HomeMy WebLinkAboutCHANGE ORDER - RFP - 7033 DISCOVERY MUSEUM FACILITY (2)SECTION 00950
CHANGE ORDER NO. 6
PROJECT TITLE: Discovery Museum
CONTRACTOR:- Hensel Phelps Construction Company
BID NUMBER: 7033
DESCRIPTION: The construction of a 46,928 square feet Discovery Museum facility complete with related site
work, curb & gutter, paving, sidewalks, utilities and landscaping.
1. Reason for change: Incorporation of Various Change Estimates (CE) into the Contract.
2. Description of changes: CE006R Redesign of Natural Areas at Exterior- $5,269.00; CE105 Provide
Winter Heating/Protection - $44,737.00; CE137 Metal Panel Color Change—:$6,448.00; CE161 R Descope
Landscaping/irrigation — ($176,323.00); CE225 Add Shutoff Valves & Gas Turrets to Bunsen Burners -
$1,292.00; CE228 Lobby Changes — $2,428.00; CE245 Remove Wall & Casework for Storage @ Curved Stair
1 - $305.00;'CE258 Handrail for Observation, Deck Conference Room — $1,647.00; CE274 Provide Prime Coat
& Base for Collection Storage Walls — $911.00; CE299 Install Pull String for Qwest - $359.00; CE306
Additional Power/Data per Owner - $685.00; CE311 R/311.3 Design Services for Exhibit Enclosures —
$11,839.00; CE318 Insurance Policy for Museum Soiree - $314.00; CE326 Deleted Monument &Building
Name Signs — ($9,256.00); GE327 Bench Marks @ Lobby & Observation Deck - $428.00; CE334 Conduit Stub
Through Roof for FRII - $237.00; CE348 Provide Revised Cabinet & Shelving for Gift Shop - $4,070.00; CE360
Provide Design Services for Vestas Wind Blade Foundation - $1,000.00; CE361 Refund Unused Budget —
Mezzanine & Digital Dome — ($4,172.00).
3. Change in Contract Cost: ($107,782.00)
4. Change in Contract Time: 0 Days
ORIGINAL CONTRACT COST $11,400,000.00
TOTAL.APPROVED CHANGE ORDERS 982,859.00
TOTAL PENDING CHANGE ORDERS 0.00
TOTAL THIS CHANGE ORDER-107,782.00
ADJUSTED CONTRACT COST $12,275,077.00
ACCEPTED
ACCEPTED BY:
ACCEPTED BY:
ACCEPTED BY;
Contractor's Representative D to
Facilities
of
Museum Director (City of Fort Collins)
and Risk Management
2 2-lz
Date
Date
, � R
a6
a
Dat6
cc: Purchasing l / Architect Contractor
Project File
Change Estimates
1/19/12
2/1/12
CE # J
Description
Cost
Contingency
006R
Redesign of Natural Areas at Exterior
$5,269.00
105
Provide Winter Heating/Protection
$44,737.00
137
Metal Panel Color Change
$6,448.00
156
PV Conduit
$0.00
156A
PV Connection to BAS
$0.00
161R
Descope Landscaping/Irrigation
-$176,323.00
225
Add Shut Off Valves & Gas Turets to Bunsen Burners
$1,292.00
228
Lobby Changes
$2,428.00
232
Add Remote Fire Annunciator Panel at Main Vestibule
$0.00
245
Remove Wall & Casework for Storage @ Curved Stair 1
$305.00
253
Opening to Traveling Exhibit
$0.00
258
Handrail for Observation Deck Conference Room
$1,647.00
274
Provide Prime Coat & Base for Collection Storage Walls
$911.00
299
Install Pull String for Qwest
$359.00
306
Additional Power/Data per Owner Request
$685.00
309
Add Curtain to Hot Water Heater in Artifact Processing
$0.00
311R
Design Services for Exhibit Enclosures
$11,190.00
311.3
Structural Design Services for Exhibit Enclosures
$649.00
318
Insurance Policy for Museum Soiree 9/21111
$314.00
326
Deleted Monument Sign & Building Name Sign
-$9,256.00
327
Bench Marks at the Lobby & Observation Deck
$428.00
334
Conduit Stub Through Roof for FRII
$237.00
347
Provide Power & Data @ Gift Shop, Stair 1 & Ref. Room
$0.00
348
Provide Revised Cabinet & Shelving for the Gift Shop
$4,070.00
353
Furnish & Install Added Exit Signs & Heat Detector, per PFA
$0.00
360
Provide Design Services for Vestas Wind Blade Foundation
$1,000.00
361
Refund Unused Budget - Mezzanine & Digital Dome
-$4,172.00
Total
-$160,326.00
$52,544.00
Change Order #6 Total-$107,782.00