HomeMy WebLinkAboutCHANGE ORDER - PURCHASE ORDER - 9121299RECONCILIATION CHANGE ORDER NO. C-I PROJECT TITLE: CONTRACTOR: P.O. NUMBER: CHARGE NUMBER: DESCRIPTION: PETERSON - LOCUST 16” WATERLINE REPAIR Connell Resources, Inc 9121299 502.243000.535101 1. Schedule of Values used Unit Pricing and project was constructed using Time and Materials pricing, resulting in savings. 2. Primary cost savings from deleting asphalt milling and installation 3. Decrease Contract Cost by <$30,992.45>. 4. WJt’%III PROJECT: PETERSON - LOCUST 16” WATERLINE REPAIR City of RECONCILIATION CHANGE ORDER #C-1 SUMMARY Fort CoLLins l) 5/18/2012 Op’rans SCHEDULE OF VALUES ACTUALLY INSTALLED ITEM NUMBER DESCRIPTION QUANTITY UOM UNIT COST COST TOTAL DIFFERENCE ITEM NUMBER 00-100 Mobilization (Mob., Supervision) 1 LS $8,500.00 S8.500.00 56,954.53 (Si .545.47) 00-100 00-175 Pothole Existing Utilities 10 EA 5290.00 S2.900.00 $0.00 (52,900.00) 00-175 03-111 16 DIP Waterline Repair 1 LS S26.500.00 S26.500.00 $31,729.74 $5,229.74 03-111 08-302 Concrete Curb and Gutter 30 LF $33.00 $990.00 $0.00 (S990.00) 08-302 08-410 Temp Concrete Surfacing 700 SF $4.40 $3,080.00 $0.00 ($3,080.00) 08-410 22-105 Asphalt Removal Milling 3- 5” 830 SY $7.00 $5,810.00 $390.78 (S5,41 9.22) 22-105 47-106 Asphalt Paving Streets 4’ Asphalt /6 Class 5 Agg Base 830 SY $31.00 S25,730.00 S0.00 (S25.730.00) 47-106 Mark-ups General Office Activities (4%) Si .563.00 Si .563.00 Field Office Activities (4%) $1,563.00 Si .563.00 Bonds (.75%) S31 6.50 $316.50 TOTALS s73,51o.oa S42,517.55 ($30,992.45) No change in Contract Times. ORIGINAL CONTRACT COST TOTAL APPROVED CHANGE ORDERS TOTAL PENDING CHANGE ORDERS TOTAL THIS CHANGE ORDER TOTAL % OF ORIGINAL CONTRACT, THIS CO: TOTAL % OF ORIGINAL CONTRACT, ALL CO’S: ADJUSTED CONTRACT COST (Assuming all change orders approved) $73,510.00 I $0.00 $0.00 -$30,992.45 ACCEPTED BY: REVIEWED BY: APPROVED BY: APPROVED BY: Dan. Giesler, Contractr’s Representative D Owen L. RandaI C’Fiief Engineer Jon Haukaas, Water Engineering and Field Services Operations Manager DATE: DATE: DATE: DATE: I CC: Finance Contractor Purchasing Project File NOTE: Signature of Contractor indicates agreement herewithin, including any adjustmer in contract sum or contract time. -42.2% -42.2% $42,517.55 I:Eng/pmmanual/general/forms/change order form