI,'D DESCRIPTION
CVL MASON STREET CO DI V FRONT RANGE SUB LS 476 - REMOVAL OF ETTSTING STREET, SUB -BALLAST PLACEMENT, AND
UNDERDRALN PLACEMENT
BILLABLE:
CITY OF FORT COLLINS
•r'NEED CONTACT AND WO PRIOR TO AFE LOADING FOR APPROVAL...
RFA REQUEST BY: GLE EST BY: SST
NBS REQUEST:
DESCRIPTION QUANTITY U/M COST
LABOR
TOTAL LABOR COST
MATERIAL
TOTAL MATERIAL COST
.rrr.rr..r
OTHER
arr.r.rr•
DESIGN S CONSTRUCTION MANAGEMENT
ENVIRONMENTAL
EXCAVATION
MOBILIZATION
SAW CUT ASPHALT
SUBBALLAST
SUBEXCAVATION
UNDERDRAM
TOTAL OTHER ITEMS COST
PROJECT SUBTOTAL.
CONTINGENCIES
BILL PREPARATION FEE
GROSS PROJECT COST
LESS COST PAID BY BNSF
TOTAL BILLABLE COST
0
TOTALS
0
0 0
1.0
LS
38,683
10.0
LS
10.000
12000.0
CY
144.000
1.0
LS
50,000
20480.0
LS
30,720
3600.0
CY
114.000
2000.0
CY
40,000
5120.0
LF
256.000
693,403 693,403
683,403
170.8$0
8,543
862,796
0
M2.796
Page 1 of 1
Al,
17,4 /L WA Y
BNSF RAILWAY COMPANY
REQUEST FOR PROPOSAL
Asphalt and Drainage Installation
Fort Collins, CO
BNSF Division: Colorado
BID (D# GE02720
April 111 2012
CONFIDENTIAL
COPYRIGHT
This specification is published by BNSF Railway Company. For this specification the intellectual
property rights of BNSF are applicable,
Without prior consent, disclosure to third parties is prohibited.
Location Information
Street Address: Mason Street
Cities: Fort Collins
States/Provinces: CO
Division: Colorado
Sub -Division: Frontrange
Mileposts / Line Segments: 73.46 - 74.30 / LS 476
Schedule - Dates are subject to change
Pre -Bid Meeting Date: 4/30/2012
Pre -Bid Meeting Time: (13:00j 1:00 PM, Local (Railroad) Time based on Pre -Bid Location
Pre -Bid Meeting Location: 281 North College Avenue, Fort Collins, CO
Bid Due Date: 5/4/2012, 12:00 pm CDT
Required Service Start Date: 7/9/2012
Estimated Service Start Time: [07:001 7:00 AM, Local (Railroad) Time based on Project Location
Early Submissions Are Accepted and Appreciated
Scope
Removal of asphalt and track, excavation down to suitable material, placement of sub -ballast, placement
of drain pipe and drain aggregate, placement of curb & gutter, and placement of asphalt.
NOTE:
When applicable, the disposition of metallic scrap and treated timber products is not included in the scope
of work. All metallic scrap and treated timber products must be stacked in an orderly manner in a location
determined by the BNSF Project Manager.
NOTE 2:
Also when applicable, please refer to the BNSF Commodity Clean -Up, Salvage or Recycling Guidelines
document regarding any work related to bulk commodity recoveries. This document outlines BNSF's
environmental standard for bulk commodity recoveries.
'This document will be included in this RFP email as a pdf attachment, regardless of applicability to the
cited work in this RFP.
Equipment Required
Large backhoes and frontend loaders, trucks - large side dumps,, graders, compactors, concrete
equipment and forms, and pavers.
Requestor Contact
First Name: Gene L
Last Name: Eliassen
Phone Number: 303-480-6586
E-Mail Address: gene.eliassen@bnsf.com
Invoices
All invoices are to be routed to the Requestor Contact listed above for approval and payment. All invoices
MUST contain the BID ID alphanumeric reference number in the invoice notes or invoice number. The
Contract Number associated with the services should also be included on the bid. Failure to include die
BID ID on the invoice could delay payment processing.
CONFIDENTIAL SNSF RAILWAY
Pricina
All suppliers should make efforts to review the area for proper scope coverage for the bid. Pricing forth is
service must be "NOT TO EXCEED" and cover all aspects of the work including delays up to 2 hours daily
including required safety briefings, manpower and additional tools and equipment. Please consider in
your bid that track delays may impact duration on site.
All proposal participants and their pricing submissions are confidential and become BNSF property.
BNSF's Sourcing policy does not permit sharing of information pertaining to the competition including
pricing information to alternative participants at any time or in any fashion.
Contact
Contact regarding the RFP with members of BNSF, other than with or through those provided herein, may
result in disqualification of Supplier for this RFP and/or other business with BNSF.
All communications concerning the RFP process shall be addressed to:
Shannon Stack
BNSF Railway Company
2500 Lou Menk Drive
Fort Worth, TX 76131
Phone: 817-352-2296
Email: DirectServices@bnsf.com
RFP Acknowledgement
The supplier must acknowledge receipt of the RFP by email upon receipt.
RFP Clarification
All questions regarding the RFP should be directed to the RFP Coordinator. Contact, telephone numbers,
and e-mail addresses are listed in the Contact section. BNSF's preference is all questions should be sent
by email. These questions and responses may be shared with all suppliers who are participating in the
RFP process.
Pre Bid Meeting
When scheduled, all pre bid meetings are mandatory unless the Contractor and BNSF contact mutually
agree that they do not need to be present. The BNSF contact must be notified in writing before the pre bid
date if the Contractor will not be at the pre bid meeting. If the Contractor fails to attend the pre bid
meeting and has not contacted the BNSF contact, they will be disqualified from the RFP.
Proposal Format
Supplier response to this RFP must utilize RFP Response Template:
Pricing Options — MUST INCLUDE A FULL AND COMPREHENSIVE EQUIPMENT LIST
INCLUDING EQUIPMENT AVAILABLE AND MANPOWER REQUIRED
Submission Guidelines
Supplier should read the entire RFP carefully to understand deliverables expected. The supplier must
submit their RFP response electronically noting the Bid ID alpha numeric coding in the subject
line of the response email.
Awarding of Business
Upon conclusion of this process, all suppliers that participate in the RFP process will be notified of any
decisions made in writing via email.
CONFIDENTIAL BNSF RAILWAY
Terms of Negotiation
Supplier's response to this RFP indicates its understanding and agreement that the RFP is not an offer to
contract by BNSF to Supplier and neither the RFP nor the response constitutes a contract between
Supplier and BNSF. BNSF reserves the right, in its sole discretion, to reject or to disqualify Proposals and
select Suppliers without explanation. In addition, BNSF retains the right to withdraw this RFP any time, to
select or not select a supplier and to modify the terms of the RFP without explanation. Only the execution
of a written agreement between BNSF and a provider will obligate BNSF in accordance with the terms
and conditions contained in such agreement.
Suppliers must agree to the terms and conditions set forth in BNSF's standard service contract. Terms
and conditions are not negotiable.
Confidential Information
BNSF Proprietary Information: Supplier shall not use Proprietary Information for any purpose other than
performing Services under this Request for Proposal. All tangible Proprietary Information in Supplier's
possession or control shall be promptly returned to BNSF on request or upon termination of this Proposal
whichever first occurs.
Supplier must return any material provided by BNSF upon request by BNSF.
All proposals and materials submitted by the Supplier become the property of BNSF.
In the event Supplier believes any materials included in the proposal are confidential or proprietary, the
proposal must be so noted. Supplier agrees that, unless an option, scenario, opportunity, idea or process
included in its proposal, is clearly identified as proprietary to Supplier AND meets the generally accepted
criteria which give rise to intellectual proprietary rights, Supplier will not be entitled to claim any
compensation of any nature if said option, scenario, opportunity, idea or process is later used or
implemented by BNSF.
Proposal Preparation
Proposal Costs — Any resources expended by Supplier in responding to this RFP, including any costs
incurred in proposal preparation, product demonstrations, presentations or site visits are the sole
responsibility of the Supplier.
Validity Period
Supplier must guarantee that its price quotes and delivery schedules shall remain valid for a period of at
least 180 days following submission.
Service Requirements
1. Implementation plan and timeline
Provide an example of your typical plan to implement these services. Include a suggested plan
outline and sample timeline.
2. Problem escalation
Supplier will be required to provide clear escalation paths for issues resolution. Outline the chain
of command for escalating problems that are not resolved to BNSF's satisfaction.
3. Resources
BNSF makes no specific commitments of minimum levels of business to retain resources
necessary to accomplish our objectives. The successful supplier will be required to provide on
call personnel to effectively maintain open communication with BNSF's end customer to clarify all
schedules and work completeness.
CONFIDENTIAL BNSF RAILWAY
4. P&P Bond
When required, the P&P Bond must be issued by an insurance company with an A-7 rating or
better by AM Best, and the bond value needs to be 100% of the project cost.
5. Submission Format
All pricing submissions MUST utilize the accompanying response spreadsheet. Please list the
normal contract rate in the contract rate column and the actual bid rate in the bid rate column.
Also, contractors must list equipment, manpower, materials, mobilization and additional
comments as required for completing the service requested.
CONFIDENTIAL BNSF RAILWAY