HomeMy WebLinkAboutPrebid - BID - 7336 SHIELDS STREET & LAPORTE AVE BRIDGE REPLACEMENT (2)Arthurs Ditch Replacement at Laporte and Whitcomb
Shields St. Bridge Replacement at Larimer County
Canal No. 2
Federal Aid Project No. BRO M455-100
Bid No. 7336
PRE -BID CONFERENCE
February 8, 2012
10:00 A.M.
215 N. Mason Street
Training Room
City of Fort Collins
Engineering Dept.
Capital Improvements Program
Introductions
• Engineering:
• Capital Projects Program:
• Rick Richter - Program Manager
221-6798
• Jin Wang - Project Manager
416-2292
• Kyle Lambrecht - Project Engineer
221.6566
• Craig Fewer - Construction Inspector
222-0854
• John Von Nieoa - City Surveyor
221-6565
• Purchasing:
• John Stephen - Purchasing Agent
221-6777
• Traffic:
• Syl Mireles -Traffic Eng. Tech
221-6815
• Consultant Engineer:
Attendance
• Please be sure to reaister
• BID OPENING
• When: Feb 22 @ 3:00 P.M. (Our Clock)
• Where: 215 North Mason Street (2n° Floor)
Bid Documents are available at:
http:ltfcgov.com/eprocuremeni
TRAFFIC CONTROL
Section 630
• Construction Zone Traffic Control
• Covers all traffic control devices necessary for this phase,
including Detour Signage and Orange Safety Fence for bike
and pedestrian protection
• To be based on a 120 day full closure of the LaporteNJhitcomb
Intersection
• Contractor to develop traffic control plans for the project
• Plans reviewed by the City
• Flagging is not expected
• Traffic Control Management— For working days
• Traffic Control Inspection— For non -working days
REMOVALS
Section 201
-Clearing and Grubbing
Section 202 ha
-Removal of Tree (April 2012)
• Tree Removal by licensed amorist
-Removal of Sidewalk
-Removal of Curb and Gutter"='�
-Removal of Asphalt Mat
-Removal of Pavement Marking
-Removal of Bridge
EARTHWORK
Section 203
-Unclassified Excavation (Complete in Place) (Paid per Plan)
-Potholing
• Must locate existing 30" watermain and 6" gas line
• City potholing and utility survey during design does not
preclude contractors from being required to do their own
potholing
• All shallow utilities and pipe structures shall be backfilled
with flowfill
-Muck Excavation
EARTHWORK
Section 206
-Structure Excavation
-Structure Backfill (Class 1)
-Structure Backfill (Class 2)
-Fitter Material (Class B)
-Shoring (Area 1)
-Shoring (Area 2)
EROSION CONTROL
Contractor will obtain and maintain the SWMP from the Colorado Dept
of Public Health and Environment (CDPHE)
• The Erosion Control Plans provided are not the SWMP. However,
plan quantities were calculated from the Erosion Control Plan
Erosion Control is broken into several measurable pay items
• Erosion Log, gravel bags, concrete washout structure, vehicle
tracking pad, etc.
• Contractor is required to have an Erosion Control Supervisor that shall
enforce all policies that apply to this project
LANDSCAPING
Section 212
• Seeding (Native)
• Soils Conditioning
• Tree Retention and Protection
(Coord with City Forester)
Section 213
• Mulching (Weed Free Hay)
Section 214
• Deciduous Tree (3' Caliper)
• Mitigation trees to be planted
near project
BASES AND PAVEMENT
Section 304
• Aggregate Base Course Class 5
Section 403
• HMA (Grading SG)(100)(PG 58-
28)(Temp Pavement)
• HMA (Grading SG)(100)(PG 58-28)
• HMA (Grading S)(100)(PG 64-28)
5
BRIDGE CONSTRUCTION
Section 420
• Geotexdle (Draingage)(Class 1)
• Geolemile (Separator)(Class 2)
Section 502
• Pile Tip
• Steel Pile (HP 12x74)
Section 506
• Riprap(18")
• Geognd Reinforcement m,��
BRIDGE CONSTRUCTION
Section 514
• Pedestrian Railing (Steel)(Special)
• Concrete Sealer
i
CONCRETE & STEEL
Section 601
• Concrete Class D (Bridge)
• Concrete Class HT (Deck Topping)
• Structural Concrete Coating
1117�
Section 602
• Reinforcing Steel
_
• Reinforcing Steel (Epoxy Coated)
-
Section 606
T,
•�!
_
• Decorative Column Type 1
S t�
:,
• Decorative Column Type 2
'
CONCRETE & STEEL
Section 608
• Concrete Sidewalk (6")
.LI.f:.:ri:riinilannlltlllllllrtll!ilnilialllilitllinllFlnt!In!nerrnllnl +�
onunuannnnnmunnnw nnu tnmmrrrmrmmnnnnnn nnnun
� nmtnesuunnnnne nnn iammuunuanmmmnmma n nun!ar.
CONCRETE & STEEL
Section 609
. Curb and Gutter Type 11 (Section IIB)
Section 610
• Median Cover Material (Patterned Concrete)
CONCRETE & STEEL
Section 613
• 3" Electrical Conduit
- Coordinate with City L&P; they will lay own conduit
C
CONCRETE & STEEL
Section 618
• Prestressing Steel Bar
• Prestressed Concrete Stab
M
I i IN F W- WE E,
-mlam. It
MOBILIZATION
Section 620
• Sanitary Facility
Section 626
• Mobilization
• Payment Schedule per CDOT
Surveying to be Provided by the City of Fort Collins
TRAFFIC CONTROL
Section 627
• Pavement Marking Paint (Waterborne)
• No temp pavement marking on the new structure or approach slabs
Section 630
• Construction Zone Traffic Control
Covers all traffic control devices necessary for all phases
ln-
x
_ 4^�
TRAFFIC CONTROL
Section 630
• Construction Zone Traffic Control — All devices needed
• Includes necessary traffic control for tree removals in April 2012
• Flagging — Discussed and approved during weekly meeting
• Traffic Control Management — For working days
• Traffic Control Inspection — For non -working days
Portable Message Sign Panel
• Up and above message sign panels necessary for approved traffic
control developed for the project
• To be used for Special Events as directed by designated City
Representative
Impact Attenuator (Sand Filled Plastic Barrel) (Temp)
Thanks For Attending!
• Any Ouestions or concerns can be addressed to:
Jin Wang (Technical)
• Office: (970) 416-2292
• Email: iwano®fcaov.com
John Stephen (Purchasing)
• Office: (970) 221-6777
• Email: isteohen@fcaov.com
Vicinity Maps
LaporteMhitcomb Bridge
Shields Bridge
CDOT Local Agency Project
UDBE goal for this project is 13%
OJT goal for this project is 640
hours.
Project Overview
Phasing
• Laporte/Whitcomb Bridge — Start in Spring of 2012
• Structure must be complete by April 15, 2012
• Shields Street Bridge — Start late summer/early fall of 2012
• Neither bridge construction can impact ability of ditch to
deliver water
Traffic control
• Laporte/Whitcomb Bridge — Full Closure for 120 days
• Shields Street Bridge — Built under Traffic. One lane each
direction
Coordination with other utilities
Project Overview
• Contractor responsible to acquire all appropriate permits and
submit required documentation
• SWMP— permit and inspections
• Dewatering Permit if applicable
• CDOT Form 205 for each subcontractor
• TCS Diaries, Payrolls
Partnering session prior to construction
No designated staging area provided
Summary of Work — Laporte/Whitcomb
• Removal of 278' of existing box culvert
• Replace with 278' of cast in place box
— 240' of 4.67' x 18', two transitions to existing box
• 1098 SY of Concrete Pavement
• 375 tons of HMA
• Various concrete work, erosion control, and excavation
• surveying to be provided by the City of Fort Collins
• Traffic control to be provided by Contractor
• Work within the Floodway and Floodfringe
• Coordinate with City Survey Crew
Summary of Work — Shields Bridge
• Removal of existing box culvert, fill and pavement
• Locate unknown u0lifies before piling
- Existing 30" COFC waterlme
- Existing Xcel gas line
• Coordinate relocation of know utilities
• Replace with new structure
- Concrete foundation on H-piles
- 4254 SF of prestressed concrete girders
- Concrete deck topping
• 270 Tons HMA
• Various concrete work, erosion control, and excavation
• Urban Design Elements
• Surveying to be provided by the City of Fort Collins
• Traffic control to be provided by Contractor
• Prniart In ho ennptn impd undpr traffic
Important Contract Dates:
• PRE -CONSTRUCTION MEETING
• Mandatory Meeting Prior to Start of Construction
• Date to be determined after contract is awarded
• CONSTRUCTION START DATES
• Laporte/Whitcomb Bridge
• 120 Calendar Days under a Full Closure
• Structure must be complete by April 15, 2012
• Final Completion - 14 days after 120 day count
Shields Bridge
• 275 Calendar Days from commencement date
• Final Completion -14 days after 275 day count
HIGHLIGHTS FROM GENERAL CONDITIONS AND
GENERAL REO'S:
• SUPERINTENDENTS:
• The General Contractor SHALL employ a full time Superintendent
whose sole responsibility is to monitor and coordinate all facets of
the work
LIQUIDATED DAMAGES:
SUBSTANIAL COMPLETION:
• Laporte Avenue Bridge 120 days after commencement of work.
• Shields Street Bridge 275 days after commencement of work.
• Damages in the amount of Three Thousand Dollars
($3,000.00) for each calendar day will be assessed.
FINAL ACCEPTANCE
• Within 14 days of Substantial Completion.
• Damaaes in the amount of Three Thousai
HIGHLIGHTS FROM GENERAL CONDITIONS AND
GENERAL REO'S:
• WARRANTY:
• Hot Mix Asphalt Warranty Bond for $25,000
• 2 year Concrete warrantee
• 2 year landscaping establishment period
• CONSTRUCTION TIME:
• Standard Hours of Operation
• 7:00 AM thm 6:00 PM - Monday thnr Friday.
• Given the scope of the proposed improvements, the City will
allow extended working hours
• Extended Hours requests must be made at the weekly
meeting prior to the request date
HIGHLIGHTS FROM GENERAL CONDITIONS AND
GENERAL REO'S:
• PROJECT MEETINGS:
• Once a week. Location and time to be determined
• Agree to weekly quantities, 2 weeks schedule, traffic control
• PROGRESS AND SCHEDULE REVISIONS:
• Prior to construction, initial schedule must be submitted and approved
• Schedules shall be updated weekly
• The Contractor may be required to submit additional
schedules depending on the progress of the project.
• RECORD DRAWINGS PLAN SET
• Contractor will be required to keep record drawings
• Will be submitted to the City at the end of the project
HIGHLIGHTS FROM GENERAL CONDITIONS AND GENERAL
REO'S:
HAUL ROUTES:
• Arterial and Collector streets only. Contractor will not be allowed to
use residential streets to access the site with trucks hauling
materials.
SITE CLEAN-UP:
• The construction work shall be kept and accomplished in a neat,
clean and orderly fashion.
• Tracking pads and street sweeping will need to be used in order to
minimize tracking and meet EPA storm water quality requirements.
• Dust control will be required.
REMOVALS
Section 201
-Clearing and Grubbing
Section 202
{
-Removal of Inlet
-Removal of Curb and Gutter
-Removal of Curb Ramp
-Removal of Concrete Pavement
-Removal of Asphalt Mat
`
-Removal of Structure
EARTHWORK
Section 203
-Unclassified Excavation (Complete in Place) - Paid per Plan
-Potholing
• City potholing and utility survey during design does not preclude
Contractors from being required to do their own potholing
-Muck Excavation
Section 206
-Structure Excavation
-Structure Backfill (Class 1)
Erosion Control
Contractor will obtain and maintain the SWMP from the Colorado Dept
of Public Health and Environment (CDPHE)
• The Erosion Control Plans provided are not the SWMP. However,
plan quantities were calculated from the Erosion Control Plan
• Erosion Control is broken into several measurable pay items
• Erosion Log, gravel bags, concrete washout structure, etc.
• Contractor is required to have an Erosion Control Supervisor that shall
enforce all policies that apply to this project (LS Item)
RESET STRUCTURES
Section 210
• Adjust Manhole - 2
• Adjust Valve Box - 2
• Reset Ground Sign - 2
LANDSCAPING
Section 212
• Seeding (Native)
• Soils Conditioning
• Tree Retention and
Protection
• Will require coordination
with City Forester
Section 213
• Mulching (Weed Free Hay)
BASES AND PAVEMENT
Senion 304
• Aggregale Base Course Class5
Section 403
• HMA (Grading SG)(100)(PG 58-26)
• HMA (Grading S)(100)(PG 64-26)
Section 412
• Concrete Pavement (61
• Concrete Pavement (9.5•)
• Constructed within the P100dw2y
CONCRETE
Section 601
• Concrete Class D (Box Culvert)
Section 602
. Reinforcing Steel (Epoxy Coated)
4
CONCRETE
Section 604
• Inlet Special
• Manhole Ring and Cover
I
Section 608
• . 7
Concrete Sidewalk (6")
• Concrete Curb Ramp
Section 609
. Curb and Gutter Type 11 (Section 11B)
MOBILIZATION
Section 620
- Sanitary Facility
Section 626
• Mobilization
- Payment Schedule per CDOT
Surveying to be Provided by the City of Fort Collins