HomeMy WebLinkAboutPrebid - BID - 7366 HARMONY ROAD MAINTENANCE PROJECT - COLLEGE AVE TO TIMBERLINE RD (2)HARMONY MAINTENANCE PROJECT
BID NUMBER: 7366
PRE -BID CONFERENCE
April 3, 2012
10:00am @ 215 North Mason Community Room
City of Fort Collins — Engineering Department
Capital Projects Group
I[kTktffoj 1111114flierk&9
• Engineering —Capital
Projects
Rick Richter—
Program Manager 221-6798
Tim Kemp—
Project Engineer 219-9762
Craig Farver—
Construction Inspector 222-0854
• Purchasing
John Stephen — Senior Buyer 221-6777
• Traffic
Syl Mireles— Traffic Eng. Tech 221-6815
ATTENDANCE
• Please be sure to register
• Bid Opening
April 17, 2012 ® 3:00pm (Our Clock)
Location - 215 North Mason Street
Submit Bids to Purchasing Department
EARTHWORK
• 203-01
Unclassified Excavation (CIP)
• 203-02
Muck Excavation
• 203-03
Borrow
203-04
Shouldering (Recycled Asphalt) (Haul and Place)
• 203-05
Flowable Fill (Utility Backfill)
EROSION CONTROL
• 208-01
Erosion Log (12 Inch)
• 208-02
Storm Drain Inlet Protection
• 208-03
Concrete Washout Structure
208-04
Erosion Control Supervisor
10
RESET STRUCTURES
210-01 Adjust Valve Box
210-02 Adjust Manhole 5 24 Inch
• 210-03 Adjust Manhole > 24 Inch
SEED, SOD & TREE PROTECTION
• 212-01 Seeding (Native)
• 212-02 Sod
• 212-03 Tree Retention and Protection
s Trees along the Dixon Lateral Structure Removal
> Trees along the NB Lemay Turn Lane
s Trees along the WB Turn Lane @ Timberline
MULCHING & BOULDERS
• 213-01
Mulching (Weed Free Hay)
• 213-02
Mulching (Wood Chip)
• 213-03 thru Inorganic Mulch (Rock) Various Sizes
213-05
• 213-06
Landscape Weed Barrier Fabric
• 213-07
Landscape Boulder
PLANTING
• 214-01
Deciduous Tree (3 Inch Caliper)
• 214-02 &
Evergreen Tree Various Sizes
214-03
• 214-04 thru
Deciduous Tree Various Sizes
214-06
214-07
Shrub (5 Gallon Container)
• 214-08
Perennials and Om. Grasses (1 Gallon)
SOIL RETENTION COVERING
• 216-01 Soil Retention Blanket (Biodegradable)
> For Restored Slopes Steeper than 4:1
BASE & ASPHALT
• 304-01 Aggregate Base Course (Class 6)
• 403-01 Hot Mix Asphalt (Grading S) (100)
(PG 64-28) (Modified Binder)
• 403-02 Hot Mix Asphalt (Grading SG) (100)
(PG 58-28)
• 403-03 Hot Mix Asphalt (Hand Patching)
Narrow Widening Areas less than Paver Width
12
PAVEMENT SECTIONS
Harmony Road — Full Depth Section
2" HMA (S) over 6" HMA (SG) over 14" ABC
22" TOTAL
Lemay Avenue — Full Depth Section
2" HMA (S) over 6" HMA (SG) over 9" ABC
17" TOTAL
Harmony Road — Pavement Rehabilitation Areas
4" Mill and Inlay (SG) topped with 2" HMA (S)
CONCRETE PVMT & GEOTEXTILES
• 412-01 Concrete Pavement (8 Inch) (Colored) (Median)
> Median Noses around Union Pacific Signals
• 420-01 Geotextile Paving Fabric
• 420-02 Geotextile (Reinforcement)
As Required for Stabilization (Turn Lanes and Harmony
Road Widening Areas)
CULVERTS AND SEWERS
• 603-01
18 Inch RCP Class III
• 603-02
24 Inch RCP Class III
• 603-03
19 x 30 Inch RCP Elliptical Class III
Pipe Extension for New Type'R' Inlet on Lemay
• 603-04
24 Inch RCP End Section Class III
13
MANHOLES AND INLETS
• 604-01 Inlet, Type R (5 Foot)
• 604-02 Inlet, Type D (5 Fool)
• 604-03 Manhole (6 Foot)
May be Required based upon Field Conditions as part of
the Storm Sewer work at the Lemay Turn Lane
SUBSURFACE DRAINS
• 605-01 4 Inch Perforated Pipe Underdrain
n Refer to Details and Specifications
s Items Including in this Work (Incidental to the Pay Item)
a Placement of 10 Mil Plastic Visqueen
o Wrapped, Perforated Underdrain
❑ Class "A" Filter Material
❑ 4 Inch Riser Pipe, Tee and Cleanout Cap
GUARDRAIL AND FENCES
• 606-01 Guardrail Type 3
• 606-02 End Anchorage
• 607-01 Fence (3 Rail)
To Replace Fence Removed along the East Side of the
Dixon Lateral
14
SIDEWALKS, CURB & GUTTER
• 608-01 Concrete Sidewalk (6 Inch)
608-02 Concrete Crosswalk It Inch) (Colored)
r Crosswalk at Harmony and JFK
608-03 Concrete Curb Ramp w/ Truncated Domes
• 609-01 Curb and Gutter, Type 2 (Section I-B)
• 609-02 Curb and Gutter, Type 2 (Section II-B)
• 609-03 Curb and Gutter, Type 2 (Section I-B) (Modified)
613-01 2 Inch Conduit (Schedule 80)
For Irrigation Connection at Union Pacific Tracks
FIELD FACILITIES
• 620-01 Sanitary Facility
IRRIGATION SYSTEM
• 623-01 Irrigation System (Relay Turfed Areas)
Businesses Own and Irrigate the Harmony Road
Parkways — anticipated repairs adjacent to turn lanes
• 623-02 Irrigation System (Median)
MOBILIZATION
626-01 Mobilization
PAVEMENT MARKING
• 627-01 Temporary Striping
TRAFFIC CONTROL
• 630-01 Construction Zone Traffic Control
• 630-02 Traffic Control Management
• 630-03 Flagging
15
TURN LANES / UTILITIES
• Northbound Lemay Right Turn Lane
• Comcast is moving Vault and Pedestal
• City L & P is moving Vault and Power
s City Traffic is moving Vault and Fiber
> Contractor will relocate Hydrant
• Eastbound Harmony Right Turn Lane @ Lemay
Contractor Adjust Manholes and Sprinkler Relocation
TCE to be in place prior to construction
• Eastbound Harmony Right Turn Lane @ Timberline
Contractor Adjust Manholes and Sprinkler Relocation
Thanks for Attending!
Questions and Clarifications can be Directed to:
Tim Kemp
— Capital Projects Engineer
• Office
(970) 416-2719
> Cell
(970) 219-9762
• Email
tkemr)@fcoov.com
16
IMPORTANT CONTRACT DATES
• Pre -Construction Meeting
s Mandatory Meeting prior to Commencing Construction
> Date and Time to be determined after Contract Award
Construction Start Date
• Approximately mid -May, 2012
> Ninety (90) Calendar Day Contract
IMPORTANT CONTRACT DATES
• Substantial Completion
• Seventy (70) Calendar Days
> Further Defined in General Conditions Slides
• Final Acceptance
> Twenty (20) Calendar Days from Substantial Comp.
a Further Defined in General Conditions Slides
CONTRACT DOCUMENTS BID #7366
Plan Sheets
> Prepared by: Atkins, Ripley Design Inc., Hines Irrigation
(Sheets 1 to 132)
• Potholing of Existing Utilities (Sheets Pt to P3)
• Existing Pavement Cores (Sheets C1 to C13)
s Dixon Lateral Inspection Sheets (Sheets 131 to 34)
TOTAL 152 Plan Sheets
• Specification Book
Prepared by: City of Fort Collins
2
SUMMARY OF WORK
• Removals — Asphalt, Concrete, Storm Sewer, Bridge
• Install Aggregate Base, Curb, Gutter and Asphalt
• Install Concrete Sidewalk and Curb Ramps
• Pavement Rehab — Mill, Inlay and Paving Fabric
• Unclassified Excavation and Topsoil Placement
• Install Irrigation System
• Install Landscape Materials
Trees, Shrubs, 1 Gallon Perennials
Landscape Boulders, Mulch and Stone
• Provide Traffic Control
SUMMARY OF WORK
• Construction Staking
> Provided by the City of Fort Collins
48 Hours (Minimum) Required for Notification
• Testing
• Provided by the City of Fort Collins thru CTL Thompson
> Contractor will schedule Testing as required
• Striping
• Temporary — Provided by the Contractor
• Final — Provided by the City of Fort Collins
3
HIGHLIGHTS OF GENERAL CONDITIONS
• Superintendents
The General Contractor SHALL employ a full time
superintendent whose sole responsibility is to monitor and
coordinate all facets of the work
Liquidated Damages — Substantial Completion
If the Contractor goes past the 70 calendar days for
substantial completion, damages in the amount of Five
Thousand Dollars ($5,000.00) for each calendar day will be
assessed.
Derived from the CDOT "Road User Cost Calculation"
HIGHLIGHTS OF GENERAL CONDITIONS
• Liquidated Damages —Final Acceptance
If the Contractor goes past the 70 calendar days for final
acceptance, damages in the amount of Five Thousand
Dollars ($5,000.00) for each calendar day will be assessed.
• Project Coordination Meetings
s Weekly On -Site Meetings (including ticket collection)
• Contractor to update Schedule weekly. The Contractor
may be required to submit additional Schedules
dependent upon progress of the project.
HIGHLIGHTS OF GENERAL CONDITIONS
• Construction Hours
Standard Working Hours are from 7:00am to 6:00pm
Monday through Friday
Weekend Work and / or Extended Hours Work may be
granted. Requests for either must be made in Writing a
minimum of 48 hours in advance. Requests are subject
to approval by the City of Fort Collins.
Special Conditions for Arterial / Arterial Intersections
o Not Permitted between 7 to 8:30am or 3:30 to 6pm
o Weekend or Extended Hours may be granted
HIGHLIGHTS OF GENERAL CONDITIONS
• Haul Routes
Arterial and Collector Streets ONLY. Contractor will not
be allowed to use Residential Streets to access the site.
• Site Clean Up
The construction work shall be kept and accomplished in
a neat, clean and orderly fashion
Street sweeping may be required in order to minimize
vehicle tracking and to meet EPA storm water quality
requirements
Dust control will be required as necessary
TRAFFIC CONTROL
• Contractor Responsibilities:
Maintain vehicle, bicycle, pedestrian and Transfort traffic
at all times. ALL detour for ALL modes of transportation
shall be approved by the City prior to construction.
Maintain access to all local businesses
Review all upcoming lane closure needs and /or changes
in traffic control set up at Weekly Progress Meetings
> Traffic Control Plans need to be submitted to the City 10
days prior to setup
EROSION CONTROL - SWMP
Contractor Responsibilities:
Erosion Control in accordance with Sheets 52-62
The Contractor is responsible for maintaining and
repairing all erosion control devices throughout the
project. This is incidental to the "Work".
Contractor will designate a SWMP Administrator prior to
the start of construction. The SWMP Administrator will
conduct weekly inspections and submit a signed, log of
activity weekly to the City.
Payment will be made under the "208" line items
MATERIAL SUBMITTALS
• Reviewed by the City, Ripley Design and Hines Irrigation
• Process Time — 10 days per submittal
• Shop Drawings — 4 copies (1 City, 1 CDOT, 2+ Contractor)
AC COST ADJUSTMENT
• Revision of Section 109 (Asphalt Cement Cost Adjustment):
> Only for the "403" Pay Items
n First month (May) will be paid at the Contract Unit Price
s June and July are eligible for the "Adjustment"
• No "Adjusted Payment" will be made past the allotted
Calendar Days under the terms of the Contract
HIGHLIGHTS FROM
SPECIFICATIONS
101
201 Clearing and Grubbing
202 REMOVALS
• 202-01
Removal of Tree
• 202-02 thru
Removal of Various Storm Pipes
202-05
• 202-06
Removal of End Section
''I I ow
202 REMOVALS
202-08
Removal of Sidewalk
• 202-09
Removal of Curb and Gutter
• 202-10 thru
Removal of Asphalt Mat
202-13
(Full Depth, Planing, Tapering)
202-14
Removal of Pavement Markings
202-11 Removal of Mat (Planing) 0-4"
202-16 Removal of Fence (3 Rail)