HomeMy WebLinkAboutCHANGE ORDER - BID - 7289 FOSSIL CREEK TRAIL AT STANTON CREEK0
PROJECT TITLE:
CONTRACTOR:
PROJECT NUMBER:
PURCHASE ORDER NO.:
DESCRIPTION:
CHANGE ORDER NO. 1
Fossil Creek Trail at Stanton Creek
Walsh Construction, Inc.
7289
9116848
Description of change
1. Reason for change: Restabilization of subgrade under proposed trail
2. Description of Change:
1) Remove Forms and Re -grade Trail Station 8+00 - 11+00 $ 2,972.75
2) Additional Wall Sta. 20+96 - 22+93 $ 2,139.28
3) Additional Stabilization Work Sta. 11+00 — 26+00 thru March 31 $ 41,020.25
3. Change in Contract Cost:
4. Change in Contract Time: 19 Days
46,132.28
TOTAL APPROVED CHANGE ORDER $ -
TOTAL PENDING CHANGE ORDER $
TOTAL THIS CHANGE ORDER $ 46,132.28
TOTAL % OF ORIGINAL CONTRACT, THIS C.O. 9.94%
TOTAL % OF ORIGINAL CONTRACT, ALL C.O.'S 9.94%
ADJUSTED CONTRACT COST $510,072.28
(Assuming all change orders approved)
ACCEPTED BY:
Contractor's Represent
ACCEPTED BY:
Project Manager
REVIEWED BY:
Title:
APPROVED BY:
Title:
DATE: 6-11-12
DATE: 611 / ((Z
DATE:
DATE:
APPROVED BY: DATE:
Purchasing Agent over $30,000
cc: City Clerk Architect
Contractor Engineer
__ Project File Purchasing