Change Order Form
PROJECT TITLE: N. College Rd. Improvements
PROJECT NUMBER: 400903900.6 (Bid #7273)
CONTRACTOR: Connell Resouces, Inc. (PO 49116026)
CHANGE ORDER NUMBER: 9
n preparing c ange orders show in order as separate -numbered paregrapris the following:
1. Reason for change.' 2. Description of change.
3. Change in contract cost. 4. Change In contract time.
1 &2. See attached sheet for detail.
3. The contract cost vAll increase by $1,769.66
4. There will be no change In contract time.
ORIGINAL CONTRACT COST
$6,111,000.00
TOTAL APPROVED CHANGE ORDERS
$53.880.64
TOTAL PENDING CHANGE ORDERS
WOO
TOTAL THIS CHANGE ORDER
$1,769.56
TOTAL % OF THIS CHANGE ORDER
0.03%
TOTAL C.O. % OF ORIGINAL CONTRACT
0.91%
ADJUSTED CONTRACT COST
$6,166,650.20
(Assuming all change orders approved)
ACCEPTED BY:
REVIEWED BY:
I
SUBMITTED BY:
APPROVED BY:
APPROVED BY: DATE:
(Purchasing Agent over $60,000)
cc: Contractor
Purchasing
Project File
%- 7.7'
0
CHANGE ORDER 9
North College - Vine to Conifer
SUMMARY OF WORK
Item
Quantity
Unit
$ / Unit
Total
Bore 2" Electric Conduit
170
LF
$
18A5
$
3,085.50
2" Electric Conduit Material
190
LF
$
1.21
$
229.90
Pothole Existing Utilities
3
EA
$
165.00
$
495.00
Contract Bond
1
LS
$
16.16
$
16.16
613
Credit - 2' Elec. Conduit (Pedestrian)
-170
LF
$
12.10
$
(2,057.00
Total Cost
$
1,769.56
REASON FOR CHANGE
Contractor could not trench excavate for 2" conduit installation due to concrete paving in the alley not shown in
the plans. Proposed boring 170 LF of conduit under the alley paving.
WHEN POSTED
Pay Application #7