HomeMy WebLinkAboutCHANGE ORDER - RFP - 7100 JEFFERSON STREET ALTERNATIVES ANALYSIS PROJECT (4)City of
,Fort Collins
Planning, Development & Transportation
Transportation Planning & Special Projects
250 North Mason Street ,
P.O. Sox 580
Fort Collins. CO 80522.0580
970.224.6058
970.221.6239 - fax
fcgov.com/transportation
CHANGE ORDER FORM
PROJECT TITLE: Jefferson SUSH 14 Project
PROJECT NUMBER: 400901804
CONTRACTOR: ATKINS (PO#9102518)
CHANGE ORDER NUMBER: 5
In preparing change orders show in order as separate numbered paragraphs the following:
1. Reason for change. 2. Description of change.
3. Change in contract cost. 4. Change in contract time.
1. & 2. See attached for reason and description of change.
3. The contract cost will increase $5,115.00.
4. The contract time will be extended thru July 30, 2012.
ORIGINAL CONTRACT COST
$401,975.00
TOTAL APPROVED CHANGE ORDERS
$53,470.00
TOTAL PENDING CHANGE ORDERS
$0.00
TOTAL THIS CHANGE ORDER
$5,115.00
ADJUSTED CONTRACT COST
$460,560.00
(Assuming all change orders approved)
ACCEPTED BY: � o-v E `C(, Cif S DATE: 7/9112
(C t s , tativelL
SUBMITTED BY: G DATE: 61;�'
(Pr ject Manager)
REVIEWED BY:
APPROVED BY:
APPROVED BY: YNJ / tf�_ DATE:
(Purchasing Agent)
cc: City Clerk
Contractor
Purchasing
Project File
Atkins North America, Inc.
4601 DTC Boulevard, Suite 700
Denver, Colorado 80237
Telephone: +1.303.221.7275
Fax: +1.303.221.7276
www.atkinsgiobal.com/northamerica
June 22, 2012
Kathleen Bracke
City of Fort Collins
281 North College Avenue
Fort Collins, Colorado 80524
RE: Jefferson Street Alternatives Analysis
Purchase Order Number: 9102518
Atkins Project Number: 100015273
Additional Budget Request: $5,115.00
Dear Kathleen:
Please accept this budget request for an additional $5,115.00 for the Jefferson Street Alternatives
Analysis Project. The purpose of the budget request is described below.
Project Management
Previously, the project was estimated through the end of April 2012. Management activities also
include management of contracts and submittals to Fort Collins and conference calls.
Agency Coordination
• Attendance at one Technical Advisory Committee meeting
• Attendance at Executive Oversight Committee meeting
• Attendance at City Council meeting
Public Involvement
The consultant will participate in the final public meeting to actively engage the corridor property
owners, tenants, and general public in the process. This input will be used to make a final decision
on the preferred recommendation for the corridor.
Task Summary Hours Cost
Project Management (2 months) 11 $1,675.00
Agency Coordination 16 $2,600.00
Public Involvement 6 $840.00
Total $5,115.00
Thank you for consideration. If you have any questions regarding this information, please contact
me at 303-221-7275, or carrie.wallis@atkinsglobal.com.
Carrie Wallis, P.E., Project Manager