Loading...
HomeMy WebLinkAboutCHANGE ORDER - RFP - 7084 CONSULTING ENGINEERING SERVICESCHANGE ORDER NO.1 PROJECT TITLE: FOSSIL CREEK TRAIL @ CR 38E GOCO PROJECT CONTRACTOR: Anderson Consulting Engineers PROJECT NUMBER: COFC2012.02 PURCHASE ORDER NO.: 9120646 DESCRIPTION: ADDITIONAL FEMA DESIGN SERVICES 1. Reason for change: Additional consulting services were required to complete design work 2. Description of Change: FEMA additional data request Item # i $ 900.00 FEMA additional data request Item # 2-3 $ 2,500.00 Coordinate, compile, and distribute the Additional Data Request $ 950,00 submittal to FEMA and the local floodplaln regulatory agencies 3. Change in Contract Cost: $ 4,350.00 4. Change in Contract Time: 30 calendar days ORIGINAL CONTRACT COST $21,570.00 TOTAL APPROVED CHANGE ORDER $0,00 TOTAL PENDING CHANGE ORDER $0.00 TOTAL THIS CHANGE ORDER $ 4,350.00 TOTAL % OF ORIGINAL CONTRACT, THIS C.O. 20.2% TOTAL % OF ORIGINAL CONTRACT, ALL C.O.'S 202% ADJUSTED CONTRACT COST $25,920.00 (Assuming all change orders approved) ACCEPTED BY: Contractor's Representative ACCEPTED BY: Project Manager / REVIEWED BY: Title: APPROVED BY: Title: DATE: DATE: DATE: DATE: APPROVED BY: DATE: Purchasing Agent over $30,000 cc: City Clerk Architect Contractor Engineer Project File Purchasing CITY OF FORT COLLINS REQUISITION VENDOR: Anderson Consulting Eng. DATE ENTERED: 8l3/ f ,7- REQ #: -42y'42j_0 Fossil Creek Trail Extension crossing Spring VENDOR#: r� I-Lf379 / FOR: Creek - LOMRcomments ADDRESS: 772 Whnlers Way, Suite 200 BID #: Mise Contract Fort Collins. CO 80525 INSTRUCTIONS: PHONE #: (970) 226-0120 Craig F to approve FAX #: (970) 226-0121 VENDOR CONTACT Chris Pauley