Change Order Form
'PROJECTTITLE: N. College Rd. Improvements
PROJECT NUMBER: 400903900.6 (Bid #7273)
CONTRACTOR: Connell Resouces, Inc. (PO #9116026)
CHANGE ORDER NUMBER: 8
n preparing criange or ers s ow in order as separate numbered paragraphs the rouowgrg:
1. Reason for change. 2, Description of change.
3. Change in contract cost. 4. Change in contract time.
1&2. See attached sheet for detail.
3. The contract cost will increase by $2,475.04
4. There will be no change in contract time.
ORIGINAL CONTRACT COST
TOTAL APPROVED CHANGE ORDERS
TOTAL PENDING CHANGE ORDERS
TOTAL THIS CHANGE ORDER
TOTAL % OF THIS CHANGE ORDER
TOTAL C.O. % OF ORIGINAL CONTRACT
ADJUSTED CONTRACT COST
(Assuming all change orders approved)
0,04%
0.0%
$6.111,000.00
$51,405.60
$0.00
$2,475.04
$6,164,880.64
ACCEPTED BY. �XX DATE:
Con cto s R esentative) p
REVIEWED BY: G DATE: O
(Engl eer)
SUBMITTED BY: DATE:
(Project ana er)
APPROVED BY: DATE:
(Idepartment Head)
APPROVED BY: DATE:
(Purchasing Agent over $60,000)
cc: contractor
Purchasing
Project File
CHANGE ORDER 8
North College - Vine to Conifer
SUMMARY OF WORK
Item
lQuantity
Unit
I $ / unit
Total
Replace 3FT White Vinyl Fence at 909 N. College
62
LF
$ 39.92
$ 2,475,.04
Total Cost $ 2,475.04
REASON FOR CHANGE
Plans called out fence removal at the Vet Clinic at 901 N. College but did not call for reset. Resetting the fence was
discussed with the property owner during ROW negotiations but not included in final compensation. The plans should have
included resetting the fence by the contractor.
WHEN POSTED Pay Application #6