HomeMy WebLinkAboutCHANGE ORDER - BID - 7125 WATERS WAY NEIGHBORHOOD PARK (3)PROJECT TITLE: CONTRACTOR: PROJECT NUMBER: PURCHASE ORDER NO.: DESCRIPTION: CHANGE ORDER NO. 3 Water's Way Neighborhood Park Walsh Construction Change in work request 1. Reason for change: Ongoing field orders T, (o d K �f,td� 2. Description of Change: Tot playground structure equipment upgrade, restroom remodel of changing room and cupala, corrected keyways, and alternate door frame. JVIAAMS5 5zt0ec'Poo1e(t12.2VLSlow!%CA'Pl 11) IA41�1 3. Change in Contract Cost: $2,092.40 4. Change in Contract Time: 6 days ORIGINAL CONTRACT COST $1,216,250.00 TOTAL APPROVED CHANGE ORDER ($23,600:00) TOTAL PENDING CHANGE ORDER $0.00- TOTAL THIS CHANGE ORDER $2,092.40 TOTAL % OF ORIGINAL CONTRACT, THIS C.O. 0.17% TOTAL % OF ORIGINAL CONTRACT, ALL C.O.'S --17677 ADJUSTED CONTRACT COST 1,194,942. 0 - ACCEPTED BY: Contractor's Rec ACCEPTED BY: Project Manager REVIEWED BY: Title: APPROVED BY: Title: APPROVED BY: Purchasing Agent over $30,000 ca City Clerk Architect Contractor Engineer Project File Purchasing DATE: DATE: / ZO DATE: DATE: DATE: PROJECT TITLE: CONTRACTOR: PROJECT NUMBER PURCHASE ORDER NO.: DESCRIPTION: 1. Reason for ctwW. 2 Daettpm, of Change. Wstsfs way Neighborhood Park Walsh ComRuetlon Change In work request Tranafamer location moved per Ctty Ugttt aid PMM roquest Fldd Order 3 and 4 (relocate transformer to the ROW and change the electric panel at the rostroom). 3. Change h Conbad Cat $4,149.94 4. Change In Contract Thor 4 days TOTAL APPROVED CHANGE ORDER TOTAL PENDING CHANGE ORDER TOTAL THIS CHANGE ORDER TOTAL % OF ORIGINAL CONTRACT. THIS C.O. TOTAL % OF ORIGINAL CONTRACT, ALL C.O.'S ADJUSTED CONTRACT COST ACCEPTED W. Cor*actora Reps ACCEPTED BY: PnoJactmmmgi r' REVIEWED BY: Twin APPROVED BY: Mr. oz atrawa Anliasu ftl dFar Aadmft DATE:. 2.4 . jj & DATE: LO / OATS DATE: