HomeMy WebLinkAboutWORK ORDER - RFP - 7291 GEOTECHNICAL TESTING SERVICES (2)PROFESSIONAL SERVICE AGREEMENT
WORK ORDER FORM
PURSUANT TO AN AGREEMENT BETWEEN
THE CITY OF FORT COLLINS
AND
CTL Thompson Inc.
DATED: January 4, 2012
Work Order Number: CTL-Elizabeth-1
Purchase Order Number: 112a %
Project Title: Elizabeth Street Waterline Replacement - Compaction Testing
Commencement Date: May 21, 2012
Completion Date: August 30, 2012
Maximum Fee: (time and reimbursable direct costs): Not to exceed
Five Thousand Two Hundred Twenty Dollars ($5,220)
Project Description: Testing services for open trench backfill.
Scope of Services: See Attached Scope of Work
Professional agrees to perform the services identified
above and on the attached forms in accordance with
the terms and conditions contained herein an in the
Professional Services Agreement between the parties.
In the event of a conflict between or ambiguity in the
terms of the Professional Services Agreement and
this work order (including the attached forms) the
Professional Services Agreement shall control.
The attached forms consisting of two (2) pages are
hereby accepted and incorporated herein, by this
reference, and Notice to Proceed is hereby given.
Professional:
��� (, 1 l�C�✓ Spl L
�V A
Date:- ` t
stdwopsa rev 7/09
City of Fort Collins
':�l��
Matt Fater, Project Manager
Submitted By:
Date: 6' - O -/
Reviewed By: G!;
Owen Randall,
S nigr Utility Engineer
Date: r/,.P//Z
Approved By
Jon Haukaas,
Water Engineering and Field
Services Operations Manager
Date: AZ(
L
r.r ■ o ■ r o a.•-r ■ o
May 3, 2012
City of Fort Collins Utilities
700 Wood Street
P.O. Box 580
Fort Collins, Colorado 80522-0580
Attention: Mr. Matt Fater
Subject: Fee Estimate for Construction Observation
and Materials Testing Services
Elizabeth Street Waterline
College Avenue to Smith Street
Fort Collins, Colorado
Proposal No. FC-12-0167
At your request, CTLIThompson, Inc. is pleased to provide this fee estimate for Construction
Observation and Materials Testing services for the Elizabeth Street Waterline project located on
Elizabeth Street between College Avenue and Smith Street in Fort Collins, Colorado. We
appreciate your time spent on the phone to discuss the scope of the project.
We anticipate that the city will use our estimate for the basis of establishing a budget for the project
and to issue a purchase order for our services. Our estimated scope of services and associated
fees were prepared according to the terms and conditions of our professional services agreement
with the City of Fort Collins and are presented below.
Earthwork: Compaction testing will be required for waterline trench backfill. We understand the
project will last approximately 8 weeks. We estimate one site visit per day for a total of 40 site visits.
Engineering Technician 40 days x 2 hrs/day x $60/hr $4,800.00
Standard Proctor 2 tests x $80/ea $160.00
Atterberg Limits 2 tests x $60/ea $120.00
Gradation 2 tests x $70/ea $140.00
Subtotal: $5,220.00
TOTAL ESTIMATED FEE: $5,220.00
It should be emphasized that this estimate is based upon assumptions of actual quantities and
contractor's schedule. The fee will be charged only for the actual hours and unit rates presented for
tests and observations requested by the owner, contractor or subcontractors who schedule the
services.
351 Linden Street I Suite 140 1 Fort Collins. Colorado 80524
Telephone: 970-206-9455 Fax: 970-206-9441
T
If we can be of further assistance, please contact us at your convenience.
Very truly yours,
CTL I THOMPSON, INC.
Heather Grubb
Field Department Manager
CITY OF FORT COLLINS
ELIZABETH STREET WATERLINE
CTL I T PROPOSAL NO. FC-12.0167