HomeMy WebLinkAboutPrebid - BID - 7338 TROUTMAN PARKWAY GRADE SEPARATED CROSSING (2)Troutman Parkway Bicycle/Pedestrian Underpass
Federal Aid Project No. AQC-M455-089
Bid No. 7338
PRE -BID CONFERENCE
February 15, 2012
10:00 A.M.
215 N. Mason Street
Community Room
City of Fort Collins
Engineering Dept.
Capital Improvements Program
Introductions
Engineering:
Capital Projects Program:
• Rick Richter - Program Manager 221-6798
• Jin Wang - Project Manager 416-2292
• Mark Laken - Project Engineer 222-3546
• John Von Nieda — City Surveyor 221-6565
Purchasing:
• John Stephen - Purchasing Agent 221-6777
Traffic:
• Syl Mireles - Traffic Eng. Tech 221-6815
Consultant Engineer:
• JF Sato & Associates
BNSF Railroad Coordination Requirements:
• Required BNSF Railroad Agreement between
Contractor and BNSF — See Exhibit "C" in contract
• BNSF will review box culvert design for precast box
culvert - 4 week review period
BNSF Railroad Coordination Requirements:
The contract specifies a "work window" which is the 7 day full
shutdown of the tracks for:
• BNSF to remove rail, ties, & ballast (Day 1)
• Structure excavation
• RCP installation
• 75' minimum box culvert installation
• Spray on bridge deck membrane
• Structural backfill
• BNSF re -install rail, ties, & ballast (Day 7)
• Day 8 the BNSF RR will be in full operation
Currently Scheduled for July 23-29, 2012
BNSF Railroad Coordination Requirements:
• The contract specifies a `work window" which is the
7 day full shutdown of the BNSF tracks.
• Completing work in the time window is critical to
the completion of the project
• Contractor needs to be ready for this work
window and have materials and equipment on
hand for work
• Failure to do so will be considered a breach of
contract
Anticipated Project Timeline for BNSF
Coordination
• Notice To Proceed — Mid -March
• Precast design — 2 to 3 weeks
• Submit Design for Approval
— City & BNSF Review — 4 weeks
— Address Comments — 1 week
— Final Review — 2 weeks
• Fabrication During June
• AREMA Box Culvert & Slab available by mid -July
• Installation anticipated for July 23-29, 2012
City Utility Coordination
• City Utilities will install 1 valve on the 12" DIP
waterline prior to construction and remove 162 LF
of DIP waterline prior to construction
• City Utilities will work around Contractors schedule
to finish installing a 50' casing pipe, and 162 LF of
12" DIP waterline after the box culvert is installed
Traffic Control
• Traffic Control provided by contractor
• 1 Lump Sum for all Traffic Control on the project
including: Flagger Hours, TCS, Inspections &
Traffic Control Devices
• Contractor and traffic control subcontractor
need to coordinate on construction
• Full Time onsite TCS is not required - only
during initial devices setup
• Daily Logs required
Traffic Control
Sheet 40 shows an acceptable detour route and
sheet 7 shows a summary of devices.
• This detour route is required to minimize the
detour for Mason Trail users
• Additional Traffic Control will be required to
bring in materials from Harmony Road
• Additional Traffic Control will also be necessary
at Troutman Road to barricade traffic from the
workzone
Haul Routes
Access to the Site will be from:
• Troutman Road on the east side of the box culvert
• Mason Trail from Harmony Road on the west side of the
box culvert
• Mason trail is 6" Fibermesh reinforced Class D
concrete on compacted fill
• 5 CY maximum concrete loads on trail to Minimize
damage to Mason Trail
• If larger loads are delivered and damage occurs to
existing trail, Contractor will be responsible for repair
No Text
EARTHWORK & FILL
Section 203 & 304
-Structure Excavation — Paid per Plan
-Structure Backfill (Class 1) — Paid per Plan
-Shoring Area (Area 1) — Paid Lump Sum
• To minimize excavation
•4" Compacted Aggregate Base Course (Class 6) bedding — Paid per
Ton
-Excess material hauled to SE corner of Turnberry Road and Richard's
Lake Road
EROSION CONTROL
Contractor will obtain and maintain the SW MP from the Colorado Dept
of Public Health and Environment (CDPHE)
• The Erosion Control Plans provided are not the SWMP. However,
plan quantities were calculated from the Erosion Control Plan
• Erosion Control is broken into several measurable pay items
• Erosion Log, Inlet Protection, Concrete Washout Structure, &
Tracking Pad
• Contractor is required to have an Erosion Control Supervisor that shall
enforce all policies that apply to this project (HR Item)
DEWATERING
• Dewatering Paid Lump Sum
• Anticipated to encounter water at 5032' at west
side and 5030' at east side
• Per Addendum, aline item will be added for Muck
Excavation which will include backfill with suitable
rock material
• Discovery of unsuitable material will not change
the work window that the BNSF railroad is
providing to the City
BASES AND PAVEMENT
Section 304
• Aggregate Base Course Class 6
Section 506
• Rip Rap Outlet Protection
Section 507
• Slope and Ditch Paving
PEDESTRIAN AND BIKEWAY RAILING
• Pedestrian and Bikeway Railing — Type 1
• Pedestrian and Bikeway Railing (Side Mounted) —
Type 2
• Pedestrian and Bikeway Railing (Top Mounted) —
Type 3a
• Pedestrian and Bikeway Railing (Side Mounted) —
Type 4
• Pedestrian and Bikeway Railing (Top Mounted) —
Type 3b
NOTES ON STRUCTURE:
2 Types of box culvert sections
• BNSF RR Requirements
• 1'8" Top ; 2' 9" Bottom
• More intensive waterproofing
• AASHTO Requirements (underneath BRT)
• 1'4" Top ; 1'2" Bottom
Cast -In -Place Headwalls & End Section — Class D (Box)
Cast -In -Place Stairs & Concrete Overlay— Class D (Misc)
Cast -In -Place Walls — Class D (Walls)
NOTES ON STRUCTURE:
• Certifications required for Precast Culvert Supplier
• National Precast Concrete Association
• Post Tensioning Institute (PTI) Certification for post
tensioned design
• Precast Prestressed Concrete Institute (PCI)
Certification for prestressed design
• AREMA Design Criteria (on plan sheet 13):
• Ballast Depth: Minimum 8", maximum 30"
• E80 Live Load
• Standard Grade 5 Timber Tie are 7" nominal Depth
NOTES ON STRUCTURE:
• Weld Plate Connections
• Per Shop Drawings
• 5' Centers minimum
• On top of base slabs and top of 3 sided culvert
• Detail B-6/13 Sheet 18
• Concrete Overlay - walking surface
• On roughened surface
• 1 % cross slope for drainage
• Thickness varies — see Tables on sheets 18 &
19
Attendance
Please be sure to resister
• BID OPENING
• When: March 1, 2012 @ 3:00 P.M. (Our Clock)
• Where: 215 North Mason Street (20d Floor)
• Bid Documents are available at:
hftp://fcgov.com/eprocuremen
hftp://fcgov.com/purchasing/
Contract Documents for Bid 7338
• Bid Set Plans for Troutman Parkway Bicycle /
Pedestrian Underpass by J.F. Sato & Associates
• Sheets 1 thru 46
• Specifications Book
• Addendum to be released on February 23, 2012
• Revised Bid Tab
NOTES ON STRUCTURE:
• Trench Underdrain
• Trench Drain running the entire length of the
structure on North and South sides
• Entire structure flows to the East
• Trench Drain at the face of each entrance into
the box culvert
• Catch Basin at the Southeast corner of
structure
4" Perforated Underdrain Pipe — installed on each
side of box and at the middle of the Box — Sheet
10
WATERPROOFING MEMBRANE
• Sprayed on Deck Membrane — 221 SY
• Sprayed 80mils thick with 2 layers of Yi' thick asphalt
impregnated fiberboard
• BNSF AREMA Area —Top Only
• Waterproofing (Membrane) — 259 SY
• BRT AASHTO Area —Top Only
• Sprayed on Deck Membrane
• Sprayed on 80 mils thick — no asphalt impregnated
fiberboard
• BNSF AREMA Area and BRT AASHTO Area — Sides
Only
• Quantities to be modified by Addendum
• Detail B-6 Joint Wrap Detail (Sheet 18) — Incidental to Box
Culvert Cost
CONCRETE
Section 601
• Concrete Class D (Box Culvert)
• Concrete Class D (Misc)
• Concrete Class D (Wall)
• Structural Concrete Coating
Section 602
• Reinforcing Steel (Epoxy Coated)
REINFORCED CONCRETE PIPE
Section 603
• 15' RCP
• 24x9.75 Foot Concrete 3-Sided Culvert Base Slab
(Precast AASHTO)
• 24x9.75 Foot Concrete 3-Sided Culvert Base Slab
(Precast AREMA)
• 24x9.75 Foot Concrete 3-Sided Culvert (Precast
AASHTO)
• 24x9.75 Foot Concrete 3-Sided Culvert (Precast
AREMA)
REINFORCED CONCRETE PIPE
Section 604
• Catch Basin 24"x24"
• Manhole Slab Base (20')
• Trench Drain 1 (8 Inch)
• Trench Drain 2 (12 Inch)
• Trench Drain 3 (8 Inch)
• 4 Inch Perforated Underdrain
FENCING & SIDEWALK
• Section 607
• Fence Chain Link (Special) (92 Inch)
• Section 608
• Sidewalk (6 Inch)
• Mason Trail
• Ramps
613 ELECTRICAL
• '/2" Electrical Conduit
• %" Electrical Conduit
• 1/4" Electrical Conduit (Plastic)
• 1 '/4" Electrical Conduit (Plastic)
• 2" Electrical Conduit (Plastic)
• 3" Electrical Conduit (Plastic)
• Wiring
613 ELECTRICAL
• Luminaire (Special) ("A" Type Under Bridge Luminaire)
• Luminaire (Special) ("B" Type Step Light Luminaire)
• Light Standard and Luminaire ("C" Type Pedestrian)(18
Foot)
• Light Standard and Luminaire ("C1" Type
Pedestrian)(18 Foot)
• Concrete Foundation Pad
• Light Standard Foundation
• Lighting Control Center
TRAFFIC CONTROL
Section 630
• Construction Zone Traffic Control
• Covers all traffic control devices, flaggers, TCS,
Inspection necessary for the project.
• Contractor to develop traffic control plans for the
project
• Plans reviewed by the City
• Maintain Access to Mason Trail / Troutman
Pedestrian Bridge
FORCE ACCOUNT
• F/A Minor Contract Revisions
• F/A Partnering
• F/A Fuel Cost Adjustment
• F/A On the Job trainee
• F/A Railroad
• F/A Erosion Control
Thanks For Attending!
• Any Questions or concerns can be addressed to:
Jin Wang (Technical)
• Office: (970) 416-2292
• Email: iwang(cDfcgov.com
Mark Laken (Technical)
• Mobile:970-222-3546
• Email: mlaken@fcgov.com
John Stephen (Purchasing)
• Office: (970) 221-6777
• Email: isteohen(alfcgov.com
Vicinity
Map
NkR
FoKiC• llin
PROJECT LOCATION
MAP
1
I
ND
q AVE !
�,qq t
C�EGER
R�
DENT ISG A �
�
L
��
�
DR
SDPRDNMIH
DR
t
I-
W
5 ARCING ST
PROJECT
TROUtR4W PARK
UT PKWY
�
•zz'
ETpOUT
RE K O
NG',1N'fAl
�
D w
W
PgNL
��I
�
KEN �SINGT
�T
DR
FES
W HARMONY RD
�_
Summary of Work
• Structure Excavation and Structure Backfill
• CIP Structural Concrete (Walls, Box, Misc.) w/ Rebar
• 2-piece Precast Box Culvert (AREMA and AASHTO types)
• RCP Pipe, Manholes, and Trench Drain System
• Concrete Sidewalk
• Electrical wiring and lighting
• Pedestrian Railing
• Traffic Control
Important Contract Dates:
AWARD CONTRACT
• Bid Opening March 1, 2012 at 3:00 PM
PRE -CONSTRUCTION MEETING
• Mandatory Meeting Prior to Start of Construction
• Date to be determined after contract is awarded
CONSTRUCTION START DATE
• Anticipate Notice to Proceed in mid -March, 2012
• Anticipated Begin Construction in late May, 2012
SUBTANTIAL COMPLETION - 180 Calendar days from beginning of
construction
FINAL COMPLETION — 14 Calendar Days after substantial completion
is obtained.
Project Overview
Contractor responsible to acquire all appropriate permits and
submit required documentation
• SW MP — permit and inspections
• Dewatering Permit if applicable
• CDOT Form 205 for each subcontractor
• Payrolls, EEO Documents, Trainee Forms
• Shop Drawings, Material Submittals, Mix Designs
Partnering session prior to construction
• No designated staging area provided
Project Overview
• Survey
• Provided by City of Fort Collins
• Engineering Department Survey Staff
• 48 hour written request for survey
• Testing
• Provided by City of Fort Collins
• Thru contract with CTL Thompson
• Contractor will setup testing as required
HIGHLIGHTS FROM GENERAL CONDITIONS AND
GENERAL REQ'S:
SUPERINTENDENTS:
The General Contractor SHALL employ a full time Superintendent
whose sole responsibility is to monitor and coordinate all facets of the
work
LIQUIDATED DAMAGES:
• SUBSTANIAL COMPLETION:
• 180 days after commencement of work.
• Damages in the amount of Two Thousand Dollars ($2,000.00) for
each calendar day will be assessed.
• FINAL ACCEPTANCE
• Within 14 days of Substantial Completion.
• Damages in the amount of Two Thousand Dollars ($2,000.00) for
each calendar day will be assessed.
HIGHLIGHTS FROM GENERAL CONDITIONS AND
GENERAL REQ'S:
=40101 .VGi1I0041]►r1Rif, 114
• Standard Hours of Operation
• 7:00 AM thru 6:00 PM - Monday thru Friday.
• Given the scope of the proposed improvements, the City will
allow extended working hours
• Extended Hours requests must be made at the weekly meeting
prior to the request date
HIGHLIGHTS FROM GENERAL CONDITIONS AND
GENERAL REQ'S:
PROJECT MEETINGS:
• Once a week. Location and time to be determined
• Agree to weekly quantities, 2 weeks schedule, traffic control
PROGRESS AND SCHEDULE REVISIONS:
• Prior to construction, initial schedule must be submitted and approved
• Schedules shall be updated weekly
• The Contractor may be required to submit additional schedules
depending on the progress of the project.
RECORD DRAWINGS PLAN SET
Contractor will be required to keep record drawings
• Will be submitted to the City at the end of the project
HIGHLIGHTS FROM GENERAL CONDITIONS AND GENERAL
REQ'S:
SITE CLEAN-UP:
• The construction work shall be kept and accomplished
in a neat, clean and orderly fashion.
• Tracking pads and street sweeping will need to be used
in order to minimize tracking and meet EPA storm water
quality requirements.
• Dust control will be required.
General Notes on Federal Aid Project
Requirements:
• Change Orders will follow CDOT procedures
• Federal Aid = Davis Bacon Wages and Wage
Reporting Requirements
• Weekly Payroll Submittals to City Staff
• UDBE Goals = 9.5% of contract amount
• On -Job Training Goals = 320 hours
• OJT Trainee Payroll Documentation
• CDOT Materials Requirements & "Buy American"
• CDOT Form Submittals
Troutman Underpass Project
UDBE Requirements
Underutilized Disadvantaged Business Enterprise (UDBE)
Goal is 9.5% of Total Contract
If UDBE goal is met, submit CDOT Form 715
If UDBE Goal is not met
• Submit CDOT Form 718
• 3 Copies of Good Faith Effort documentation needs to
be supplied to the City of Fort Collins by 4:30 PM on the
next business day following Bid Opening.
• Good Faith Effort includes all correspondences and
supporting documentation that was amassed in effort to
meet the UDBE project goal.
Troutman Underpass Project
UDBE Requirements
• For UDBE Questions contact:
• CDOT EEO Office at: (303) 757-9303
• CDOT maintains a DBE contractor list at:
• http://www.dot.state.co.us/EEO/DBEProgramPa
ge.htm
• The list is updated monthly.
BNSF Railroad Safety Requirements:
• Contractor's Superintendent is required to
complete online RR Safety Training Program
• www.contractororientation.com
• 30 Day verbal notice to BNSF Roadmaster for
RR Flagger — Roadmaster: (307)-432-7357
• Railroad Flagger required when work is within
25' of Centerline of RR tracks
• Railroad Flagger to be paid thru RR Force
Account line item
BNSF Railroad Safety Requirements:
• 30 Day written notification prior to commencing
construction on BNSF property
• Proposed shoring, falsework, & cribbing (with
support calculations) need to be submitted to
BNSF for approval prior to work
• BNSF Railroad Insurance required prior to
working on BNSF ROW