PROJECTTF LE: Roselawn Cemetery - Office / Restrooms
CONTRACTOR Classic Contractors, INC.
PROJECTNUMBER OP-432320
DESCRIPTION: Office and Restrooms
I�
City •
F6rtCollins
In preparing change orders show in order as separate numbered paragraphs the following:
Reason for change: Please reference Classic Contractors C.O.R. dated May 18, 2012.
Description ofchange:Add IT closet, Add flow fill and extra conduit, change windows to tan, access
Change in contract cost This will increase the contract cost by $5.060.
4. Change in contract time:
(Attach additional sheets as required)
ORIGINAL CONTRACT COST
TOTALAPPROVED CHANGE ORDERS
TOTAL PENDING CHANGE ORDERS
TOTAL THIS CHANGE ORDER
TOTAL % OF THIS CHANGE ORDER
Total C.O. % of Original Contract
ADJUSTED CONTRACT COST
WOMI
$136,870.00
$0.00
$0.00
$5,060.00
3.70%
3.70%
$141,930.00
- ;S 2%7
Karl Schmidt D to
Project Manager � Ethan Cozzens
6 z
Da e
to�r
D
2-
Print Name Etha Cozzens Date
oc: City Clerk Project File
Contractor Purchasing
Engineer
Classic C011t [IC101'S, i,vr.
P.O. Box 2798
Loveland, CO. 80539
970-227-2951
970-371-1604
May 18, 2012
City of Fort Collins
7312 Roselawn Office Building
Revised front iblay 4, 2012 letter
Attn: Ethan Cozzens
Request for changes:
I. Previous change for slab on grade in lieu or crawl space was a deduct of $
4,575.00, add full underslab 2" insulation would add S 925.00, move insulation to
outside of the monolithic pour and add flashing and FRP at exposed insulation would
add S 760.00. The total deduct for slab on grade would be S 2,890.00.
2. Paint gutters and downspouts in lieu of standard color, REJECTED
3. Add flow -fill to electrical trench, add $ 1,219.00
4. Change exterior doors to solid at double, and half lite at entry, deduct S 340.00.
5. Change window color front white to tan, add $ 519.00.
6. HVAC changes to draw return air front close to floor, add S 544.00
7. Add rr Roont, add $ 4,014.00
8. Add access wiring, City of Fort Collins to furnish wire to be pulled by
electrical contractor to blanked boxes for City of Fort Collins to furnish and
install card readers, add $ 544.00.
9. Add drinking fountain per ASI-I, add $ 1,365.00.
10. Add solar shading to one skylight, add $ 85.00.
Bold items are changes from previous letter of May 4, 2012.
If you have any questions, please contact me at 970-371-1604.
Classic Contractors, [tic