HomeMy WebLinkAboutCHANGE ORDER - AGREEMENT MISC - BISHOP-BROGDEN ASSOC INCCHANGE ORDER NO.
PROJECT TITLE: Gravel Pit Plan for Augmentation and Boxelder and Coy Ditch
change of use
CONTRACTOR: Bishop-Brogden Associates, Inc
PROJECT NUMBER: PO 9112133
DESCRIPTION:
1. Reason for change: Expanded scope to include unanticipated tasks associated
with original scope of work
2. Description of Change: See attached
3. Change in Contract Cost $29,900
4. Change in Contract Time: No change in contract time
ORIGINAL CONTRACT COST
$_26,700 —
TOTAL APPROVED CHANGE ORDER
TOTAL PENDING CHANGE ORDER
_20.500
_29,900_
_
TOTAL THIS CHANGE ORDER
TOTAL % OF THIS CHANGE ORDER 1. 1 Z'/,>
TOTAL C.O.% OF ORIGINAL CONTRACT
ADJUSTED CONTRACT COST
$ _77,100
(Assuming all change orders approved)
��L2
ACCEPTED BY: DATE:
Contractor's Representative
BY: DATE: Cr
BY:
'L
Project Manager
REVIEWED
BY:
DATE:
Title:
APPROVED
BY:
DATE:
Title:
APPROVED
BY:
DATE:
Purchasing Agent over $30,000
Contractor
Project File
Architect
Engineer
Purchasing
-;1 i_ 70 -f I o. 2 q c, oS
421 B
MEMORANDUM BBA
water consultants
BISHOP-BROGDEN ASSOCIATES, INC.
To: Daylan Figgs
From: Mike Sayler
Subject: Second Amended Scope of Work for Gravel Pit Plan for Augmentation and Box Elder and
Coy Ditches Change of Use
Job: 9625.03
Date: June 13, 2012
This memorandum summarizes a second revision to the scope of work for the Gravel Pits Plan for
Augmentation and Box Elder Ditch shares change of use. We have previously provided an estimate of
the costs for Phase 1 of the work, which will take us through completion of an engineering report and
submission of a water court application. That scope of work was previously approved in PO #9112133
on April 14, 2011 for $26,700, The purchase order was changed in Change Order 1 on December 16,
2011 for $20,500 more work. Since that time, several additional tasks have been identified which have
been added to this work. A summary of the additional tasks and the estimated additional costs to
completed the Phase 1 work is as follows.
1. Submit a 2012-3 Substitute Water Supply Plan (SWSP). This fall we anticipate subnutting
another request to the Division of Water Resources (DWR) for an extension of the SWSP for the
Resource Recovery Farm. This task will include calculating the augmentation requirements for
next year, coordinating replacement supplies with City staff, and preparing a letter report for
submittal to the DWR. In addition, this year, you have asked as to review the possibility of
making excess Box Elder water available to LPAC in exchange for storage. We have estimated
the amount of storage that would be required, we well as the amount of excess Box Elder water
that might be available to LPAC. We estimate the cost for this task, including the work already
done in determining LPAC storage requirements, to be approximately $4,000.
2. We have encountered various tasks related to the Coy Ditch water that were not included in our
previous scope of work. These included attending the Hoffman deposition and assisting legal
counsel, interviewing Mr. Hoffman at his home, additional work in evaluating the ELCO change
of use, extending the study period back to 1911 in order to address recent lack of use issues,.and .
modeling the yield of both 5 and 10% ownership of the water right. The costs for these additional
tasks was approximately $5,700.
3. In order to address recent lack of use issues with the Box Elder Ditch shares, we extended the
study period back to 1911 and recalculated the historical use for this longer period of records.
The costs for this additional work was approximately $4,400.
4. We have reviewed issues related to possible high water table conditions that might potentially
affect the transferable yield of both the Coy and Box Elder Ditch shares. This included reviewing
seed mixes and rooting depths, understanding the source of storm water inflows to the Coy
property, analyzing survey data from the Box Elder lands, and running water budgets with
possible reductions for future consumptive use of ground water. The costs of this task was
approximately $4,100.
5. Attend two extra meeting beyond the two meetings we had previously planned. One of these
meetings has already occurred and the other will be held when our draft report is completed. This
will result in a total of four meetings rather than the two budgeted last December. We estimate
the cost of this task will be $3,400.
6. We have completed several additional modeling scenarios with our planning model to determine
Daylan Figgs
Page 2
June 13,2012
how much storage and leased water will be needed in the future based upon several additional
scenarios for future exposed ground water, recharge operations, Box Elder and Coy Ditch yields.
The cost of these additional modeling scenarios has been approximately $3,200.
7. We have worked on lagging depletions from the Cottonwood Hollow/Wren pit, which has
required additional modeling. Initially it was thought these pits could be considered to cause
instantaneous depletions to the stream. However, due to the DWR's new policy on headgate
wells, it will not be possible to claim instantaneous depletions any longer. The cost of this task is
approximately $1,000.
8. We are reviewing various wetlands related issues for the RiverBend Ponds site in order to
determine if there are additional depletions from this site that need to be included in the plan for
augmentation. The cost of this task is approximately $1,700.
9. We will include in the augmentation plan the ability to allow the plan to be administered based
upon varying water levels in the pits and varying exposed ground water areas. This will allow the
City to reduce its augmentation requirements in the future if the water levels in the ponds can be
decreased. The cost of this task is approximately $2,400.
Based upon these additions to the previous Scope of Work, we estimate the total additional costs to
complete Phase I of the gravel pit plan for augmentation and the Box Elder and Coy Ditch changes of use
to be $29,900.