HomeMy WebLinkAboutWORK ORDER - BID - 7019 ASSET MANAGEMENT PLAN DEVELOPMENT & IMPLEMENTATION (3)EXHIBIT "A"
WORK ORDER FORM
PURSUANT TO AN AGREEMENT BETWEEN
THE CITY OF FORT COLLINS
AND
MWH Americas, Inc.
DATED: May 8, 2012
Work Order Number.
Purchase Order Number:
Project Title: Asset Management Program Work Planning — Phase 4
Commencement Date: May 8, 2012
Completion Date: December 31", 2012
Maximum Fee: (tune and reimbursable direct costs): $300.000
See attached Exhibit "C" for a schedule of fees associated with each task within Work Order No. 4.
Project Description: 2012 Asset Management Planning Efforts
Scope of Services: See attached exhibit B
Professional agrees to perform the services
identified above and on the attached forms
in accordance with the terms and
conditions contained herein and in the
Professional Services Agreement between
the parties. In the event of a conflict
between or ambiguity in the terms of the
Professional Services Agreement and this
work order (including the attached fortes)
the Professional Services Agreement shall
control.
The attached fortes consisting of Exhibit B,
3 consisting of six (6) pages, are hereby
accepted and incorporated herein, by this
reference, and Notice to Proceed is hereby
given.
cc: Purchasing
Professional/al
By:
Date:IB mo_" Roix
City of Fort Collins
Submitted By:
(,�P of er
Date: Z_
Reviewed by: L.." � oaf
Strategic Financial Planning
Ma aggr,
Date: � I, 12-
Approved by:
Utilities Executive Director
Date:
Approved b c_
EQ
Director,of rchasin & Risk Management
(if over $60,00 1
Date: C9
final scopes, deliverables and budget estimates. Work for as -needed services shall be
approved based on an email authorization from Christopher Parton, or other named
representative of the UTILITY. MWH shall update the fee schedule to reflect the as -
needed services.
As -Needed Task A - CMMS Support If
Assist UTILITY staff by providing implementation guidance, management, and
support to promote successful implementation of the CMMS.
CMMS Initial Schedule Support
• Develop a detailed pilot implementation plan that identifies the existing FCU
systems and functionality that will be replaced by the new CMMS, systems
that will require integration to CMMS via UTILITY system integration strategy,
existing FCU systems and functionality that will remain in production, and
timeline for migrating existing functionality and data into the new CMMS.
Site Visit Support
• MWH to assist FCU in visiting up to three (3) similar utilities with Maximo
implementations. Similar utilities should have a customer base similar to FCU
and manage water, wastewater and electric operations. Maximo
implementations should include Maximo Linear and Maximo Spatial, with one
implementation performed by Aquitas Solutions. Site visit assumptions
include 2 "local" utilities located within 150 miles of Denver, CO and one
remote visit within a two hour flight distance from Denver, CO.
Contract Negotiation Support
• MWH to assist FCU in negotiating the final contract dollars and scope with
Aquitas Solutions to protect FCU's interests with regards to scope to be
delivered and fee to be paid.
Pilot Implementation Support
• Assist UTILITY and CMMS vendor with oversight and assistance during pilot
implementation of the selected CMMS system at the UTILITY Water
Production Facility and selected linear assets. Goal is to show that the CMMS
system implementation will effectively support the specked business
processes and KPIs.
• UTILITY will arrange for its business and information systems experts to work
with CONSULTANT to identify key system needs and improvement
opportunities.
I I i • l'A§siif with designland deploymentl'of'comrriunicationland d'utreach efforts to
UTILITY and City staff to promote ongoing communications, support, and
buy -in to the asset management program enhancement efforts.
• Review and refine the three to five specific CMMS-based business processes
used to measure success of the pilot implementation.
Exhibit B
City of Fort Collins Utilities Department
Asset Management Plan Development and Implementation
Task 1 — Project Management
The purpose of this task is to provide project management services in accordance with
industry standards in order to promote coordinated, comprehensive, and cost-effective
planning, management, and delivery of the asset management program implementation
efforts.
Key CONSULTANT steps to assist with the delivery of this task are expected to include:
• Project Execution Plan development, including baseline schedule development
and outlining key roles, responsibilities, communication channels, milestones,
and deliverables necessary to meet the contract scope of services
• Project Monitoring, Cost Controls, and Coordination to promote high quality
deliverables, submitted on schedule, and in accordance with the project budget
• Project Communications and Administration including a monthly status meeting
and progress reports, meeting scheduling and coordination, weekly coordination
calls among key project staff, and subconsultant management, as appropriate
• Quality Management including workshop feedback evaluations and quality
reviews of deliverables
• Monthly Invoices
• File Management and Recordkeeping in accordance with standard project
management practices
Task 1 Key Assumptions
• Planned level of effort for this task assumes execution of similar nature and
extent of project management efforts and activities as conducted for Phase 3
• Planned level of effort assumes a project duration of nine months (until the end of
December, 2012)
Task 1 Deliverables
• Baseline project schedule and monthly schedule revisions as appropriate
• Schedule of project workshops
• Monthly status coordination calls
• Workshop meeting notes and evaluation summaries
• Monthly invoices
Task 2 — CMMS Support I
The purpose of this task is to provide support regarding upfront budgeting, and to
quantify FCU's potential return on investment with regard to the upcoming IBM Maximo
CMMS implementation. Additional support for the CMMS project), should it move
forward, can be found below under as -needed services.
Key CONSULTANT steps to assist with the delivery of this task include:
CMMS Budgeting Support
• MWH will liaise with Aquitas Solutions to verify scope items proposed to FCU in
the RFP response, collect scope additions with estimated fees, and assemble a
comprehensive listing of Aquitas pricing. MWH will collect hardware requirements
to run the proposed CMMS system, meet with members of the Fort Collins City
IT department to determine hardware compatibility with the current City of Fort
Collins IT infrastructure and identify upcoming hardware costs to FCU
Develop CMMS RO/ Model
• To assist FCU in demonstrating projected Return On Investment (ROI) of the
IBM Maximo Computerized Maintenance Management System, MWH will
produce an ROI calculator leveraging industry standard savings levels realized
with the implementation of a CMMS. Working alongside of FCU, MWH will adjust
the industry standard benchmarks to reflect the benefit expected at FCU
Task 2 Key Assumptions
• Pricing received from Aquitas Solutions will be accurate
• The IT infrastructure at the City of Fort Collins will remain consistent
• FCU will perform a full implementation of the CMMS with a full user migration to
the new system
Task 2 Deliverables
• Interactive ROI calculation model
• Spreadsheet outlining 2012 — 2014 CMMS related budget items
As -Needed Services for Implementation of Asset Management
Program
The purpose of the following tasks is to provide as -needed implementation guidance,
training, and support to promote successful implementation of the various asset
management program (AMP) elements designed and implemented during Phases 1-3
of the AMP. Such assistance could pertain to: performance management using levels of
service targets and KPIs; risk -scoring and risk -based financial planning; data collection,
migration and management in accordance with the revised data framework; life cycle
management plan development and implementation; business process enhancement
and/or related services.
The tasks listed below provide a starting point for potential services which may be
authorized. Upon the request from UTILITY for as -needed services, MWH shall provide