HomeMy WebLinkAboutCHANGE ORDER - RFP - 7307 TRANSPORTATION PLANNING & ENGINEERING CONSULTANT ON-CALLCHANGE ORDER NO. 1
PROJECT TITLE: Transportation Planning & Engineering On -call
CONSULTANT: Atkins
PROJECT NUMBER: 7307
DESCRIPTION: Add a $75,000 work order limit.
Reason for change: Add a work order limit of $75,000 to match City Purchasing
requirements.
2. Description of Change: Have maximum work order of $75,000
3. Change in Contract Cost: NONE
4. Change in Contract Time: NONE
ORIGINAL CONTRACT COST
TOTAL APPROVED CHANGE ORDER
TOTAL PENDING CHANGE ORDER
TOTAL THIS CHANGE ORDER
TOTAL % OF THIS CHANGE ORDER
TOTAL C.O.% OF ORIGNINAL CONTRACT
ADJUSTED CONTRACT COST
(Assuming all chang orders approved) /
ACCEPTED BY: C i /(/(,IL 1 /-S
Contractor's Reoresentativel
DATE: 5 ��
ACCEPTED
BY: �.4, DATE:
Project Manager
APPROVED
BY: DATE:
Purchasing Agent over $60,000
Contractor
Project File
Engineer
Purchasing