HomeMy WebLinkAboutCHANGE ORDER - RFP - P1123 GENERAL CONTRACTOR FOR FIRE STATION EXPANSION AND RENOVATION PROJECTSECTION 00950
CHANGE ORDER NO. 3
PROJECT TITLE: Poudre Fire Authority Station #1 Remodel BID NUMBER: P1123
CONTRACTOR: Drahota Commercial, LLC o/' / S ZZ
DESCRIPTION: The complete remodel of PFA Fire Station #1, including asbestos removal, deconstruction, an
addition, sitework, utilities and landscaping. Exterior renovation will match the existing as much as practicable.
Interior finishes will include painted gypsum board partitions, ceramic tile, carpet, VCT, sealed concrete,
suspended acoustical ceiling, wood and hollow metal doors and hollow metal frames.
Reason for change: Incorporation of various Proposed Change Orders (PCO's).
2. Description of change: PCO #9 — PR #4 - Option #3 — Replace Wall Tile @ Fire Pole - $2,217.40; PCO
#23R — RFI #5 — Electrical Changes - $4,897.20; PCO #28 — PR #16 — Credit for Revised Flashing —
($145.95); PCO #34 — PR #20 - Exterior Lighting Changes - $1,896.97; PCO #35 — PR #21 — Changes to
Specialty Items — $0.00; PCO #37 — PR #23 — Add Partial Height Walls Between Stair Runs - $1,546.94; PCO
#38 — PR #24 - $275.56; PCO #41 — Replace Soffits @ Apparatus Bay - $3,074.72; PCO #42 — Credit for
Reuse of Drinking Fountain — ($646.80); PCO #44 — Epoxy Floors in Utility Rooms — $1,624.59; PCO #45 —
Landscape Rock Refresh — $601.12.
3. Change in Contract Cost: $15,341.75
4. Change in Contract Time: 0 Days
ORIGINAL CONTRACT COST $1,189,225.00
TOTAL APPROVED CHANGE ORDERS $54,213.16
TOTAL PENDING CHANGE ORDERS 0.00
TOTAL THIS CHANGE ORDER $15,341.75
ADJUSTED CONTRACT COST $1,258,779.91
ACCEPTED BY:
Contractor's Representative
REVIEWED BY:
Facilities Project
APPROVED BY:
PFA Special Operations Chief
cc: Contractor Purchasing Architect Project File
I Ia
Da e
Z 2"
Date
Z/2 12--
Date