HomeMy WebLinkAboutPrebid - BID - 7341 GRADE SEPARATED CROSSING AT NRRC (2)Mason Grade Seperation at NRRC
Federal Aid Project No. AOC-M455-071
Bid No. 7341
PRE -BID CONFERENCE
February 16, 2012
10:00 A.M.
215 N. Mason Street
Training Room
City of Fort Collins
Engineering Dept.
Capital Improvements Program
Introductions
Engineering:
Capital Projects Program:
• Rick Richter - Program Manager 221-6798
• Jin Wang - Project Manager 416-2292
• Mark Laken - Project Engineer 222-3546
• John Von Nieda — City Surveyor 221-6565
Purchasing:
• John Stephen - Purchasing Agent 221-6777
• Traffic:
• Syl Mireles - Traffic Eng. Tech 221-6815
Consultant Engineer:
• Felsburg Holt and Ullevig
BNSF Railroad Coordination Requirements:
• Required BNSF Railroad Agreement between
Contractor and BNSF — See Exhibit "E1" in contract
• Delay to trains is specified as $382.20 per Hour
• BNSF Review for horizontal and vertical clearances
• BNSF will not review structural design
calculations
• BNSF does require structural design review of any
proposed shoring, falsework and cribbing
• None is anticipated on this project
BNSF Railroad Coordination Requirements:
• The contract specifies a "work window" which is the
7 day full shutdown of the tracks for:
• Mason Street Work
• Troutman Underpass work
• Opportunity for NRRC Overpass work
• Currently Scheduled for July 23-29, 2012
Utility Coordination
• CenturyLink (Qwest):
• Has a pedestal to relocate and a 900 Pair and a
50 Pair to relocate on the East Plaza
• City has met with CenturyLink, a vault has
already been installed by CenturyLink, and
CenturyLink is scheduled to relocate the
pedestal and facilities to the new vault prior to
construction
• Coordinate with CenturyLink for telephone POC
Utility Coordination
• City Light & Power
• Has completed the relocation of an existing
duct bank
• Will require coordination for power POC
• CSU has an existing phone line that is under the
west plaza
• Contractor needs to coordinate with CSU
during construction to maintain existing phone
line
Building Permit
• City has already pulled a building permit
• City's Building Dept. will perform inspections on
Electrical, Fire, HVAC,
• Elevators require outside inspection that City will
coordinate
• Awarded contractor will not be required to pay any
inspection fees
• Awarded contractor will not be required to have a
license with City's Building Dept.
Traffic Control
Traffic Control provided by contractor
1 Lump Sum for all Traffic Control on the project
including: Flagger Hours, TCS, Inspections &
Traffic Control Devices
• Contractor and traffic control subcontractor
need to coordinate on construction
• Full Time onsite TCS is not required - only
during initial devices setup
Traffic Control
• Detour routes for Mason Trail when overhead work
is underway
• Detour Bay Farm Road when necessary (Detour to
Center Ave/College Ave from Drake & Prospect)
• Traffic Control will be necessary behind Whole
Foods
• Flaggers may be necessary for material deliveries
• Daily Logs required per CDOT
Haul Routes
• Access to the Site will be from:
• The alley behind Whole Foods, King Soopers,
Kmart on the east side of the structure
• Do not use the Whole Foods parking lot for
construction deliveries
• Bay Farm Road from Drake Road on the west
side of the structure
REMOVALS
Section 201
•Clearing and Grubbing
Section 202
•Removal of Tree — East Plaza
•Removal of Asphalt Mat
•Removal of Fence (Mesh Only)
•Removal of Median (to be added via
EARTHWORK & FILL
Section 203 & 206
•Blading
-Structure Excavation — Paid per Plan
-Structure Backfill (Class 1) — Paid per Plan
-Structure Backfill (Class 2) — Paid per Plan
-Mechanical Reinforcement of Soil — Paid per Plan
-Shoring Area (Area 1) — Paid Lump Sum
• East Plaza
-Stockpile Topsoil — Paid per CY
-Planter Soil Mix — Paid per CY delivered
EROSION CONTROL
• Contractor will obtain and maintain the SW MP from the Colorado Dept
of Public Health and Environment (CDPHE)
• The Erosion Control Plans provided are not the SW MP. However,
plan quantities were calculated from the Erosion Control Plan.
• Erosion Control is broken into several measurable pay items
• Erosion Log, Silt Fence, Concrete Washout Structure, Removal
and Disposal of Sediment
• No Tracking Pads — access is paved
• Contractor is required to have an Erosion Control Supervisor that shall
enforce all policies that apply to this project (HR Item)
LANDSCAPING
Section 212
• Seeding (Native)
• Soil Preparation (Special)
• Compost
Section 213
• Mulching (Weed Free Straw)
• Mulching (Wood Chip)
• Mulching (Decorative)
• Mulch Tackifier
• Landscape Weed Barrier Fabric
• Landscape Boulders (Special)
LANDSCAPING
Section 214
• Landscape Maintenance (24 Months)
• 2 growing seasons per CDOT
• Contract stay open and monthly payments are made
• Deciduous Shrub
• Landscape plan (Sheets 94-96)
• Section 215
• Transplant Tree
• Evergreens on West Side Plaza
• Labeled T1 thru T5 on Sheet 94
PAVEMENT
Section 403
• Hot Mix Asphalt (Patching) - SY
Section 412
• Concrete Pavement (6 Inch) — SY
• Plaza Paving
• Concrete Pavement (8 Inch) (Special) — SY
• Raised Crosswalk on Bay Farm Road
• Revised detail to be released in Addendum
Section 420
• Geomembrane - SY
• Impervious Lining at MSE Retaining wall system
DRILLED CAISSONS
Section 503
• Drilled Caisson (30") — For Elevators
• Drilled Caisson (42") — For Stairs and Piers
• Caisson cages are included in line item price per
CDOT
• See Sheet 49 for more detail
CRIBBING
Section 504
• Block Facing
• MSE Block Wall at West Plaza
• Neutral grey block
• Style resembling Keystone "Century Wall"
pattern
• Sheet 17, 69-71
Attendance
• Please be sure to register
• BID OPENING
• When: March 5, 2012 @ 3:00 P.M. (Our Clock)
• Where: 215 North Mason Street (2nd Floor)
• Bid Documents are available at:
http://fcaov.com/eprocuremen t
http://fcgov.com/purchasing/
Contract Documents for Bid 7338
• Bid Set Plans for Mason Grade Separation at
NRRC by Felsburg, Holt & Ullevig
• Sheets 1 thru 96
• Specifications Book
• Addendum to be released on February 27, 2012
STEEL STRUCTURES
Section 509
• Structural Steel
— Mounting Hardware for Elevators
— Paid by LBS — requires bill of lading
— Does not include weld plates, which are
incidental to precast assemblies
STEEL STRUCTURES
• Hand Rail
• Pedestrian railing is Hand Rail — mounts to the interior walls of the
stairways and does not feature steel cables
• Pedestrian Railing (Steel)
• per Architectural Drawings (Sheet 38) - features steel cables
• Imbeds with threads protruding from concrete for bolting mounting
plates with slotted holes (Sheet 72-73)
• Sheet 68 calls out Handrail and Pedestrian Rail quantities — but it does
not add up to plan quantities
• City will address in addendum
STRUCTURAL CONCRETE
Section 601
• Concrete Class D (Misc)
• CIP Stairs at west plaza ,
• CIP Ramp Walls at west plaza
• Concrete Class D (Bridge)
• Elevator Pits
• Piers
• Stair Tower Foundations
• Bridge Deck (note that steel in bridge deck is per
shop drawings and incidental to cost of bridge)
• Corrugated Paper Void Material - 6" Void material
on all caisson based foundations
STRUCTURAL CONCRETE
Section 601
• Structural Concrete Coating
• Class 2 Finish followed by Structural Concrete
Coating on all exposed surfaces except landings
and stair treads
• Extend 1 foot below finished grade
Section 602
• Reinforcing Steel (Epoxy Coated)
• East Pier only
• Reinforcing Steel
• All other CIP concrete
FENCING
• Section 607
• Fence (Plastic) — Temporary Safety Fencing —
shows 150 LF on plans
• Wire Mesh — new welded wire fabric to repair
existing fence
• Includes replacement of missing fence rails
ELECTRICAL
Section 613
• Lighting and Power Equipment
• Includes relocating an existing overhead luminaire
• Includes connections for elevator controls
• Includes telecom for elevator
• Includes heat and smoke detection equipment
• Includes lighting systems
• Includes Nema 3R Electrical Enclosure w/
necessary electrical panels
ELECTRICAL
Section 613
• 1" Electrical Conduit
• 2" Electrical Conduit (Plastic)
• 2" Electrical Conduit (Plastic)
• 2 %" Electrical Conduit (Plastic)
• 3" Electrical Conduit (Plastic)
• Buried Conduit w/ warning tape
• Power is pulled from south of the east plaza, through
the bridge structure to the west plaza
PRESTRESSED CONCRETE
Section 618
• Precast Stairs
• Consists of precast towers with cantilevers to
support precast stairway/landings
• 'Windows" in the center of the tower will get
fiberglass panels installed in them
• Conduit for wiring precast inside assemblies for
lighting
• Anchorage detail by precaster prior to
installation of CIP foundations
• Imbed weld plates
• Precast Design review by City/FHU
REST AREAS AND BUILDINGS
Section 622
• Precast Concrete Wall Panels
• Consists of precast walls with canopies and
doorways for the elevator towers
• 'Windows" in the North and South facing walls
will get Aluminum Glass Storefront treatment
• Anchorage detail by precaster prior to
installation of CIP foundations
• Imbed weld plates
• Precast Design review by City/FHU
REST AREAS AND BUILDINGS
Section 622
• Bicycle Rack
• 3 Suppliers provided in specifications
• Trash Receptacle
• 3 Suppliers provided in specifications
BRIDGE GIRDER AND DECK
Section 628
• Bridge Girder and Deck Unit (204')
• Steel Pedestrian bridge consisting of 174' span
with a cantilevered deck on each end
• Price includes delivery, assembly, erection, and
all costs associated with manufacturing and
setting the bridge
• Incidentals include bearing pads & plates,
anchor bolts, rubrails, toe plates, corrugated
steel bridge deck falsework, rebar for the bridge
deck
BRIDGE GIRDER AND DECK
Section 628
• Bridge Girder and Deck Unit (204')
• Crane Operator and setting crew will be Davis -
Bacon
• Shop Drawing Review by BNSF for clearances
• Shop Drawing Design review by City/FHU
BRIDGE FINISH
Section 632
• Bridge Finishes
• See Table on Sheet 45
• Price includes:
• Roof
• Fiberglass Panels
• Aluminum Wall Panels
• Gutters and Drains
• Gypsum Board Assemblies
• All incidentals (brackets, hardware, etc.)
ELEVATOR
Section 636
Elevator Facilities
• See Table on Sheet 45
• Price includes:
• Roof
• Aluminum Storefront with Glazes
• Drain Pipes
• Insulation
• Electric Traction Elevator
• Rooftop HVAC
• Sheet Metal Flashing and Trim
• Steel Door and Hardware
Sump Pump
All incidentals (brackets, hardware, etc.)
ELEVATOR
Section 636
• Elevator Facilities
Buy American applies to all elevator hardware
Basis of design Product:
• ThyssenKrupp 300EH 50/20
• Page 234 of Project Specials
• Substitutions will be entertained under Division 1
requirements
• Substituted product must meet requirements of plan
drawings and specifications
City will coordinate required State Inspection
TRAFFIC CONTROL
Section 630
• Construction Zone Traffic Control
• Covers all traffic control devices, flaggers, TCS,
Inspection necessary for the project.
• Contractor to develop traffic control plans for the
project
• Plans reviewed by the City
• Minimize closures to Mason Trail / Bay Farm Road
Thanks For Attending!
• Any Questions or concerns can be addressed to:
Jin Wang (Technical)
• Office: (970) 416-2292
• Email: iwanp(a�fcgov.com
Mark Laken (Technical)
• Mobile:970-222-3546
• Email: mlaken@fcgov.com
John Stephen (Purchasing)
• Office: (970) 221-6777
• Email: isteohenCu�fcaov.com
Summary of Work
• Structure Excavation and Structure Backflll
• Drilled Caissons
• CIP Structural Concrete (Piers) w/ Rebar
• Two Precast Elevator Tower w/ Elevators
• Two Precast Concrete Stair Assemblies
• One Prefabricated 205' Enclosed Bridge
• Landscaping
• MSE Retaining Walls
• Asphalt and Concrete Pavement
• Concrete Curb & Gutter
• Electrical wiring and lighting
• Pedestrian Railing
• Traffic Control
Important Contract Dates:
• AWARD CONTRACT
• Bid Opening March 5, 2012 at 3:00 PM
• PRE -CONSTRUCTION MEETING
• Mandatory Meeting Prior to Start of Construction
• Date to be determined after contract is awarded
• CONSTRUCTION START DATE
• Anticipate Notice to Proceed in late March, 2012
• Anticipated Begin Construction in mid May, 2012
• SUBTANTIAL COMPLETION .270 Calendar days from Notice to
Proceed (late December, 2012)
• FINAL COMPLETION — 14 Calendar Days after substantial completion
is obtained.
Project Overview
Contractor responsible to acquire all appropriate permits and submit
required documentation
• SW MP — permit and inspections
• Dewatering Permit if applicable
• CDOT Form 205 for each subcontractor
• Payrolls, EEO Documents, Trainee Forms
• Shop Drawings, Material Submittals, Mix Designs
Partnering session prior to construction
Staging Area for bridge assembly is on the north east side of project.
All other staging is within the BNSF and adjacent property owner
easements
• BNSF — within 10' of center of tracks
• BRT Easement behind Whole Foods on east side
• Ped Bridge Construction Easement on west side
Project Overview
• Survey
• Provided by City of Fort Collins
• Engineering Department Survey Staff
• 48 hour written request for survey
• Testing
• Provided by City of Fort Collins
• Thru contract with CTL Thompson
• Contractor will setup testing as required
• Sionino and Strioino by City of Fort Collins Traffic
HIGHLIGHTS FROM GENERAL CONDITIONS AND
GENERAL REQ'S:
SUPERINTENDENTS:
The General Contractor SHALL employ a full time Superintendent
whose sole responsibility is to monitor and coordinate all facets of the
work
LIQUIDATED DAMAGES:
• SUBSTANIAL COMPLETION:
• 270 days after Notice to Proceed
• Damages in the amount of Three Thousand Dollars ($3,000.00)
for each calendar day will be assessed.
• FINAL ACCEPTANCE
• Within 14 days of Substantial Completion.
• Damages in the amount of Three Thousand Dollars ($3,000.00)
for each calendar day will be assessed.
HIGHLIGHTS FROM GENERAL CONDITIONS AND
GENERAL REQ'S:
• CONSTRUCTION TIME:
• Standard Hours of Operation
• 7:00 AM thru 6:00 PM - Monday thru Friday.
• Given the scope of the proposed improvements, the City will
allow extended working hours
• Extended Hours requests must be made at the weekly meeting
prior to the request date
HIGHLIGHTS FROM GENERAL CONDITIONS AND
GENERAL REQ'S:
PROJECT MEETINGS:
• Once a week. Location and time to be determined
• Agree to weekly quantities, 2 weeks schedule, traffic control
• PROGRESS AND SCHEDULE REVISIONS:
• Prior to construction, initial schedule must be submitted and approved
• Schedules shall be updated weekly
• The Contractor may be required to submit additional schedules
depending on the progress of the project.
RECORD DRAWINGS PLAN SET
Contractor will be required to keep record drawings
• Will be submitted to the City at the end of the project
HIGHLIGHTS FROM GENERAL CONDITIONS AND GENERAL
REQ'S:
SITE CLEAN-UP:
The construction work shall be kept and accomplished
in a neat, clean and orderly fashion.
Tracking pads are not required - street sweeping will
need to be used in order to minimize tracking and meet
EPA storm water quality requirements.
Dust control will be required.
General Notes on Federal Aid Project
Requirements:
• Change Orders will follow CDOT procedures
• Federal Aid = Davis Bacon Wages and Wage
Reporting Requirements
• Weekly Payroll Submittals to City Staff
• UDBE Goals = 6.5% of contract amount
• On -Job Training Goals = 320 hours
• OJT Trainee Payroll Documentation
• CDOT Materials Requirements & "Buy American"
• CDOT Form Submittals
NRRC Overpass Project
UDBE Requirements
Underutilized Disadvantaged Business Enterprise (UDBE)
Goal is 6.5% of Total Contract
If UDBE goal is met, submit CDOT Form 715
If UDBE Goal is not met
• Submit CDOT Form 718
• 3 Copies of Good Faith Effort documentation needs to
be supplied to the City of Fort Collins by 4:30 PM on the
next business day following Bid Opening.
• Good Faith Effort includes all correspondences and
supporting documentation that was amassed in effort to
meet the UDBA project goal.
NRRC Overpass Project
UDBE Requirements
• For UDBE Questions contact:
• CDOT EEO Office at: (303) 757-9303
• CDOT maintains a DBE contractor list at:
• http://www.dot.state.co.us/EEO/DBEProgramPa
ge.htm
• The list is updated monthly.
BNSF Railroad Safety Requirements:
• Contractor's Superintendent is required to
complete online RR Safety Training Program
• www.contractororientation.com
• 30 Day verbal notice to BNSF Roadmaster for
RR Flagger — Roadmaster: (307)-432-7357
• Railroad Flagger to be paid thru RR Force
Account line item and is required when:
• Work is within 25' of Railroad Centerline
• Work is with equipment that is tall enough to
fall onto the Railroad — measured from edge
of rail to the base of equipment
BNSF Railroad Safety, Requirements:
• 30 Day written notification prior to commencing
construction on BNSF property
• Proposed shoring, falsework, & cribbing (with
support calculations) need to be submitted to
BNSF for approval prior to work
• BNSF Railroad Insurance required prior to
working on BNSF ROW
• No Crossing the tracks with equipment
• Exhibit "E" Contractor Requirements