PROJECT TITLE: Title VI Review
CONTRACTOR: Federal Compliance Consulting
PROJECT NUMBER: N/A
PURCHASE ORDER NO.: 9123985
DESCRIPTION: Addition of Written Report
1. Reason for Change: Addition of Written Report
2. Description of Change: Professional will provide a written report within 60 days of
completion of the on -site interviews.
3. Change in Contract Cost: $6,900
4. Change in Contract Time: Addition of 60 days
ORIGINAL CONTRACT COST
TOTAL APPROVED CHANGE ORDERS
TOTAL PENDING CHANGE ORDERS
TOTAL THIS CHANGE ORDER
TOTAL % OF ORIGINAL CONTRACT, THIS C.O.: 66%
TOTAL % OF ORIGINAL CONTRACT, ALL f O.'S: 66%
ADJUSTED CONTRACT COST / /%
ACCEPTED BY
V Contractor's Rep
ACCEPTED BY:
Project Manager
REVIEWED BY:
Title:
$_10,500
_0 _
_0_
_6,900_
$ _17,400