Memorandum
To: Jim O'Neil, Director of Purchasing and Risk Management
From: Erika Keeton, Special Projects gineer
Date: 6/28/2012
Re: BID 7390: Construction Manager for MAX BRT Project - Cost Analysis
The City issued a Request for Proposals (RFP) for construction management and materials testing
services for the MAX Bus Rapid Transit Project. Four proposals were received on May 23, 2012. The
proposals were evaluated, and all four firms were invited to interview in accordance with City and federal
procurement procedures. The CH2M Hill team was selected on June 6, 2012 by a team of six City staff
members.
City staff met with the CH2M Hill team to discuss the scope and fee on June 15, 2012, and an original fee
estimate was provided for $4,731,122. This included a 15% fee for CH2M Hill and a 5% fee on
subcontractors, plus expenses. At this meeting the proposed hours for each team member was discussed,
and a variety of reductions were proposed.
Negotiations continued by phone on June 21, 26, and 27 related to expenses, hours, and fees. After
several iterations, a final scope and fee was agreed upon by all parties totaling $3,835,369. This included
a 12% fee for CH2M Hill, and a 4% fee on subcontractors, plus expenses.
Firm
Hours
Labor
Outside Direct
Material
12%
CH2M
4% Fee on
Total
proposed
Costs
Testing
Hill Fee
Subs
City ICE
16,755
$ 2,233,100
$ 172,755
$ 1,222,000
$ 3,627,855
CH2M Hill
20,162
$ 2,585,480
$ 328,014
$ 678,000
$ 165,620
$ 78,255
$ 3,835,369
The Independent Cost Estimate (ICE) for this work was prepared on May 16, 2012 for $3,627,855. This is
5.7% below the final negotiated fee. This difference can be attributed to variations in the overtime hours,
outside direct costs, and material testing. The ICE was developed using the organizational chart provided
in the RFP of anticipated staff members to be provided by the consultant. The estimated number of hours
to perform these services was based on my experience managing (or consultants who are managing) other
large projects. Comparable rates of City staff and other consultants under current contract were used for
Examples of deliverables include
• Progress Reports
• Shop Drawing Submittals/Status/Logs
• Schedule Tracking Reports/Updates
• Budget Status Reports
• Earned Value Reports
• DBEIMBEIWBE & MIW Workforce Utilization Reports
• Material Test Reports (concrete, asphalt, etc.)
• Daily Construction Reports
• Construction Photographic Logs
• Updates to Established Plans (PMP, etc)
• Pay Applications, Change Orders, Independent Estimates
• Job Schedules (overall, look ahead, special)
• Certified Payroll Reports
Proposed Fee:
Estimated labor: $ 2,585,480
Estimated Material testing (QC) $ 678,000
Consultant expenses: $ 328,014
Fixed Fee CH2M HILL $ 243,875
Total: $ 3,835,369
A detailed task breakdown is included in rev 14 of an Excel spreadsheet as discussed June 27, 2012. Please find this
on a separate attachment in same e-mail.
The fee shown above is assumed as a cost plus fixed fee contract type. All reimbursable "consultant expenses" will be billed at
cost no mark up.
Page 5 of.6
Exhibit B
Mason MAX BRT Project
Project Construction Management Services
Schedule
Schedule
The anticipated schedule for the Mason MAX BRT Project is as follows:
Pre -Construction:
CH21VI Limited NTP
CH21VI HILL NTP
Construction:
Start up/Commissioning:
June — July 2012
July 2, 2012
July 16, 2012
July 2012 — December 2013
January — April 2014
A detailed construction scheduled is also attached as Exhibit A
Page 6 of 6
C112M Hill Reference Check
By Erika Keeton, Special Projects Engineer
Grant Nelson
Republic Investment Group
707 17`h Street
Denver, CO 80202
303-228-3594
303-887-2508
RE: Timnath Development Authority — Infrastructure Improvements (Ditesco)
Per phone conversation 6-11-12: Based on his understanding of our project, Grant felt
Ditesco was suited for this type of work. Grant has known Keith for 5-6 years. Keith
performed various CM jobs for Grant over the years and has done a great job. Republic
developed the Wal Mart site in Timnath, and because Timnath was such a small town,
Wal Mart required the developer provide off site improvements. Keith managed the 3.5
mile sewer line installation, and $2.5 million of infrastructure improvements on Harmony
Road. He coordinated this work, and took over all different functions that touched the
project. He coordinated with all parties. Grant said what he liked most about Keith was
his ability to see things beyond just the immediate construction activities. The value of
this project was $6 million, which was non-FTA funded. Grant indicated he and Keith
both underestimated the amount of work need to complete the projects, and felt Keith
was fair when negotiating the changes to the scope approximately 10%. Coordination the
Town should have done, Keith did, including a variety of utility coordination. The project
was delivered on time and under budget. No public meetings per se, but sewer line went
through 7 properties, 3 were good to work with, 3 not great, 1 awful. Connell and Keith
were great and professional when dealing with these folks. Ditesco was adequately
staffed for the project. They turned over all documents to the Town, both digital and hard
copies. This excellent documentation has come in handy many times since. The
documents were thorough, well organized and easily accessible. Grant would hire Keith
and Ditesco again, "definitely". Keith is very professional and does a very good job.
Grant said he was glad they hired him, and in fact did hire him again for another project.
Tracey Abel
Project Manager
Colorado State University
Facilities Service Center North
Fort Collins, CO 80523
970-491-0306
RE: Various CSU Projects (Ditesco)
CH2M Hill Reference Check
By Erika Keeton, Special Projects Engineer
Per phone conversation 6-8-2012: Tracey worked with Keith on quite a few state funded
controlled maintenance projects. Keith managed a large sanitary sewer project totaling
$1.3M. This included design and construction management of C-basin, a 3 year 3 phase
project. Tracey stated Keith understands the state system very well. CSU utilized Keith as
the engineer and project manager, and he managed all aspects of the project. Keith
designed the project, managed the contractor, and provided all contract administration.
He has also managed a variety of other non -civil projects as the project manager. Tracey
indicated Keith works extremely well with CSU, and looks out for CSU as the client. He
holds the Contractor to the contract, keeps CSU's best interests at heart, yet tries to
maintain a group relationship. There have been no problems on any of the projects.
Keith stands behind his word. He found an issue with a lift station pump and covered the
cost of repair even when the project was out of warranty. He felt it was missed during
design and wanted to make it right. His paper work is always timely, and he keeps VERY
good records and photo documentation. At the end of a project Keith provided complete
documentation in whatever format CSU wanted. His fees were in line with the expected
budget, and he only has asked for more funding when design efforts exceeded 10% of the
design scope. There have been no additional construction administration requests. Tracey
said Keith has a "soft personality" and can work with everybody - but draws a hard line
when needed. He is very personable, and very professional. CSU would definitely hire
Ditesco again.
Matt Robenalt, Executive Director
Downtown Development Authority
19 Old Town Square, Ste 230
Fort Collins, CO 80524
970-419-4381
RE: DDA Alley (Ditesco)
Per Voice Mail 6-7-12: Overall I can tell you we've worked with Ditesco. They were our
Construction Managers on the Montezuma Fuller and Old Firehouse Alley projects, and
also involved during design, development, utility coordination, and construction
management on the West Myrtle Alley last summer. Very, very, high quality group of
folks. Keith Meyer is incredible; we use him regularly today on anything related to civil
engineering or construction management. Ditesco is going to help the DDA prepare bid
documents and specifications for deconstructing the Elk's building because it has
significant engineering components to take it down in a way to preserve the materials for
future use. I think Keith's approach to things is incredible, he's outside the box, and
solution oriented. He has all the right relationships with City Utilities and City
Engineering staff. I know he has been very interested in being involved in the MAX
project and knows it is a very high risk project. He has all the right skills and capabilities
to coordinate with CHM2Hill — the combination of those two groups is what the City is
going to need to manage this project.
2
CH2M Hill Reference Check
By Erika Keeton, Special Projects Engineer
Link Mueller, Project Manager
City of Fort Collins Utilities
700 Wood Street
Fort Collins, CO 80521
970-222-0465
RE: Water Reclamation Facility (Ditesco)
Per phone conversation 6-7-2012: Link said he can't say enough good things about
Keith. Keith works his people hard, but drives himself just as hard. The Mulberry project
is a testament to Keith's attention to detail, but Link was not familiar with the rest of the
team. Mulberry was a $26M construction project. Keith was the Resident Engineer, and
was 95% onsite during 95% of the construction. He adjusted his time accordingly to
manage his business and the project at the same time. He has adequate staff to run the
business in his absence. As Ditesco is the contract engineer for Utilities, Link mentioned
Utilities has light construction planned for 2013/2014 so Keith is available for this
project. "If you let Keith be in charge, it will be a good product."
Phil Washington, CEO
RTD
1600 Blake Street
Denver, CO 80202
303-299-2671
720-323-1762
RE: Gold Line (CH2M Hill)
Per phone conversation 6-11-12: Phil said he knows CH very well, and has worked with
them for a number of years. They did one of RTD's rail line EIS, and did a great job. The
Gold line is part of very unique public private partnership, including FTA. CH was also a
major sub contractor on the NW Rail EIS, and they did a very, very good job on that as
well. Phil has known Dan Heilig for many years, and several other principles. CH is a
great firm, and has done good work for RTD. While RTD does a lot of rail, they are
familiar with BRT (US 36 project) and CH is suited for the work. CH has not performed
CM for RTD lately, but has in the past, and were top notch in that area. Phil
communicates with many other government agencies around the country — and knows his
counterparts are happy with CH's CM work. They provide great public outreach, meet
the dbe goals, and Phil was happy with the overall community impact and small business
involvements. CH has a great track record. CH understands the FTA guidelines, which is
a MUST. The feds don't give you a billion dollars unless you manage it right. CH is
definitely one of the top firms in the industry in understanding federal guidelines and
3
CH2M Hill Reference Check
By Erika Keeton, Special Projects Engineer
federal compliance, including how to approach the feds and grant drawdowns. The
timliness of the EIS allowed RTD to start construction without any delays on their part.
CH orked with RTD well on scope changes, and were flexible when the funding didn't
work out as originally planned. They were very fair when negotiating the change orders.
The project was adequately staffed, and a provision was included to approve any
replacements. RTD has no issues with the staff provided, or any replacements, although
most folks were on the job for the duration. Phil would hire CH again, most definitely.
CH will always be at the top of the list, and will likely be getting more work with RTD
when they find more money. CH is a "First class organization".
Charmaine Knighton, Acting Regional Administrator
FTA Region 8
12300 W. Dakota Ave., Suite 310
Lakewood, CO 80228-2583
720-963-3327
303-229-4058
Per voice mail 6-11-12: Charmaine was uncomfortable providing any information on
CH2M Hill, as they do provide PMO services for FTA.
Ashland Vaughn, PM Gold Line
RTD
303-299-6986
303-944-5369
RE: RTD Gold Line (CH2M Hill)
Per phone conversation 6-1 1-12: Ashland is currently the CM on the Eagle project, and
worked with CH2M Hill on the gold line and east corridor rail projects. CH2M Hill was
the Engineering Project Manager on the gold line, a 12 mile commuter rail project. CH
was contracted to complete the Environmental Impact statement and 30% design. The
project was a 4 year project totaling $18M. CH also completed alternatives analysis and
conducted numerous public meetings large and small. Going forward to the next phase of
Design build, Ashland felt the work done by CH was of greater quality, and superior to
the other companies working on the east corridor. CH's diligence and professionalism
has shown through.
John Spencer was Ashland's direct counterpart on the engineering side of the project.
John was very thorough, diligent, and Ashland enjoyed working with him. They did have
differences on occasion, but easily worked through any issues. The project was FTA
funded and John did the FTA reporting/tracking, and provided support and delivery of
various stages, but more on the engineering side. The last FTA submission was 6 dvd's of
4
CH2M Hill Reference Check
By Erika Keeton, Special Projects Engineer
information and FTA actually complained it was too much information. John has also
performed in a PMO capacity, but not on this project. Everything was submitted to FTA
on time and on schedule, despite a number of curve balls due to railroad real estate deals
that fell through. CH had to re -design the alignment based on field negotiations, and was
still able to meet all requirements. Dan Heilig was a consultant for RTD, and Ashland
actually worked for Dan for a short time. He said Dan has always been a solid individual.
Ashland felt CH is qualified for this type of work, and although his project was design, he
felt the responsibilities were similar. CH is very conscientious, very organized, and
would have no problem with performing CM duties. There were scope changes, and these
were pretty easy to negotiate. CH bent over backwards to re -negotiate — and actually
came in under budget despite 4 or 5 significant changes. The project included 4
jurisdictions, and regular meetings were held with stakeholders. CH was very good
working with those folks and communicating on a professional level. Ashland would hire
them again — definitely. Staffing levels were adequate. He said he was very happy with
their performance would love it if CH2M Hill was on the current project.
Paul Price, Executive Director
Napa County Transportation and Planning Agency
707 Randolph St., Suite 100
Napa, CA 94559
707.259.5634
RE: Sosocol Gateway Transit Center, Napa County, CA
WRONG NUMBER
Mike Allegra, General Manager
Utah Transit Authority
669 West 200 South
Salt Lake City, UT 84101
801-243-5082
RE: University Line and Medical Center Light Rail Transit Extensions, Utah Transit
Authority
Left Message 6-7-2012
Joe Gildner, Executive Project Director
Sound Transit
401 Jackson Street
R
CH2M Hill Reference Check
By Erika Keeton, Special Projects Engineer
Seattle Washington, 9104
206-398-5394
RE: University Link Light Rail Transit Extension Construction Management, Sound
Transit, Seattle, WA (CH2M Hill)
WRONG NUMBER
Questions:
1. Scope of this project:
2. Is the MAX project suitable for their abilities? FTA?
3. What are your thoughts on the company?
2. Did you work directly with the following people (Keith Meyer, John Spencer, Dan
Helig, Tim Hackworth)? If so what are your thoughts on each one? Was there much
turnover in staff during your project?
3. How would you rate the consultants supervision, reporting, budgeting on the project?
4. How would you rate the Consultants ability to perform according to the contract
documents?
5. How would you rate the Consultants willingness/ability to work with your staff in
carrying out the intent of the contract documents? (Excellent, Average, Very Poor)
6. Approximately how many scope changes/change orders requests did the Contractor
submit?
7. What was the final change order to contract value ratio? (Le., change order dollars
compared to original contract value.)
8. Did you have difficulty obtaining documentation for change order requests?
9. Did the consultant have adequate staff and equipment to perform the work?
10. Did the consultant turn in paperwork in timely manner?
11. Did the consultant communicate well with all project stakeholders?
12. Would you hire them again?
Jeff Mack
CH2M Hill
CM Lead
Joe Biedenbach
CH2M Hill
Maint. Facility Lead
Wayne Gilles
CH2M Hill
Safety and Security
City of Fort Collins
Program Manager
(City Engineer)
Erika Keeton
City of Fort Collins
Project Manager
Dan Heilig
CH2M Hill
Project Principal
FTA Compliance Officer
Keith Meyer
Ditesco
Construction Project Manager
Jon Spencer
CH2M Hill
Asst. CM Document Control
Jill Colasuonno
Ditesco
Office/Field Engineer
Diana Yust
CH2M Hill
Financial Coordinator
Willie Franklin
CH2M Hill
DBE Admin
Beau Javernick
Ditesco
Estimator/Scheduling
Sandy O'Brien
COFC Financial
Coordinator
Terry Tyrrell
AECOM
Consultant Project I
General Contractor
QA Testing
Firm
FHU
ALM
Tim Hackworth
CH2M Hill
Asst. CM Inspection
Ron Kechter
City of Fort Collins
Project Manager (STC)
Tracy Dyer
City of Fort Collins
Chief Inspector
George Latour ■■ Chip Leadbetter
COFC Senior CTL Thompson
Inspector Project Principal
TC Bohnet Heather Grubb
COFC Inspector CTL Thompson
NoField Manager
Kari Craven Craig Ellis
COFC Inspector CTL Thompson
Field/Lab Supervisor
TBD Jeff ODell
LS Gallegos CTL Thompson
Inspector MTT
Raymundo Leon Jack Pappert
LS Gallegos CTL Thompson
"dVfMTT
un
pson
CONTRACT CHECKLIST FOR COMPETITIVE PROPOSALS
RFP No./Title: 7390 CONSTRUCTION MANAGER FOR MAX BRT PROJECT
Checklist Item
Contract File
Comments
Location
7) Independent Cost Estimate
yes
The City made and documented an
independent cost estimate before receipt of
proposals.
9) Unreasonable Qualification
NO
Requirements This solicitation did not contain
unreasonable requirements placed on firms in
order for them to qualify to do business.
10) Unnecessary Experience and
NO
Excessive Bonding
Unnecessary experience and excessive
bonding requirements were not included in
this solicitation or contract documents.
11) Organizational Conflict of
NO
Interest (OCI)
If there is an apparent or potential OCI the
solicitation contains provisions to eliminate or
mitigate the conflict (e.g. by inserting a clause
that prohibits the contractor from competing
for the follow-on contract to the current design
or research contact) and OCI Certification is
submitted by the contractor.
12) Arbitrary Action
CORRECT
There was no arbitrary action in the
procurement process. (An example of
arbitrary action is when award is made to
other than the contractor who most satisfied
all the City requirements as specified in the
solicitation and as evaluated by staff.
13) Brand Name Restrictions
NOT APPLICABLE
Brand Name or Equal. When it is impractical
or uneconomical to provide a clear and
accurate description of the technical
requirements of the property to be acquired, a
"brand name or equal" description may be
used to define the performance or other
salient characteristics of a specific type of
property. The City must identify the salient
characteristics of the named brand that
offerors must provide. When using a "brand
name" specification, the City does not need to
reverse -engineer a complicated part to
identify precise measurements or
specifications in order to describe its salient
characteristics. FT A's "Best Practices
Procurement Manual," (BPPM) contains
additional information on preparation of
specifications including examples with
specific language.
14) Geographic Preferences
NO
The solicitation contains no in -State or local
geographic preference except where Federal
statutes mandate or encourage them.
�rof
tfins
hourly rate estimation purposes, including those of AECOM and FHU. The rates provided by CH2M Hill
are comparable to the rates used in the ICE, and are reasonable for these services.
CH2M Hill is adequately staffed and skilled to perform the work, and I recommend entering into a
contract for $3,835,369.
Please find attached the following supporting documents:
• Original ICE
• Initial fee proposal
• Final fee and scope proposal
2
15) Contract Term Limitation
YES PROFESSIONAL
The contract period of performance for rolling
SERVICES AGREEMENT
stock and replacement parts does not exceed
five (5) years inclusive of options without prior
written FTA approval. For all other types of
contracts, the procurement file contains
evidence that the contract term is based on
sound business judgment.
16) Written Procurement Selection
YES
Procedures
The City has written selection procedures and
the solicitation also identifies all requirements
that offerors must fulfill and all other factors to
be used in evaluating bids or proposals.
17) Solicitation Prequalification
NO
Criteria
The solicitation required prequalification of
persons, firms, or products. The list is current
includes enough qualified sources to ensure
maximum full and open competition, and
potential bidders are not precluded from
qualifying during solicitation period from
issuance of the solicitation to its closing date.
If the solicitation does not contain a
prequalification requirement, check NA.
18) Award to Responsible
1. Yes
Contractor
2. Yes
The City made a determination that it was
3. Yes
awarding to a responsible contractor
4. Yes
considering such matters as contractor
5. Yes
integrity, compliance with public policy, record
of past performance, and financial and
technical resources.
Please see reference
1. Appropriate Financial, equipment, facility
checks that were positive
and personnel. (Y/N)
2. Ability to meet delivery schedule. (Y/N)
3. Satisfactory period of performance. (Y/N)
4. Satisfactory record of integrity, not on
declined or suspended listings. (Y/N)
5. Receipt of all necessary data from
vendor. (Y/N)
19) Sound and Complete Agreement
YES
This contract is a sound and complete
agreement. In addition, it includes remedies
for breach of contract and provisions covering
termination for cause and convenience.
24) Clear, Accurate, and Complete
YES
Specification
A complete, adequate, and realistic
specification or purchased description was
available and included any specifications and
pertinent attachments which define the items
or services sought in order for the bidder to
properly respond.
25) Two Bidders
We had 3 proposals
Two or more responsible bidders were willing
and able to compete effective) for the
business.
26) Firm Fixed Price
yes
A firm fixed price contract was appropriate for
this procurement.
29) Advertising
Yes...Coloradoan and Daily
The Invitation for Bids was publically
Journal 2 times each
advertised.
30) Adequate Number of Sources
FROM BUYSPEED VENDOR
Solicited
SYSTEM
Bids were solicited from an adequate number
of known suppliers.
36) Evaluation
STANDARD RFP RATING
A method is in place for conducting technical
evaluations of the proposals received and the
solicitation has evaluation factors identified
along with their relative importance.
37) Price -and Other Factors
YES Price only considered after
For this procurement, award was made to the
selection of highest ranked firm.
responsible firm whose proposal is most
advantageous to the grantee's Program with
rice and other factors considered.
40) Evaluation of Options
YES
The option quantities or periods contained in
the contractor's bid or offer were evaluated in
order to determine contract award. (To be
eligible for Federal funding, options must be
evaluated as part of the price evaluation of
offers, or must be treated as sole source
awards.
41) Cost or Price Analysis
Yes from Erika dated 6-28-12
Either a cost analysis or a price analysis was
performed and documented. The price was
determined to be fair and reasonable.
42) Written Record of Procurement
1) Yes City standard procedure is
History
to use RFP process for A&E
The file contains records detailing the history
selection.
of this procurement. At a minimum, these
2) Yes
records include:
3 ) Yes
(1) the rationale for the method of
procurement,
4) negotiated from $4,731,122 to
(2) Selection of contract type,
$3,835,369
(3) reasons for contractor selection or
rejection, and
4 the basis for the contract price.
43) Exercise of Options
NA
The grantee exercised an option on this
contract adhering to the terms and conditions
of the option stated in the contract and
determined that the option price was better
than prices available in the market or that the
option was a more advantageous offer at the
time the option was exercised.
If an option was not exercised under this
contract, check NA.
44) Out of Scope Changes
NA
The grantee amended this contract outside
the scope of the original contract. The
amendment was treated as a sole source
procurement (complying with the FTA
requirements for a justification, cost analysis
and profit ne otiation .
45) Advance Payment Provisions
NO
The contractor did not receive an advance
payment utilizing FTA funds and the contract
does not contain advance payment provisions
or, if it did, prior written concurrence was
obtained from FTA.
46) Progress Payment Provisions
YES
The contract contains progress payments
based on costs incurred (as opposed to
percent of completion) and the contract
contains a provision giving the grantee title to
property (materials, work in progress, and
finished goods) for which progress payments
are made. The contract may contain other
security in lieu of obtaining title.
47) Time and Materials Contracts
no
This is a time and materials contract; the
grantee determined that no other type of
contract is suitable; and the contract specifies
a ceiling rice.
48) Cost Plus Percentage of Cost
no
This is not a cost plus a percentage of cost
type contract.
49) Liquidated Damages Provisions
NO
This contract contains liquidated damages
provisions and the assessment for damages
is specified in the contract at a specific rate
per day for each day of overrun in contract
time.
50) Piggybacking
NO RFP PROCESS
1) The file contains: Assignability provisions.
2) The procurement file contains: Price
reasonableness determination.
56) Clauses
YES
This contract contains the appropriate FTA
required clauses.
Exclude Parties Search
yes
EPS run and include in the file
SUPPLEMENT
FOR ARCHITECT & ENGINEERING SERVICES
Checklist Item
Contract File
Comments
Location
8) A&E Geographic Preferences
yes
Geographic location is not a selection
criterion or it is a selection criterion and its
application leaves an appropriate number of
qualified firms, given the nature and size of
the project, to compete for the contract.
51) Qualifications Exclude Price
Yes
The City evaluated the offeror's qualifications
and excluded price as an evaluation factor.
52) Serial Price Negotiations
yes
The City conducted negotiations with only the
most qualified offeror and failing agreement
on price would conduct negotiations with the
next most qualified offeror until contract
award could be made to the most qualified
offeror whose price is fair and reasonable to
the grantee.
Excluded Parties List System
Page 1 of I
Search - Current Exclusions EPLS Search-1 Resources
>Advanced Search
> Multiple Names
> Exact Name and SSN/TIN
> MyEPLS
> Recent Updates
> Browse All Records
View Cause and Treatment Code
Descriptions
> Reciprocal Codes
> Procurement Codes
> Nonprocurement Codes
Agency & Acronym Information
> Agency Contacts
> Agency Descriptions
> State/Country Code Descriptions
OFFICIAL GOVERNMENT USE ONLY
> Debar Maintenance
> Administration
> Upload Login
Search Results for Parties
Excluded by
i
Firm, Entity, or Vessel : CH2M Hill
State: COLORADO
Country : UNITED STATES
CT Code : E (Procurement)
As of 05-Jul-2012 6:28 PM EDT
Save to MyEPLS
Your search returned no results.
Back New Search Printer -Friendly
> Search Help
>Advanced Search Tips
> Public User's Manual
>FAQ
> Acronyms
> Privacy Act Provisions
> News
System for Award Management
> (SAM)
Reports
I
i
>Advanced Reports
> Recent Updates
> Dashboard
Archive Search - Past Exclusions
>Advanced Archive Search
> Multiple Names
> Recent Updates
> Browse All Records
Contact Information
> For Help: Federal Service Desk
https://www.epls.gov/epls/search.do 7/5/2012
Account#: 003450
l..C)LO cRADOAN
Invoice Text NOTICE Proposals will be received by the
NOTICE
Proposals will be recefved by the City of Fort
Collins at the office of the Purchasing Division,
215 North Mason 2nd Floor, Fort Collins, COIo-
redo until 3:00 P.M. our clock on May 23, 2012
for the Construction Manager for MAX BRT
Project, Bid Number 7390.
The Scope includes overseeing, asssting and
advising the City of Fort Call in an phases of
the project, as it relates tp construction,man-
_ agement of the MAX BRT project, ensuring de-
livery of the project on time and on budget in
accordance with local, state and federal re-
quirements. Work includes geotechnical engi-
neering and testing services, inspection serv-
ices, project reporting to varlous governmental
agencies as it relates to construction including
the Cry Of Fort Collins, Federal Transit Adminis-
tration, and the Colorado Department' of
Trensportatlon. For more information tail (970)
221-6775 or download a copy of RFP Number
I7390 at www.fcgov.com/eprocurement.
James B, O'Neill II, CPPO, FNIGP
Director of Purchasing & Risk Management
May 2, 2012
STATE OF COLORADO )
) ss: AFFIDAVIT OF PUBLICATION
COUNTY OF LARIMER )
Andrew Troncoso , being duly sworn, deposes and says that said is the legal clerk of the Fort
Collins Coloradoan; that the same is a daily newspaper of general circulation and printed and
published in the City of Fort Collins, in said county and state; that the notice or advertisement, of
which the annexed is a true copy, has been published in said daily newspaper for
2 Non -Consecutive Days;
that the notice was published in the regular and entire issue of every number of said newspaper
during the period and time of publication of said notice, and in the newspaper proper and not in (
supplement thereof; that the first publication of said notice was contained in the issue of sait
newspaper on
Monday, May 7, 2012
that the last publication thereof was contained in the issue of said newspaper on
341BB475
Ft. Carl Coloradoan
May7,14, 2012 Monday, May 14, 2012
that said Fort Collins Coloradoan has been published continuously and uninterruptedly during thi
period of at least six months next prior to the first publication of said notice or advertisemen
above referred to; that said newspaper has been admitted to the United States mails as second -clan
matter under the provisions of the Act of March 3, 1879, or any amendments thereof; and that saif
newspaper is a daily newspaper duly qualified for publishing legal notices and advertisement.
within the meaning of the
Legaht ter L. C
I �� ....... �t��
....�0
Subscribed and sworn to before me, within the County of Larimer, State of Colo
e' R Z
rndBthisNOTAY —
Monday, May 14, 2012 /1 = m `•, PUBLIC =
My Commission expires: ,l LLB � z(i 9p�................�QO
�OF
Er�Ores °ti16'
Notary Public
Legal No.0034188475
Delivered to:
CITY OF FC-PURCHASING-LEGAL,
Affidavit Prepared
PO BOX 580 Monday, May 14, 2012
FORT COLLINS, CO 80522-0580 9:20 am
C6MSIR6CT OII Regional Publications INVOICE
TEAR SHEETS 1
REMIT TO: THE MCGRAW-HILL COMPANIES
75 REMITTANCE DRIVE SUITE 3085
CHICAGO, IL 60675-3085
BILL TO:
CITY OF FORT COLLINS
BETH DIVEN
P 0 BOX 580
FORT COLLINS CO 80522
INVOICE #A333220 01
ACCOUNT # A30027004
INVOICE DATE 05/17/12
INQUIRIES TO:
TEL 800-648-3045 FAX 609-426-7143-;':,
ADVERTISER/AGENCY:
5/14/12 DENVER DAILY JOURNAL FULL RUN
3 X INCHXICOLUMN
071522301 OFFICIAL PROPOSAL 1 X RATE 153.60
BID#7390 RFP-CONSTRUCTIO
5/7/12 5/14/12
1DVOE5
TOTAL FOR JOB 071522301 153.60
BILLING TERMS: TOTAL 153.60
PAYMENT IN FULL DUE SALES TAX/VAT
UPON RECEIPT OF INVOICE _.
The MCGraw•Hill Companies
0.00
153.60
153.60
C9NssTRuaIONRegional Publications INVOICE TheMCGrpw•HillCompanies
FEDERAL EIN 13-1026995
REMIT TO: THE MCGRAW-HILL COMPANIES DATE05/17/12 ACCOUNT#A30027004 INVOICE# A333220 01
CHARGE MY CREDIT CARD. (CIRCLE ONE)
75 REMITTANCE DRIVE SUITE 3085 VISA MASTERCARD AMERICAN EXPRESS
CHICAGO, IL 60675-3085
CARD # EXPIRE DATE
SIGNATURE
PLEASE DO NOT WRITE IN SPACE BELOW CITY OF FORT COLLINS
BETH DIVEN
P 0 BOX 580
FORT COLLINS CO 80522
A30027004A33322001000015360
TO INSURE PROPER CREDIT, INDICATE ACCOUNT NUMBER ON CHECK. TOTAL AMOUNT DUE I- AMOUNT ENCLOSED
AR233M
RETURN THIS PORTION WITH PAYMENT IN U.S. DOLLARS DRAWN ON U.S. BANK.
153.60
comm'Ir"1MRegional Publications AFFIDAVIT
INVOICE # A333220 01
ACCOUNT # A30027004
INVOICE DATE 05/17/12
INQUIRIES TO:
TEL 800-648-3045 FAX 609-426-7143
ADVERTISERIAGENCY:
BILL TO: CITY OF FORT COLLINS
BETH DIVEN
P 0 BOX 580
FORT COLLINS CO 80522
The MCGraW,Hil! Companies
PUBLICATION: DENVER DAILY JOURNAL
STATE OF COLORADO
COUNTY OF DENVER
I, DOTTY MONTANTI, OF THE CITY AND COUNTY OF MERCER, STATE OF NEW JERSEY,
HAVING DULY BEEN SWORN, DEPOSES AND SAYS:
I AM NOW AND AT ALL TIME HEREINAFTER MENTIONED A CITIZEN OF THE UNITED STATES
OF AMERICA, OVER TWENTY-ONE YEARS OF AGE, AND COMPETENT TO BE A WITNESS ON THE
HEARING OF THE MATTERS MENTIONED IN THE ANNEXED PRINTED COPY NOTICE HEREINAFTER
SET FORTH; I HAVE NO INTEREST WHATSOEVER IN ANY OF THE SAID MATTERS; I AM NOW
AND DURING ALL TIMES EMBRACED IN THE PUBLICATION HEREIN MENTIONED WAS THE
CHIEF CLERK OF THE NEWSPAPER, A NEWSPAPER OF GENERAL CIRCULATION PRINTED AND
PUBLISHED IN SAID CITY AND COUNTY; AS CHIEF CLERK DURING ALL TIME MENTIONED
IN THE AFFIDAVIT I HAVE HAD AND I STILL HAVE CHARGE OF ALL ADVERTISEMENTS AND
NOTICES PUBLISHED IN SAID NEWSPAPER; THAT SAID LEGAL NOTICE OF WHICH THE
ANNEXED IS A TRUE PRODUCTION COPY OF THE PRINTED PAGE IN WHICH THE ADVERTISEMENT
WAS PUBLISHED IN THE ABOVE NAMED NEWSPAPER ON THE FOLLOWING DAYS TO WIT:
BID#7390 RFP-CONSTRUCTIO - 5/7/12 5/14/12
I CERTIFY (OR DECLARE) UNDER PENALTY OF PERJURY THAT THE FOREGOING IS TRUE AND
CORRECT.
SIGNED
CHIEF CLERK
AF233B
Ink MITERI CMI M"37-3a59
W.I. Mey 14, 2012 L'?%:17.r Jr+r. 16
OFFICE THE STATE
. STATEUI THE STATE ARCHITECT
STATE BUILDINGS PROGRAMS
NOTICE OF CONTRACTOR'S SETTLEMENT
In.jrurinrr/ARmry Arapahoecnomtmiycanlepe
NOIue NumMr ACC 2-12
ProjectNo/Doe: MO`IWB Replace Energy Management
Control System
Nm . thereby fi—An thanon 1111112 ar I nd's a Cnlemdo
final setrlemmt will be made by the SiAll! OI COEORADE
with h.rei nafter, rated tit
'CI1NI Mlal11'. lm ran ran amount,d l he.n,nart far lh
1. saw:rn e
or med b
noIf abm
2. All such claims shall be filed with the Act for
Wlt lnsimlian. De a urn <
Pr Rnry.
3. failure on their of a ednona file such nm neT0,
1. such final Acrohmom mwill relieve the State of Cl,AJr
o
form my and all liability formrh claim
Authorized NeUlry Minister or AuNorlud IndMdual
Name: I.K. Cady
Approval Date : ;spanoe Community College
hi
}3hm ro iliam
EmmiP. IOM1n Wady®ampah« edo
Post— airy] 414. se" Arsenio
DENVER HEALTH
AND HOSPITAL AUTHORITY
REQUEST FOR QUALIFICATIONS NO. 280A
hesitate. 10 Submit Qualificrtlon. roe Architectural
SeMm: Denver llalih h liespjtal Auction, (DIIIIA) is
seeking Arrhlteaunl/Oi s.rnm hn me ten, in remodel
the Inwry I ly Pmajce Center (LFI'C), located ar 1001
Yosemite Sueet Denver, Co
A rosy of the Rrqued for Qualifications on ber obtained by
mailing lion Sangster at tom sangver®dhhs or, or calling
303-602.2102. A miry will be .mailed to you.
Palmated Can of Design and C.smteucnlen: lb, current
bud, for frjs work indud ti, design, all permitstestingg and
rosy (including themma). is tin million dollar
S lo.o00A00)
score DeresiA Hansa will shes list firma deemed to he bat
qualified. The short I .... it firms will be provided an UP.
,lam At Specification and and ed m Omiddle. bid price
RIQ DeadBee.aire Closing Date Cut tact M" Qualification'
is May 25, 2012, 2:o0PM, MT, in the llrdtavng DepanmenL
located At ]A Delaware Sven, D[nne, Colorado 80204
Rap1npnto this Reeuna for Qualifiation must be delivemd
to the purchasing Depmorem rely and received by titl
and dart indicated ahosre.
MBE/WBE Participation:'Ihe Denver Ilealth and Hospital
AuNomY isovid limit, committed 1. pron, o,pmlo una lot
the pam[i�minn of Minority and Women Owned business
•minconstructionerpris s its construction and pmYesi mtal design sconce
..trans. the goal for MBE/WBE pamctpalon for this Projm
is 15%(fifteen).
Mry Mead mWre a reauh ill this .111 Yiall l`eitain u lely I i
riseneeds of DIIIIA Cenral telephone inquirer re,Arding
djonn It. math tan be d. ed u, Denver HealA I'urdraing
OF e, TA. GngslrL Purchasing Manager, (303) 602-]I0].
webrarn.n Darr, sa ,Isar r"noI tram
N1WESYOU`R\,
I♦M ��^
INESsr-S NEED A
N
ADVERTISE IN
L
Dail The
'�. Uournal
13
' 703
rhill.com
r
Thompson School Divcjn R2-) will acceppt bids for of
rrylamnr<m I'm" Mandatory walk enti s begin it 900
ram., Mnndnp May 14.
Submittal, will be acceprd until 2-.00 pm. Tuesd,sy. May 29,
2ol2 and sno ild be sulmon eJ in
ThrmPum School Dianna U I
Doalmma at
th nN)w:.w nnm n k 2 m �ID'n=
hi-Ifinfiross bnicef
�f "n"dry nA`hrml �Es
Pnblirauon DanMay 10. 11614. 20" IEISBB
4
GRO
Invitation for Bid
Sealed Bids will be accepted by the City of Aurora
Purchasing Department until MAY 30. 2012 at 2:7$Im
for the Animal [neber nllido,, Kennel Meo. pride
15181A. Central Contractors have been...qualified
4e is.. palm. Dewitt; and gpenfiarinnA arc.mnilaMe
for $25.00 per CD in the purchasing Deparint at
15151 Fast Alameda Parham, Suite 3500, 303-739-7100,
For additional information please go to
w anihisis com and select Rocky Mountain
if Purrh,Wng System.
1'ubli.atinn Date: MAY 14, 2012 1 F02IYA
Reauest for Pr000sals
Pmpn,da win be rmi.N by drt]ry of rim tuilim it 0re•fi of
the ILMIarinR I)ivi un4114 µ,TN Maim 2nl 0—r. rim famjna
Colorado until 300 PM, n r dn4 on May D. 1012 for the
Umnurvon Manager Tar MAX BRT rental Bid Numbc 73.
The Smyr includes women, avudr, and Assume the Gry of
Fora Gdlins in a0 phase of the pmlm As it roan in, mmouruun
n,, umt rah do, MAX All pin ec. enumnR delhvry of the
omtm on Anne anti on Mohr in.rm d.an, sift local, rule Aral
Colorado Department of Tmnspnwdnn. For more -of rmation'
rall (AM) III 6]]5 or dlorniond a mq of Nnmbe 7390 at
waoretwvm /ep
lama n O Neill flCAM, FN1eP
DirrAA fPurrha' R h Rik Managanail
.MAY 2. 2012
Publ n x,n Forei .Puny ] a tar 2nl2 Iment
THE DAILY
JOURNAL
♦ Construction Notices
♦ Legal Notices
♦ Classified Ads
For Next Day Publication
Call
Ph:888-814-0513 or
Fax:888-478-7703
Independent Consultant Cost Estimate: RFP 7390 Construction Management for MAX BRT Project
MAX Project Construction Management and Administrative
Title
Name Organization Responsibility
Date 5/1612012
Hours f Duration Rate I Lump Sum
Month (Months) Hour
Total
Project Construction Manager
TBD
Consultant
Coordinates all construction and administrative related activities
120
20
$
190
$ 456.000
Assistant Project CM
TBD
Consultant
Assists CM with all construction and administrative related activities
155
20
$
150
$ 465,000
Scheduling
TBD
Consultant
Maintains clos loaded schedule for all project components
40
20
$
150
$ 120,000
Financial Coordinator (Consultant)
TBD
Consultant
Consultant financial administrator
80
20
$
150
$ 240,000
DBE Administrator
TBD
Consultant
Coordinates DBE administrative requirements, such as Davis Bacon and document
40
18
$
100
$ 72,000
control
Project Management Support -
TBD
Consultant
Performs independent cost estimates, change order documentation, insurance,
Estimator
bonds, pay applications
g0
18
$
150
$ 216,000-
Senior Inspector
TBD
Consultant
Manages and inspects construction activities for BRT/Guideway, including private
155
19
$
130
$ 382,850
utility relocations
Geolechnical & Material Testing
TBD
Consultant
Provides all materials testing for the project (budget located in separate SCC budget)
$ 1,222,000
$ 1,222,000
(3 / of Construction Cost Q $40M)
Inspector
TBD
Consultant
Daily inspection of guideway and structural elements, quantity measurements, and
155
18
$
75
$ 209,250
criteria compliance.
Inspector
TBD
Consultant
Daily Inspection of guideway and structural elements, quantity measurements, and
80
12
$
75
$ 72,000
criteria compliance.
Outside Direct Costs (5%)
_
$ 172,755
Total
Completed By: Erik R. Keeton, Special Projects
$ 3,627,855
Fee Estimate 6-15-12
Prime risk
HOURS
LABOR COST
EXPENSES
TOTAL
FEE on Subs
TOTAL
PERCECTAGE
5%
Contract COST
CH2M HILL, Inc. 12,122
$
1,927,604
$
329,807
$
2,257,411
$ -
$
2,257,411
56%
Ditesco 9,488
$
1,184,440
$
11,844
$
1,196,284
$ 59,814
$
1,256,098
30%
LS Gallegos 5,800
$
459,571
$
84,460
$
544,031
$ 27,202
$
571,233
13.6%,DBE percentage
subtotal 27,410
$
3,571,615
$
426,111
$
3,997,726
$ 87,016
$
4,084,742
:DBE target 11%
CTL Thompson lab and
testing costs 8,436 $ - $ - $ 615,600 $ 30,780 $ 646,380
total cost 35,846 $ 3,571,615 $ 426,111 $ 4,613,326 $ 30,780 $ 4,731,122
5.44%
project cost $ 87,000,000
Fee Estimate 6-27-12
Prime risk
HOURS
LABOR COST
FEE CH2M HILL
EXPENSES
TOTAL
FEE on Subs
TOTAL
PERCECTAGE
4%
Contract COST
CH2M HILL, Inc.
10,022
$ 1,380,164
$ 165,620
$ 254,951
$ 1,800,735
$ -
$ 1,800,735
58%
Ditesco
5,820
$ 860,300
$ -
$ 8,603
$ 868,903
$ 34,756
$ 903,659
28%
LS Gallegos
4,320
$ 345,016
$ -
$ 64,460
$ 409,476
$ 16,379
$ 425,855
13.3%
DBE percentage
subtotal
20,162
$ 2,585,480
$ 165,620
$ 328,014
$ 3,079,114
$ 51,135
$ 3,130,249
DBE target 11%
CA Testing
$ -
$ -
$ -
CTLThompson lab and
testing costs
9,252
$ -
$ -
$ 678,000
$ 678,000
$ 27,120
$ 705,120
total cost
29,414
$ 2,585,480
$ 165,620
$ 1,006,014
$ 3,757,114
$ 78,255
$ 3,835,369
$ 3,757,114
4.41%
project cost
$ 87,000,000
1 $ 243,875
Exhibit A
Scope of Work and Fee Proposal
forthe
Mason MAX BRT Protect
Project Construction Management Services June 17, 2012 thru April 30, 2014
Understanding
The City of Fort Collins is pursuing construction of a Bus Rapid Transit project along the Mason Corridor from south of Harmony
Road to Cherry Street in Fort Collins, Colorado. The project is funded through multiple local sources with primary funding
coming from the Federal Transit Administration Small Starts Program. The project includes a new guideway, multiple bridge
structures, stations, retaining walls, earthwork, paving, freight rail reconstruction and site restoration. The project also includes
a new bus maintenance facility, transit center and pedestrian crossing structures.
The project has been designed by multiple consultants working for the City including Michael Baker Inc., Aller Lingle Massey,
and other subconsultants. Various parts of the project including the main BRT guideway have been bid and are in various
stages of review and award. For the various construction parts, the City is anticipating approximately $40 million in construction
value with an overall project budget of $87 million.
As the project proceeds to the construction phase, the City desires to supplement its existing workforce with specific expertise to
assist in the project construction management, contractor oversight, quality assurance and quality control testing for the project.
Specifically, this contract covers the MAX BRT, South Transit Center and Bus Maintenance Facility construction management.
Construction Scope of Work
The MAX Bus Rapid Transit (BRT) project is a proposed north -south BRT system in the central core of the City of Fort Collins,
Colorado. The MAX BRT is located just west of and parallel to College Avenue (US 287), one of the busiest arterials within the
City and the entire North Front Range region. The project corridor extends from Cherry Street on the north, to approximately'/<
mile south of Harmony Road, with a total length of five miles.
The project contains three main components that include: the Mason Corridor, the South Transit Center and the Maintenance
Facility Expansion. The Mason Corridor is proposed within an exclusive guideway for 2.8 miles, with the remaining 2.2 miles
intermixed with street traffic on portions of McClelland Drive and Mason Street. Additionally, there are two bridge structures and
multiple retaining walls along the MAX BRT route as part of this project. Components also included in the Mason Corridor
portion of the project are: signing and striping, intersection improvements, various utility improvements, thirteen stations and
stop locations, landscaping, irrigation, traffic control, and guardrail installation. The South Transit Center comprises of a 4,300
square foot transit center, complete with related site work, landscaping, parking and driveways. The Maintenance Facility
Expansion includes construction of a 16,240 square foot addition to the existing building, an approximately 65,620 square foot
concrete driver training area, and a 680 square foot addition to the Chassis Wash Facility, plus minor interior and exterior
renovations.
Along the entire length of the corridor, the BRT runs parallel to existing Burlington Northern and Santa Fe (BNSF) Railway
tracks. At varying locations, the BRT system is proposed within a combination of properties owned by the BNSF, the City of Fort
Collins, Colorado State University (CSU), and private land owners which will require extensive coordination efforts. It is
anticipated that the MAX BRT service will begin operation in the first quarter of 2014. The BRT project includes the Mason
Corridor construction plans provided by Michael Baker Jr, Inc. and the South Transit Center and Maintenance Facility
Expansion plans provided by Aller Lingle Massey Architects P.C. Reference to the MAX BRT incorporates the Mason Corridor
South Transit Center and the Maintenance Facility Expansion.
Primary Scope of Work Goalsfor Proiect Construction ManagerServices
Page 1 of 6
• Oversee, assist, and advise the City of Fort Collins in all parts, as it relates to construction management of the MAX
BRT project, ensuring delivery of the project on time and on budget in accordance with local, state and federal
requirements.
• Evaluation and selection of contractor bids if not already awarded and pending bid phase development.
• Horizontal and vertical construction inspection services that coincide with construction delivery schedules developed by
multiple general contractors.
• Quality Control--Geotechnical engineering and construction material testing services for horizontal and vertical
construction (by CTL Thompson).
• Environmental oversight for hazardous material removal and mitigation.
• Financial oversight and budget management.
• Project reporting to various governmental agencies as it relates to construction including the City of Fort Collins,
Federal Transit Administration, and the Colorado Department of Transportation.
• Coordination and collaboration with local businesses/property owners, community stakeholders, local organizations
and authorities including Colorado State University, the Downtown Development Authority, and the Burlington Northern
Santa Fe Railway Company (BNSF).
• Oversight of completion of punch list items, project close-out activities, start-up, testing, commissioning and initial
phases of operation.
Scope of Work
Our consultant team will provide overall project construction management support services in conjunction with the City of Fort
Collins team. We will integrate our services with those provided by the City to form a cohesive management team. The
services summary will include:
Preconstruction Phase
• Participation in a formal partnering session with project team members such as the City, contractor and third party
agencies.
• Potential constructability review of existing or proposed plans for various parts of the project.
• Document management organization including preparation of a SharePoint site accessible by all team members.
• Participation in value engineering sessions as applicable to various project parts.
• Coordination, management and attendance for preconstruction meetings for various project parts.
Construction Phase
• Financial and budget management providing monthly billing reports and periodic reports as required by the City of Fort
Collins, the FTA, and CDOT. Our team will develop, analyze, and prepare monthly cash flow reports and forecasts for
the project; advising of variances between actual and budgeted or estimated costs. We will prepare, at least monthly,
contractor earned value reports; monitor contractor payroll compliance; and track, verify and document compliance
with the Davis Bacon Act, DBE requirements and DBE goals.
• Contract document compliance including construction material quality assurance, control and inspection services.
Provide review and approval of contractor supplied pay applications, project schedules and close out documentation.
Page 2 of 6
• Management of construction progress meetings; specialized individual meetings to coordinate third party work and
other professional services. Provide meeting minutes for each through City or consultant supplied personnel.
• Detailed construction inspection to supplement City personnel including maintaining photographic logs, written daily
construction reports, record drawings documenting as -built plan changes. Construction inspection efforts are expected
to include structural foundation, wall, bridge substructure and superstructure, vertical building, structural steel,
reinforcing steel, masonry, earthwork, paving (concrete and asphalt), flatwork and adherence to approved TCPs/MHTs.
• Quantity take -offs and unit pay item verification; prepare independent cost estimates for cost analysis to contract
changes.
• Analysis of the project schedule and budget with advice on necessary changes or modifications to each, at monthly
intervals or more frequently.
• Communication liaison to the public, various boards, commissions, City Council and contractor's construction group in
a partnership role with the City and contractor's PIO.
• Management of the submittal review process including maintenance of submittal review logs (for each project part),
submittal review responses, contractor clarifications on comments, routing of responses, review and document
management of process.
• Management request for information (RFI) process including addressing comments, routing to appropriate design lead
and ensuring responses are received by the contractor in a timely fashion to facilitate construction delivery.
• Construction material testing services including soils, concrete, asphalt, specialty tests, masonry and others as may be
required. All tests will be in accordance with current CDOT and City of Fort Collins testing standards. Specific
reference is made to the current version of the CDOT Field Materials Manual and LCUASS.
• Assistance in the coordination and communication with local agencies, third parties, utility companies and other
stakeholders to ensure their work or interests are addressed within the project schedule and job delivery.
• Management of contract changes including review, analysis, recommendations; preparation of change orders and
document management.
• Record drawing management including tracking jobsite changes, construction details and notes to be used in
preparation of as -built plans. Coordination of contractor record drawings for inclusion in one set of final as built
drawings for the job. Review final record drawings for accuracy and completeness.
• Performing special tests, investigations, or monitoring to fulfill the intent of the FTA, CDOT and the City of Fort Collins
inspection program. Providing special inspections and certify: (i) all construction work performed substantially
conforms to approved construction contract documents, the contract drawings and has been performed in accordance
designated federal, state and City rules and regulations; and (ii) for progress and final inspections, that all construction
work substantially conforms to the approved construction documents and has been performed in accordance with
applicable provisions of the construction contract documents and other designated rules and regulations. Performing
initial, follow-up, and final inspections of work in progress including interim and final measurements for payment.
• Monitoring compliance and initiating action preserving safety on the project for all workers and the traveling public.
Monitoring jobsite for compliance with approved safety and security plans during construction, testing and pre -
operations phases.
• Preparation and delivery, not less than once each month a report addressing progress, problems, issues, and
concerns with respect to the status of the services and the status of any additional services for this contract.
Page 3 of 6
• Management of the permitting process ensuring any necessary contractor obtained permits are identified and procured
according to the delivery schedule. Coordinating and assisting with securing City building permits pertaining to the bus
stop shelters.
• Providing environmental oversight and monitoring as it relates the removal of the PSCO building, and BNSF materials
removal and disposal.
• Oversight, creation and management of construction punch lists including completion of all items to achieve milestone
dates in contract.
• Coordinating and management of delivery, installation, and commissioning of equipment, commissioning processes
and procedures, and the initial start-up and testing of all systems to confirm compliance with specifications.
• Preparation and transmittal of updates to construction activities to the City of Fort Collins Public Information Office.
• Updates to existing FTA required plans (PMP, SSC, etc) as necessary throughout construction delivery for the
Construction Management sections.
Post Construction Phase
• Collection and verification of necessary lien waivers, certificates of payment and consents of surety to release final
payment.
• Management of advertisement and retainage release process coordinated with City personnel.
• Compilation and verification of all job documentation including record drawings for transmittal to City personnel.
• Participation and management of final safety, testing, commissioning and operator training process to ensure a safe,
functional BRT system including ITS integration.
• Participation in pre -revenue service operation providing support to City personnel as needed.
• Oversight, management and coordination of delivery of keys, manuals, plans and specifications, as -built drawings and
operation and maintenance manuals to ensure a complete project.
Deliverables
Deliverable
Due Date
Progress Reports
Monthly
Procurement Procedures/ Plan
As Required
Shop Drawing Submittals
Weekly
Schedule Tracking
Monthly
Construction Contract Change Order Log
Monthly
Earned Value Report
Monthly
DBE/MBE/WBE & M/W Workforce Utilization Reports
Monthly
Contract week look ahead
Weekly
We will provide status reports, progress reports, and other deliverables as required. We will provide and maintain
electronic and paper filing documentation for all reports and deliverables using the City of Fort Collins documentation
procedures on a bi-weekly basis.
We will maintain a web based document management site (SharePoint) for all construction documentation providing
access to all team members including City of Fort Collins personnel.
Page 4 of 6